CENTRAL MAINTENANCE SERVICES

PM EQUIPMENT TASK LIST DATA IN SAP


FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
1 2340PVSV-0117 FEMA-1 SAPCO MECH-SAP SPM 2340PVSV-0117 Mechanical 1 Years FEMA 10 To inspect of inlet & outlet nozzle 2 mech.
20 To perform inspection/ calibration. 2 mech.
2 23AB-1501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
3 23AB-1501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
4 23AB-1501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
5 23AB-1502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
6 23AB-1502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
7 23AB-1502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
8 23AB-1503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
9 23AB-1503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
10 23AB-1503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
11 23AB-1504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
12 23AB-1504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
13 23AB-1504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
14 23AB-1505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
15 23AB-1505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
16 23AB-1505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
17 23AB-1506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
18 23AB-1506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
19 23AB-1506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
20 23AB-1507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
21 23AB-1507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
22 23AB-1507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
23 23AB-1508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
24 23AB-1508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
25 23AB-1508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
26 23AB-1509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
27 23AB-1509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
28 23AB-1509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
29 23AB-1510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
30 23AB-1510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
31 23AB-1510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.

358122780.xlsx Page 1 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
32 23AB-1511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
33 23AB-1511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
34 23AB-1511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
35 23AB-1512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
36 23AB-1512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
37 23AB-1512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
38 23AB-1513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
39 23AB-1513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
40 23AB-1513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
41 23AB-1514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
42 23AB-1514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
43 23AB-1514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
44 23AB-1515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
45 23AB-1515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
46 23AB-1515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
47 23AB-1516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
48 23AB-1516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
49 23AB-1516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
50 23AB-1517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
51 23AB-1517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
52 23AB-1517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
53 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
54 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
55 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 6 Months FEMA Task 10 Suction filter to be cleaned 4 mech.
20 To inspect & clean filter 4 mech.
56 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 4 mech.
20 Inspect shaft seal tightness & damage 4 mech.
30 To check impeller condition 4 mech.
57 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 2 Years FEMA Task 10 Check HX suction & discharge lines 2 mech.
58 23AB-1530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1530 Mechanical 5 Years FEMA Task 10 Check condition of bearing and coupling 8 mech.
59 23AB-1541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1541 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
20 Inspect shaft seal tightness & damage 8 mech.
60 23AB-1541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1541 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 To do visual inspect for casing 2 mech.
61 23AB-1541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1541 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 To inspect impeller condition 2 mech.
62 23AB-1541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1541 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 4 mech.
63 23AB-1720 FEMA-1 SAPCO MECH-SAP SPM 23AB-1720 Mechanical 1 Months FEMA Task 10 Check foundation spring vibration damper 2 mech.
20 Check bearing temperature 2 mech.
30 Inspect shaft seal tightness & damage 2 mech.
64 23AB-1720 FEMA-1 SAPCO MECH-SAP SPM 23AB-1720 Mechanical 3 Months FEMA Task 10 Regrease bearing and coupling 2 mech.
65 23AB-1720 FEMA-1 SAPCO MECH-SAP SPM 23AB-1720 Mechanical 6 Months FEMA Task 10 To inspect and clean suction filters 2 mech.
66 23AB-1720 FEMA-1 SAPCO MECH-SAP SPM 23AB-1720 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 To check rotor condition 2 mech.
67 23AB-1720 FEMA-1 SAPCO MECH-SAP SPM 23AB-1720 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
68 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
69 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.

358122780.xlsx Page 2 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 Inspect shaft seal tightness & damage 2 mech.
70 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 3 Months FEMA Task 10 Regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
71 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
30 To inspect impeller condition 2 mech.
72 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 4 mech.
73 23AB-1740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1740 Mechanical 5 Years FEMA Task 10 Complete overhauling for blower 8 mech.
74 23AB-2501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
75 23AB-2501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
76 23AB-2501 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
77 23AB-2502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
78 23AB-2502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
79 23AB-2502 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
80 23AB-2503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
81 23AB-2503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
82 23AB-2503 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
83 23AB-2504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
84 23AB-2504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
85 23AB-2504 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
86 23AB-2505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
87 23AB-2505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
88 23AB-2505 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
89 23AB-2506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
90 23AB-2506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
91 23AB-2506 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
92 23AB-2507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
93 23AB-2507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
94 23AB-2507 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
95 23AB-2508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
96 23AB-2508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
97 23AB-2508 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
98 23AB-2509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
99 23AB-2509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
100 23AB-2509 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
101 23AB-2510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.

358122780.xlsx Page 3 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
102 23AB-2510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
103 23AB-2510 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
104 23AB-2511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
105 23AB-2511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
106 23AB-2511 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
107 23AB-2512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
108 23AB-2512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
109 23AB-2512 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
110 23AB-2513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
111 23AB-2513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
112 23AB-2513 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
113 23AB-2514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
114 23AB-2514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
115 23AB-2514 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
116 23AB-2515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
117 23AB-2515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
118 23AB-2515 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
119 23AB-2516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
120 23AB-2516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
121 23AB-2516 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
122 23AB-2517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
123 23AB-2517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
124 23AB-2517 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
125 23AB-2530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
126 23AB-2530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
127 23AB-2530 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
128 23AB-2541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.
50 Visual check and cleaning of fan pulley 2 mech.
129 23AB-2541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
130 23AB-2541 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
131 23AB-2740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 35 Days FEMA Task 10 Check fan,wheel & shaft bolts tightness 2 mech.
20 Grease (Lubricate) bearing 2 mech.
30 Visual check & clean of fan inlet cone 2 mech.
40 Inspect belt condition 2 mech.

358122780.xlsx Page 4 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
50 Visual check and cleaning of fan pulley 2 mech.
132 23AB-2740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 6 Months FEMA Task 10 Check for alignment 2 mech.
133 23AB-2740 FEMA-1 SAPCO MECH-SAP SPM 23AB-1501 Mechanical 5 Years FEMA Task 10 Inspect for bearing 2 mech.
20 Inspect for shaft & if required replace 2 mech.
134 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
135 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
136 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
137 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 6 Months FEMA Task 10 To inspect & clean Demister of scrubber 2 mech.
138 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect scrubber Demister 2 mech.
30 Inspect blower suction & discharge pipe 2 mech.
40 To inspect impeller condition 2 mech.
139 23AB-7201 FEMA-1 SAPCO MECH-SAP SPM 23AB-7201 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
140 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
141 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
142 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
143 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 6 Months FEMA Task 10 To inspect & clean Demister of scrubber 2 mech.
144 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect scrubber Demister 2 mech.
30 Inspect blower suction & discharge pipe 2 mech.
40 To inspect impeller condition 2 mech.
145 23AB-7210 FEMA-1 SAPCO MECH-SAP SPM 23AB-7210 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
146 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
147 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 8 mech.
148 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
149 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 6 Months FEMA Task 10 To inspect & clean Demister of scrubber 2 mech.
150 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect scrubber Demister 2 mech.
30 Inspect blower suction & discharge pipe 2 mech.
40 To inspect impeller condition 2 mech.
151 23AB-7220 FEMA-1 SAPCO MECH-SAP SPM 23AB-7220 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
152 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
153 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
154 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
155 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 6 Months FEMA Task 10 To inspect & clean Demister of scrubber 2 mech.
156 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect scrubber Demister 2 mech.
30 Inspect blower suction & discharge pipe 2 mech.
40 To inspect impeller condition 2 mech.
157 23AB-7230 FEMA-1 SAPCO MECH-SAP SPM 23AB-7230 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
158 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
159 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
160 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 To do visual inspect for casing 2 mech.
161 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 6 Months FEMA Task 10 To inspect & clean Dust / Safety filters 2 mech.
162 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.
30 To inspect impeller condition 2 mech.
163 23AB-7240 FEMA-1 SAPCO MECH-SAP SPM 23AB-7240 Mechanical 5 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
164 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
165 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
166 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
167 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 6 Months FEMA Task 10 To inspect & clean Dust / Safety filters 2 mech.
168 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.
30 To inspect impeller condition 2 mech.
169 23AB-7250 FEMA-1 SAPCO MECH-SAP SPM 23AB-7250 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
170 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 35 Days FEMA Task 10 Check foundation spring vibration damper 2 mech.
171 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 1 Months FEMA Task 10 Check bearing temperature 2 mech.
20 Inspect shaft seal tightness & damage 2 mech.
172 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing 2 mech.
173 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 6 Months FEMA Task 10 To inspect & clean Dust / Safety filters 2 mech.
174 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.

358122780.xlsx Page 5 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 To inspect impeller condition 2 mech.
175 23AB-7260 FEMA-1 SAPCO MECH-SAP SPM 23AB-7260 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
176 23AB-7501 FEMA-1 SAPCO MECH-SAP SPM 23AB-7501 Mechanical 35 Days FEMA Task 10 Check vibration dampers & packing plates 2 mech.
20 To inspect & clean Dust filters 2 mech.
177 23AB-7501 FEMA-1 SAPCO MECH-SAP SPM 23AB-7501 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing & frame 2 mech.
40 Visual inspection of coupling and shaft 2 mech.
178 23AB-7501 FEMA-1 SAPCO MECH-SAP SPM 23AB-7501 Mechanical 6 Months FEMA Task 10 Inspect Packing plate tightness & damage 2 mech.
179 23AB-7501 FEMA-1 SAPCO MECH-SAP SPM 23AB-7501 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.
30 To inspect impeller condition 2 mech.
40 To inspect impeller condition 2 mech.
50 To inspect impeller condition 2 mech.
180 23AB-7501 FEMA-1 SAPCO MECH-SAP SPM 23AB-7501 Mechanical 5 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
181 23AB-7502 FEMA-1 SAPCO MECH-SAP SPM 23AB-7502 Mechanical 35 Days FEMA Task 10 Check vibration dampers & packing plates 2 mech.
20 To inspect & clean Dust filters 2 mech.
182 23AB-7502 FEMA-1 SAPCO MECH-SAP SPM 23AB-7502 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing & frame 2 mech.
40 Visual inspection of coupling and shaft 2 mech.
183 23AB-7502 FEMA-1 SAPCO MECH-SAP SPM 23AB-7502 Mechanical 6 Months FEMA Task 10 Inspect Packing plate tightness & damage 2 mech.
184 23AB-7502 FEMA-1 SAPCO MECH-SAP SPM 23AB-7502 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.
30 To inspect impeller condition 2 mech.
40 To inspect impeller condition 2 mech.
50 To inspect impeller condition 2 mech.
185 23AB-7502 FEMA-1 SAPCO MECH-SAP SPM 23AB-7502 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
186 23AB-7511 FEMA-1 SAPCO MECH-SAP SPM 23AB-7511 Mechanical 35 Days FEMA Task 10 Check vibration dampers & packing plates 2 mech.
20 To inspect & clean Dust filters 2 mech.
187 23AB-7511 FEMA-1 SAPCO MECH-SAP SPM 23AB-7511 Mechanical 3 Months FEMA Task 10 Check and regrease bearing and coupling 2 mech.
20 Check bearing temperature 2 mech.
30 To do visual inspect for casing & frame 2 mech.
40 Visual inspection of coupling and shaft 2 mech.
188 23AB-7511 FEMA-1 SAPCO MECH-SAP SPM 23AB-7511 Mechanical 6 Months FEMA Task 10 Inspect Packing plate tightness & damage 2 mech.
189 23AB-7511 FEMA-1 SAPCO MECH-SAP SPM 23AB-7511 Mechanical 1 Years FEMA Task 10 Casing and foundation frame inspection 2 mech.
20 Inspect blower suction & discharge pipe 2 mech.
30 To inspect impeller condition 2 mech.
40 To inspect impeller condition 2 mech.
50 To inspect impeller condition 2 mech.
190 23AB-7511 FEMA-1 SAPCO MECH-SAP SPM 23AB-7511 Mechanical 3 Years FEMA Task 10 Check condition of bearing and coupling 2 mech.
191 23DV-1660 FEMA-1 SAPCO MECH-SAP SPM 23DV-1660 Mechanical 3 Months FEMA Task 10 To inspect valve sealing 2 instrument
192 23DV-1660 FEMA-1 SAPCO MECH-SAP SPM 23DV-1660 Mechanical 6 Months FEMA Task 10 To inspect limit bolt condition 2 instrument
20 To inspect limit pin condition 2 mech.
193 23E-1100 FEMA-1 SAPCO MECH-SAP SPM 23E-1100 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
194 23E-1100 FEMA-1 SAPCO MECH-SAP SPM 23E-1100 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
195 23E-1100 FEMA-1 SAPCO MECH-SAP SPM 23E-1100 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
196 23E-1101 FEMA-1 SAPCO MECH-SAP SPM 23E-1101 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
197 23E-1101 FEMA-1 SAPCO MECH-SAP SPM 23E-1101 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
198 23E-1101 FEMA-1 SAPCO MECH-SAP SPM 23E-1101 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
199 23E-1101 FEMA-1 SAPCO MECH-SAP SPM 23E-1101 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
200 23E-1101 FEMA-1 SAPCO MECH-SAP SPM 23E-1101 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
201 23E-1102 FEMA-1 SAPCO MECH-SAP SPM 23E-1102 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
202 23E-1102 FEMA-1 SAPCO MECH-SAP SPM 23E-1102 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
203 23E-1102 FEMA-1 SAPCO MECH-SAP SPM 23E-1102 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
204 23E-1103 FEMA-1 SAPCO MECH-SAP SPM 23E-1103 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
205 23E-1103 FEMA-1 SAPCO MECH-SAP SPM 23E-1103 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
206 23E-1103 FEMA-1 SAPCO MECH-SAP SPM 23E-1103 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
207 23E-1725 FEMA-1 SAPCO MECH-SAP SPM 23E-1725 Mechanical 6 Months FEMA Task 10 Check condition of gasket 2 mech.
20 Check condition of plate exchangers 2 mech.
30 Inspecte CW pumps strainer 2 mech.
40 Check function of exchangers for DA & IA 2 mech.
50 Inspect Hot air lines and inlet nozzles 2 mech.
60 Inspection and cleaning of vent lines 2 mech.
208 23E-1725 FEMA-1 SAPCO MECH-SAP SPM 23E-1725 Mechanical 2 Years FEMA Task 10 Check condition of plate exchangers 2 mech.
20 Check Performance of plate type HE 2 mech.
209 23E-1725 FEMA-1 SAPCO MECH-SAP SPM 23E-1725 Mechanical 5 Years FEMA Task 10 Overhauling of CW pump to be done 8 mech.
210 23E-4001 FEMA-1 SAPCO MECH-SAP SPM 23E-4001 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
211 23E-4001 FEMA-1 SAPCO MECH-SAP SPM 23E-4001 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
212 23E-4001 FEMA-1 SAPCO MECH-SAP SPM 23E-4001 Mechanical 1 Years FEMA Task 10 Backflush heat exchanger 2 mech.
213 23E-4001 FEMA-1 SAPCO MECH-SAP SPM 23E-4001 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
214 23E-7201 FEMA-1 SAPCO MECH-SAP SPM 23E-7201 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
215 23E-7201 FEMA-1 SAPCO MECH-SAP SPM 23E-7201 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
216 23E-7201 FEMA-1 SAPCO MECH-SAP SPM 23E-7201 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
217 23E-7210 FEMA-1 SAPCO MECH-SAP SPM 23E-7210 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
218 23E-7210 FEMA-1 SAPCO MECH-SAP SPM 23E-7210 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
219 23E-7210 FEMA-1 SAPCO MECH-SAP SPM 23E-7210 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
220 23E-7220 FEMA-1 SAPCO MECH-SAP SPM 23E-7220 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
221 23E-7220 FEMA-1 SAPCO MECH-SAP SPM 23E-7220 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
222 23E-7220 FEMA-1 SAPCO MECH-SAP SPM 23E-7220 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
223 23E-7230 FEMA-1 SAPCO MECH-SAP SPM 23E-7230 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
224 23E-7230 FEMA-1 SAPCO MECH-SAP SPM 23E-7230 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.

358122780.xlsx Page 6 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
225 23E-7230 FEMA-1 SAPCO MECH-SAP SPM 23E-7230 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
226 23E-9001 FEMA-1 SAPCO MECH-SAP SPM 23E-9001 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
227 23E-9001 FEMA-1 SAPCO MECH-SAP SPM 23E-9001 Mechanical 3 Months FEMA Task 10 Check and apply lubrication for bolts 2 mech.
228 23E-9001 FEMA-1 SAPCO MECH-SAP SPM 23E-9001 Mechanical 6 Months FEMA Task 10 Backflush heat exchanger with HOT water 2 mech.
229 23E-9001 FEMA-1 SAPCO MECH-SAP SPM 23E-9001 Mechanical 2 Years FEMA Task 10 To check all plates and gaskets 2 mech.
230 23EJ-4001 FEMA-1 SAPCO MECH-SAP SPM 23EJ-4001 Mechanical 1 Years FEMA Task 10 Inspection and cleaning of Ejector 2 mech.
231 23EX-1410 FEMA-1 SAPCO MECH-SAP SPM 23EX-1410 Mechanical 35 Days FEMA Task 10 Check condition of Hole plate 2 mech.
20 Check condition of knife 2 mech.
30 Check for all holding bolts 2 mech.
40 Check oil level and top up 2 mech.
50 Check oil level and top up if required 2 mech.
60 Clean edge of drive hexagon 2 mech.
70 Clean edge of drive hexagon 2 mech.
80 Inspect condition of hose for leak etc 2 mech.
90 Inspect coupling unit 2 mech.
100 Inspect fora any oil leakages and attend 2 mech.
110 Cooler visual inspect & external clean 2 mech.
120 To grease rail motor transmission chain 2 mech.
130 To grease drive of discharge worm 2 mech.
140 Visual inspection of gear box 2 mech.
232 23EX-1410 FEMA-1 SAPCO MECH-SAP SPM 23EX-1410 Mechanical 6 Months FEMA Task 10 Inspect condition & tightness of hose 2 mech.
20 Replace oil with fresh oil 2 mech.
233 23EX-1410 FEMA-1 SAPCO MECH-SAP SPM 23EX-1410 Mechanical 1 Years FEMA Task 10 Dust filters to be cleaned 2 mech.
20 Replace oil with fresh oil 2 mech.
30 To clean & check condition of chain 2 mech.
234 23EX-1410 FEMA-1 SAPCO MECH-SAP SPM 23EX-1410 Mechanical 3 Years FEMA Task 10 Inspect of hose & replace if required 2 mech.
235 23EX-1410 FEMA-1 SAPCO MECH-SAP SPM 23EX-1410 Mechanical 5 Years FEMA Task 10 Check for condition of coupling unit 2 mech.
20 Gear box overhauling to be done 8 mech.
30 Inspect drive screw of discharge worm 2 mech.
40 Inspect of hose & replace if required 2 mech.
236 23EX-1420 FEMA-1 SAPCO MECH-SAP SPM 23EX-1420 Mechanical 35 Days FEMA Task 10 Check condition of Hole plate 2 mech.
20 Check condition of knife 2 mech.
30 Check for all holding bolts 2 mech.
40 Check oil level and top up 2 mech.
50 Check oil level and top up if required 2 mech.
60 Clean edge of drive hexagon 2 mech.
70 Clean edge of drive hexagon 2 mech.
80 Inspect condition of hose for leak etc 2 mech.
90 Inspect coupling unit 2 mech.
100 Inspect fora any oil leakages and attend 2 mech.
110 Cooler visual inspect & external clean 2 mech.
120 To grease rail motor transmission chain 2 mech.
130 To grease drive of discharge worm 2 mech.
140 Visual inspection of gear box 2 mech.
237 23EX-1420 FEMA-1 SAPCO MECH-SAP SPM 23EX-1420 Mechanical 6 Months FEMA Task 10 Inspect condition & tightness of hose 2 mech.
20 Replace oil with fresh oil 2 mech.
238 23EX-1420 FEMA-1 SAPCO MECH-SAP SPM 23EX-1420 Mechanical 1 Years FEMA Task 10 Dust filters to be cleaned 2 mech.
20 To clean & check condition of chain 2 mech.
239 23EX-1420 FEMA-1 SAPCO MECH-SAP SPM 23EX-1420 Mechanical 3 Years FEMA Task 10 Inspect of hose & replace if required 2 mech.
240 23EX-1420 FEMA-1 SAPCO MECH-SAP SPM 23EX-1420 Mechanical 5 Years FEMA Task 10 Check for condition of coupling unit 2 mech.
20 Gear box overhauling to be done 8 mech.
30 Inspect drive screw of discharge worm 2 mech.
40 Inspect of hose & replace if required 2 mech.
241 23EX-2410 FEMA-1 SAPCO MECH-SAP SPM 23EX-2410 Mechanical 35 Days FEMA Task 10 Check condition of Hole plate 2 mech.
20 Check condition of knife 2 mech.
30 Check for all holding bolts 2 mech.
40 Check oil level and top up 2 mech.
50 Check oil level and top up if required 2 mech.
60 Clean edge of drive hexagon 2 mech.
70 Clean edge of drive hexagon 2 mech.
80 Inspect condition of hose for leak etc 2 mech.
90 Inspect coupling unit 2 mech.
100 Inspect fora any oil leakages and attend 2 mech.
110 Cooler visual inspect & external clean 2 mech.
120 To grease rail motor transmission chain 2 mech.
130 To grease drive of discharge worm 2 mech.
140 Visual inspection of gear box 2 mech.
242 23EX-2410 FEMA-1 SAPCO MECH-SAP SPM 23EX-2410 Mechanical 6 Months FEMA Task 10 Inspect condition & tightness of hose 2 mech.
20 Replace oil with fresh oil 2 mech.
243 23EX-2410 FEMA-1 SAPCO MECH-SAP SPM 23EX-2410 Mechanical 1 Years FEMA Task 10 Dust filters to be cleaned 2 mech.
20 To clean & check condition of chain 2 mech.
244 23EX-2410 FEMA-1 SAPCO MECH-SAP SPM 23EX-2410 Mechanical 3 Years FEMA Task 10 Inspect of hose & replace if required 2 mech.
245 23EX-2410 FEMA-1 SAPCO MECH-SAP SPM 23EX-2410 Mechanical 5 Years FEMA Task 10 Check for condition of coupling unit 2 mech.
20 Gear box overhauling to be done 8 mech.
30 Inspect drive screw of discharge worm 2 mech.
40 Inspect of hose & replace if required 2 mech.
246 23EX-2420 FEMA-1 SAPCO MECH-SAP SPM 23EX-2420 Mechanical 35 Days FEMA Task 10 Check condition of Hole plate 2 mech.
20 Check condition of knife 2 mech.
30 Check for all holding bolts 2 mech.
40 Check oil level and top up 2 mech.
50 Check oil level and top up if required 2 mech.
60 Clean edge of drive hexagon 2 mech.

