Quantity Progres Claim No. 7 Toll Road Medan - Kualanamu:: Pt. Prima Vira Perkasa

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Quantity Progres Claim No.

7
Toll Road Medan - Kualanamu

No Kontrak : Subcontract No.043


Subcontractor : PT. PRIMA VIRA PERKASA
Contract Name : Earthwork Construction

Quantity Progress claim


Estimate
No Description Unit Previous This
Quantity
Periode Period
1 Land Clearing Sq.m 2,000.00 0.00 27,333.30

2 Borrow Material Cu.m 120,000.00 68,536.92 15,130.82


Compacted

3 Common Excavation Cu.m 0.00 1,411.42

Total Volume

Lubuk Pakam, 31
Prepare
PT. PRIMA VIR

Aisyah Wan
Direc
y Progres Claim No. 7
d Medan - Kualanamu

Quantity Progress claim Remark


Accumulate

27,333.30

83,667.74

1,411.42

Lubuk Pakam, 31 Agustus 2015


Prepared by
PT. PRIMA VIRA PERKASA

Aisyah Wan Granie


Director