INSTALLATION OF HVAC DUCT WORK SYSTEM

Project: IR No.:
Owner: Building No.:
Project Manager: Level:
Consultant: Date:
Main Contractor :

CHECKED BY
NO. DESCRIPTION
REMARKS

Ensure drawing used for installation are


1
current and approved.
Check materials installed on site are in
2
accordance with the approved materials.

Check the installaltion of support as per the


3
approved drawing and delivered materials

The internal side of duct work have been


4
cleaned & if free from debris and odstruction

Ensure all the duct be braced and stiffened


5
and tightened so that they will no breath.

Check the duct fewest joints and allowances


6
for insulation thickness.

Check the flexible connection of the duct are


7
properly sealed/ clip.

Check the sizes for supply and return are


8
same size as equipment
Check the duct conenction is accessible
9 location and ensure the the clearance of the
collar of the flexible duct.
Check that equipment and dcut work are
10 aligned with maximum misalignment of
30mm.
All access doors are sealed around the entire
11
perimeter.

Proper application of heavy mastic type


12
sealants done.
Remarks/Comments (if any):