358122780.xlsx Page 7 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
70 Clean edge of drive hexagon 2 mech.
80 Inspect condition of hose for leak etc 2 mech.
90 Inspect coupling unit 2 mech.
100 Inspect fora any oil leakages and attend 2 mech.
110 Cooler visual inspect & external clean 2 mech.
120 To grease rail motor transmission chain 2 mech.
130 To grease drive of discharge worm 2 mech.
140 Visual inspection of gear box 2 mech.
247 23EX-2420 FEMA-1 SAPCO MECH-SAP SPM 23EX-2420 Mechanical 6 Months FEMA Task 10 Inspect condition & tightness of hose 2 mech.
20 Replace oil with fresh oil 2 mech.
248 23EX-2420 FEMA-1 SAPCO MECH-SAP SPM 23EX-2420 Mechanical 1 Years FEMA Task 10 Dust filters to be cleaned 2 mech.
20 To clean & check condition of chain 2 mech.
249 23EX-2420 FEMA-1 SAPCO MECH-SAP SPM 23EX-2420 Mechanical 3 Years FEMA Task 10 Inspect of hose & replace if required 2 mech.
250 23EX-2420 FEMA-1 SAPCO MECH-SAP SPM 23EX-2420 Mechanical 5 Years FEMA Task 10 Check for condition of coupling unit 2 mech.
20 Gear box overhauling to be done 8 mech.
30 Inspect drive screw of discharge worm 2 mech.
40 Inspect of hose & replace if required 2 mech.
251 23F-1601 FEMA-1 SAPCO MECH-SAP SPM 23F-1601 Mechanical 3 Months FEMA Task 10 Inspect & clean Dust & safety filters 2 mech.
252 23F-1601 FEMA-1 SAPCO MECH-SAP SPM 23F-1601 Mechanical 6 Months FEMA Task 10 Inspect receiver buffer & bottom portion 2 mech.
253 23F-1610 FEMA-1 SAPCO MECH-SAP SPM 23F-1610 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 3 mech.
20 To check and replace screen 3 mech.
30 To check rubber spring elements 3 mech.
40 To check hose condition 3 mech.
50 To check the ball size 3 mech.
60 To check condition of pulley 3 mech.
70 To check the tension 3 mech.
80 To inspect clamp condition & retight 3 mech.
90 To inspect the seal condition 3 mech.
100 To regrease the bearing 3 mech.
254 23F-1610 FEMA-1 SAPCO MECH-SAP SPM 23F-1610 Mechanical 2 Months FEMA Task 10 To check condition of belt 3 mech.
255 23F-1610 FEMA-1 SAPCO MECH-SAP SPM 23F-1610 Mechanical 6 Months FEMA Task 10 To check counterweight settings 6 mech.
256 23F-1610 FEMA-1 SAPCO MECH-SAP SPM 23F-1610 Mechanical 1 Years FEMA Task 10 To replace the V-belt 2 mech.
257 23F-1610 FEMA-1 SAPCO MECH-SAP SPM 23F-1610 Mechanical 5 Years FEMA Task 10 To replace the bearing 72 mech.
20 To replace the shaft 72 mech.
258 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
259 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
260 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
261 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 6 Months FEMA Task 10 To check counterweight settings 6 mech.
262 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 1 Years FEMA Task 10 To replace the V-belt 6 mech.
263 23F-1611 FEMA-1 SAPCO MECH-SAP SPM 23F-1611 Mechanical 5 Years FEMA Task 10 To replace the bearing 72 mech.
20 To replace the shaft 72 mech.
264 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
265 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
266 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
267 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 6 Months FEMA Task 10 To check counterweight settings 6 mech.
268 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 1 Years FEMA Task 10 To replace the V-belt 2 mech.
269 23F-1612 FEMA-1 SAPCO MECH-SAP SPM 23F-1612 Mechanical 5 Years FEMA Task 10 To replace the bearing 2 mech.
20 To replace the shaft 72 mech.
270 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 35 Days FEMA Task 10 To inspect hose condition 72 mech.
271 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
272 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
273 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 6 Months FEMA Task 10 To check counterweight settings 2 mech.
274 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 1 Years FEMA Task 10 To replace the V-belt 2 mech.
275 23F-1613 FEMA-1 SAPCO MECH-SAP SPM 23F-1613 Mechanical 5 Years FEMA Task 10 To replace the bearing 72 mech.
20 To replace the shaft 72 mech.
276 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
277 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.

358122780.xlsx Page 8 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
278 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
279 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 6 Months FEMA Task 10 To check counterweight settings 6 mech.
280 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 1 Years FEMA Task 10 To replace the V-belt 2 mech.
281 23F-1620 FEMA-1 SAPCO MECH-SAP SPM 23F-1620 Mechanical 5 Years FEMA Task 10 To replace the bearing 72 mech.
20 To replace the shaft 72 mech.
282 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
283 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
284 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
285 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 6 Months FEMA Task 10 To check counterweight settings 2 mech.
286 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 1 Years FEMA Task 10 To replace the V-belt 2 mech.
287 23F-1621 FEMA-1 SAPCO MECH-SAP SPM 23F-1621 Mechanical 5 Years FEMA Task 10 To replace the bearing 2 mech.
20 To replace the shaft 72 mech.
288 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
289 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
290 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 2 Months FEMA Task 10 To check condition of belt 2 mech.
291 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 6 Months FEMA Task 10 To check counterweight settings 6 mech.
292 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 1 Years FEMA Task 10 To replace the V-belt 6 mech.
293 23F-1622 FEMA-1 SAPCO MECH-SAP SPM 23F-1622 Mechanical 5 Years FEMA Task 10 To replace the bearing 72 mech.
20 To replace the shaft 72 mech.
294 23F-1624 FEMA-1 SAPCO MECH-SAP SPM 23F-1624 Mechanical 3 Months FEMA Task 10 Inspect & clean Dust & safety filters 4 mech.
295 23F-1624 FEMA-1 SAPCO MECH-SAP SPM 23F-1624 Mechanical 6 Months FEMA Task 10 Inspect receiver buffer & bottom portion 2 mech.
296 23F-1740 FEMA-1 SAPCO MECH-SAP SPM 23F-1740 Mechanical 3 Months FEMA Task 10 Clean Dust Filter and safety filter 5 mech.
20 Filter to be opened and cleaned 5 mech.
297 23F-2601 FEMA-1 SAPCO MECH-SAP SPM 23F-2601 Mechanical 3 Months FEMA Task 10 Inspect & clean Dust & safety filters 2 mech.
298 23F-2601 FEMA-1 SAPCO MECH-SAP SPM 23F-2601 Mechanical 6 Months FEMA Task 10 Inspect receiver buffer & bottom portion 2 mech.
299 23F-2740 FEMA-1 SAPCO MECH-SAP SPM 23F-2740 Mechanical 3 Months FEMA Task 10 Clean Dust Filter and safety filter 5 mech.
20 Filter to be opened and cleaned 5 mech.
300 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect chain condition. 2 mech.
30 To inspect base bolts tightness 2 mech.
40 To lubricate the chain. 2 mech.
301 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
302 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
303 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 2 mech.
304 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
305 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To inspect the condition of ball bearing 2 mech.
306 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
307 23FH-1540 FEMA-1 SAPCO MECH-SAP SPM 23FH-1540 Mechanical 5 Years FEMA Task 10 To check rotary & replace O-ring &spacer 2 mech.
20 To overhaul rotary feeder. 2 mech.
30 To perform overhauling work 2 mech.
40 To perform overhauling work. 2 mech.
50 To replace feeder & motor chain wheel 2 mech.
60 To replace gear box 2 mech.
70 To replace the deepgrove ball bearing 2 mech.
308 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To inspect base bolts tightness 2 mech.
309 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
310 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 2 mech.
311 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
312 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
313 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 2 mech.
20 To perform overhauling work 2 mech.
30 To perform overhauling work. 2 mech.
40 To replace feeder & motor chain wheel 2 mech.
50 To replace gear box 2 mech.
314 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.

358122780.xlsx Page 9 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 To lubricate the chain. 2 mech.
315 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
316 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
317 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
318 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
319 23FH-1601 FEMA-1 SAPCO MECH-SAP SPM 23FH-1601 Mechanical 5 Years FEMA Task 10 To replace the deepgrove ball bearing 2 mech.
320 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect chain condition. 2 mech.
30 To inspect base bolts tightness 2 mech.
40 To lubricate the chain. 2 mech.
321 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
322 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
323 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 2 mech.
324 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
325 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
30 To inspect the condition of ball bearing 2 mech.
326 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
327 23FH-1602 FEMA-1 SAPCO MECH-SAP SPM 23FH-1602 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work 4 mech.
30 To perform overhauling work. 4 mech.
40 To replace feeder & motor chain wheel 4 mech.
50 To replace gear box 4 mech.
60 To replace the deepgrove ball bearing 4 mech.
328 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
329 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
330 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 2 mech.
331 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
332 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
333 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
334 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To replace feeder & motor chain wheel 4 mech.
30 To replace gear box 2 mech.
335 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
336 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
337 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
338 23FH-1622 FEMA-1 SAPCO MECH-SAP SPM 23FH-1622 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace the deepgrove ball bearing 4 mech.
339 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
340 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 3 Months FEMA Task 10 To check alignment & realign if required 2 mech.
20 To check the condition of rotary feeder. 2 mech.
341 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
342 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
343 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
30 To inspect the condition of ball bearing 2 mech.
344 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
345 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To replace feeder & motor chain wheel 4 mech.
30 To replace gear box 4 mech.
40 To replace the deepgrove ball bearing 4 mech.
346 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
347 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
348 23FH-1624 FEMA-1 SAPCO MECH-SAP SPM 23FH-1624 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace the deepgrove ball bearing 4 mech.
349 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
350 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
351 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
352 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
353 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
354 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
355 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To replace feeder & motor chain wheel 4 mech.
30 To replace gear box 4 mech.
356 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
357 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
358 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
359 23FH-1650 FEMA-1 SAPCO MECH-SAP SPM 23FH-1650 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.

358122780.xlsx Page 10 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 To perform overhauling work. 4 mech.
30 To replace the deepgrove ball bearing 4 mech.
360 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
361 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
362 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
363 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
364 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 1 Years FEMA Task 10 To ensure product line free of scaling 2 mech.
20 To replace gear box oil 2 mech.
365 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To inspect the condition of ball bearing 2 mech.
366 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
367 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 5 Years FEMA Task 10 To check rotary & replace O-ring &spacer 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace feeder & motor chain wheel 4 mech.
40 To replace gear box 4 mech.
50 To replace shaft sleeve & support ring 4 mech.
60 To replace the deepgrove ball bearing 4 mech.
368 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
369 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
370 23FH-1660 FEMA-1 SAPCO MECH-SAP SPM 23FH-1660 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work 4 mech.
371 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To inspect base bolts tightness 2 mech.
372 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
373 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
374 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
375 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
376 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
377 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace feeder & motor chain wheel 4 mech.
40 To replace gear box 4 mech.
378 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To lubricate the chain. 2 mech.
379 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
380 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
381 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
382 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
383 23FH-1725 FEMA-1 SAPCO MECH-SAP SPM 23FH-1725 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace shaft sleeve & support ring 4 mech.
40 To replace the deepgrove ball bearing 4 mech.
384 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
385 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
386 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
387 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
388 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
389 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
390 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To replace feeder & motor chain wheel 4 mech.
30 To replace gear box 4 mech.
391 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
392 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
393 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
394 23FH-1830 FEMA-1 SAPCO MECH-SAP SPM 23FH-1830 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace deepgrove ball bearing & seal 4 mech.
395 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect chain condition. 2 mech.
30 To inspect base bolts tightness 2 mech.
40 To lubricate the chain. 2 mech.
396 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
397 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
398 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
399 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
400 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
30 To inspect the condition of ball bearing 2 mech.
401 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
402 23FH-2540 FEMA-1 SAPCO MECH-SAP SPM 23FH-2540 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work 4 mech.
30 To perform overhauling work. 4 mech.
40 To replace feeder & motor chain wheel 4 mech.
50 To replace gear box 4 mech.

358122780.xlsx Page 11 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
60 To replace the deepgrove ball bearing 4 mech.
403 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect base bolts tightness 2 mech.
404 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
405 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
406 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
407 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
408 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
409 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To replace feeder & motor chain wheel 4 mech.
30 To replace gear box 4 mech.
410 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To lubricate the chain. 2 mech.
411 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
412 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
413 23FH-2601 FEMA-1 SAPCO MECH-SAP SPM 23FH-2601 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace the deepgrove ball bearing 4 mech.
414 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To inspect chain condition. 2 mech.
30 To inspect base bolts tightness 2 mech.
40 To lubricate the chain. 2 mech.
415 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
416 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
417 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
418 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
419 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
30 To inspect the condition of ball bearing 2 mech.
420 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
20 To replace the chain. 2 mech.
421 23FH-2602 FEMA-1 SAPCO MECH-SAP SPM 23FH-2602 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work 4 mech.
30 To perform overhauling work. 4 mech.
40 To replace feeder & motor chain wheel 4 mech.
50 To replace gear box 4 mech.
60 To replace the deepgrove ball bearing 4 mech.
422 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To inspect base bolts tightness 2 mech.
423 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
424 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
425 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
426 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
427 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
428 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace feeder & motor chain wheel 4 mech.
40 To replace gear box 4 mech.
429 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To lubricate the chain. 2 mech.
430 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
431 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
432 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
433 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
434 23FH-4272 FEMA-1 SAPCO MECH-SAP SPM 23FH-4272 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace shaft sleeve & support ring 4 mech.
40 To replace the deepgrove ball bearing 4 mech.
435 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To inspect base bolts tightness 2 mech.
436 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
437 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
438 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
439 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
440 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
441 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace feeder & motor chain wheel 4 mech.
40 To replace gear box 4 mech.
442 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To lubricate the chain. 2 mech.
443 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
444 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
445 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
446 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
447 23FH-4275 FEMA-1 SAPCO MECH-SAP SPM 23FH-4275 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace shaft sleeve & support ring 4 mech.

358122780.xlsx Page 12 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
40 To replace the deepgrove ball bearing 4 mech.
448 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 1 Months FEMA Task 10 To inspect chain condition. 2 mech.
20 To inspect base bolts tightness 2 mech.
449 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
450 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 4 Months FEMA Task 10 To check oil level & top up if required 2 mech.
451 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 1 Weeks FEMA Task 10 To monitor gearbox lube oil leaks 1 mech.
452 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 2 Years FEMA Task 10 To check condition of gear box 2 mech.
20 To check rotary & replace O-ring &spacer 2 mech.
453 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 3 Years FEMA Task 10 To replace the chain. 2 mech.
454 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 5 Years FEMA Task 10 To overhaul rotary feeder. 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace feeder & motor chain wheel 4 mech.
40 To replace gear box 4 mech.
455 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 1 Months FEMA Task 10 To check chain looseness 2 mech.
20 To lubricate the chain. 2 mech.
456 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 3 Months FEMA Task 10 To check the condition of rotary feeder. 2 mech.
457 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 1 Years FEMA Task 10 To replace gear box oil 2 mech.
458 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 2 Years FEMA Task 10 To inspect the condition of ball bearing 2 mech.
459 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 3 Years FEMA Task 10 To inspect Oil seals visually 2 mech.
460 23FH-4470 FEMA-1 SAPCO MECH-SAP SPM 23FH-4470 Mechanical 5 Years FEMA Task 10 To perform overhauling work 4 mech.
20 To perform overhauling work. 4 mech.
30 To replace shaft sleeve & support ring 4 mech.
40 To replace the deepgrove ball bearing 4 mech.
461 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 35 Days FEMA Task 10 Check and realign scrapper 4 mech.
20 Check rollers and idlers 4 mech.
30 Check pulleys, rollers condition 4 mech.
40 Check oil level and top up if required 4 mech.
50 Clean and apply lubrication for bearing 4 mech.
60 Clean dust tray & adjust scrapper 4 mech.
70 Visual checking and cleaning for pulley 4 mech.
80 Visual checking and cleaning of idller 4 mech.
90 Visual checking and cleaning of rollers 4 mech.
100 Visual checking for bearing operation 4 mech.
110 Visual checking for pulley 4 mech.
120 Visual inspection rubber lining 4 mech.
130 Visual inspect & condition of gear box 4 mech.
462 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 1 Months FEMA Task 10 Check overall condition of belt 1 mech.
463 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 3 Months FEMA Task 10 Check for overall condition of belt 1 mech.
464 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 1 Weeks FEMA Task 10 Check proper rotation for idllers 1 mech.
20 Inspect condition of collection belt 1 mech.
465 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 2 Weeks FEMA Task 10 Check scrapper 2 mech.
20 Check belt condition & bolts tightness 2 mech.
30 Visual inspection for any oil leak 2 mech.
40 Inspect condition of collection belt 2 mech.
466 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 4 Years FEMA Task 10 Replace with fresh oil 2 mech.
467 23FX-1400 FEMA-1 SAPCO MECH-SAP SPM 23FX-1400 Mechanical 5 Years FEMA Task 10 Check and if required replace bearing 4 mech.
20 Check and if required replace idller 4 mech.
30 Check and if required replace pulley 4 mech.
40 Check and if required replace rollers 4 mech.
468 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 35 Days FEMA Task 10 Check and realign scrapper 4 mech.
20 Check rollers and idlers 4 mech.
30 Check pulleys, rollers condition 4 mech.
40 Check oil level and top up if required 4 mech.
50 Clean and apply lubrication for bearing 4 mech.
60 Clean dust tray & adjust scrapper 4 mech.
70 Visual checking and cleaning for pulley 4 mech.
80 Visual checking and cleaning of idller 4 mech.
90 Visual checking and cleaning of rollers 4 mech.
100 Visual checking for bearing operation 4 mech.
110 Visual checking for pulley 4 mech.
120 Visual inspect & rubber lining condition 4 mech.
130 Visual inspect & condition of gear box 4 mech.
469 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 1 Months FEMA Task 10 Check overall condition of belt 1 mech.
470 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 3 Months FEMA Task 10 Check for overall condition of belt 1 mech.
471 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 1 Weeks FEMA Task 10 Check proper rotation for idllers 1 mech.
20 Inspect condition of collection belt 1 mech.
472 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 2 Weeks FEMA Task 10 Check scrapper 2 mech.
20 Check belt condition & bolts tightness 2 mech.
30 Visual inspection for any oil leak 2 mech.
40 Inspect condition of collection belt 2 mech.
473 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 4 Years FEMA Task 10 Replace with fresh oil 2 mech.
474 23FX-1401 FEMA-1 SAPCO MECH-SAP SPM 23FX-1401 Mechanical 5 Years FEMA Task 10 Check and if required replace bearing 4 mech.
20 Check and if required replace idller 4 mech.
30 Check and if required replace pulley 4 mech.
40 Check and if required replace rollers 4 mech.
475 23FX-1410 FEMA-1 SAPCO MECH-SAP SPM 23FX-1410 Mechanical 1 Months FEMA Task 10 Check and tight foundation bolts 2 mech.
20 Check for proper chain tightness 2 mech.
30 Clean and lubricate sproket 2 mech.
40 Inspect & check for tensioning of chain 2 mech.
50 Inspect and lubricate bearing 2 mech.
60 Visual inspection for abnormality & leak 2 mech.
70 Visual inspect & clean of lub chain 2 mech.

358122780.xlsx Page 13 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
80 Visual inspect & clean of lubr sproket 2 mech.
90 Inspect alignment 2 mech.
476 23FX-1410 FEMA-1 SAPCO MECH-SAP SPM 23FX-1410 Mechanical 3 Months FEMA Task 10 Top up oil and check for any leak 2 mech.
20 Inspect chain overall condition 2 mech.
30 Inspect condition of sproket 2 mech.
40 Visual inspection of oil seal 2 mech.
477 23FX-1410 FEMA-1 SAPCO MECH-SAP SPM 23FX-1410 Mechanical 1 Years FEMA Task 10 Replace Gearbox oil with fresh oil 2 mech.
20 Visual inspect internals of screw 2 mech.
478 23FX-1410 FEMA-1 SAPCO MECH-SAP SPM 23FX-1410 Mechanical 5 Years FEMA Task 10 Visual inspect of bearing 2 mech.
479 23FX-1410 FEMA-1 SAPCO MECH-SAP SPM 23FX-1410 Mechanical 10 Years FEMA Task 10 Replace Gearbox & do O/H of old gearbox 4 mech.
480 23FX-1420 FEMA-1 SAPCO MECH-SAP SPM 23FX-1420 Mechanical 1 Months FEMA Task 10 Check and tight foundation bolts 2 mech.
20 Check for proper chain tightness 2 mech.
30 Clean and lubricate sproket 2 mech.
40 Inspect & check for tensioning of chain 2 mech.
50 Inspect and lubricate bearing 2 mech.
60 Visual inspection for abnormality & leak 2 mech.
70 Visual inspect & clean of lub chain 2 mech.
80 Visual inspect & clean of lubr sproket 2 mech.
90 Inspect alignment 2 mech.
481 23FX-1420 FEMA-1 SAPCO MECH-SAP SPM 23FX-1420 Mechanical 3 Months FEMA Task 10 Top up oil and check for any leak 2 mech.
20 Inspect chain overall condition 2 mech.
30 Inspect condition of sproket 2 mech.
40 Visual inspection of oil seal 2 mech.
482 23FX-1420 FEMA-1 SAPCO MECH-SAP SPM 23FX-1420 Mechanical 1 Years FEMA Task 10 Replace Gearbox oil with fresh oil 2 mech.
20 Visual inspect internals of screw 2 mech.
483 23FX-1420 FEMA-1 SAPCO MECH-SAP SPM 23FX-1420 Mechanical 5 Years FEMA Task 10 Visual inspect of bearing 2 mech.
484 23FX-1420 FEMA-1 SAPCO MECH-SAP SPM 23FX-1420 Mechanical 10 Years FEMA Task 10 Replace Gearbox & do O/H of old gearbox 8 mech.
485 23FX-1500 FEMA-1 SAPCO MECH-SAP SPM 23FX-1500 Mechanical 35 Days FEMA Task 10 Inspect & clean Belt drum 2 mech.
20 Inspect & clean belt guide 2 mech.
30 Inspect and clean belt rod and rod cup 2 mech.
40 Inspect & clean Feeder belt & rollers 2 mech.
50 Inspect & clean Feeder belt 2 mech.
60 Inspect & clean Head pulley 2 mech.
70 Inspect motion plate, side skirting 2 mech.
80 Inspect & clean Scrapper plate 2 mech.
90 Inspect and clean Tesnioner plate 2 mech.
100 Inspect & retight holding bolts & washer 2 mech.
110 Inspect holding bolts for Belt Drum 2 mech.
120 Inspect holding bolts for Belt GUIDE 2 mech.
130 Inspect holding bolts for Head Pulley 2 mech.
140 Inspect motion plate & base spacer bolts 2 mech.
150 Inspect and retight rod and rod cup 2 mech.
160 Inspect of gearbox & top up oil 2 mech.
170 Inspect of scrapper supports 2 mech.
180 Inspect of scrapper supports 2 mech.
190 Replace oil for Gear Box 2 mech.
486 23FX-1500 FEMA-1 SAPCO MECH-SAP SPM 23FX-1500 Mechanical 2 Years FEMA Task 10 Inspect of Tensioner plate 2 mech.
20 Replace belt every 2 years (If required) 2 mech.
487 23FX-1500 FEMA-1 SAPCO MECH-SAP SPM 23FX-1500 Mechanical 5 Years FEMA Task 10 Overhauling of Gear box to be done 4 mech.
488 23FX-1501 FEMA-1 SAPCO MECH-SAP SPM 23FX-1501 Mechanical 210 Days FEMA Task 10 Check alignment for coupling 2 mech.
489 23FX-1501 FEMA-1 SAPCO MECH-SAP SPM 23FX-1501 Mechanical 1 Months FEMA Task 10 Check screw & outlet scaling of pipes 2 mech.
20 Inspect condition of bearing housing 2 mech.
30 Check and inspect condition of coupling 2 mech.
40 Check and tight holding bolts 2 mech.
50 Check oil level 2 mech.
60 Check gearbox oil system ventilation 2 mech.
70 Clean and inspect gland packing 2 mech.
80 Clean and lubricate bearing 2 mech.
90 Inspect and clean internals of screw 2 mech.
100 Inspect foundation & holding bolts 2 mech.
490 23FX-1501 FEMA-1 SAPCO MECH-SAP SPM 23FX-1501 Mechanical 2 Years FEMA Task 10 2 mech.
20 Check gland packing 2 mech.
30 Replace gearbox oil 2 mech.
491 23FX-1501 FEMA-1 SAPCO MECH-SAP SPM 23FX-1501 Mechanical 5 Years FEMA Task 10 Replace with new gearbox & O/H old G/B 8 mech.
492 23FX-1622 FEMA-1 SAPCO MECH-SAP SPM 23FX-1622 Mechanical 1 Months FEMA Task 10 Check screw & outlet scaling of pipes 2 mech.
20 Inspect condition of bearing housing 2 mech.
30 Check and inspect condition of coupling 2 mech.
40 Check and tight holding bolts 2 mech.
50 Check oil level 2 mech.
60 Check gearbox oil system ventilation 2 mech.
70 Clean and lubricate bearing 2 mech.
80 Clean gland packing condition 2 mech.
90 Inspect and clean internals of screw 2 mech.
100 Inspect foundation & holding bolts 2 mech.
493 23FX-1622 FEMA-1 SAPCO MECH-SAP SPM 23FX-1622 Mechanical 6 Months FEMA Task 10 Check alignment of coupling 2 mech.
494 23FX-1622 FEMA-1 SAPCO MECH-SAP SPM 23FX-1622 Mechanical 2 Years FEMA Task 10 Check bearing with gasket 2 mech.
20 Check gland packing 2 mech.
30 Replace gearbox oil 2 mech.
495 23FX-1622 FEMA-1 SAPCO MECH-SAP SPM 23FX-1622 Mechanical 5 Years FEMA Task 10 Check bearing with gasket 2 mech.
20 Replace with new gearbox & O/H old G/B 2 mech.
496 23FX-1701 FEMA-1 SAPCO MECH-SAP SPM 23FX-1701 Mechanical 3 Months FEMA Task 10 Visual inspect & clean external parts 2 mech.
497 23FX-1701 FEMA-1 SAPCO MECH-SAP SPM 23FX-1701 Mechanical 6 Months FEMA Task 10 Inspection and cleaning for outlet pipe 2 mech.

