SAPL - Near Miss Report

NMR-E-009-
Project Information P1434/8-SF-0001
Project Name MOH-Dammam South Housing Project
Contractor Name Al-Yamama Contracting Company
Work Activity
Supervisor/ Manager

Near Miss Details


12.5.201 13.5.2
Date & Time of Near Miss 3.20pm Date & Time Reported 11.AM
4 014

Notifications
Reported by SAPL
Persons Notified Company Contact # Notification Date Notification Time
Al-yamama 13.5.2014 11.AM

MOH-Dammam South- Near Miss Report Rev 00, 1/05/2014


Witnesses
Witness Name Title / Position Company Contact #
Abdul-salaam Construction manager Al-yamama

Description of Near Miss Incident


Give exact location where the Near Miss occurred. Provide details as to the activity(s) occurring, actions of the worker(s), tools
and/or equipment in use, and moment by moment summary of the incident

Unsafe lifting observed in lay down area, rigging team was not there, safety coverage,
lifting plan didnt seen. Workers were holding huge weight without tag lines and under
boom and suspended load.

Details of Involved Person(s)


If more than two persons were involved, please attach separate sheet.

Person 1 Person 2
Name
Role/ Position/ Title Material
coordinator/workers/crane
operator
Experience (years)
Country of Origin
Iqama #

Loss Potential (Describe)


Injuries/ Fatality Un certified persons were carried out the job called critical lifting.
Property Damage Surrounding could be damage
Environmental Impact
Fire There was fire protection for equipment which could be cause of fire
Explosion
Other

Analysis (Why did it Happen)


List unsafe acts, unsafe conditions, incorrect procedures, equipment or other factors

MOH-Dammam South- Near Miss Report Rev 00, 1/05/2014


1.un skilled crews were doing the critical job.
2.there was no safety coverage by contractor.
3.concern job training was not given.
4.This subject was not taken before in tool box meeting which should be conducted by
contractor HSE.
5.Lack of coordination.

Corrective and Preventive Actions


What must be done to prevent a Near-Miss re-occurrence, or ACTUAL INCIDENT? Use attachments if needed.

A. Corrective and Preventive Actions (list recommendations)

Job had been stopped and explain to contractor assure the next time for this type of
activity should be done by certification holder crews. Before start the job HSE should
analyse the hazard and must be taken controlling measures

B. Person(s) Responsible for Implementing Corrective / Preventive Actions

Name Title/ Position Schedule for Completion Completion Date


Activity incharge supervisor

Approvals
Name (Print / Sign) Date
Report Originator
HSE Representative
Foreman/ Supervisor
Project Manager

MOH-Dammam South- Near Miss Report Rev 00, 1/05/2014


Add Photos to Show/Describe the Near Miss

MOH-Dammam South- Near Miss Report Rev 00, 1/05/2014