PROJECT DATA

Name of Project Design, engineering, finance, construct, Operation and Maintenance of

Thanjavur-Trichy section from Km. 80.000 to Km. 136.490 of NH-67 under

NHDP Phase-IIIA on Build, Operate and Transfer (BOT) basis.


Package no:

Source of Fund BOT Basis & + Grant from NHAI


Client: National Highways Authority of India,G5 &6, Sector 10,Dwaraka,NewDelhi

Concessionaire M/s Trichy-Thanjavur Expressways Limited,Madhucon House, Plot No.


1129/A,Road No. 36, Hitech City Road,Jubilee Hills, Hyderabad
500033.Project Office:No 3/252,Thanjavur Main road, Devarayenaeri,
Opposite to Police Check post,Asur,Trichy -15.Project Manager :
Mr.M.Narayanan Mobil No:094433 11418

Independent Consultant (IC) M/s Louis Berger Group Inc., USA2300 N Street, NW, Washington DC 20037,
USA.
Site Office:No: 8/6-15E,I st Lakshmipuram,Ariyamangalam,Trichy-10.
Team Leader: Mr Joy Abraham, Mobile no:099948 11877

EPC Contractor: M/s Madhucon Projects Limited,Madhucon House, Plot No. 1129/A,Road No.
36, Hitech City Road,
Jubilee Hills, Hyderabad 500033
Executive Director: Mr.Srinivasa Rao Mobile No:094435 58888

Date of signing of agreement 15.06.2006


period:

Development Period: 15.06.2006-15.12.2009(180 days)

Appointed Date: 12.12.2006

Construction Period: 30 months from Appointed date(12.12.2006 to 11.06.2009)

COD: 11.06.2009

Concession period: 20 years


Length 56.490 Km

Existing Four lane: 6.200 Kms

Four lane Byepass: 4.10 Kms

ROB 3 nos

Major bridges 02 nos

Minor bridges 21 nos

Box culverts 37 nos

Pipe culverts 57 nos

Underpasses: 12 nos

Toll Plaza 1 no

Rest area 1 no

Truck laybye 1 no

Bus bays 22 Nos

Median openings: 32 Nos


DATA
ance, construct, Operation and Maintenance of

from Km. 80.000 to Km. 136.490 of NH-67 under

d, Operate and Transfer (BOT) basis.

T Basis & + Grant from NHAI


ority of India,G5 &6, Sector 10,Dwaraka,NewDelhi

Expressways Limited,Madhucon House, Plot No.


6, Hitech City Road,Jubilee Hills, Hyderabad
:No 3/252,Thanjavur Main road, Devarayenaeri,
heck post,Asur,Trichy -15.Project Manager :
arayanan Mobil No:094433 11418

nc., USA2300 N Street, NW, Washington DC 20037,

st Lakshmipuram,Ariyamangalam,Trichy-10.
aham, Mobile no:099948 11877

mited,Madhucon House, Plot No. 1129/A,Road No.

500033
nivasa Rao Mobile No:094435 58888

15.06.2006

06.2006-15.12.2009(180 days)

12.12.2006

Appointed date(12.12.2006 to 11.06.2009)

11.06.2009

20 years
6.200 Kms

4.10 Kms

3 nos

02 nos

21 nos

37 nos

57 nos

12 nos

1 no

1 no

1 no

22 Nos

32 Nos
PIU - THANJAVUR
Name of work:Four Laning Thanjavur Trichy Section of NH67
PIU: Thanjavur
I. Pre Construction Activities :
TWAD PIPE LINE
Status of Work
Estimated
NH No District Name of work Total to be Action Plan
Amount Completed Balance
shifted

TWAD pipe line


The Conceessionaire Programme
Thanjavur shifting ( from 80.000 53.66 Lakhs 13.663Km 8.955 Km 4.708 Km
to complete the work by 30.11.09
to 117.000)
67
TWAD pipe line
shifting ( from The Conceessionaire Programme
Trichy Km.121.840
12.417 Crores 43.892Km 8.13Km 35.762Km
to complete the work by 30.11.09
to136.260)

EB POLE SHIFTING
Status of Work
Estimated
NH No District Name of work Total to be Remarks
Amount Completed Balance
shifted

The Conceessionaire Programme


Thanjavur EB pole shifting 2.70 Crores 748 632 116
to complete the work by 30.09.09

The Conceessionaire Programme


67 EB pole shifting 2.88 Crores 798 353 445
to complete the work by 30.09.09

Trichy

H.T Tower line shifting 1.38 Crores 3 3 - Work Completed.

PWD
Status of Work
Estimated
NH No District Name of work Total to be Remarks
Amount Completed Balance
shifted
Shifting of Surplus
Weir at Muthodayan
Thanjavur tank near Vallam
25 lakhs 1 - 1
PWD has started the work & likely
Bypass to be completed by 30.11.09.

67 The Conceessionaire Programme


Shifting of Canal 1.28 crores 1.60Km 0.50Km 1.10Km
to complete the work by 30.11.09
Trichy
Shifting of Surplus The Conceessionaire Programme
6.0 Lakhs 1 - 1
weir to complete the work by 30.11.09

Page 5