358122780.xlsx Page 14 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 Inspect & clean internals of dosing pipe 2 mech.
30 Inspect & clean internals of dosing tool 2 mech.
40 Inspection condition of sealing plate 2 mech.
50 Visual inspection and oil topup 2 mech.
60 Inspect dust filter clean or replace 2 mech.
70 Inspect shaft sealing 2 mech.
498 23FX-1701 FEMA-1 SAPCO MECH-SAP SPM 23FX-1701 Mechanical 1 Years FEMA Task 10 Inspection and cleaning for hopper 2 mech.
499 23FX-1701 FEMA-1 SAPCO MECH-SAP SPM 23FX-1701 Mechanical 2 Years FEMA Task 10 Change oil for gear box 1 mech.
500 23FX-1701 FEMA-1 SAPCO MECH-SAP SPM 23FX-1701 Mechanical 5 Years FEMA Task 10 Replace gearbox 1 mech.
501 23FX-1725 FEMA-1 SAPCO MECH-SAP SPM 23FX-1725 Mechanical 1 Months FEMA Task 10 Check and tight holding bolts 2 mech.
20 Check oil level 2 mech.
30 Check gearbox oil system ventilation 2 mech.
40 Clean and check gland packing 2 mech.
50 Clean and lubricate bearing 2 mech.
60 Inspect foundation & holding bolts 2 mech.
70 Visual check condition of bearing house 2 mech.
80 Visual check condition of coupling 2 mech.
502 23FX-1725 FEMA-1 SAPCO MECH-SAP SPM 23FX-1725 Mechanical 6 Months FEMA Task 10 Check screw & outlet scaling of pipes 2 mech.
20 Check coupling alignment 2 mech.
30 Inspect and clean internals of screw 2 mech.
503 23FX-1725 FEMA-1 SAPCO MECH-SAP SPM 23FX-1725 Mechanical 2 Years FEMA Task 10 Check bearing with gasket 2 mech.
20 Check gland packing 2 mech.
30 Replace gearbox oil 2 mech.
504 23FX-1725 FEMA-1 SAPCO MECH-SAP SPM 23FX-1725 Mechanical 5 Years FEMA Task 10 Replace with new gearbox & O/H old G/B 8 mech.
505 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 35 Days FEMA Task 10 Check and realign scrapper 2 mech.
20 Check rollers and idlers 2 mech.
30 Check pulleys, rollers condition 2 mech.
40 Check oil level and top up if required 2 mech.
50 Clean and apply lubrication for bearing 2 mech.
60 Clean dust tray & adjust scrapper 2 mech.
70 Visual checking and cleaning for pulley 2 mech.
80 Visual checking and cleaning of idller 2 mech.
90 Visual checking and cleaning of rollers 2 mech.
100 Visual checking for bearing operation 2 mech.
110 Visual checking for pulley 2 mech.
120 Visual inspect & rubber lining condition 2 mech.
130 Visual inspect & condition of gear box 2 mech.
506 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 1 Months FEMA Task 10 Check overall condition of belt 2 mech.
507 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 3 Months FEMA Task 10 Check for overall condition of belt 2 mech.
508 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 1 Weeks FEMA Task 10 Check proper rotation for idllers 2 mech.
20 Inspect condition of collection belt 1 mech.
509 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 2 Weeks FEMA Task 10 Check scrapper 2 mech.
20 Check belt condition & bolts tightness 2 mech.
30 Visual inspection for any oil leak 2 mech.
40 Inspect condition of collection belt 2 mech.
510 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 4 Years FEMA Task 10 Replace with fresh oil 2 mech.
511 23FX-2400 FEMA-1 SAPCO MECH-SAP SPM 23FX-2400 Mechanical 5 Years FEMA Task 10 Check and if required replace bearing 2 mech.
20 Check and if required replace idller 2 mech.
30 Check and if required replace pulley 2 mech.
40 Check and if required replace rollers 2 mech.
512 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 35 Days FEMA Task 10 Check and realign scrapper 2 mech.
20 Check rollers and idlers 2 mech.
30 Check pulleys, rollers condition 2 mech.
40 Check oil level and top up if required 2 mech.
50 Clean and apply lubrication for bearing 2 mech.
60 Clean dust tray & adjust scrapper 2 mech.
70 Visual checking and cleaning for pulley 2 mech.
80 Visual checking and cleaning of idller 2 mech.
90 Visual checking and cleaning of rollers 2 mech.
100 Visual checking for bearing operation 2 mech.
110 Visual checking for pulley 2 mech.
120 Visual inspect & rubber lining condition 2 mech.
130 Visual inspect & condition of gear box 2 mech.
513 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 1 Months FEMA Task 10 Check overall condition of belt 2 mech.
514 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 3 Months FEMA Task 10 Check for overall condition of belt 2 mech.
515 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 1 Weeks FEMA Task 10 Check proper rotation for idllers 2 mech.
20 Inspect condition of collection belt 2 mech.
516 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 2 Weeks FEMA Task 10 Check scrapper 2 mech.
20 Check belt condition & bolts tightness 2 mech.
30 Visual inspection for any oil leak 2 mech.
40 Inspect condition of collection belt 2 mech.
517 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 4 Years FEMA Task 10 Replace with fresh oil 2 mech.
518 23FX-2401 FEMA-1 SAPCO MECH-SAP SPM 23FX-2401 Mechanical 5 Years FEMA Task 10 Check and if required replace bearing 3 mech.
20 Check and if required replace idller 3 mech.
30 Check and if required replace pulley 3 mech.
40 Check and if required replace rollers 3 mech.
519 23FX-2410 FEMA-1 SAPCO MECH-SAP SPM 23FX-2410 Mechanical 1 Months FEMA Task 10 Check and tight foundation bolts 2 mech.
20 Check for proper chain tightness 2 mech.
30 Clean and lubricate sproket 2 mech.
40 Inspect & check for tensioning of chain 2 mech.
50 Inspect and lubricate bearing 2 mech.
60 Visual inspection for abnormality & leak 2 mech.

358122780.xlsx Page 15 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
70 Visual inspect & clean of lub chain 2 mech.
80 Visual inspect & clean of lubr sproket 2 mech.
90 Inspect alignment 2 mech.
520 23FX-2410 FEMA-1 SAPCO MECH-SAP SPM 23FX-2410 Mechanical 3 Months FEMA Task 10 Top up oil and check for any leak 2 mech.
20 Inspect chain overall condition 2 mech.
30 Inspect condition of sproket 2 mech.
40 Visual inspection of oil seal 2 mech.
521 23FX-2410 FEMA-1 SAPCO MECH-SAP SPM 23FX-2410 Mechanical 1 Years FEMA Task 10 Replace Gearbox oil with fresh oil 2 mech.
20 Visual inspect internals of screw 2 mech.
522 23FX-2410 FEMA-1 SAPCO MECH-SAP SPM 23FX-2410 Mechanical 5 Years FEMA Task 10 Visual inspect of bearing 2 mech.
523 23FX-2410 FEMA-1 SAPCO MECH-SAP SPM 23FX-2410 Mechanical 10 Years FEMA Task 10 Replace Gearbox & do O/H of old gearbox 8 mech.
524 23FX-2420 FEMA-1 SAPCO MECH-SAP SPM 23FX-2420 Mechanical 1 Months FEMA Task 10 Check and tight foundation bolts 2 mech.
20 Check for proper chain tightness 2 mech.
30 Clean and lubricate sproket 2 mech.
40 Inspect & check for tensioning of chain 2 mech.
50 Inspect and lubricate bearing 2 mech.
60 Visual inspection for abnormality & leak 2 mech.
70 Visual inspect & clean of lub chain 2 mech.
80 Visual inspect & clean of lubr sproket 2 mech.
90 Inspect alignment 2 mech.
525 23FX-2420 FEMA-1 SAPCO MECH-SAP SPM 23FX-2420 Mechanical 3 Months FEMA Task 10 Top up oil and check for any leak 2 mech.
20 Inspect chain overall condition 2 mech.
30 Inspect condition of sproket 2 mech.
40 Visual inspection of oil seal 2 mech.
526 23FX-2420 FEMA-1 SAPCO MECH-SAP SPM 23FX-2420 Mechanical 1 Years FEMA Task 10 Replace Gearbox oil with fresh oil 2 mech.
20 Visual inspect internals of screw 2 mech.
527 23FX-2420 FEMA-1 SAPCO MECH-SAP SPM 23FX-2420 Mechanical 5 Years FEMA Task 10 Visual inspect of bearing 2 mech.
528 23FX-2420 FEMA-1 SAPCO MECH-SAP SPM 23FX-2420 Mechanical 10 Years FEMA Task 10 Replace Gearbox & do O/H of old gearbox 8 mech.
529 23FX-2500 FEMA-1 SAPCO MECH-SAP SPM 23FX-2500 Mechanical 35 Days FEMA Task 10 Inspect & clean Belt drum 4 mech.
20 Inspect & clean belt guide 2 mech.
30 Inspect and clean belt rod and rod cup 2 mech.
40 Inspect & clean Feeder belt & rollers 2 mech.
50 Inspect & clean Feeder belt 2 mech.
60 Inspect & clean Head pulley 2 mech.
70 Inspect motion plate, side skirting 2 mech.
80 Inspect & clean Scrapper plate 2 mech.
90 Inspect and clean Tesnioner plate 2 mech.
100 Inspect & retight holding bolts & washer 2 mech.
110 Inspect holding bolts for Belt Drum 2 mech.
120 Inspect holding bolts for Belt GUIDE 2 mech.
130 Inspect holding bolts for Head Pulley 2 mech.
140 Inspect motion plate & base spacer bolts 2 mech.
150 Inspect and retight rod and rod cup 2 mech.
160 Inspect of gearbox & top up oil 2 mech.
170 Inspect of scrapper supports 2 mech.
180 Inspect of scrapper supports 2 mech.
190 Replace oil for Gear Box 2 mech.
530 23FX-2500 FEMA-1 SAPCO MECH-SAP SPM 23FX-2500 Mechanical 2 Years FEMA Task 10 Inspect of Tensioner plate 2 mech.
20 Replace belt every 2 years (If required) 2 mech.
531 23FX-2500 FEMA-1 SAPCO MECH-SAP SPM 23FX-2500 Mechanical 5 Years FEMA Task 10 Overhauling of Gear box to be done 8 mech.
532 23FX-2501 FEMA-1 SAPCO MECH-SAP SPM 23FX-2501 Mechanical 1 Months FEMA Task 10 Check screw & outlet scaling of pipes 3 mech.
20 Inspect condition of bearing housing 3 mech.
30 Inspect coupling & check alignment 3 mech.
40 Check and inspect condition of coupling 3 mech.
50 Check and tight holding bolts 3 mech.
60 Check oil level 3 mech.
70 Check gearbox oil system ventilation 3 mech.
80 Clean and inspect gland packing 3 mech.
90 Clean and lubricate bearing 3 mech.
100 Inspect and clean internals of screw 3 mech.
110 Inspect foundation & holding bolts 3 mech.
533 23FX-2501 FEMA-1 SAPCO MECH-SAP SPM 23FX-2501 Mechanical 2 Years FEMA Task 10 Check bearing with gasket 2 mech.
20 Check gland packing 2 mech.
30 Replace gearbox oil 2 mech.
534 23FX-2501 FEMA-1 SAPCO MECH-SAP SPM 23FX-2501 Mechanical 5 Years FEMA Task 10 Replace with new gearbox & O/H old G/B 8 mech.
535 23FX-2701 FEMA-1 SAPCO MECH-SAP SPM 23FX-2701 Mechanical 3 Months FEMA Task 10 Visual inspect & clean external parts 2 mech.
20 Inspect shaft sealing 2 mech.
536 23FX-2701 FEMA-1 SAPCO MECH-SAP SPM 23FX-2701 Mechanical 6 Months FEMA Task 10 Inspection and cleaning for outlet pipe 2 mech.
20 Inspect & clean internals of dosing pipe 2 mech.
30 Inspect & clean internals of dosing tool 2 mech.
40 Inspection condition of sealing plate 2 mech.
50 Visual inspection and oil topup 2 mech.
60 Inspect dust filter clean or replace 2 mech.
537 23FX-2701 FEMA-1 SAPCO MECH-SAP SPM 23FX-2701 Mechanical 1 Years FEMA Task 10 Inspection and cleaning for hopper 2 mech.
538 23FX-2701 FEMA-1 SAPCO MECH-SAP SPM 23FX-2701 Mechanical 2 Years FEMA Task 10 Change oil for gear box 2 mech.
539 23FX-2701 FEMA-1 SAPCO MECH-SAP SPM 23FX-2701 Mechanical 5 Years FEMA Task 10 Check and if required replace gearbox 8 mech.
540 23K-7401A FEMA-1 SAPCO MECH-SAP SPM 23K-7401A Mechanical 3 Months FEMA Task 10 Dust filters delta pressure to noted 2 mech.
20 Oil level to be checked 2 mech.
541 23K-7401A FEMA-1 SAPCO MECH-SAP SPM 23K-7401A Mechanical 6 Months FEMA Task 10 Dust filters to be cleaned 3 mech.
20 Inspect and clean filters 3 mech.
30 Inspect main motor & compressor coupling 3 mech.
40 Inspect coupling of oil pumps 3 mech.

358122780.xlsx Page 16 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
50 Inspection and cleaning of oil strainer 3 mech.
60 Inspection flexible pipes & couplings 3 mech.
70 Inspection of oil pump & its functioning 3 mech.
80 Visual inspection for any abnormility 3 mech.
542 23K-7401A FEMA-1 SAPCO MECH-SAP SPM 23K-7401A Mechanical 1 Years FEMA Task 10 Check oil temperature record 2 mech.
20 Inspect condition of inlet guide vanes 2 mech.
30 Inspect condition of cyclone fan/blower 2 mech.
40 Inspect overall condition of gearbox 2 mech.
50 Replace oil with fresh oil 2 mech.
543 23K-7401A FEMA-1 SAPCO MECH-SAP SPM 23K-7401A Mechanical 3 Years FEMA Task 10 Replacement of flexible pipes 2 mech.
544 23K-7401A FEMA-1 SAPCO MECH-SAP SPM 23K-7401A Mechanical 5 Years FEMA Task 10 Inspection of all three stage elements 3 mech.
20 Overhauling for inlet guide vanes 3 mech.
30 Overhauling of gearbox to be done 3 mech.
545 23K-7401B FEMA-1 SAPCO MECH-SAP SPM 23K-7401B Mechanical 3 Months FEMA Task 10 Dust filters delta pressure to noted 2 mech.
20 Oil level to be checked 2 mech.
546 23K-7401B FEMA-1 SAPCO MECH-SAP SPM 23K-7401B Mechanical 6 Months FEMA Task 10 Dust filters to be cleaned 3 mech.
20 Inspect and clean filters 3 mech.
30 Inspect main motor & compressor coupling 3 mech.
40 Inspect coupling of oil pumps 3 mech.
50 Inspection and cleaning of oil strainer 3 mech.
60 Inspection flexible pipes & couplings 3 mech.
70 Inspection of oil pump & its functioning 3 mech.
80 Visual inspection for any abnormility 3 mech.
547 23K-7401B FEMA-1 SAPCO MECH-SAP SPM 23K-7401B Mechanical 1 Years FEMA Task 10 Check oil temperature record 3 mech.
20 Inspect condition of inlet guide vanes 3 mech.
30 Inspect condition of cyclone fan/blower 3 mech.
40 Inspect overall condition of gearbox 3 mech.
50 Replace oil with fresh oil 3 mech.
548 23K-7401B FEMA-1 SAPCO MECH-SAP SPM 23K-7401B Mechanical 3 Years FEMA Task 10 Replacement of flexible pipes 3 mech.
549 23K-7401B FEMA-1 SAPCO MECH-SAP SPM 23K-7401B Mechanical 5 Years FEMA Task 10 Inspection of all three stage elements 3 mech.
20 Overhauling for inlet guide vanes 3 mech.
30 Overhauling of gearbox to be done 3 mech.
550 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 3 Days FEMA Task 10 Top up oil for gear box 4 mech.
551 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 35 Days FEMA Task 10 Check for proper alignment for rollers 2 mech.
20 Clean roller and its groves 2 mech.
30 Clean tooth for gear and gresase 2 mech.
40 Clean tooth for gear and gresase 2 mech.
552 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 105 Days FEMA Task 10 Inspect flexible hose 1 mech.
553 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 1 Months FEMA Task 10 Check overall condition of gearbox 4 mech.
20 Check for proper alignment for rollers 2 mech.
30 Clean roller and its groves 2 mech.
40 Clean tooth for gear and gresase 2 mech.
554 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 1 Years FEMA Task 10 Clean the Nails and check its condition 2 mech.
20 Replace gear box oil 2 mech.
555 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 3 Years FEMA Task 10 Inspect of rollers & replace if required 4 mech.
556 23M-1410 FEMA-1 SAPCO MECH-SAP SPM 23M-1410 Mechanical 5 Years FEMA Task 10 Check for overall condition of gearbox 4 mech.
20 Inspect and if required replace gear 2 mech.
30 Inspect of Nails & replace if required 2 mech.
40 Inspect roller bearings 2 mech.
557 23M-1420 FEMA-1 SAPCO MECH-SAP SPM 23M-1420 Mechanical 1 Months FEMA Task 10 Check overall condition of gearbox 3 mech.
20 Check for proper alignment for rollers 2 mech.
30 Clean roller and its groves 2 mech.
40 Clean tooth for gear and gresase 2 mech.
50 Clean tooth for gear and gresase 2 mech.
60 Top up oil for gear box 2 mech.
558 23M-1420 FEMA-1 SAPCO MECH-SAP SPM 23M-1420 Mechanical 3 Months FEMA Task 10 Inspect flexible hose 2 mech.
559 23M-1420 FEMA-1 SAPCO MECH-SAP SPM 23M-1420 Mechanical 1 Years FEMA Task 10 Clean the Nails and check its condition 2 mech.
20 Replace gear box oil 2 mech.
560 23M-1420 FEMA-1 SAPCO MECH-SAP SPM 23M-1420 Mechanical 3 Years FEMA Task 10 Inspect of rollers & replace if required 2 mech.
561 23M-1420 FEMA-1 SAPCO MECH-SAP SPM 23M-1420 Mechanical 5 Years FEMA Task 10 Check for overall condition of gearbox 8 mech.
20 Inspect and if required replace gear 2 mech.
30 Inspect of Nails & replace if required 2 mech.
40 Inspect roller bearings 2 mech.
562 23M-1721 FEMA-1 SAPCO MECH-SAP SPM 23M-1721 Mechanical 3 Months FEMA Task 10 Filter PDI to be noted 2 mech.
20 Inspect flange & thread in bearing unit 2 mech.
30 Note oil level in Oil tank 2 mech.
40 Visual inspect & collect oil temp data 2 mech.
563 23M-1721 FEMA-1 SAPCO MECH-SAP SPM 23M-1721 Mechanical 1 Years FEMA Task 10 Backflush Oil cooler (CW side) 2 mech.
564 23M-1721 FEMA-1 SAPCO MECH-SAP SPM 23M-1721 Mechanical 2 Years FEMA Task 10 Replace oil with fresh oil 2 mech.
565 23M-2410 FEMA-1 SAPCO MECH-SAP SPM 23M-2410 Mechanical 1 Months FEMA Task 10 Check overall condition of gearbox 4 mech.
20 Check for proper alignment for rollers 2 mech.
30 Clean roller and its groves 2 mech.
40 Clean tooth for gear and gresase 2 mech.
50 Clean tooth for gear and gresase 2 mech.
60 Top up oil for gear box 2 mech.
566 23M-2410 FEMA-1 SAPCO MECH-SAP SPM 23M-2410 Mechanical 3 Months FEMA Task 10 Inspect flexible hose 2 mech.
567 23M-2410 FEMA-1 SAPCO MECH-SAP SPM 23M-2410 Mechanical 1 Years FEMA Task 10 Clean the Nails and check its condition 2 mech.
20 Replace gear box oil 2 mech.
568 23M-2410 FEMA-1 SAPCO MECH-SAP SPM 23M-2410 Mechanical 3 Years FEMA Task 10 Inspect of rollers & replace if required 2 mech.
569 23M-2410 FEMA-1 SAPCO MECH-SAP SPM 23M-2410 Mechanical 5 Years FEMA Task 10 Check for overall condition of gearbox 2 mech.
20 Inspect and if required replace gear 2 mech.
30 Inspect of Nails & replace if required 2 mech.

358122780.xlsx Page 17 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
40 Inspect roller bearings 2 mech.
570 23M-2420 FEMA-1 SAPCO MECH-SAP SPM 23M-2420 Mechanical 1 Months FEMA Task 10 Check overall condition of gearbox 4 mech.
20 Check for proper alignment for rollers 2 mech.
30 Clean roller and its groves 2 mech.
40 Clean tooth for gear and gresase 2 mech.
50 Clean tooth for gear and gresase 2 mech.
60 Top up oil for gear box 2 mech.
571 23M-2420 FEMA-1 SAPCO MECH-SAP SPM 23M-2420 Mechanical 3 Months FEMA Task 10 Inspect flexible hose 2 mech.
572 23M-2420 FEMA-1 SAPCO MECH-SAP SPM 23M-2420 Mechanical 1 Years FEMA Task 10 Clean the Nails and check its condition 2 mech.
20 Replace gear box oil 2 mech.
573 23M-2420 FEMA-1 SAPCO MECH-SAP SPM 23M-2420 Mechanical 3 Years FEMA Task 10 Inspect of rollers & replace if required 2 mech.
574 23M-2420 FEMA-1 SAPCO MECH-SAP SPM 23M-2420 Mechanical 5 Years FEMA Task 10 Check for overall condition of gearbox 4 mech.
20 Inspect and if required replace gear 2 mech.
30 Inspect of Nails & replace if required 2 mech.
40 Inspect roller bearings 2 mech.
575 23M-2721 FEMA-1 SAPCO MECH-SAP SPM 23M-2721 Mechanical 3 Months FEMA Task 10 Filter PDI to be noted 2 mech.
20 Inspect flange & thread in bearing unit 2 mech.
30 Note oil level in Oil tank 2 mech.
40 Visual inspect & collect oil temp data 2 mech.
576 23M-2721 FEMA-1 SAPCO MECH-SAP SPM 23M-2721 Mechanical 6 Months FEMA Task 10 Inspect oil filter clean 2 mech.
577 23M-2721 FEMA-1 SAPCO MECH-SAP SPM 23M-2721 Mechanical 1 Years FEMA Task 10 Backflush Oil cooler (CW side) 2 mech.
20 Replace oil with fresh oil 2 mech.
578 23MX-1702 FEMA-1 SAPCO MECH-SAP SPM 23MX-1702 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
579 23MX-1702 FEMA-1 SAPCO MECH-SAP SPM 23MX-1702 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
580 23MX-1702 FEMA-1 SAPCO MECH-SAP SPM 23MX-1702 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
581 23MX-1702 FEMA-1 SAPCO MECH-SAP SPM 23MX-1702 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
582 23MX-1702 FEMA-1 SAPCO MECH-SAP SPM 23MX-1702 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
583 23MX-1716 FEMA-1 SAPCO MECH-SAP SPM 23MX-1716 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
584 23MX-1716 FEMA-1 SAPCO MECH-SAP SPM 23MX-1716 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
585 23MX-1716 FEMA-1 SAPCO MECH-SAP SPM 23MX-1716 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 3 mech.
586 23MX-1716 FEMA-1 SAPCO MECH-SAP SPM 23MX-1716 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
587 23MX-1716 FEMA-1 SAPCO MECH-SAP SPM 23MX-1716 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
588 23MX-1718 FEMA-1 SAPCO MECH-SAP SPM 23MX-1718 Mechanical 1 Months FEMA Task 10 Visual inspect & clean boot from inside 2 mech.
20 Visual inspect & lub with Silicone spray 2 mech.
30 Visual inspect and clean 2 mech.
589 23MX-1718 FEMA-1 SAPCO MECH-SAP SPM 23MX-1718 Mechanical 3 Months FEMA Task 10 Visual inspect & clean of bearing house 2 mech.
20 Visual inspection and cleaning of shaft 2 mech.
30 Visual inspect & apply new grease 2 mech.
40 Visual inspection & if required replace 2 mech.
50 Visual inspection of coupling condition 2 mech.
60 Visual inspection & tighteening bolts 2 mech.
590 23MX-1718 FEMA-1 SAPCO MECH-SAP SPM 23MX-1718 Mechanical 6 Months FEMA Task 10 Visual inspection and cleaning 2 mech.
591 23MX-1718 FEMA-1 SAPCO MECH-SAP SPM 23MX-1718 Mechanical 5 Years FEMA Task 10 Replace bearing 2 mech.
592 23MX-1825 FEMA-1 SAPCO MECH-SAP SPM 23MX-1825 Mechanical 1 Months FEMA Task 10 Visual inspect & clean boot from inside 2 mech.
20 Visual inspect & lub with Silicone spray 2 mech.
30 Visual inspect and clean 2 mech.
593 23MX-1825 FEMA-1 SAPCO MECH-SAP SPM 23MX-1825 Mechanical 3 Months FEMA Task 10 Visual inspect & clean of bearing house 2 mech.
20 Visual inspection and cleaning of shaft 2 mech.
30 Visual inspect & apply new grease 2 mech.
40 Visual inspection & if required replace 2 mech.
50 Visual inspection of coupling condition 2 mech.
60 Visual inspection & tighteening bolts 2 mech.
594 23MX-1825 FEMA-1 SAPCO MECH-SAP SPM 23MX-1825 Mechanical 6 Months FEMA Task 10 Visual inspection and cleaning 2 mech.
595 23MX-1825 FEMA-1 SAPCO MECH-SAP SPM 23MX-1825 Mechanical 5 Years FEMA Task 10 Replace bearing 8 mech.
596 23MX-2716 FEMA-1 SAPCO MECH-SAP SPM 23MX-2716 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
597 23MX-2716 FEMA-1 SAPCO MECH-SAP SPM 23MX-2716 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
598 23MX-2716 FEMA-1 SAPCO MECH-SAP SPM 23MX-2716 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
599 23MX-2716 FEMA-1 SAPCO MECH-SAP SPM 23MX-2716 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.

358122780.xlsx Page 18 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
600 23MX-2716 FEMA-1 SAPCO MECH-SAP SPM 23MX-2716 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
601 23MX-2718 FEMA-1 SAPCO MECH-SAP SPM 23MX-2718 Mechanical 1 Months FEMA Task 10 Visual inspect & clean boot from inside 2 mech.
20 Visual inspect & lub with Silicone spray 2 mech.
30 Visual inspect and clean 2 mech.
602 23MX-2718 FEMA-1 SAPCO MECH-SAP SPM 23MX-2718 Mechanical 3 Months FEMA Task 10 Visual inspect & clean of bearing house 2 mech.
20 Visual inspection and cleaning of shaft 2 mech.
30 Visual inspect & apply new grease 2 mech.
40 Visual inspection & if required replace 2 mech.
50 Visual inspection of coupling condition 2 mech.
60 Visual inspection & tighteening bolts 2 mech.
603 23MX-2718 FEMA-1 SAPCO MECH-SAP SPM 23MX-2718 Mechanical 6 Months FEMA Task 10 Visual inspection and cleaning 2 mech.
604 23MX-2718 FEMA-1 SAPCO MECH-SAP SPM 23MX-2718 Mechanical 5 Years FEMA Task 10 Replace bearing 8 mech.
605 23MX-3310 FEMA-1 SAPCO MECH-SAP SPM 23MX-3310 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
606 23MX-3310 FEMA-1 SAPCO MECH-SAP SPM 23MX-3310 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
607 23MX-3310 FEMA-1 SAPCO MECH-SAP SPM 23MX-3310 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
608 23MX-3310 FEMA-1 SAPCO MECH-SAP SPM 23MX-3310 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
609 23MX-3310 FEMA-1 SAPCO MECH-SAP SPM 23MX-3310 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
610 23MX-3320 FEMA-1 SAPCO MECH-SAP SPM 23MX-3320 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
611 23MX-3320 FEMA-1 SAPCO MECH-SAP SPM 23MX-3320 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
612 23MX-3320 FEMA-1 SAPCO MECH-SAP SPM 23MX-3320 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
613 23MX-3320 FEMA-1 SAPCO MECH-SAP SPM 23MX-3320 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
614 23MX-3320 FEMA-1 SAPCO MECH-SAP SPM 23MX-3320 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
615 23MX-3430 FEMA-1 SAPCO MECH-SAP SPM 23MX-3430 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
616 23MX-3430 FEMA-1 SAPCO MECH-SAP SPM 23MX-3430 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
617 23MX-3430 FEMA-1 SAPCO MECH-SAP SPM 23MX-3430 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
618 23MX-3430 FEMA-1 SAPCO MECH-SAP SPM 23MX-3430 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
619 23MX-3430 FEMA-1 SAPCO MECH-SAP SPM 23MX-3430 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
620 23MX-3520 FEMA-1 SAPCO MECH-SAP SPM 23MX-3520 Mechanical 3 Months FEMA Task 10 Check condition of coupling 2 mech.
20 Check tighteening loose & holding bolts 2 mech.
30 To do greasing for bearing 2 mech.
40 Inspect condition of agitator housing 2 mech.
50 Visual inspetion of Mechanical seal 2 mech.
621 23MX-3520 FEMA-1 SAPCO MECH-SAP SPM 23MX-3520 Mechanical 6 Months FEMA Task 10 Top up gearbox oil and clean GB oil vent 2 mech.
20 Visual inspection for bearing 2 mech.
622 23MX-3520 FEMA-1 SAPCO MECH-SAP SPM 23MX-3520 Mechanical 1 Years FEMA Task 10 Inspect oveall condition of gear box 2 mech.
623 23MX-3520 FEMA-1 SAPCO MECH-SAP SPM 23MX-3520 Mechanical 2 Years FEMA Task 10 Inspect shaft, shaft & mixing elements 2 mech.
20 Inspect shaft alignment & bearing 2 mech.
30 Inspect shaft mixing elements 2 mech.
40 Replace GB oil with fresh oil 2 mech.
50 To clean bearing and apply fresh grease 2 mech.
624 23MX-3520 FEMA-1 SAPCO MECH-SAP SPM 23MX-3520 Mechanical 5 Years FEMA Task 10 Complete gearbox overhauling 8 mech.
625 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 1 Months FEMA Task 10 Check and top up oil level 2 mech.
20 to check the level guage regularly 2 mech.
626 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 2 Months FEMA Task 10 To monitor the discharge pressure 2 mech.
627 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
20 To check the strainer partially clogged 2 mech.
30 to replace the oil 2 mech.
628 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 2 mech.
20 To check strainer mesh/screen & replace 2 mech.
629 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 3 Years FEMA Task 10 To replace the Ball Bearings 3 mech.
630 23P-1100 FEMA-1 SAPCO MECH-SAP SPM 23P-1100 Mechanical 5 Years FEMA Task 10 to inspect impeller 2 mech.
20 To inspect or replace the pump shaft 2 mech.

358122780.xlsx Page 19 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 To replace magnetic coupling 2 mech.
40 To replace the Ball Bearings 2 mech.
50 To replace impellor based on inspection 2 mech.
60 To replace impellor based on inspection 2 mech.
70 To replace the mechanical seal 2 mech.
80 to replace the wearing 2 mech.
631 23P-1150 FEMA-1 SAPCO MECH-SAP SPM 23P-1150 Mechanical 3 Months FEMA Task 10 Inspect tight foundation bolts 2 mech.
20 Check hoses 2 mech.
632 23P-1150 FEMA-1 SAPCO MECH-SAP SPM 23P-1150 Mechanical 5 Years FEMA Task 10 Bearing to be replaced 2 mech.
633 23P-1160 FEMA-1 SAPCO MECH-SAP SPM 23P-1160 Mechanical 3 Months FEMA Task 10 Inspect tight foundation bolts 2 mech.
20 Check hoses 2 mech.
634 23P-1160 FEMA-1 SAPCO MECH-SAP SPM 23P-1160 Mechanical 5 Years FEMA Task 10 Bearing to be replaced 2 mech.
635 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 1 Months FEMA Task 10 Check and top up oil level 2 mech.
636 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 2 Months FEMA Task 10 To monitor the discharge pressure 2 mech.
637 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 6 Months FEMA Task 10 To check the strainer partially clogged 2 mech.
20 to replace the oil 2 mech.
638 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 2 instrument
639 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 2 mech.
20 To check strainer mesh/screen & replace 2 mech.
640 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 2 mech.
641 23P-1721 FEMA-1 SAPCO MECH-SAP SPM 23P-1721 Mechanical 5 Years FEMA Task 10 to inspect impeller (Overhauling) 4 mech.
20 To inspect or replace the pump shaft 4 mech.
30 To replace coupling 4 mech.
40 To replace the Ball Bearings 4 mech.
50 To replace impellor based on inspection 4 mech.
60 To replace impellor based on inspection 4 mech.
70 To replace the mechanical seal 4 mech.
80 to replace the wearing 4 mech.
642 23P-1722 FEMA-1 SAPCO MECH-SAP SPM 23P-1722 Mechanical 5 Years FEMA Task 10 To replace the pump 4 mech.
643 23P-1722 FEMA-1 SAPCO MECH-SAP SPM 23P-1722 Mechanical 5 Years FEMA Task 10 To replace Seal during Pump O/H 2 mech.
644 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
645 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 2 Months FEMA Task 10 To monitor the discharge pressure 1 mech.
646 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
20 to replace the oil 2 mech.
647 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 2 mech.
20 To check strainer mesh/screen & replace 2 mech.
648 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 5 Years FEMA Task 10 To replace the Ball Bearings 4 mech.
20 To replace impellor based on inspection 4 mech.
30 to replace the wearing 4 mech.
649 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 6 Months FEMA Task 10 To clean strainer 1 mech.
650 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 2 instrument
651 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 2 mech.
20 to inspect impeller 2 mech.
30 To replace coupling 2 mech.
40 To replace impellor based on inspection 2 mech.
652 23P-1726 FEMA-1 SAPCO MECH-SAP SPM 23P-1726 Mechanical 5 Years FEMA Task 10 To inspect or replace the pump shaft 4 mech.
20 To replace the mechanical seal 4 mech.
653 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
654 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 2 Months FEMA Task 10 To monitor the discharge pressure 1 mech.
655 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 6 Months FEMA Task 10 To check the strainer partially clogged 2 mech.
20 to replace the oil 2 mech.
656 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 2 instrument
657 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 1 mech.
20 To check strainer mesh/screen & replace 1 mech.
658 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 2 mech.
20 To replace the Ball Bearings 2 mech.
30 To replace impellor based on inspection 2 mech.
659 23P-2721 FEMA-1 SAPCO MECH-SAP SPM 23P-2721 Mechanical 5 Years FEMA Task 10 to inspect impeller 4 mech.
20 To inspect or replace the pump shaft 4 mech.
30 To replace coupling 4 mech.
40 To replace the Ball Bearings 4 mech.
50 To replace impellor based on inspection 4 mech.
60 To replace the mechanical seal 4 mech.
70 to replace the wearing 4 mech.
660 23P-2722 FEMA-1 SAPCO MECH-SAP SPM 23P-2722 Mechanical 5 Years FEMA Task 10 To replace the pump 4 mech.
20 To replace Seal during Pump O/H 4 mech.
661 23P-3310 FEMA-1 SAPCO MECH-SAP SPM 23P-3310 Mechanical 1 Months FEMA Task 10 Inspect hose condition 1 mech.
662 23P-3310 FEMA-1 SAPCO MECH-SAP SPM 23P-3310 Mechanical 3 Months FEMA Task 10 Inspect & clean 1 mech.
663 23P-3310 FEMA-1 SAPCO MECH-SAP SPM 23P-3310 Mechanical 6 Months FEMA Task 10 Air valve cleaning to be done 2 mech.
20 Clean and overhaul air valve 2 mech.
30 Air valve cleaning to be done 2 mech.
40 Clean and overhaul air valve 2 mech.
50 muffler to be cleaned 2 mech.
664 23P-3310 FEMA-1 SAPCO MECH-SAP SPM 23P-3310 Mechanical 1 Years FEMA Task 10 Check valve cleaning 2 mech.
20 Inspect and cleaning externals of pump 2 mech.
665 23P-3310 FEMA-1 SAPCO MECH-SAP SPM 23P-3310 Mechanical 3 Years FEMA Task 10 Inspect internals of diaphragm plates 2 mech.
666 23P-3320 FEMA-1 SAPCO MECH-SAP SPM 23P-3320 Mechanical 1 Months FEMA Task 10 Inspect hose condition 1 mech.
667 23P-3320 FEMA-1 SAPCO MECH-SAP SPM 23P-3320 Mechanical 3 Months FEMA Task 10 Inspect & clean 1 mech.
668 23P-3320 FEMA-1 SAPCO MECH-SAP SPM 23P-3320 Mechanical 6 Months FEMA Task 10 Clean air valve and muffler 2 mech.
20 Clean and overhaul air valve 2 mech.
30 Clean and overhaul air valve 2 mech.
669 23P-3320 FEMA-1 SAPCO MECH-SAP SPM 23P-3320 Mechanical 1 Years FEMA Task 10 Check valve cleaning 2 mech.

358122780.xlsx Page 20 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 Inspect and cleaning externals of pump 2 mech.
670 23P-3320 FEMA-1 SAPCO MECH-SAP SPM 23P-3320 Mechanical 3 Years FEMA Task 10 Inspect internals of diaphragm plates 2 mech.
671 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
672 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 2 instrument
673 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 2 mech.
20 To check strainer mesh/screen & replace 2 mech.
674 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 3 Years FEMA Task 10 To replace the Ball Bearings 4 mech.
675 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 5 Years FEMA Task 10 To inspect or replace the pump shaft 4 mech.
20 To replace magnetic coupling 4 mech.
30 To replace impellor based on inspection 4 mech.
40 to replace the wearing 4 mech.
676 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 1 Months FEMA Task 10 To check the strainer partially clogged 1 mech.
677 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 2 Months FEMA Task 10 to check the level guage regularly 2 instrument
20 To monitor the discharge pressure 2 mech.
678 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
20 to replace the oil 2 mech.
679 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 1 mech.
20 To replace impellor based on inspection 4 mech.
680 23P-3430 FEMA-1 SAPCO MECH-SAP SPM 23P-3430 Mechanical 5 Years FEMA Task 10 to inspect impeller 4 mech.
20 To replace the Ball Bearings 1 mech.
30 To replace the mechanical seal 1 mech.
681 23P-3431 FEMA-1 SAPCO MECH-SAP SPM 23P-3431 Mechanical 1 Months FEMA Task 10 Inspect hose condition 1 mech.
682 23P-3431 FEMA-1 SAPCO MECH-SAP SPM 23P-3431 Mechanical 3 Months FEMA Task 10 Inspect & clean 1 mech.
683 23P-3431 FEMA-1 SAPCO MECH-SAP SPM 23P-3431 Mechanical 6 Months FEMA Task 10 Clean air valve and muffler 2 mech.
20 Clean and overhaul air valve 4 mech.
30 Clean and overhaul air valve 4 mech.
684 23P-3431 FEMA-1 SAPCO MECH-SAP SPM 23P-3431 Mechanical 1 Years FEMA Task 10 Check valve cleaning 2 mech.
20 Inspect and cleaning externals of pump 2 mech.
685 23P-3431 FEMA-1 SAPCO MECH-SAP SPM 23P-3431 Mechanical 3 Years FEMA Task 10 Inspect internals of diaphragm plates 2 mech.
686 23P-3520 FEMA-1 SAPCO MECH-SAP SPM 23P-3520 Mechanical 1 Months FEMA Task 10 Inspect hose condition 1 mech.
687 23P-3520 FEMA-1 SAPCO MECH-SAP SPM 23P-3520 Mechanical 3 Months FEMA Task 10 Inspect & clean 1 mech.
688 23P-3520 FEMA-1 SAPCO MECH-SAP SPM 23P-3520 Mechanical 6 Months FEMA Task 10 Clean air valve and muffler 2 mech.
20 Clean and overhaul air valve 4 mech.
30 Clean and overhaul air valve 4 mech.
689 23P-3520 FEMA-1 SAPCO MECH-SAP SPM 23P-3520 Mechanical 1 Years FEMA Task 10 Check valve cleaning 2 mech.
20 Inspect and cleaning externals of pump 2 mech.
690 23P-3520 FEMA-1 SAPCO MECH-SAP SPM 23P-3520 Mechanical 3 Years FEMA Task 10 Inspect internals of diaphragm plates 1 mech.
691 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
20 To check the strainer partially clogged 2 mech.
692 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
693 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 1 Years FEMA Task 10 To check strainer mesh/screen & replace 2 mech.
694 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 3 Years FEMA Task 10 To replace the Ball Bearings 4 mech.
10 to inspect and cleaning cooling line 4 mech.
695 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 5 Years FEMA Task 20 To replace the mechanical seal 8 mech.
30 to replace the wearing 4 mech.
696 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 2 Months FEMA Task 10 to check the level guage regularly 1 mech.
20 To monitor the discharge pressure 1 mech.
697 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 6 Months FEMA Task 10 to replace the oil 1 mech.
698 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 2 instrument
699 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 1 mech.
700 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 3 Years FEMA Task 10 to inspect impeller 2 mech.
20 To replace coupling 2 mech.
30 To replace impellor based on inspection 2 mech.
701 23P-3701 FEMA-1 SAPCO MECH-SAP SPM 23P-3701 Mechanical 5 Years FEMA Task 10 To inspect or replace the pump shaft 4 mech.
20 To replace the Ball Bearings 2 mech.
30 To replace impellor based on inspection 1 mech.
702 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 1 Months FEMA Task 10 To check the strainer partially clogged 1 mech.
703 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 2 Months FEMA Task 10 To monitor the discharge pressure 1 mech.
704 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
20 to replace the oil 4 mech.
705 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 5 Years FEMA Task 10 To replace the Ball Bearings 4 mech.
20 To replace the mechanical seal 4 mech.
706 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
20 to check the level guage regularly 1 mech.
707 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 1 mech.
708 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 1 mech.
20 To check strainer mesh/screen & replace 1 mech.
709 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 1 mech.
20 To replace the Ball Bearings 1 mech.
30 To replace impellor based on inspection 1 mech.
710 23P-4001 FEMA-1 SAPCO MECH-SAP SPM 23P-4001 Mechanical 5 Years FEMA Task 10 to inspect impeller 4 mech.
20 To inspect or replace the pump shaft 2 mech.
30 To replace magnetic coupling 2 mech.
40 To replace impellor based on inspection 2 mech.
50 to replace the wearing 2 mech.
711 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
20 To check the strainer partially clogged 1 mech.
712 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 2 Months FEMA Task 10 to check the level guage regularly 1 mech.
20 To monitor the discharge pressure 1 mech.
713 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 6 Months FEMA Task 10 To check the alignment 2 mech.
20 to replace the oil 1 mech.
714 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 1 mech.

358122780.xlsx Page 21 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
715 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 1 mech.
20 To check strainer mesh/screen & replace 2 mech.
716 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 4 mech.
20 to inspect impeller 2 mech.
30 To replace the Ball Bearings 2 mech.
40 To replace impellor based on inspection 2 mech.
717 23P-4101 FEMA-1 SAPCO MECH-SAP SPM 23P-4101 Mechanical 5 Years FEMA Task 10 To inspect or replace the pump shaft 4 mech.
20 To replace magnetic coupling 2 mech.
30 To replace the Ball Bearings 2 mech.
40 To replace impellor based on inspection 2 mech.
50 To replace the mechanical seal 4 mech.
60 to replace the wearing 2 mech.
718 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 1 Months FEMA Task 10 Check and top up oil level 1 mech.
20 To check the strainer partially clogged 2 mech.
719 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 2 Months FEMA Task 10 to check the level guage regularly 2 instrument
20 To monitor the discharge pressure 1 mech.
720 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 6 Months FEMA Task 10 To check the alignment 1 mech.
20 to replace the oil 1 mech.
721 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 2 Weeks FEMA Task 10 to check the level guage regularly 1 mech.
722 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 1 Years FEMA Task 10 To check foundation bolt condition 2 mech.
20 To check strainer mesh/screen & replace 2 mech.
723 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 3 Years FEMA Task 10 to inspect and cleaning cooling line 2 mech.
20 to inspect impeller 2 mech.
30 To replace the Ball Bearings 2 mech.
40 To replace impellor based on inspection 2 mech.
724 23P-4102 FEMA-1 SAPCO MECH-SAP SPM 23P-4102 Mechanical 5 Years FEMA Task 10 To inspect or replace the pump shaft 2 mech.
20 To replace magnetic coupling 2 mech.
30 To replace the Ball Bearings 2 mech.
40 To replace impellor based on inspection 2 mech.
50 To replace the mechanical seal 2 mech.
60 to replace the wearing 2 mech.
725 23PK-6003A FEMA-1 SAPCO MECH-SAP SPM 23PK-6003A Mechanical 3 Months FEMA Task 10 Check and tight all holding bolts 2 mech.
20 Note discharge pressure of compressor 2 mech.
30 Note discharge pressure of compressor 2 mech.
40 Note refrigerant level & leak 2 mech.
50 Oil level to be checkd 2 mech.
726 23PK-6003A FEMA-1 SAPCO MECH-SAP SPM 23PK-6003A Mechanical 1 Years FEMA Task 10 Clean or backflush condensor exchanger 2 mech.
20 Clean or backflush evaporator exchanger 2 mech.
30 Oil filter to be cleaned 2 mech.
727 23PK-6003A FEMA-1 SAPCO MECH-SAP SPM 23PK-6003A Mechanical 2 Years FEMA Task 10 Calibrate PRV & replace repture disk 2 mech.
20 Inspection for oil pump 2 mech.
728 23PK-6003A FEMA-1 SAPCO MECH-SAP SPM 23PK-6003A Mechanical 5 Years FEMA Task 10 Overahulling for compressor to be done 72 mech.
20 Overhauling of oil pump to be done 12 mech.
30 Overhauling of Oil seperator to be done 12 mech.
729 23PK-6003B FEMA-1 SAPCO MECH-SAP SPM 23PK-6003B Mechanical 3 Months FEMA Task 10 Check and tight all holding bolts 2 mech.
20 Note discharge pressure of compressor 2 mech.
30 Note discharge pressure of compressor 2 mech.
40 Note refrigerant level & leak 2 mech.
50 Oil level to be checkd 2 mech.
730 23PK-6003B FEMA-1 SAPCO MECH-SAP SPM 23PK-6003B Mechanical 1 Years FEMA Task 10 Clean or backflush condensor exchanger 2 mech.
20 Clean or backflush evaporator exchanger 2 mech.
30 Oil filter to be cleaned 2 mech.
731 23PK-6003B FEMA-1 SAPCO MECH-SAP SPM 23PK-6003B Mechanical 2 Years FEMA Task 10 Calibrate PRV & replace repture disk 4 mech.
20 Inspection for oil pump 2 mech.
732 23PK-6003B FEMA-1 SAPCO MECH-SAP SPM 23PK-6003B Mechanical 5 Years FEMA Task 10 Overahulling for compressor to be done 72 mech.
20 Overhauling of oil pump to be done 12 mech.
30 Overhauling of Oil seperator to be done 12 mech.
733 23PK-6103A FEMA-1 SAPCO MECH-SAP SPM 23PK-6103A Mechanical 3 Months FEMA Task 10 Check and tight all holding bolts 2 mech.
20 Note discharge pressure of compressor 2 mech.
30 Note discharge pressure of compressor 2 mech.
40 Note refrigerant level & leak 2 mech.
50 Oil level to be checkd 2 mech.
734 23PK-6103A FEMA-1 SAPCO MECH-SAP SPM 23PK-6103A Mechanical 1 Years FEMA Task 10 Clean or backflush condensor exchanger 2 mech.
20 Clean or backflush evaporator exchanger 2 mech.
30 Oil filter to be cleaned 2 mech.
735 23PK-6103A FEMA-1 SAPCO MECH-SAP SPM 23PK-6103A Mechanical 2 Years FEMA Task 10 Inspection for oil pump 1 mech.
736 23PK-6103A FEMA-1 SAPCO MECH-SAP SPM 23PK-6103A Mechanical 5 Years FEMA Task 10 Overahulling for compressor to be done 72 mech.
20 Overhauling for gears (High speed) 12 mech.
30 Overhauling gears(Low speed) to be done 12 mech.
40 Overahulling for inlet vanes to be done 12 mech.
50 Overhauling of compressor & inlet Vanes 12 mech.
60 Overhauling of oil pump to be done 12 mech.
737 23PK-6103B FEMA-1 SAPCO MECH-SAP SPM 23PK-6103B Mechanical 3 Months FEMA Task 10 Check and tight all holding bolts 2 mech.
20 Note discharge pressure of compressor 2 mech.
30 Note discharge pressure of compressor 2 mech.
40 Note refrigerant level & leak 2 mech.
50 Oil level to be checkd 2 mech.
738 23PK-6103B FEMA-1 SAPCO MECH-SAP SPM 23PK-6103B Mechanical 1 Years FEMA Task 10 Clean or backflush condensor exchanger 2 mech.
20 Clean or backflush evaporator exchanger 2 mech.
30 Oil filter to be cleaned 2 mech.
739 23PK-6103B FEMA-1 SAPCO MECH-SAP SPM 23PK-6103B Mechanical 2 Years FEMA Task 10 Inspection for oil pump 1 mech.
740 23PK-6103B FEMA-1 SAPCO MECH-SAP SPM 23PK-6103B Mechanical 5 Years FEMA Task 10 Overahulling for compressor to be done 72 mech.

358122780.xlsx Page 22 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 Overahulling for gears to be done 12 mech.
30 Overahulling for inlet vanes to be done 12 mech.
40 Overhauling of compressor & inlet Vanes 12 mech.
50 Overhauling of oil pump to be done 12 mech.
741 23PK-6103C FEMA-1 SAPCO MECH-SAP SPM 23PK-6103C Mechanical 3 Months FEMA Task 10 Check and tight all holding bolts 2 mech.
20 Note discharge pressure of compressor 2 mech.
30 Note discharge pressure of compressor 2 mech.
40 Note refrigerant level & leak 2 mech.
50 Oil level to be checkd 2 mech.
742 23PK-6103C FEMA-1 SAPCO MECH-SAP SPM 23PK-6103C Mechanical 1 Years FEMA Task 10 Clean or backflush condensor exchanger 2 mech.
20 Clean or backflush evaporator exchanger 2 mech.
30 Oil filter to be cleaned 2 mech.
743 23PK-6103C FEMA-1 SAPCO MECH-SAP SPM 23PK-6103C Mechanical 2 Years FEMA Task 10 Inspection for oil pump 1 mech.
744 23PK-6103C FEMA-1 SAPCO MECH-SAP SPM 23PK-6103C Mechanical 5 Years FEMA Task 10 Overahulling for compressor to be done 72 mech.
20 Overahulling for gears to be done 12 mech.
30 Overahulling for inlet vanes to be done 12 mech.
40 Overhauling of compressor & inlet Vanes 12 mech.
50 Overhauling of oil pump to be done 12 mech.
745 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 15 Days FEMA Task 10 Inspect smooth operation of polybelt 2 mech.
746 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 35 Days FEMA Task 10 Check and if required adjust GEL cutter 2 mech.
20 Check door gasket &remove accumulte gel 2 mech.
30 Check condition of Splashing guard 2 mech.
40 Check oil level and if required top up 2 mech.
50 Clean and inspect feeding table 2 mech.
60 Clean and lubricate chain 2 mech.
70 Clean and lubricate chain wheel 2 mech.
80 Clean belt with luke warm water 2 mech.
90 Inspect and clean knives 2 mech.
100 Inspection and surface cleaning 2 mech.
110 Inspection & surface cleaning 2 mech.
120 Inspection cleaning & apply fresh grease 2 mech.
130 Inspection overall condition of bearing 2 mech.
140 Inspect overall condition of gearbox 2 mech.
747 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 70 Days FEMA Task 10 Clean surface & screw thread 2 mech.
748 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 6 Months FEMA Task 10 Replace gearbox oil every six months 2 mech.
749 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 2 Years FEMA Task 10 Inspect conveying belt 2 mech.
750 23R-1310 FEMA-1 SAPCO MECH-SAP SPM 23R-1310 Mechanical 5 Years FEMA Task 10 Check overall condition of rollers 8 mech.
20 Inspect condition of Driving drum 4 mech.
30 Inspect condition of pulley 2 mech.
40 Inspection condition of Snup 2 mech.
50 Iinspect condition of Tax Role 2 mech.
60 Ensure condition of knives and shaft 2 mech.
70 Inspect feeding table 2 mech.
80 Inspect Tension bearing 2 mech.
90 Inspect overall condition of Chain 2 mech.
100 Inspect overall condition of Chain 2 mech.
751 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 15 Days FEMA Task 10 Inspect smooth operation of polybelt 2 mech.
752 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 35 Days FEMA Task 10 Check and if required adjust GEL cutter 2 mech.
20 Check door gasket &remove accumulte gel 2 mech.
30 Check condition of Splashing guard 2 mech.
40 Check oil level and if required top up 2 mech.
50 Clean and inspect feeding table 2 mech.
60 Clean and lubricate chain 2 mech.
70 Clean and lubricate chain wheel 2 mech.
80 Clean belt with luke warm water 2 mech.
90 Inspect and clean knives 2 mech.
100 Inspection and surface cleaning 2 mech.
110 Inspection & surface cleaning 2 mech.
120 Inspection cleaning & apply fresh grease 2 mech.
130 Inspection overall condition of bearing 2 mech.
140 Inspect overall condition of gearbox 2 mech.
753 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 70 Days FEMA Task 10 Clean surface & screw thread 2 mech.
754 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 6 Months FEMA Task 10 Replace gearbox oil every six months 2 mech.
755 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 2 Years FEMA Task 10 Inspect conveying belt 2 mech.
756 23R-1320 FEMA-1 SAPCO MECH-SAP SPM 23R-1320 Mechanical 5 Years FEMA Task 10 Check overall condition of rollers 8 mech.
20 Inspect condition of Driving drum 4 mech.
30 Inspect condition of pulley 2 mech.
40 Inspection condition of Snup 2 mech.
50 Iinspect condition of Tax Role 2 mech.
60 Ensure condition of knives and shaft 2 mech.
70 Inspect and if required replace bearing 2 mech.
80 Inspect feeding table 2 mech.
90 Inspect overall condition of Chain 2 mech.
100 Inspect overall condition of Chain 2 mech.
757 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 15 Days FEMA Task 10 Inspect smooth operation of polybelt 2 mech.
758 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 35 Days FEMA Task 10 Check and if required adjust GEL cutter 2 mech.
20 Check door gasket &remove accumulte gel 2 mech.
30 Check condition of Splashing guard 2 mech.
40 Check oil level and if required top up 2 mech.
50 Clean and inspect feeding table 2 mech.
60 Clean and lubricate chain 2 mech.
70 Clean and lubricate chain wheel 2 mech.

358122780.xlsx Page 23 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
80 Clean belt with luke warm water 2 mech.
90 Inspect and clean knives 2 mech.
100 Inspection and surface cleaning 2 mech.
110 Inspection & surface cleaning 2 mech.
120 Inspection cleaning & apply fresh grease 2 mech.
130 Inspection overall condition of bearing 2 mech.
140 Inspect overall condition of gearbox 2 mech.
759 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 70 Days FEMA Task 10 Clean surface & screw thread 2 mech.
760 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 6 Months FEMA Task 10 Replace gearbox oil every six months 2 mech.
761 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 2 Years FEMA Task 10 Inspect conveying belt 2 mech.
762 23R-2310 FEMA-1 SAPCO MECH-SAP SPM 23R-2310 Mechanical 5 Years FEMA Task 10 Check overall condition of rollers 8 mech.
20 Inspect condition of Driving drum 4 mech.
30 Inspect condition of pulley 2 mech.
40 Inspection condition of Snup 2 mech.
50 Iinspect condition of Tax Role 2 mech.
60 Ensure condition of knives and shaft 2 mech.
70 Inspect and if required replace bearing 2 mech.
80 Inspect feeding table 2 mech.
90 Inspect overall condition of Chain 2 mech.
100 Inspect overall condition of Chain 2 mech.
763 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 15 Days FEMA Task 10 Inspect smooth operation of polybelt 2 mech.
764 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 35 Days FEMA Task 10 Check and if required adjust GEL cutter 2 mech.
20 Check door gasket &remove accumulte gel 2 mech.
30 Check condition of Splashing guard 2 mech.
40 Check oil level and if required top up 2 mech.
50 Clean and inspect feeding table 2 mech.
60 Clean and lubricate chain 2 mech.
70 Clean and lubricate chain wheel 2 mech.
80 Clean belt with luke warm water 2 mech.
90 Inspect and clean knives 2 mech.
100 Inspection and surface cleaning 2 mech.
110 Inspection & surface cleaning 2 mech.
120 Inspection cleaning & apply fresh grease 2 mech.
130 Inspection overall condition of bearing 2 mech.
140 Inspect overall condition of gearbox 2 mech.
765 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 70 Days FEMA Task 10 Clean surface & screw thread 2 mech.
766 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 6 Months FEMA Task 10 Replace gearbox oil every six months 2 mech.
767 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 2 Years FEMA Task 10 Inspect conveying belt 2 mech.
768 23R-2320 FEMA-1 SAPCO MECH-SAP SPM 23R-2320 Mechanical 5 Years FEMA Task 10 Check overall condition of rollers 8 mech.
20 Inspect condition of Driving drum 4 mech.
30 Inspect condition of pulley 2 mech.
40 Inspection condition of Snup 2 mech.
50 Iinspect condition of Tax Role 2 mech.
60 Ensure condition of knives and shaft 2 mech.
70 Inspect and if required replace bearing 2 mech.
80 Inspect feeding table 2 mech.
90 Inspect overall condition of Chain 2 mech.
100 Inspect overall condition of Chain 2 mech.
769 23Z-1410 FEMA-1 SAPCO MECH-SAP SPM 23Z-1410 Mechanical 35 Days FEMA Task 10 Function test operation of gate 2 mech.
20 To do greasing for bearing 2 mech.
30 Visual inspection for any abnormility 2 mech.
40 Inspect bearing & shaft rotation 2 mech.
50 Visual inspection of blades and cleaning 2 mech.
60 Visual inspection of shaft and cleaning 2 mech.
70 Visual inspection of stuffing box 2 mech.
80 Visual inspection of trough gasket 2 mech.
770 23Z-1410 FEMA-1 SAPCO MECH-SAP SPM 23Z-1410 Mechanical 3 Months FEMA Task 10 Inspect and grease bearing for gate 2 mech.
20 Top up oil 2 mech.
771 23Z-1410 FEMA-1 SAPCO MECH-SAP SPM 23Z-1410 Mechanical 1 Years FEMA Task 10 Replace GB oil 2 mech.
772 23Z-1410 FEMA-1 SAPCO MECH-SAP SPM 23Z-1410 Mechanical 5 Years FEMA Task 10 Inspect and if required replace bearing 8 mech.
20 Inspect replace blades 2 mech.
30 Inspect replace stuffing box internals 2 mech.
40 Inspect replace trough gasket 2 mech.
50 Overhauling for GB 2 mech.
773 23Z-1420 FEMA-1 SAPCO MECH-SAP SPM 23Z-1420 Mechanical 35 Days FEMA Task 10 Function test operation of gate 2 mech.
20 To do greasing for bearing 2 mech.
30 Visual inspection for any abnormility 2 mech.
40 Inspect bearing & shaft rotation 2 mech.
50 Visual inspection of blades and cleaning 2 mech.
60 Visual inspection of shaft and cleaning 2 mech.
70 Visual inspection of stuffing box 2 mech.
80 Visual inspection of trough gasket 2 mech.
774 23Z-1420 FEMA-1 SAPCO MECH-SAP SPM 23Z-1420 Mechanical 3 Months FEMA Task 10 Inspect and grease bearing for gate 2 mech.
20 Top up oil 2 mech.
775 23Z-1420 FEMA-1 SAPCO MECH-SAP SPM 23Z-1420 Mechanical 1 Years FEMA Task 10 Replace GB oil 2 mech.
776 23Z-1420 FEMA-1 SAPCO MECH-SAP SPM 23Z-1420 Mechanical 5 Years FEMA Task 10 Inspect and if required replace bearing 8 mech.
20 Inspect replace blades 2 mech.
30 Inspect replace stuffing box internals 2 mech.
40 Inspect replace trough gasket 2 mech.
50 Overhauling for GB 2 mech.
777 23Z-1500 FEMA-1 SAPCO MECH-SAP SPM 23Z-1500 Mechanical 35 Days FEMA Task 10 Bearing greasing to be done 2 mech.
20 Inspect shaft & blades 2 mech.

358122780.xlsx Page 24 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
30 To check & clean shaft & blades 2 mech.
40 Visual inspect & clean externals of GB 2 mech.
778 23Z-1500 FEMA-1 SAPCO MECH-SAP SPM 23Z-1500 Mechanical 3 Months FEMA Task 10 Check oil level & visual oil quality 2 mech.
20 Visual checking for coupling 2 mech.
30 Visual inspection & external clean of GB 2 mech.
40 Visual inspection & replace grease 2 mech.
779 23Z-1500 FEMA-1 SAPCO MECH-SAP SPM 23Z-1500 Mechanical 1 Years FEMA Task 10 Replace GB oil with fresh oil 2 mech.
780 23Z-1500 FEMA-1 SAPCO MECH-SAP SPM 23Z-1500 Mechanical 3 Years FEMA Task 10 To check bearing 2 mech.
781 23Z-1500 FEMA-1 SAPCO MECH-SAP SPM 23Z-1500 Mechanical 5 Years FEMA Task 10 Complete Overhauling to be done for GB 8 mech.
20 To check shaft 2 mech.
30 To check shaft blade 2 mech.
40 To check coupling 2 mech.
782 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 35 Days FEMA Task 10 Check & clean DRY air inlet & Vent line 2 mech.
20 Check and clean screen for cutting mill 2 mech.
30 Check belt tension 2 mech.
40 Check condition of belt 2 mech.
50 Check sealing for cutting mill covers 2 mech.
60 Check condition rotor and stator knives 2 mech.
70 Check condition of Rotor & stator knives 2 mech.
80 Clean cutting mill internals 2 mech.
90 Inspect & clean screen for cutting mill 2 mech.
100 Inspect knife and replace if required 2 mech.
783 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 3 Months FEMA Task 10 Check condition of drive pulley 2 mech.
20 Check condition of flywheel 2 mech.
30 Visual inspect unusual sound of bearing 2 mech.
784 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 6 Months FEMA Task 10 Check condition of Screen 2 mech.
20 Inspect of Screen replace if required 2 mech.
785 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 1 Weeks FEMA Task 10 Lubrication (Greasing) for bearing 1 mech.
786 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 3 Years FEMA Task 10 Inspect bearing 2 mech.
787 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 5 Years FEMA Task 10 Check condition of Belt flywheel 4 mech.
20 Check condition of Drive pulley 2 mech.
30 Replace the belts with new 2 mech.
788 23Z-1601 FEMA-1 SAPCO MECH-SAP SPM 23Z-1601 Mechanical 35 Days FEMA Task 10 Check gap of rotor & stator knives 2 mech.
789 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 35 Days FEMA Task 10 Check & clean DRY air inlet & Vent line 2 mech.
20 Check belt tension 2 mech.
30 Check condition of belt 2 mech.
40 Check sealing for cutting mill covers 2 mech.
50 Check condition rotor and stator knives 2 mech.
60 Check condition of Rotor & stator knives 2 mech.
70 Check gap of rotor & stator knives 2 mech.
80 Clean cutting mill internals 2 mech.
90 Inspect & clean screen for cutting mill 2 mech.
790 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 3 Months FEMA Task 10 Inspect condition of drive pulley 2 mech.
20 Inspect condition of flywheel 2 mech.
30 Visual inspect unusual sound of bearing 2 mech.
791 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 6 Months FEMA Task 10 Inspect of Screen replace if required 2 mech.
792 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 1 Weeks FEMA Task 10 Lubrication (Greasing) for bearing 1 mech.
793 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 2 Years FEMA Task 10 Inspect belt condition 8 mech.
20 Inspect knife and replace if required 4 mech.
794 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 3 Years FEMA Task 10 Inspect bearing 2 mech.
795 23Z-1602 FEMA-1 SAPCO MECH-SAP SPM 23Z-1602 Mechanical 5 Years FEMA Task 10 Inspect condition of Belt flywheel 2 mech.
20 Inspect of Drive pulley 2 mech.
796 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 40 Days FEMA Task 10 Greasing to be done 1 mech.
797 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 3 Months FEMA Task 10 Bearing greasing to be done 1 mech.
20 Greasing to be done for bearing 1 mech.
30 Clean Inlet chute of machine form inside 1 mech.
40 Visual insepction for gear box 1 mech.
798 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 6 Months FEMA Task 10 Check aspiration lines 2 mech.
20 Checking of bearings 2 mech.
30 Visual check for oil level & top up 2 mech.
40 Visual insepction for oil level 2 mech.
50 Visual inspection for condition bearing 2 mech.
799 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 1 Weeks FEMA Task 10 Check and adjust tension for Pol V-Belt 2 mech.
20 Check condition of belt 2 mech.
30 Check condition of belt & adjust tension 2 mech.
40 Clean grinder rolls 2 mech.
50 clean rolls and check condition of teeth 2 mech.
60 Open cover and clean feed rollers 2 mech.
70 Visual inspection for pulley 2 mech.
80 Visual inspection for shaft 2 mech.
800 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 1 Years FEMA Task 10 Check condition of belt 1 mech.
801 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 2 Years FEMA Task 10 Replace Gearbox oil with fresh oil 1 mech.
802 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 5 Years FEMA Task 10 Check condition of bearing 12 mech.
20 Check condition of rollers 12 mech.
30 Complete gear box overhauling 12 mech.
803 23Z-1610 FEMA-1 SAPCO MECH-SAP SPM 23Z-1610 Mechanical 10 Years FEMA Task 10 Check Homokinetic cardan shaft condition 2 mech.
20 Check condition of Pulley 2 mech.
804 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 3 Months FEMA Task 10 Bearing greasing to be done 2 mech.
20 Greasing to be done for bearing 2 mech.
30 Clean Inlet chute of machine form inside 2 mech.
40 Visual insepction for gear box 2 mech.
805 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 6 Months FEMA Task 10 Check aspiration lines 2 mech.

358122780.xlsx Page 25 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 Visual insepction for oil level 2 mech.
30 Visual inspection for condition bearing 2 mech.
40 Visual inspection of bearings 2 mech.
806 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 40 Months FEMA Task 10 Greasing to be done 1 mech.
807 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 1 Weeks FEMA Task 10 Check and adjust tension for Pol V-Belt 2 mech.
20 Check condition of belt 2 mech.
30 Check condition of belt & adjust tension 2 mech.
40 Clean grinder rolls 2 mech.
50 clean rolls and check condition of teeth 2 mech.
60 Open cover and clean feed rollers 2 mech.
70 Visual inspection for pulley 2 mech.
80 Visual inspection for shaft 2 mech.
808 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 1 Years FEMA Task 10 Check condition of belt 1 mech.
809 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 2 Years FEMA Task 10 Replace Gearbox oil with fresh oil 1 mech.
810 23Z-1611 FEMA-1 SAPCO MECH-SAP SPM 23Z-1611 Mechanical 5 Years FEMA Task 10 Complete gear box overhauling 12 mech.
811 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 3 Months FEMA Task 10 Bearing greasing to be done 2 mech.
20 Greasing to be done for bearing 2 mech.
30 Clean Inlet chute of machine form inside 2 mech.
40 Visual insepction for gear box 2 mech.
812 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 6 Months FEMA Task 10 Check aspiration lines 2 mech.
20 Visual insepction for oil level 2 mech.
30 Visual inspection for condition bearing 2 mech.
40 Visual inspection of bearings 2 mech.
813 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 40 Months FEMA Task 10 Greasing to be done 2 mech.
814 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 1 Weeks FEMA Task 10 Check and adjust tension for Pol V-Belt 2 mech.
20 Check condition of belt 2 mech.
30 Check condition of belt & adjust tension 2 mech.
40 Clean grinder rolls 2 mech.
50 clean rolls and check condition of teeth 2 mech.
60 Open cover and clean feed rollers 2 mech.
70 Visual inspection for pulley 2 mech.
80 Visual inspection for shaft 2 mech.
815 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 1 Years FEMA Task 10 Check condition of belt 2 mech.
816 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 2 Years FEMA Task 10 Replace Gearbox oil with fresh oil 1 mech.
817 23Z-1612 FEMA-1 SAPCO MECH-SAP SPM 23Z-1612 Mechanical 5 Years FEMA Task 10 Complete gear box overhauling 12 mech.
818 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 3 Months FEMA Task 10 Bearing greasing to be done 2 mech.
20 Greasing to be done for bearing 2 mech.
30 Clean Inlet chute of machine form inside 2 mech.
40 Visual insepction for gear box 2 mech.
819 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 6 Months FEMA Task 10 Check aspiration lines 1 mech.
20 Visual insepction for oil level 1 mech.
30 Visual inspection for condition bearing 1 mech.
40 Visual inspection of bearings 1 mech.
820 23F-1622-23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 40 Months FEMA Task 10 Greasing to be done 2 mech.
821 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 1 Weeks FEMA Task 10 Check and adjust tension for Pol V-Belt 2 mech.
20 Check condition of belt 2 mech.
30 Check condition of belt & adjust tension 2 mech.
40 Clean grinder rolls 2 mech.
50 clean rolls and check condition of teeth 2 mech.
60 Open cover and clean feed rollers 2 mech.
70 Visual inspection for pulley 2 mech.
80 Visual inspection for shaft 2 mech.
822 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 1 Years FEMA Task 10 Check condition of belt 2 mech.
823 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 2 Years FEMA Task 10 Replace Gearbox oil with fresh oil 2 mech.
824 23Z-1613 FEMA-1 SAPCO MECH-SAP SPM 23Z-1613 Mechanical 5 Years FEMA Task 10 Complete gear box overhauling 2 mech.
825 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
826 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 1 mech.
827 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 2 Months FEMA Task 10 To check condition of belt 1 mech.
828 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 6 Months FEMA Task 10 To check counterweight settings 2 mech.
829 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 1 Years FEMA Task 10 To replace the V-belt 1 mech.
830 23Z-1620 FEMA-1 SAPCO MECH-SAP SPM 23Z-1620 Mechanical 5 Years FEMA Task 10 To replace the bearing 24 mech.
20 To replace the shaft 24 mech.
831 23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
832 23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
833 23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 2 Months FEMA Task 10 To check condition of belt 1 mech.
834 23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 6 Months FEMA Task 10 To check counterweight settings 1 mech.

358122780.xlsx Page 26 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
835 23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 1 Years FEMA Task 10 To replace the V-belt 1 mech.
836 23F-1622-23Z-1621 FEMA-1 SAPCO MECH-SAP SPM 23Z-1621 Mechanical 5 Years FEMA Task 10 To replace the bearing 24 mech.
20 To replace the shaft 24 mech.
837 23F-1622-23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 35 Days FEMA Task 10 To inspect hose condition 2 mech.
838 23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 1 Months FEMA Task 10 Inspect the bearing condition visually 2 mech.
20 To check and replace screen 2 mech.
30 To check rubber spring elements 2 mech.
40 To check the ball size 2 mech.
50 To check condition of pulley 2 mech.
60 To check the tension 2 mech.
70 To inspect clamp condition & retight 2 mech.
80 To inspect the seal condition 2 mech.
90 To regrease the bearing 2 mech.
839 23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 2 Months FEMA Task 10 To check condition of belt 1 mech.
840 23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 6 Months FEMA Task 10 To check counterweight settings 1 mech.
841 23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 1 Years FEMA Task 10 To replace the V-belt 1 mech.
842 23Z-1622 FEMA-1 SAPCO MECH-SAP SPM 23Z-1622 Mechanical 5 Years FEMA Task 10 To replace the bearing 24 mech.
20 To replace the shaft 2 mech.
843 23Z-1720 FEMA-1 SAPCO MECH-SAP SPM 23Z-1720 Mechanical 3 Months FEMA Task 10 Check and retight all holding bolts 2 mech.
20 Check and tight all the holding bolts 2 mech.
30 Check bearing temperature for DE and NDE 2 mech.
40 Check level of oil and if required topup 2 mech.
50 Complete visual inspection for bearing 2 mech.
60 Inspect bolts, studs & bearing plates 2 mech.
70 Inspection and cleaning of screen 2 mech.
80 Monitor bearing temp & HX in & out temp 2 mech.
90 Visual inspection for any abnormility 2 mech.
100 Visual inspection for bearing condition 2 mech.
110 Inspect shaft condition 2 mech.
120 Visual inspection for shaft condition 2 mech.
130 Inspect shaft coupling condition 2 mech.
844 23Z-1720 FEMA-1 SAPCO MECH-SAP SPM 23Z-1720 Mechanical 6 Months FEMA Task 10 Inspect of screen & replace if required 2 mech.
845 23Z-1720 FEMA-1 SAPCO MECH-SAP SPM 23Z-1720 Mechanical 1 Years FEMA Task 10 Replace gearbox oil 1 mech.
846 23Z-1720 FEMA-1 SAPCO MECH-SAP SPM 23Z-1720 Mechanical 3 Years FEMA Task 10 Back flush exchanger & clean external 2 mech.
20 Check for condition of blades 2 mech.
30 Check condition of bearing 2 mech.
40 Check condition of shaft 2 mech.
50 Check condition of shaft 2 mech.
60 Check condition of shaft coupling 2 mech.
70 Inspect basket 2 mech.
847 23Z-1720 FEMA-1 SAPCO MECH-SAP SPM 23Z-1720 Mechanical 5 Years FEMA Task 10 Overhauling to be done for gearbox 8 mech.
848 23Z-1850 FEMA-1 SAPCO MECH-SAP SPM 23Z-1850 Mechanical 3 Months FEMA Task 10 Check and retight all holding bolts 2 mech.
20 Check and tight all the holding bolts 2 mech.
30 Check bearing temperature for DE and NDE 2 mech.
40 Check level of oil and if required topup 2 mech.
50 Complete visual inspection for bearing 2 mech.
60 Inspect bolts, studs & bearing plates 2 mech.
70 Inspect of screen & replace if required 2 mech.
80 Inspection and cleaning of screen 2 mech.
90 Monitor bearing temp & HX in & out temp 2 mech.
100 Visual inspection for any abnormility 2 mech.
110 Visual inspection for bearing condition 2 mech.
120 Inspect shaft condition 2 mech.
130 Visual inspection for shaft condition 2 mech.
140 Inspect shaft coupling condition 2 mech.
849 23Z-1850 FEMA-1 SAPCO MECH-SAP SPM 23Z-1850 Mechanical 1 Years FEMA Task 10 Replace gearbox oil 2 mech.
850 23Z-1850 FEMA-1 SAPCO MECH-SAP SPM 23Z-1850 Mechanical 3 Years FEMA Task 10 Back flush exchanger & clean external 1 mech.
20 Check for condition of blades 1 mech.
30 Check condition of bearing 1 mech.
40 Check condition of shaft 1 mech.
50 Check condition of bearing 1 mech.
60 Check condition of shaft coupling 1 mech.
70 Inspect basket 1 mech.
851 23Z-1850 FEMA-1 SAPCO MECH-SAP SPM 23Z-1850 Mechanical 5 Years FEMA Task 10 Overhauling to be done for gearbox 4 mech.
852 23Z-2410 FEMA-1 SAPCO MECH-SAP SPM 23Z-2410 Mechanical 35 Days FEMA Task 10 Function test operation of gate 1 mech.
20 To do greasing for bearing 1 mech.
30 Visual inspection for any abnormility 1 mech.
40 Inspect bearing & shaft rotation 1 mech.
50 Visual inspection of blades and cleaning 1 mech.
60 Visual inspection of shaft and cleaning 1 mech.
70 Visual inspection of stuffing box 1 mech.
80 Visual inspection of trough gasket 1 mech.
853 23Z-2410 FEMA-1 SAPCO MECH-SAP SPM 23Z-2410 Mechanical 3 Months FEMA Task 10 Inspect and grease bearing for gate 2 mech.
20 Top up oil 1 mech.
854 23Z-2410 FEMA-1 SAPCO MECH-SAP SPM 23Z-2410 Mechanical 1 Years FEMA Task 10 Replace GB oil 2 mech.
855 23Z-2410 FEMA-1 SAPCO MECH-SAP SPM 23Z-2410 Mechanical 5 Years FEMA Task 10 Check and if required replace bearing 8 mech.
20 Inspect and if required replace bearing 8 mech.
30 Inspect replace blades 8 mech.
40 Inspect replace stuffing box internals 8 mech.
50 Inspect replace trough gasket 8 mech.
60 Overhauling for GB 8 mech.
856 23Z-2420 FEMA-1 SAPCO MECH-SAP SPM 23Z-2420 Mechanical 35 Days FEMA Task 10 Function test operation of gate 2 mech.

358122780.xlsx Page 27 of 49
CENTRAL MAINTENANCE SERVICES
PM EQUIPMENT TASK LIST DATA IN SAP
FO-MNT-CMS-20 Rev.01

ACTION REQUIRED : ADD CHANGE DELETE

SER OPERATION NO. OF ACTIVITY


EQUIPMENT NUMBER* MAINT STRATEGY* PLANT* WORK CENTER* PLANNER GROUP* TASK LIST DESCRIPTION* OPERATION DESCRIPTION *
NO. NUMBER HOURS* TYPE * D 3D 15D 35D 40D 70D 105D 210D W M Q 6M Y 2Y 3Y 2W 2M 3M 4M 40M 4Y 5Y 10Y
20 To do greasing for bearing 2 mech.
30 Visual inspection for any abnormility 2 mech.
40 Inspect bearing & shaft rotation 2 mech.
50 Visual inspection of blades and cleaning 2 mech.
60 Visual inspection of shaft and cleaning 2 mech.
70 Visual inspection of stuffing box 2 mech.
80 Visual inspection of trough gasket 2 mech.
857 23Z-2420 FEMA-1 SAPCO MECH-SAP SPM 23Z-2420 Mechanical 3 Months FEMA Task 10 Inspect and grease bearing for gate 2 mech.
20 Top up oil 2 mech.
858 23Z-2420 FEMA-1 SAPCO MECH-SAP SPM 23Z-2420 Mechanical 1 Years FEMA Task 10 Replace GB oil 2 mech.
859 23Z-2420 FEMA-1 SAPCO MECH-SAP SPM 23Z-2420 Mechanical 5 Years FEMA Task 10 Inspect and if required replace bearing 8 mech.
20 Inspect replace blades 8 mech.
30 Inspect replace stuffing box internals 8 mech.
40 Inspect replace trough gasket 8 mech.
50 Overhauling for GB 8 mech.
860 23Z-2500 FEMA-1 SAPCO MECH-SAP SPM 23Z-2500 Mechanical 35 Days FEMA Task 10 Bearing greasing to be done 2 mech.
20 Inspect shaft & blades 2 mech.
30 Visual inspect & clean externals of GB 2 mech.
861 23Z-2500 FEMA-1 SAPCO MECH-SAP SPM 23Z-2500 Mechanical 3 Months FEMA Task 10 Check oil level 2 mech.
20 Check oil level & visual oil quality 2 mech.
30 Coupling visual inspect &external clean 2 mech.
40 Visual inspection & external clean of GB 2 mech.
50 Visual inspection & replace grease 2 mech.
862 23Z-2500 FEMA-1 SAPCO MECH-SAP SPM 23Z-2500 Mechanical 1 Years FEMA Task 10 Replace GB oil with fresh oil 2 mech.
863 23Z-2500 FEMA-1 SAPCO MECH-SAP SPM 23Z-2500 Mechanical 3 Years FEMA Task 10 Inspection of bearing 2 mech.
864 23Z-2500 FEMA-1 SAPCO MECH-SAP SPM 23Z-2500 Mechanical 5 Years FEMA Task 10 Complete inspection shaft 8 mech.
20 Complete inspection shaft blade 8 mech.
30 Inspect coupling 4 mech.
40 Complete Overhauling to be done for GB 8 mech.
865 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 35 Days FEMA Task 10 Check & clean DRY air inlet & Vent line 2 mech.
20 Check belt tension 2 mech.
30 Check condition of belt 2 mech.
40 Check sealing for cutting mill covers 2 mech.
50 Check condition rotor and stator knives 2 mech.
60 Check condition of Rotor & stator knives 2 mech.
70 Check gap of rotor & stator knives 2 mech.
80 Clean cutting mill internals 2 mech.
90 Inspect & clean screen for cutting mill 2 mech.
866 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 3 Months FEMA Task 10 Inspect condition of drive pulley 2 mech.
20 Inspect condition of flywheel 2 mech.
30 Visual inspect unusual sound of bearing 2 mech.
867 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 6 Months FEMA Task 10 Inspect of Screen replace if required 1 mech.
868 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 1 Weeks FEMA Task 10 Lubrication (Greasing) for bearing 1 mech.
869 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 2 Years FEMA Task 10 Inspect belt condition 1 mech.
20 Inspect knife and replace if required 4 mech.
870 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 3 Years FEMA Task 10 Inspect bearing 1 mech.
871 23Z-2601 FEMA-1 SAPCO MECH-SAP SPM 23Z-2601 Mechanical 5 Years FEMA Task 10 Inspect condition of Belt flywheel 2 mech.
20 Inspect of Drive pulley 8 mech.
872 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 35 Days FEMA Task 10 Check & clean DRY air inlet & Vent line 2 mech.
20 Check belt tension 2 mech.
30 Check condition of belt 2 mech.
40 Check sealing for cutting mill covers 2 mech.
50 Check condition rotor and stator knives 2 mech.
60 Check condition of Rotor & stator knives 2 mech.
70 Check gap of rotor & stator knives 2 mech.
80 Clean cutting mill internals 2 mech.
90 Inspect & clean screen for cutting mill 2 mech.
873 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 3 Months FEMA Task 10 Inspect condition of drive pulley 1 mech.
20 Inspect condition of flywheel 1 mech.
30 Visual inspect unusual sound of bearing 1 mech.
874 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 6 Months FEMA Task 10 Inspect of Screen replace if required 2 mech.
875 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 1 Weeks FEMA Task 10 Lubrication (Greasing) for bearing 1 mech.
876 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 2 Years FEMA Task 10 Inspect belt condition 2 mech.
20 Inspect knife and replace if required 2 mech.
877 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 3 Years FEMA Task 10 Inspect bearing 1 mech.
878 23Z-2602 FEMA-1 SAPCO MECH-SAP SPM 23Z-2602 Mechanical 5 Years FEMA Task 10 Inspect condition of Belt flywheel 2 mech.
20 Inspect of Drive pulley 2 mech.
30 Visual inspect & lub with Silicone spray 2 mech.

Notes: * Fields are mandatory


insert rows as required
signatures required on last page only

Requested by: Approved by (end-user Supervisor): Approved by (Superintendent): Updated in SAP by:

___________________________ ___________________________ ___________________________ ___________________________


(Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date)

358122780.xlsx Page 28 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
1 SAPCO FEMA-1 2340PVSV-0117 Mechanical 1 Years FEMA 2340PVSV-0117 MECH-SAP 5 SPM 1 Y
2 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1501 MECH-SAP 5 SPM 35 D
3 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1501 MECH-SAP 5 SPM 6 M
4 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1501 MECH-SAP 5 SPM 5 Y
5 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1502 MECH-SAP 5 SPM 35 D
6 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1502 MECH-SAP 5 SPM 6 M
7 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1502 MECH-SAP 5 SPM 5 Y
8 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1503 MECH-SAP 5 SPM 35 D
9 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1503 MECH-SAP 5 SPM 6 M
10 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1503 MECH-SAP 5 SPM 5 Y
11 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1504 MECH-SAP 5 SPM 35 D
12 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1504 MECH-SAP 5 SPM 6 M
13 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1504 MECH-SAP 5 SPM 5 Y
14 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1505 MECH-SAP 5 SPM 35 D
15 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1505 MECH-SAP 5 SPM 6 M
16 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1505 MECH-SAP 5 SPM 5 Y
17 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1506 MECH-SAP 5 SPM 35 D
18 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1506 MECH-SAP 5 SPM 6 M
19 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1506 MECH-SAP 5 SPM 5 Y
20 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1507 MECH-SAP 5 SPM 35 D
21 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1507 MECH-SAP 5 SPM 6 M
22 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1507 MECH-SAP 5 SPM 5 Y
23 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1508 MECH-SAP 5 SPM 35 D
24 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1508 MECH-SAP 5 SPM 6 M
25 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1508 MECH-SAP 5 SPM 5 Y
26 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1509 MECH-SAP 5 SPM 35 D
27 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1509 MECH-SAP 5 SPM 6 M
28 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1509 MECH-SAP 5 SPM 5 Y
29 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1510 MECH-SAP 5 SPM 35 D
30 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1510 MECH-SAP 5 SPM 6 M
31 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1510 MECH-SAP 5 SPM 5 Y
32 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1511 MECH-SAP 5 SPM 35 D
33 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1511 MECH-SAP 5 SPM 6 M
34 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1511 MECH-SAP 5 SPM 5 Y
35 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1512 MECH-SAP 5 SPM 35 D
36 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1512 MECH-SAP 5 SPM 6 M
37 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1512 MECH-SAP 5 SPM 5 Y
38 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1513 MECH-SAP 5 SPM 35 D
39 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1513 MECH-SAP 5 SPM 6 M
40 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1513 MECH-SAP 5 SPM 5 Y
41 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1514 MECH-SAP 5 SPM 35 D
42 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1514 MECH-SAP 5 SPM 6 M
43 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1514 MECH-SAP 5 SPM 5 Y
44 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1515 MECH-SAP 5 SPM 35 D
45 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1515 MECH-SAP 5 SPM 6 M
46 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1515 MECH-SAP 5 SPM 5 Y
47 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1516 MECH-SAP 5 SPM 35 D
48 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1516 MECH-SAP 5 SPM 6 M
49 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1516 MECH-SAP 5 SPM 5 Y
50 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-1517 MECH-SAP 5 SPM 35 D
51 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-1517 MECH-SAP 5 SPM 6 M
52 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-1517 MECH-SAP 5 SPM 5 Y
53 SAPCO FEMA-1 23AB-1530 Mechanical 35 Days FEMA Task 23AB-1530 MECH-SAP 5 SPM 35 D
54 SAPCO FEMA-1 23AB-1530 Mechanical 3 Months FEMA Task 23AB-1530 MECH-SAP 5 SPM 3 M
55 SAPCO FEMA-1 23AB-1530 Mechanical 6 Months FEMA Task 23AB-1530 MECH-SAP 5 SPM 6 M
56 SAPCO FEMA-1 23AB-1530 Mechanical 1 Years FEMA Task 23AB-1530 MECH-SAP 5 SPM 1 Y
57 SAPCO FEMA-1 23AB-1530 Mechanical 2 Years FEMA Task 23AB-1530 MECH-SAP 5 SPM 2 Y

358122780.xlsx Page 30 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
58 SAPCO FEMA-1 23AB-1530 Mechanical 5 Years FEMA Task 23AB-1530 MECH-SAP 5 SPM 5 Y
59 SAPCO FEMA-1 23AB-1541 Mechanical 35 Days FEMA Task 23AB-1541 MECH-SAP 5 SPM 35 D
60 SAPCO FEMA-1 23AB-1541 Mechanical 3 Months FEMA Task 23AB-1541 MECH-SAP 5 SPM 3 M
61 SAPCO FEMA-1 23AB-1541 Mechanical 1 Years FEMA Task 23AB-1541 MECH-SAP 5 SPM 1 Y
62 SAPCO FEMA-1 23AB-1541 Mechanical 3 Years FEMA Task 23AB-1541 MECH-SAP 5 SPM 3 Y
63 SAPCO FEMA-1 23AB-1720 Mechanical 1 Months FEMA Task 23AB-1720 MECH-SAP 5 SPM 1 M
64 SAPCO FEMA-1 23AB-1720 Mechanical 3 Months FEMA Task 23AB-1720 MECH-SAP 5 SPM 3 M
65 SAPCO FEMA-1 23AB-1720 Mechanical 6 Months FEMA Task 23AB-1720 MECH-SAP 5 SPM 6 M
66 SAPCO FEMA-1 23AB-1720 Mechanical 1 Years FEMA Task 23AB-1720 MECH-SAP 5 SPM 1 Y
67 SAPCO FEMA-1 23AB-1720 Mechanical 3 Years FEMA Task 23AB-1720 MECH-SAP 5 SPM 3 Y
68 SAPCO FEMA-1 23AB-1740 Mechanical 35 Days FEMA Task 23AB-1740 MECH-SAP 5 SPM 35 D
69 SAPCO FEMA-1 23AB-1740 Mechanical 1 Months FEMA Task 23AB-1740 MECH-SAP 5 SPM 1 M
70 SAPCO FEMA-1 23AB-1740 Mechanical 3 Months FEMA Task 23AB-1740 MECH-SAP 5 SPM 3 M
71 SAPCO FEMA-1 23AB-1740 Mechanical 1 Years FEMA Task 23AB-1740 MECH-SAP 5 SPM 1 Y
72 SAPCO FEMA-1 23AB-1740 Mechanical 3 Years FEMA Task 23AB-1740 MECH-SAP 5 SPM 3 Y
73 SAPCO FEMA-1 23AB-1740 Mechanical 5 Years FEMA Task 23AB-1740 MECH-SAP 5 SPM 5 Y
74 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2501 MECH-SAP 5 SPM 35 D
75 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2501 MECH-SAP 5 SPM 6 M
76 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2501 MECH-SAP 5 SPM 5 Y
77 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2502 MECH-SAP 5 SPM 35 D
78 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2502 MECH-SAP 5 SPM 6 M
79 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2502 MECH-SAP 5 SPM 5 Y
80 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2503 MECH-SAP 5 SPM 35 D
81 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2503 MECH-SAP 5 SPM 6 M
82 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2503 MECH-SAP 5 SPM 5 Y
83 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2504 MECH-SAP 5 SPM 35 D
84 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2504 MECH-SAP 5 SPM 6 M
85 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2504 MECH-SAP 5 SPM 5 Y
86 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2505 MECH-SAP 5 SPM 35 D
87 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2505 MECH-SAP 5 SPM 6 M
88 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2505 MECH-SAP 5 SPM 5 Y
89 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2506 MECH-SAP 5 SPM 35 D
90 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2506 MECH-SAP 5 SPM 6 M
91 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2506 MECH-SAP 5 SPM 5 Y
92 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2507 MECH-SAP 5 SPM 35 D
93 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2507 MECH-SAP 5 SPM 6 M
94 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2507 MECH-SAP 5 SPM 5 Y
95 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2508 MECH-SAP 5 SPM 35 D
96 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2508 MECH-SAP 5 SPM 6 M
97 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2508 MECH-SAP 5 SPM 5 Y
98 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2509 MECH-SAP 5 SPM 35 D
99 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2509 MECH-SAP 5 SPM 6 M
100 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2509 MECH-SAP 5 SPM 5 Y
101 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2510 MECH-SAP 5 SPM 35 D
102 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2510 MECH-SAP 5 SPM 6 M
103 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2510 MECH-SAP 5 SPM 5 Y
104 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2511 MECH-SAP 5 SPM 35 D
105 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2511 MECH-SAP 5 SPM 6 M
106 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2511 MECH-SAP 5 SPM 5 Y
107 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2512 MECH-SAP 5 SPM 35 D
108 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2512 MECH-SAP 5 SPM 6 M
109 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2512 MECH-SAP 5 SPM 5 Y
110 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2513 MECH-SAP 5 SPM 35 D
111 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2513 MECH-SAP 5 SPM 6 M
112 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2513 MECH-SAP 5 SPM 5 Y
113 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2514 MECH-SAP 5 SPM 35 D
114 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2514 MECH-SAP 5 SPM 6 M

358122780.xlsx Page 31 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
115 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2514 MECH-SAP 5 SPM 5 Y
116 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2515 MECH-SAP 5 SPM 35 D
117 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2515 MECH-SAP 5 SPM 6 M
118 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2515 MECH-SAP 5 SPM 5 Y
119 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2516 MECH-SAP 5 SPM 35 D
120 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2516 MECH-SAP 5 SPM 6 M
121 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2516 MECH-SAP 5 SPM 5 Y
122 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2517 MECH-SAP 5 SPM 35 D
123 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2517 MECH-SAP 5 SPM 6 M
124 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2517 MECH-SAP 5 SPM 5 Y
125 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2530 MECH-SAP 5 SPM 35 D
126 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2530 MECH-SAP 5 SPM 6 M
127 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2530 MECH-SAP 5 SPM 5 Y
128 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2541 MECH-SAP 5 SPM 35 D
129 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2541 MECH-SAP 5 SPM 6 M
130 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2541 MECH-SAP 5 SPM 5 Y
131 SAPCO FEMA-1 23AB-1501 Mechanical 35 Days FEMA Task 23AB-2740 MECH-SAP 5 SPM 35 D
132 SAPCO FEMA-1 23AB-1501 Mechanical 6 Months FEMA Task 23AB-2740 MECH-SAP 5 SPM 6 M
133 SAPCO FEMA-1 23AB-1501 Mechanical 5 Years FEMA Task 23AB-2740 MECH-SAP 5 SPM 5 Y
134 SAPCO FEMA-1 23AB-7201 Mechanical 35 Days FEMA Task 23AB-7201 MECH-SAP 5 SPM 35 D
135 SAPCO FEMA-1 23AB-7201 Mechanical 1 Months FEMA Task 23AB-7201 MECH-SAP 5 SPM 1 M
136 SAPCO FEMA-1 23AB-7201 Mechanical 3 Months FEMA Task 23AB-7201 MECH-SAP 5 SPM 3 M
137 SAPCO FEMA-1 23AB-7201 Mechanical 6 Months FEMA Task 23AB-7201 MECH-SAP 5 SPM 6 M
138 SAPCO FEMA-1 23AB-7201 Mechanical 1 Years FEMA Task 23AB-7201 MECH-SAP 5 SPM 1 Y
139 SAPCO FEMA-1 23AB-7201 Mechanical 3 Years FEMA Task 23AB-7201 MECH-SAP 5 SPM 3 Y
140 SAPCO FEMA-1 23AB-7210 Mechanical 35 Days FEMA Task 23AB-7210 MECH-SAP 5 SPM 35 D
141 SAPCO FEMA-1 23AB-7210 Mechanical 1 Months FEMA Task 23AB-7210 MECH-SAP 5 SPM 1 M
142 SAPCO FEMA-1 23AB-7210 Mechanical 3 Months FEMA Task 23AB-7210 MECH-SAP 5 SPM 3 M
143 SAPCO FEMA-1 23AB-7210 Mechanical 6 Months FEMA Task 23AB-7210 MECH-SAP 5 SPM 6 M
144 SAPCO FEMA-1 23AB-7210 Mechanical 1 Years FEMA Task 23AB-7210 MECH-SAP 5 SPM 1 Y
145 SAPCO FEMA-1 23AB-7210 Mechanical 3 Years FEMA Task 23AB-7210 MECH-SAP 5 SPM 3 Y
146 SAPCO FEMA-1 23AB-7220 Mechanical 35 Days FEMA Task 23AB-7220 MECH-SAP 5 SPM 35 D
147 SAPCO FEMA-1 23AB-7220 Mechanical 1 Months FEMA Task 23AB-7220 MECH-SAP 5 SPM 1 M
148 SAPCO FEMA-1 23AB-7220 Mechanical 3 Months FEMA Task 23AB-7220 MECH-SAP 5 SPM 3 M
149 SAPCO FEMA-1 23AB-7220 Mechanical 6 Months FEMA Task 23AB-7220 MECH-SAP 5 SPM 6 M
150 SAPCO FEMA-1 23AB-7220 Mechanical 1 Years FEMA Task 23AB-7220 MECH-SAP 5 SPM 1 Y
151 SAPCO FEMA-1 23AB-7220 Mechanical 3 Years FEMA Task 23AB-7220 MECH-SAP 5 SPM 3 Y
152 SAPCO FEMA-1 23AB-7230 Mechanical 35 Days FEMA Task 23AB-7230 MECH-SAP 5 SPM 35 D
153 SAPCO FEMA-1 23AB-7230 Mechanical 1 Months FEMA Task 23AB-7230 MECH-SAP 5 SPM 1 M
154 SAPCO FEMA-1 23AB-7230 Mechanical 3 Months FEMA Task 23AB-7230 MECH-SAP 5 SPM 3 M
155 SAPCO FEMA-1 23AB-7230 Mechanical 6 Months FEMA Task 23AB-7230 MECH-SAP 5 SPM 6 M
156 SAPCO FEMA-1 23AB-7230 Mechanical 1 Years FEMA Task 23AB-7230 MECH-SAP 5 SPM 1 Y
157 SAPCO FEMA-1 23AB-7230 Mechanical 3 Years FEMA Task 23AB-7230 MECH-SAP 5 SPM 3 Y
158 SAPCO FEMA-1 23AB-7240 Mechanical 35 Days FEMA Task 23AB-7240 MECH-SAP 5 SPM 35 D
159 SAPCO FEMA-1 23AB-7240 Mechanical 1 Months FEMA Task 23AB-7240 MECH-SAP 5 SPM 1 M
160 SAPCO FEMA-1 23AB-7240 Mechanical 3 Months FEMA Task 23AB-7240 MECH-SAP 5 SPM 3 M
161 SAPCO FEMA-1 23AB-7240 Mechanical 6 Months FEMA Task 23AB-7240 MECH-SAP 5 SPM 6 M
162 SAPCO FEMA-1 23AB-7240 Mechanical 1 Years FEMA Task 23AB-7240 MECH-SAP 5 SPM 1 Y
163 SAPCO FEMA-1 23AB-7240 Mechanical 5 Years FEMA Task 23AB-7240 MECH-SAP 5 SPM 5 Y
164 SAPCO FEMA-1 23AB-7250 Mechanical 35 Days FEMA Task 23AB-7250 MECH-SAP 5 SPM 35 D
165 SAPCO FEMA-1 23AB-7250 Mechanical 1 Months FEMA Task 23AB-7250 MECH-SAP 5 SPM 1 M
166 SAPCO FEMA-1 23AB-7250 Mechanical 3 Months FEMA Task 23AB-7250 MECH-SAP 5 SPM 3 M
167 SAPCO FEMA-1 23AB-7250 Mechanical 6 Months FEMA Task 23AB-7250 MECH-SAP 5 SPM 6 M
168 SAPCO FEMA-1 23AB-7250 Mechanical 1 Years FEMA Task 23AB-7250 MECH-SAP 5 SPM 1 Y
169 SAPCO FEMA-1 23AB-7250 Mechanical 3 Years FEMA Task 23AB-7250 MECH-SAP 5 SPM 3 Y
170 SAPCO FEMA-1 23AB-7260 Mechanical 35 Days FEMA Task 23AB-7260 MECH-SAP 5 SPM 35 D
171 SAPCO FEMA-1 23AB-7260 Mechanical 1 Months FEMA Task 23AB-7260 MECH-SAP 5 SPM 1 M

358122780.xlsx Page 32 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
172 SAPCO FEMA-1 23AB-7260 Mechanical 3 Months FEMA Task 23AB-7260 MECH-SAP 5 SPM 3 M
173 SAPCO FEMA-1 23AB-7260 Mechanical 6 Months FEMA Task 23AB-7260 MECH-SAP 5 SPM 6 M
174 SAPCO FEMA-1 23AB-7260 Mechanical 1 Years FEMA Task 23AB-7260 MECH-SAP 5 SPM 1 Y
175 SAPCO FEMA-1 23AB-7260 Mechanical 3 Years FEMA Task 23AB-7260 MECH-SAP 5 SPM 3 Y
176 SAPCO FEMA-1 23AB-7501 Mechanical 35 Days FEMA Task 23AB-7501 MECH-SAP 5 SPM 35 D
177 SAPCO FEMA-1 23AB-7501 Mechanical 3 Months FEMA Task 23AB-7501 MECH-SAP 5 SPM 3 M
178 SAPCO FEMA-1 23AB-7501 Mechanical 6 Months FEMA Task 23AB-7501 MECH-SAP 5 SPM 6 M
179 SAPCO FEMA-1 23AB-7501 Mechanical 1 Years FEMA Task 23AB-7501 MECH-SAP 5 SPM 1 Y
180 SAPCO FEMA-1 23AB-7501 Mechanical 5 Years FEMA Task 23AB-7501 MECH-SAP 5 SPM 5 Y
181 SAPCO FEMA-1 23AB-7502 Mechanical 35 Days FEMA Task 23AB-7502 MECH-SAP 5 SPM 35 D
182 SAPCO FEMA-1 23AB-7502 Mechanical 3 Months FEMA Task 23AB-7502 MECH-SAP 5 SPM 3 M
183 SAPCO FEMA-1 23AB-7502 Mechanical 6 Months FEMA Task 23AB-7502 MECH-SAP 5 SPM 6 M
184 SAPCO FEMA-1 23AB-7502 Mechanical 1 Years FEMA Task 23AB-7502 MECH-SAP 5 SPM 1 Y
185 SAPCO FEMA-1 23AB-7502 Mechanical 3 Years FEMA Task 23AB-7502 MECH-SAP 5 SPM 3 Y
186 SAPCO FEMA-1 23AB-7511 Mechanical 35 Days FEMA Task 23AB-7511 MECH-SAP 5 SPM 35 D
187 SAPCO FEMA-1 23AB-7511 Mechanical 3 Months FEMA Task 23AB-7511 MECH-SAP 5 SPM 3 M
188 SAPCO FEMA-1 23AB-7511 Mechanical 6 Months FEMA Task 23AB-7511 MECH-SAP 5 SPM 6 M
189 SAPCO FEMA-1 23AB-7511 Mechanical 1 Years FEMA Task 23AB-7511 MECH-SAP 5 SPM 1 Y
190 SAPCO FEMA-1 23AB-7511 Mechanical 3 Years FEMA Task 23AB-7511 MECH-SAP 5 SPM 3 Y
191 SAPCO FEMA-1 23DV-1660 Mechanical 3 Months FEMA Task 23DV-1660 MECH-SAP 5 SPM 3 M
192 SAPCO FEMA-1 23DV-1660 Mechanical 6 Months FEMA Task 23DV-1660 MECH-SAP 5 SPM 6 M
193 SAPCO FEMA-1 23E-1100 Mechanical 3 Months FEMA Task 23E-1100 MECH-SAP 5 SPM 3 M
194 SAPCO FEMA-1 23E-1100 Mechanical 6 Months FEMA Task 23E-1100 MECH-SAP 5 SPM 6 M
195 SAPCO FEMA-1 23E-1100 Mechanical 2 Years FEMA Task 23E-1100 MECH-SAP 5 SPM 2 Y
196 SAPCO FEMA-1 23E-1101 Mechanical 6 Months FEMA Task 23E-1101 MECH-SAP 5 SPM 6 M
197 SAPCO FEMA-1 23E-1101 Mechanical 2 Years FEMA Task 23E-1101 MECH-SAP 5 SPM 2 Y
198 SAPCO FEMA-1 23E-1101 Mechanical 3 Months FEMA Task 23E-1101 MECH-SAP 5 SPM 3 M
199 SAPCO FEMA-1 23E-1101 Mechanical 6 Months FEMA Task 23E-1101 MECH-SAP 5 SPM 6 M
200 SAPCO FEMA-1 23E-1101 Mechanical 2 Years FEMA Task 23E-1101 MECH-SAP 5 SPM 2 Y
201 SAPCO FEMA-1 23E-1102 Mechanical 3 Months FEMA Task 23E-1102 MECH-SAP 5 SPM 3 M
202 SAPCO FEMA-1 23E-1102 Mechanical 6 Months FEMA Task 23E-1102 MECH-SAP 5 SPM 6 M
203 SAPCO FEMA-1 23E-1102 Mechanical 2 Years FEMA Task 23E-1102 MECH-SAP 5 SPM 2 Y
204 SAPCO FEMA-1 23E-1103 Mechanical 3 Months FEMA Task 23E-1103 MECH-SAP 5 SPM 3 M
205 SAPCO FEMA-1 23E-1103 Mechanical 6 Months FEMA Task 23E-1103 MECH-SAP 5 SPM 6 M
206 SAPCO FEMA-1 23E-1103 Mechanical 2 Years FEMA Task 23E-1103 MECH-SAP 5 SPM 2 Y
207 SAPCO FEMA-1 23E-1725 Mechanical 6 Months FEMA Task 23E-1725 MECH-SAP 5 SPM 6 M
208 SAPCO FEMA-1 23E-1725 Mechanical 2 Years FEMA Task 23E-1725 MECH-SAP 5 SPM 2 Y
209 SAPCO FEMA-1 23E-1725 Mechanical 5 Years FEMA Task 23E-1725 MECH-SAP 5 SPM 5 Y
210 SAPCO FEMA-1 23E-4001 Mechanical 3 Months FEMA Task 23E-4001 MECH-SAP 5 SPM 3 M
211 SAPCO FEMA-1 23E-4001 Mechanical 6 Months FEMA Task 23E-4001 MECH-SAP 5 SPM 6 M
212 SAPCO FEMA-1 23E-4001 Mechanical 1 Years FEMA Task 23E-4001 MECH-SAP 5 SPM 1 Y
213 SAPCO FEMA-1 23E-4001 Mechanical 2 Years FEMA Task 23E-4001 MECH-SAP 5 SPM 2 Y
214 SAPCO FEMA-1 23E-7201 Mechanical 3 Months FEMA Task 23E-7201 MECH-SAP 5 SPM 3 M
215 SAPCO FEMA-1 23E-7201 Mechanical 6 Months FEMA Task 23E-7201 MECH-SAP 5 SPM 6 M
216 SAPCO FEMA-1 23E-7201 Mechanical 2 Years FEMA Task 23E-7201 MECH-SAP 5 SPM 2 Y
217 SAPCO FEMA-1 23E-7210 Mechanical 3 Months FEMA Task 23E-7210 MECH-SAP 5 SPM 3 M
218 SAPCO FEMA-1 23E-7210 Mechanical 6 Months FEMA Task 23E-7210 MECH-SAP 5 SPM 6 M
219 SAPCO FEMA-1 23E-7210 Mechanical 2 Years FEMA Task 23E-7210 MECH-SAP 5 SPM 2 Y
220 SAPCO FEMA-1 23E-7220 Mechanical 3 Months FEMA Task 23E-7220 MECH-SAP 5 SPM 3 M
221 SAPCO FEMA-1 23E-7220 Mechanical 6 Months FEMA Task 23E-7220 MECH-SAP 5 SPM 6 M
222 SAPCO FEMA-1 23E-7220 Mechanical 2 Years FEMA Task 23E-7220 MECH-SAP 5 SPM 2 Y
223 SAPCO FEMA-1 23E-7230 Mechanical 3 Months FEMA Task 23E-7230 MECH-SAP 5 SPM 3 M
224 SAPCO FEMA-1 23E-7230 Mechanical 6 Months FEMA Task 23E-7230 MECH-SAP 5 SPM 6 M
225 SAPCO FEMA-1 23E-7230 Mechanical 2 Years FEMA Task 23E-7230 MECH-SAP 5 SPM 2 Y
226 SAPCO FEMA-1 23E-9001 Mechanical 2 Years FEMA Task 23E-9001 MECH-SAP 5 SPM 2 Y
227 SAPCO FEMA-1 23E-9001 Mechanical 3 Months FEMA Task 23E-9001 MECH-SAP 5 SPM 3 M
228 SAPCO FEMA-1 23E-9001 Mechanical 6 Months FEMA Task 23E-9001 MECH-SAP 5 SPM 6 M

358122780.xlsx Page 33 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
229 SAPCO FEMA-1 23E-9001 Mechanical 2 Years FEMA Task 23E-9001 MECH-SAP 5 SPM 2 Y
230 SAPCO FEMA-1 23EJ-4001 Mechanical 1 Years FEMA Task 23EJ-4001 MECH-SAP 5 SPM 1 Y
231 SAPCO FEMA-1 23EX-1410 Mechanical 35 Days FEMA Task 23EX-1410 MECH-SAP 5 SPM 35 D
232 SAPCO FEMA-1 23EX-1410 Mechanical 6 Months FEMA Task 23EX-1410 MECH-SAP 5 SPM 6 M
233 SAPCO FEMA-1 23EX-1410 Mechanical 1 Years FEMA Task 23EX-1410 MECH-SAP 5 SPM 1 Y
234 SAPCO FEMA-1 23EX-1410 Mechanical 3 Years FEMA Task 23EX-1410 MECH-SAP 5 SPM 3 Y
235 SAPCO FEMA-1 23EX-1410 Mechanical 5 Years FEMA Task 23EX-1410 MECH-SAP 5 SPM 5 Y
236 SAPCO FEMA-1 23EX-1420 Mechanical 35 Days FEMA Task 23EX-1420 MECH-SAP 5 SPM 35 D
237 SAPCO FEMA-1 23EX-1420 Mechanical 6 Months FEMA Task 23EX-1420 MECH-SAP 5 SPM 6 M
238 SAPCO FEMA-1 23EX-1420 Mechanical 1 Years FEMA Task 23EX-1420 MECH-SAP 5 SPM 1 Y
239 SAPCO FEMA-1 23EX-1420 Mechanical 3 Years FEMA Task 23EX-1420 MECH-SAP 5 SPM 3 Y
240 SAPCO FEMA-1 23EX-1420 Mechanical 5 Years FEMA Task 23EX-1420 MECH-SAP 5 SPM 5 Y
241 SAPCO FEMA-1 23EX-2410 Mechanical 35 Days FEMA Task 23EX-2410 MECH-SAP 5 SPM 35 D
242 SAPCO FEMA-1 23EX-2410 Mechanical 6 Months FEMA Task 23EX-2410 MECH-SAP 5 SPM 6 M
243 SAPCO FEMA-1 23EX-2410 Mechanical 1 Years FEMA Task 23EX-2410 MECH-SAP 5 SPM 1 Y
244 SAPCO FEMA-1 23EX-2410 Mechanical 3 Years FEMA Task 23EX-2410 MECH-SAP 5 SPM 3 Y
245 SAPCO FEMA-1 23EX-2410 Mechanical 5 Years FEMA Task 23EX-2410 MECH-SAP 5 SPM 5 Y
246 SAPCO FEMA-1 23EX-2420 Mechanical 35 Days FEMA Task 23EX-2420 MECH-SAP 5 SPM 35 D
247 SAPCO FEMA-1 23EX-2420 Mechanical 6 Months FEMA Task 23EX-2420 MECH-SAP 5 SPM 6 M
248 SAPCO FEMA-1 23EX-2420 Mechanical 1 Years FEMA Task 23EX-2420 MECH-SAP 5 SPM 1 Y
249 SAPCO FEMA-1 23EX-2420 Mechanical 3 Years FEMA Task 23EX-2420 MECH-SAP 5 SPM 3 Y
250 SAPCO FEMA-1 23EX-2420 Mechanical 5 Years FEMA Task 23EX-2420 MECH-SAP 5 SPM 5 Y
251 SAPCO FEMA-1 23F-1601 Mechanical 3 Months FEMA Task 23F-1601 MECH-SAP 5 SPM 3 M
252 SAPCO FEMA-1 23F-1601 Mechanical 6 Months FEMA Task 23F-1601 MECH-SAP 5 SPM 6 M
253 SAPCO FEMA-1 23F-1610 Mechanical 1 Months FEMA Task 23F-1610 MECH-SAP 5 SPM 1 M
254 SAPCO FEMA-1 23F-1610 Mechanical 2 Months FEMA Task 23F-1610 MECH-SAP 5 SPM 2 M
255 SAPCO FEMA-1 23F-1610 Mechanical 6 Months FEMA Task 23F-1610 MECH-SAP 5 SPM 6 M
256 SAPCO FEMA-1 23F-1610 Mechanical 1 Years FEMA Task 23F-1610 MECH-SAP 5 SPM 1 Y
257 SAPCO FEMA-1 23F-1610 Mechanical 5 Years FEMA Task 23F-1610 MECH-SAP 5 SPM 5 Y
258 SAPCO FEMA-1 23F-1611 Mechanical 35 Days FEMA Task 23F-1611 MECH-SAP 5 SPM 35 D
259 SAPCO FEMA-1 23F-1611 Mechanical 1 Months FEMA Task 23F-1611 MECH-SAP 5 SPM 1 M
260 SAPCO FEMA-1 23F-1611 Mechanical 2 Months FEMA Task 23F-1611 MECH-SAP 5 SPM 2 M
261 SAPCO FEMA-1 23F-1611 Mechanical 6 Months FEMA Task 23F-1611 MECH-SAP 5 SPM 6 M
262 SAPCO FEMA-1 23F-1611 Mechanical 1 Years FEMA Task 23F-1611 MECH-SAP 5 SPM 1 Y
263 SAPCO FEMA-1 23F-1611 Mechanical 5 Years FEMA Task 23F-1611 MECH-SAP 5 SPM 5 Y
264 SAPCO FEMA-1 23F-1612 Mechanical 35 Days FEMA Task 23F-1612 MECH-SAP 5 SPM 35 D
265 SAPCO FEMA-1 23F-1612 Mechanical 1 Months FEMA Task 23F-1612 MECH-SAP 5 SPM 1 M
266 SAPCO FEMA-1 23F-1612 Mechanical 2 Months FEMA Task 23F-1612 MECH-SAP 5 SPM 2 M
267 SAPCO FEMA-1 23F-1612 Mechanical 6 Months FEMA Task 23F-1612 MECH-SAP 5 SPM 6 M
268 SAPCO FEMA-1 23F-1612 Mechanical 1 Years FEMA Task 23F-1612 MECH-SAP 5 SPM 1 Y
269 SAPCO FEMA-1 23F-1612 Mechanical 5 Years FEMA Task 23F-1612 MECH-SAP 5 SPM 5 Y
270 SAPCO FEMA-1 23F-1613 Mechanical 35 Days FEMA Task 23F-1613 MECH-SAP 5 SPM 35 D
271 SAPCO FEMA-1 23F-1613 Mechanical 1 Months FEMA Task 23F-1613 MECH-SAP 5 SPM 1 M
272 SAPCO FEMA-1 23F-1613 Mechanical 2 Months FEMA Task 23F-1613 MECH-SAP 5 SPM 2 M
273 SAPCO FEMA-1 23F-1613 Mechanical 6 Months FEMA Task 23F-1613 MECH-SAP 5 SPM 6 M
274 SAPCO FEMA-1 23F-1613 Mechanical 1 Years FEMA Task 23F-1613 MECH-SAP 5 SPM 1 Y
275 SAPCO FEMA-1 23F-1613 Mechanical 5 Years FEMA Task 23F-1613 MECH-SAP 5 SPM 5 Y
276 SAPCO FEMA-1 23F-1620 Mechanical 35 Days FEMA Task 23F-1620 MECH-SAP 5 SPM 35 D
277 SAPCO FEMA-1 23F-1620 Mechanical 1 Months FEMA Task 23F-1620 MECH-SAP 5 SPM 1 M
278 SAPCO FEMA-1 23F-1620 Mechanical 2 Months FEMA Task 23F-1620 MECH-SAP 5 SPM 2 M
279 SAPCO FEMA-1 23F-1620 Mechanical 6 Months FEMA Task 23F-1620 MECH-SAP 5 SPM 6 M
280 SAPCO FEMA-1 23F-1620 Mechanical 1 Years FEMA Task 23F-1620 MECH-SAP 5 SPM 1 Y
281 SAPCO FEMA-1 23F-1620 Mechanical 5 Years FEMA Task 23F-1620 MECH-SAP 5 SPM 5 Y
282 SAPCO FEMA-1 23F-1621 Mechanical 35 Days FEMA Task 23F-1621 MECH-SAP 5 SPM 35 D
283 SAPCO FEMA-1 23F-1621 Mechanical 1 Months FEMA Task 23F-1621 MECH-SAP 5 SPM 1 M
284 SAPCO FEMA-1 23F-1621 Mechanical 2 Months FEMA Task 23F-1621 MECH-SAP 5 SPM 2 M
285 SAPCO FEMA-1 23F-1621 Mechanical 6 Months FEMA Task 23F-1621 MECH-SAP 5 SPM 6 M

358122780.xlsx Page 34 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
286 SAPCO FEMA-1 23F-1621 Mechanical 1 Years FEMA Task 23F-1621 MECH-SAP 5 SPM 1 Y
287 SAPCO FEMA-1 23F-1621 Mechanical 5 Years FEMA Task 23F-1621 MECH-SAP 5 SPM 5 Y
288 SAPCO FEMA-1 23F-1622 Mechanical 35 Days FEMA Task 23F-1622 MECH-SAP 5 SPM 35 D
289 SAPCO FEMA-1 23F-1622 Mechanical 1 Months FEMA Task 23F-1622 MECH-SAP 5 SPM 1 M
290 SAPCO FEMA-1 23F-1622 Mechanical 2 Months FEMA Task 23F-1622 MECH-SAP 5 SPM 2 M
291 SAPCO FEMA-1 23F-1622 Mechanical 6 Months FEMA Task 23F-1622 MECH-SAP 5 SPM 6 M
292 SAPCO FEMA-1 23F-1622 Mechanical 1 Years FEMA Task 23F-1622 MECH-SAP 5 SPM 1 Y
293 SAPCO FEMA-1 23F-1622 Mechanical 5 Years FEMA Task 23F-1622 MECH-SAP 5 SPM 5 Y
294 SAPCO FEMA-1 23F-1624 Mechanical 3 Months FEMA Task 23F-1624 MECH-SAP 5 SPM 3 M
295 SAPCO FEMA-1 23F-1624 Mechanical 6 Months FEMA Task 23F-1624 MECH-SAP 5 SPM 6 M
296 SAPCO FEMA-1 23F-1740 Mechanical 3 Months FEMA Task 23F-1740 MECH-SAP 5 SPM 3 M
297 SAPCO FEMA-1 23F-2601 Mechanical 3 Months FEMA Task 23F-2601 MECH-SAP 5 SPM 3 M
298 SAPCO FEMA-1 23F-2601 Mechanical 6 Months FEMA Task 23F-2601 MECH-SAP 5 SPM 6 M
299 SAPCO FEMA-1 23F-2740 Mechanical 3 Months FEMA Task 23F-2740 MECH-SAP 5 SPM 3 M
300 SAPCO FEMA-1 23FH-1540 Mechanical 1 Months FEMA Task 23FH-1540 MECH-SAP 5 SPM 1 M
301 SAPCO FEMA-1 23FH-1540 Mechanical 3 Months FEMA Task 23FH-1540 MECH-SAP 5 SPM 3 M
302 SAPCO FEMA-1 23FH-1540 Mechanical 4 Months FEMA Task 23FH-1540 MECH-SAP 5 SPM 4 M
303 SAPCO FEMA-1 23FH-1540 Mechanical 1 Weeks FEMA Task 23FH-1540 MECH-SAP 5 SPM 1 W
304 SAPCO FEMA-1 23FH-1540 Mechanical 1 Years FEMA Task 23FH-1540 MECH-SAP 5 SPM 1 Y
305 SAPCO FEMA-1 23FH-1540 Mechanical 2 Years FEMA Task 23FH-1540 MECH-SAP 5 SPM 2 Y
306 SAPCO FEMA-1 23FH-1540 Mechanical 3 Years FEMA Task 23FH-1540 MECH-SAP 5 SPM 3 Y
307 SAPCO FEMA-1 23FH-1540 Mechanical 5 Years FEMA Task 23FH-1540 MECH-SAP 5 SPM 5 Y
308 SAPCO FEMA-1 23FH-1601 Mechanical 1 Months FEMA Task 23FH-1601 MECH-SAP 5 SPM 1 M
309 SAPCO FEMA-1 23FH-1601 Mechanical 4 Months FEMA Task 23FH-1601 MECH-SAP 5 SPM 4 M
310 SAPCO FEMA-1 23FH-1601 Mechanical 1 Weeks FEMA Task 23FH-1601 MECH-SAP 5 SPM 1 W
311 SAPCO FEMA-1 23FH-1601 Mechanical 2 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 2 Y
312 SAPCO FEMA-1 23FH-1601 Mechanical 3 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 3 Y
313 SAPCO FEMA-1 23FH-1601 Mechanical 5 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 5 Y
314 SAPCO FEMA-1 23FH-1601 Mechanical 1 Months FEMA Task 23FH-1601 MECH-SAP 5 SPM 1 M
315 SAPCO FEMA-1 23FH-1601 Mechanical 3 Months FEMA Task 23FH-1601 MECH-SAP 5 SPM 3 M
316 SAPCO FEMA-1 23FH-1601 Mechanical 1 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 1 Y
317 SAPCO FEMA-1 23FH-1601 Mechanical 2 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 2 Y
318 SAPCO FEMA-1 23FH-1601 Mechanical 3 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 3 Y
319 SAPCO FEMA-1 23FH-1601 Mechanical 5 Years FEMA Task 23FH-1601 MECH-SAP 5 SPM 5 Y
320 SAPCO FEMA-1 23FH-1602 Mechanical 1 Months FEMA Task 23FH-1602 MECH-SAP 5 SPM 1 M
321 SAPCO FEMA-1 23FH-1602 Mechanical 3 Months FEMA Task 23FH-1602 MECH-SAP 5 SPM 3 M
322 SAPCO FEMA-1 23FH-1602 Mechanical 4 Months FEMA Task 23FH-1602 MECH-SAP 5 SPM 4 M
323 SAPCO FEMA-1 23FH-1602 Mechanical 1 Weeks FEMA Task 23FH-1602 MECH-SAP 5 SPM 1 W
324 SAPCO FEMA-1 23FH-1602 Mechanical 1 Years FEMA Task 23FH-1602 MECH-SAP 5 SPM 1 Y
325 SAPCO FEMA-1 23FH-1602 Mechanical 2 Years FEMA Task 23FH-1602 MECH-SAP 5 SPM 2 Y
326 SAPCO FEMA-1 23FH-1602 Mechanical 3 Years FEMA Task 23FH-1602 MECH-SAP 5 SPM 3 Y
327 SAPCO FEMA-1 23FH-1602 Mechanical 5 Years FEMA Task 23FH-1602 MECH-SAP 5 SPM 5 Y
328 SAPCO FEMA-1 23FH-1622 Mechanical 1 Months FEMA Task 23FH-1622 MECH-SAP 5 SPM 1 M
329 SAPCO FEMA-1 23FH-1622 Mechanical 3 Months FEMA Task 23FH-1622 MECH-SAP 5 SPM 3 M
330 SAPCO FEMA-1 23FH-1622 Mechanical 1 Weeks FEMA Task 23FH-1622 MECH-SAP 5 SPM 1 W
331 SAPCO FEMA-1 23FH-1622 Mechanical 1 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 1 Y
332 SAPCO FEMA-1 23FH-1622 Mechanical 2 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 2 Y
333 SAPCO FEMA-1 23FH-1622 Mechanical 3 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 3 Y
334 SAPCO FEMA-1 23FH-1622 Mechanical 5 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 5 Y
335 SAPCO FEMA-1 23FH-1622 Mechanical 1 Months FEMA Task 23FH-1622 MECH-SAP 5 SPM 1 M
336 SAPCO FEMA-1 23FH-1622 Mechanical 4 Months FEMA Task 23FH-1622 MECH-SAP 5 SPM 4 M
337 SAPCO FEMA-1 23FH-1622 Mechanical 2 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 2 Y
338 SAPCO FEMA-1 23FH-1622 Mechanical 5 Years FEMA Task 23FH-1622 MECH-SAP 5 SPM 5 Y
339 SAPCO FEMA-1 23FH-1624 Mechanical 1 Months FEMA Task 23FH-1624 MECH-SAP 5 SPM 1 M
340 SAPCO FEMA-1 23FH-1624 Mechanical 3 Months FEMA Task 23FH-1624 MECH-SAP 5 SPM 3 M
341 SAPCO FEMA-1 23FH-1624 Mechanical 1 Weeks FEMA Task 23FH-1624 MECH-SAP 5 SPM 1 W
342 SAPCO FEMA-1 23FH-1624 Mechanical 1 Years FEMA Task 23FH-1624 MECH-SAP 5 SPM 1 Y

358122780.xlsx Page 35 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
343 SAPCO FEMA-1 23FH-1624 Mechanical 2 Years FEMA Task 23FH-1624 MECH-SAP 5 SPM 2 Y
344 SAPCO FEMA-1 23FH-1624 Mechanical 3 Years FEMA Task 23FH-1624 MECH-SAP 5 SPM 3 Y
345 SAPCO FEMA-1 23FH-1624 Mechanical 5 Years FEMA Task 23FH-1624 MECH-SAP 5 SPM 5 Y
346 SAPCO FEMA-1 23FH-1624 Mechanical 1 Months FEMA Task 23FH-1624 MECH-SAP 5 SPM 1 M
347 SAPCO FEMA-1 23FH-1624 Mechanical 4 Months FEMA Task 23FH-1624 MECH-SAP 5 SPM 4 M
348 SAPCO FEMA-1 23FH-1624 Mechanical 5 Years FEMA Task 23FH-1624 MECH-SAP 5 SPM 5 Y
349 SAPCO FEMA-1 23FH-1650 Mechanical 1 Months FEMA Task 23FH-1650 MECH-SAP 5 SPM 1 M
350 SAPCO FEMA-1 23FH-1650 Mechanical 3 Months FEMA Task 23FH-1650 MECH-SAP 5 SPM 3 M
351 SAPCO FEMA-1 23FH-1650 Mechanical 1 Weeks FEMA Task 23FH-1650 MECH-SAP 5 SPM 1 W
352 SAPCO FEMA-1 23FH-1650 Mechanical 1 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 1 Y
353 SAPCO FEMA-1 23FH-1650 Mechanical 2 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 2 Y
354 SAPCO FEMA-1 23FH-1650 Mechanical 3 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 3 Y
355 SAPCO FEMA-1 23FH-1650 Mechanical 5 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 5 Y
356 SAPCO FEMA-1 23FH-1650 Mechanical 1 Months FEMA Task 23FH-1650 MECH-SAP 5 SPM 1 M
357 SAPCO FEMA-1 23FH-1650 Mechanical 4 Months FEMA Task 23FH-1650 MECH-SAP 5 SPM 4 M
358 SAPCO FEMA-1 23FH-1650 Mechanical 2 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 2 Y
359 SAPCO FEMA-1 23FH-1650 Mechanical 5 Years FEMA Task 23FH-1650 MECH-SAP 5 SPM 5 Y
360 SAPCO FEMA-1 23FH-1660 Mechanical 1 Months FEMA Task 23FH-1660 MECH-SAP 5 SPM 1 M
361 SAPCO FEMA-1 23FH-1660 Mechanical 3 Months FEMA Task 23FH-1660 MECH-SAP 5 SPM 3 M
362 SAPCO FEMA-1 23FH-1660 Mechanical 4 Months FEMA Task 23FH-1660 MECH-SAP 5 SPM 4 M
363 SAPCO FEMA-1 23FH-1660 Mechanical 1 Weeks FEMA Task 23FH-1660 MECH-SAP 5 SPM 1 W
364 SAPCO FEMA-1 23FH-1660 Mechanical 1 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 1 Y
365 SAPCO FEMA-1 23FH-1660 Mechanical 2 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 2 Y
366 SAPCO FEMA-1 23FH-1660 Mechanical 3 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 3 Y
367 SAPCO FEMA-1 23FH-1660 Mechanical 5 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 5 Y
368 SAPCO FEMA-1 23FH-1660 Mechanical 1 Months FEMA Task 23FH-1660 MECH-SAP 5 SPM 1 M
369 SAPCO FEMA-1 23FH-1660 Mechanical 3 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 3 Y
370 SAPCO FEMA-1 23FH-1660 Mechanical 5 Years FEMA Task 23FH-1660 MECH-SAP 5 SPM 5 Y
371 SAPCO FEMA-1 23FH-1725 Mechanical 1 Months FEMA Task 23FH-1725 MECH-SAP 5 SPM 1 M
372 SAPCO FEMA-1 23FH-1725 Mechanical 3 Months FEMA Task 23FH-1725 MECH-SAP 5 SPM 3 M
373 SAPCO FEMA-1 23FH-1725 Mechanical 4 Months FEMA Task 23FH-1725 MECH-SAP 5 SPM 4 M
374 SAPCO FEMA-1 23FH-1725 Mechanical 1 Weeks FEMA Task 23FH-1725 MECH-SAP 5 SPM 1 W
375 SAPCO FEMA-1 23FH-1725 Mechanical 2 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 2 Y
376 SAPCO FEMA-1 23FH-1725 Mechanical 3 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 3 Y
377 SAPCO FEMA-1 23FH-1725 Mechanical 5 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 5 Y
378 SAPCO FEMA-1 23FH-1725 Mechanical 1 Months FEMA Task 23FH-1725 MECH-SAP 5 SPM 1 M
379 SAPCO FEMA-1 23FH-1725 Mechanical 3 Months FEMA Task 23FH-1725 MECH-SAP 5 SPM 3 M
380 SAPCO FEMA-1 23FH-1725 Mechanical 1 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 1 Y
381 SAPCO FEMA-1 23FH-1725 Mechanical 2 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 2 Y
382 SAPCO FEMA-1 23FH-1725 Mechanical 3 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 3 Y
383 SAPCO FEMA-1 23FH-1725 Mechanical 5 Years FEMA Task 23FH-1725 MECH-SAP 5 SPM 5 Y
384 SAPCO FEMA-1 23FH-1830 Mechanical 1 Months FEMA Task 23FH-1830 MECH-SAP 5 SPM 1 M
385 SAPCO FEMA-1 23FH-1830 Mechanical 3 Months FEMA Task 23FH-1830 MECH-SAP 5 SPM 3 M
386 SAPCO FEMA-1 23FH-1830 Mechanical 1 Weeks FEMA Task 23FH-1830 MECH-SAP 5 SPM 1 W
387 SAPCO FEMA-1 23FH-1830 Mechanical 1 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 1 Y
388 SAPCO FEMA-1 23FH-1830 Mechanical 2 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 2 Y
389 SAPCO FEMA-1 23FH-1830 Mechanical 3 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 3 Y
390 SAPCO FEMA-1 23FH-1830 Mechanical 5 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 5 Y
391 SAPCO FEMA-1 23FH-1830 Mechanical 1 Months FEMA Task 23FH-1830 MECH-SAP 5 SPM 1 M
392 SAPCO FEMA-1 23FH-1830 Mechanical 4 Months FEMA Task 23FH-1830 MECH-SAP 5 SPM 4 M
393 SAPCO FEMA-1 23FH-1830 Mechanical 2 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 2 Y
394 SAPCO FEMA-1 23FH-1830 Mechanical 5 Years FEMA Task 23FH-1830 MECH-SAP 5 SPM 5 Y
395 SAPCO FEMA-1 23FH-2540 Mechanical 1 Months FEMA Task 23FH-2540 MECH-SAP 5 SPM 1 M
396 SAPCO FEMA-1 23FH-2540 Mechanical 3 Months FEMA Task 23FH-2540 MECH-SAP 5 SPM 3 M
397 SAPCO FEMA-1 23FH-2540 Mechanical 4 Months FEMA Task 23FH-2540 MECH-SAP 5 SPM 4 M
398 SAPCO FEMA-1 23FH-2540 Mechanical 1 Weeks FEMA Task 23FH-2540 MECH-SAP 5 SPM 1 W
399 SAPCO FEMA-1 23FH-2540 Mechanical 1 Years FEMA Task 23FH-2540 MECH-SAP 5 SPM 1 Y

358122780.xlsx Page 36 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
400 SAPCO FEMA-1 23FH-2540 Mechanical 2 Years FEMA Task 23FH-2540 MECH-SAP 5 SPM 2 Y
401 SAPCO FEMA-1 23FH-2540 Mechanical 3 Years FEMA Task 23FH-2540 MECH-SAP 5 SPM 3 Y
402 SAPCO FEMA-1 23FH-2540 Mechanical 5 Years FEMA Task 23FH-2540 MECH-SAP 5 SPM 5 Y
403 SAPCO FEMA-1 23FH-2601 Mechanical 1 Months FEMA Task 23FH-2601 MECH-SAP 5 SPM 1 M
404 SAPCO FEMA-1 23FH-2601 Mechanical 3 Months FEMA Task 23FH-2601 MECH-SAP 5 SPM 3 M
405 SAPCO FEMA-1 23FH-2601 Mechanical 1 Weeks FEMA Task 23FH-2601 MECH-SAP 5 SPM 1 W
406 SAPCO FEMA-1 23FH-2601 Mechanical 1 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 1 Y
407 SAPCO FEMA-1 23FH-2601 Mechanical 2 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 2 Y
408 SAPCO FEMA-1 23FH-2601 Mechanical 3 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 3 Y
409 SAPCO FEMA-1 23FH-2601 Mechanical 5 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 5 Y
410 SAPCO FEMA-1 23FH-2601 Mechanical 1 Months FEMA Task 23FH-2601 MECH-SAP 5 SPM 1 M
411 SAPCO FEMA-1 23FH-2601 Mechanical 4 Months FEMA Task 23FH-2601 MECH-SAP 5 SPM 4 M
412 SAPCO FEMA-1 23FH-2601 Mechanical 2 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 2 Y
413 SAPCO FEMA-1 23FH-2601 Mechanical 5 Years FEMA Task 23FH-2601 MECH-SAP 5 SPM 5 Y
414 SAPCO FEMA-1 23FH-2602 Mechanical 1 Months FEMA Task 23FH-2602 MECH-SAP 5 SPM 1 M
415 SAPCO FEMA-1 23FH-2602 Mechanical 3 Months FEMA Task 23FH-2602 MECH-SAP 5 SPM 3 M
416 SAPCO FEMA-1 23FH-2602 Mechanical 4 Months FEMA Task 23FH-2602 MECH-SAP 5 SPM 4 M
417 SAPCO FEMA-1 23FH-2602 Mechanical 1 Weeks FEMA Task 23FH-2602 MECH-SAP 5 SPM 1 W
418 SAPCO FEMA-1 23FH-2602 Mechanical 1 Years FEMA Task 23FH-2602 MECH-SAP 5 SPM 1 Y
419 SAPCO FEMA-1 23FH-2602 Mechanical 2 Years FEMA Task 23FH-2602 MECH-SAP 5 SPM 2 Y
420 SAPCO FEMA-1 23FH-2602 Mechanical 3 Years FEMA Task 23FH-2602 MECH-SAP 5 SPM 3 Y
421 SAPCO FEMA-1 23FH-2602 Mechanical 5 Years FEMA Task 23FH-2602 MECH-SAP 5 SPM 5 Y
422 SAPCO FEMA-1 23FH-4272 Mechanical 1 Months FEMA Task 23FH-4272 MECH-SAP 5 SPM 1 M
423 SAPCO FEMA-1 23FH-4272 Mechanical 3 Months FEMA Task 23FH-4272 MECH-SAP 5 SPM 3 M
424 SAPCO FEMA-1 23FH-4272 Mechanical 4 Months FEMA Task 23FH-4272 MECH-SAP 5 SPM 4 M
425 SAPCO FEMA-1 23FH-4272 Mechanical 1 Weeks FEMA Task 23FH-4272 MECH-SAP 5 SPM 1 W
426 SAPCO FEMA-1 23FH-4272 Mechanical 2 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 2 Y
427 SAPCO FEMA-1 23FH-4272 Mechanical 3 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 3 Y
428 SAPCO FEMA-1 23FH-4272 Mechanical 5 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 5 Y
429 SAPCO FEMA-1 23FH-4272 Mechanical 1 Months FEMA Task 23FH-4272 MECH-SAP 5 SPM 1 M
430 SAPCO FEMA-1 23FH-4272 Mechanical 3 Months FEMA Task 23FH-4272 MECH-SAP 5 SPM 3 M
431 SAPCO FEMA-1 23FH-4272 Mechanical 1 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 1 Y
432 SAPCO FEMA-1 23FH-4272 Mechanical 2 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 2 Y
433 SAPCO FEMA-1 23FH-4272 Mechanical 3 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 3 Y
434 SAPCO FEMA-1 23FH-4272 Mechanical 5 Years FEMA Task 23FH-4272 MECH-SAP 5 SPM 5 Y
435 SAPCO FEMA-1 23FH-4275 Mechanical 1 Months FEMA Task 23FH-4275 MECH-SAP 5 SPM 1 M
436 SAPCO FEMA-1 23FH-4275 Mechanical 3 Months FEMA Task 23FH-4275 MECH-SAP 5 SPM 3 M
437 SAPCO FEMA-1 23FH-4275 Mechanical 4 Months FEMA Task 23FH-4275 MECH-SAP 5 SPM 4 M
438 SAPCO FEMA-1 23FH-4275 Mechanical 1 Weeks FEMA Task 23FH-4275 MECH-SAP 5 SPM 1 W
439 SAPCO FEMA-1 23FH-4275 Mechanical 2 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 2 Y
440 SAPCO FEMA-1 23FH-4275 Mechanical 3 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 3 Y
441 SAPCO FEMA-1 23FH-4275 Mechanical 5 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 5 Y
442 SAPCO FEMA-1 23FH-4275 Mechanical 1 Months FEMA Task 23FH-4275 MECH-SAP 5 SPM 1 M
443 SAPCO FEMA-1 23FH-4275 Mechanical 3 Months FEMA Task 23FH-4275 MECH-SAP 5 SPM 3 M
444 SAPCO FEMA-1 23FH-4275 Mechanical 1 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 1 Y
445 SAPCO FEMA-1 23FH-4275 Mechanical 2 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 2 Y
446 SAPCO FEMA-1 23FH-4275 Mechanical 3 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 3 Y
447 SAPCO FEMA-1 23FH-4275 Mechanical 5 Years FEMA Task 23FH-4275 MECH-SAP 5 SPM 5 Y
448 SAPCO FEMA-1 23FH-4470 Mechanical 1 Months FEMA Task 23FH-4470 MECH-SAP 5 SPM 1 M
449 SAPCO FEMA-1 23FH-4470 Mechanical 3 Months FEMA Task 23FH-4470 MECH-SAP 5 SPM 3 M
450 SAPCO FEMA-1 23FH-4470 Mechanical 4 Months FEMA Task 23FH-4470 MECH-SAP 5 SPM 4 M
451 SAPCO FEMA-1 23FH-4470 Mechanical 1 Weeks FEMA Task 23FH-4470 MECH-SAP 5 SPM 1 W
452 SAPCO FEMA-1 23FH-4470 Mechanical 2 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 2 Y
453 SAPCO FEMA-1 23FH-4470 Mechanical 3 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 3 Y
454 SAPCO FEMA-1 23FH-4470 Mechanical 5 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 5 Y
455 SAPCO FEMA-1 23FH-4470 Mechanical 1 Months FEMA Task 23FH-4470 MECH-SAP 5 SPM 1 M
456 SAPCO FEMA-1 23FH-4470 Mechanical 3 Months FEMA Task 23FH-4470 MECH-SAP 5 SPM 3 M

358122780.xlsx Page 37 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
457 SAPCO FEMA-1 23FH-4470 Mechanical 1 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 1 Y
458 SAPCO FEMA-1 23FH-4470 Mechanical 2 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 2 Y
459 SAPCO FEMA-1 23FH-4470 Mechanical 3 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 3 Y
460 SAPCO FEMA-1 23FH-4470 Mechanical 5 Years FEMA Task 23FH-4470 MECH-SAP 5 SPM 5 Y
461 SAPCO FEMA-1 23FX-1400 Mechanical 35 Days FEMA Task 23FX-1400 MECH-SAP 5 SPM 35 D
462 SAPCO FEMA-1 23FX-1400 Mechanical 1 Months FEMA Task 23FX-1400 MECH-SAP 5 SPM 1 M
463 SAPCO FEMA-1 23FX-1400 Mechanical 3 Months FEMA Task 23FX-1400 MECH-SAP 5 SPM 3 M
464 SAPCO FEMA-1 23FX-1400 Mechanical 1 Weeks FEMA Task 23FX-1400 MECH-SAP 5 SPM 1 W
465 SAPCO FEMA-1 23FX-1400 Mechanical 2 Weeks FEMA Task 23FX-1400 MECH-SAP 5 SPM 2 W
466 SAPCO FEMA-1 23FX-1400 Mechanical 4 Years FEMA Task 23FX-1400 MECH-SAP 5 SPM 4 Y
467 SAPCO FEMA-1 23FX-1400 Mechanical 5 Years FEMA Task 23FX-1400 MECH-SAP 5 SPM 5 Y
468 SAPCO FEMA-1 23FX-1401 Mechanical 35 Days FEMA Task 23FX-1401 MECH-SAP 5 SPM 35 D
469 SAPCO FEMA-1 23FX-1401 Mechanical 1 Months FEMA Task 23FX-1401 MECH-SAP 5 SPM 1 M
470 SAPCO FEMA-1 23FX-1401 Mechanical 3 Months FEMA Task 23FX-1401 MECH-SAP 5 SPM 3 M
471 SAPCO FEMA-1 23FX-1401 Mechanical 1 Weeks FEMA Task 23FX-1401 MECH-SAP 5 SPM 1 W
472 SAPCO FEMA-1 23FX-1401 Mechanical 2 Weeks FEMA Task 23FX-1401 MECH-SAP 5 SPM 2 W
473 SAPCO FEMA-1 23FX-1401 Mechanical 4 Years FEMA Task 23FX-1401 MECH-SAP 5 SPM 4 Y
474 SAPCO FEMA-1 23FX-1401 Mechanical 5 Years FEMA Task 23FX-1401 MECH-SAP 5 SPM 5 Y
475 SAPCO FEMA-1 23FX-1410 Mechanical 1 Months FEMA Task 23FX-1410 MECH-SAP 5 SPM 1 M
476 SAPCO FEMA-1 23FX-1410 Mechanical 3 Months FEMA Task 23FX-1410 MECH-SAP 5 SPM 3 M
477 SAPCO FEMA-1 23FX-1410 Mechanical 1 Years FEMA Task 23FX-1410 MECH-SAP 5 SPM 1 Y
478 SAPCO FEMA-1 23FX-1410 Mechanical 5 Years FEMA Task 23FX-1410 MECH-SAP 5 SPM 5 Y
479 SAPCO FEMA-1 23FX-1410 Mechanical 10 Years FEMA Task 23FX-1410 MECH-SAP 5 SPM 10 Y
480 SAPCO FEMA-1 23FX-1420 Mechanical 1 Months FEMA Task 23FX-1420 MECH-SAP 5 SPM 1 M
481 SAPCO FEMA-1 23FX-1420 Mechanical 3 Months FEMA Task 23FX-1420 MECH-SAP 5 SPM 3 M
482 SAPCO FEMA-1 23FX-1420 Mechanical 1 Years FEMA Task 23FX-1420 MECH-SAP 5 SPM 1 Y
483 SAPCO FEMA-1 23FX-1420 Mechanical 5 Years FEMA Task 23FX-1420 MECH-SAP 5 SPM 5 Y
484 SAPCO FEMA-1 23FX-1420 Mechanical 10 Years FEMA Task 23FX-1420 MECH-SAP 5 SPM 10 Y
485 SAPCO FEMA-1 23FX-1500 Mechanical 35 Days FEMA Task 23FX-1500 MECH-SAP 5 SPM 35 D
486 SAPCO FEMA-1 23FX-1500 Mechanical 2 Years FEMA Task 23FX-1500 MECH-SAP 5 SPM 2 Y
487 SAPCO FEMA-1 23FX-1500 Mechanical 5 Years FEMA Task 23FX-1500 MECH-SAP 5 SPM 5 Y
488 SAPCO FEMA-1 23FX-1501 Mechanical 210 Days FEMA Task 23FX-1501 MECH-SAP 5 SPM 210 D
489 SAPCO FEMA-1 23FX-1501 Mechanical 1 Months FEMA Task 23FX-1501 MECH-SAP 5 SPM 1 M
490 SAPCO FEMA-1 23FX-1501 Mechanical 2 Years FEMA Task 23FX-1501 MECH-SAP 5 SPM 2 Y
491 SAPCO FEMA-1 23FX-1501 Mechanical 5 Years FEMA Task 23FX-1501 MECH-SAP 5 SPM 5 Y
492 SAPCO FEMA-1 23FX-1622 Mechanical 1 Months FEMA Task 23FX-1622 MECH-SAP 5 SPM 1 M
493 SAPCO FEMA-1 23FX-1622 Mechanical 6 Months FEMA Task 23FX-1622 MECH-SAP 5 SPM 6 M
494 SAPCO FEMA-1 23FX-1622 Mechanical 2 Years FEMA Task 23FX-1622 MECH-SAP 5 SPM 2 Y
495 SAPCO FEMA-1 23FX-1622 Mechanical 5 Years FEMA Task 23FX-1622 MECH-SAP 5 SPM 5 Y
496 SAPCO FEMA-1 23FX-1701 Mechanical 3 Months FEMA Task 23FX-1701 MECH-SAP 5 SPM 3 M
497 SAPCO FEMA-1 23FX-1701 Mechanical 6 Months FEMA Task 23FX-1701 MECH-SAP 5 SPM 6 M
498 SAPCO FEMA-1 23FX-1701 Mechanical 1 Years FEMA Task 23FX-1701 MECH-SAP 5 SPM 1 Y
499 SAPCO FEMA-1 23FX-1701 Mechanical 2 Years FEMA Task 23FX-1701 MECH-SAP 5 SPM 2 Y
500 SAPCO FEMA-1 23FX-1701 Mechanical 5 Years FEMA Task 23FX-1701 MECH-SAP 5 SPM 5 Y
501 SAPCO FEMA-1 23FX-1725 Mechanical 1 Months FEMA Task 23FX-1725 MECH-SAP 5 SPM 1 M
502 SAPCO FEMA-1 23FX-1725 Mechanical 6 Months FEMA Task 23FX-1725 MECH-SAP 5 SPM 6 M
503 SAPCO FEMA-1 23FX-1725 Mechanical 2 Years FEMA Task 23FX-1725 MECH-SAP 5 SPM 2 Y
504 SAPCO FEMA-1 23FX-1725 Mechanical 5 Years FEMA Task 23FX-1725 MECH-SAP 5 SPM 5 Y
505 SAPCO FEMA-1 23FX-2400 Mechanical 35 Days FEMA Task 23FX-2400 MECH-SAP 5 SPM 35 D
506 SAPCO FEMA-1 23FX-2400 Mechanical 1 Months FEMA Task 23FX-2400 MECH-SAP 5 SPM 1 M
507 SAPCO FEMA-1 23FX-2400 Mechanical 3 Months FEMA Task 23FX-2400 MECH-SAP 5 SPM 3 M
508 SAPCO FEMA-1 23FX-2400 Mechanical 1 Weeks FEMA Task 23FX-2400 MECH-SAP 5 SPM 1 W
509 SAPCO FEMA-1 23FX-2400 Mechanical 2 Weeks FEMA Task 23FX-2400 MECH-SAP 5 SPM 2 W
510 SAPCO FEMA-1 23FX-2400 Mechanical 4 Years FEMA Task 23FX-2400 MECH-SAP 5 SPM 4 Y
511 SAPCO FEMA-1 23FX-2400 Mechanical 5 Years FEMA Task 23FX-2400 MECH-SAP 5 SPM 5 Y
512 SAPCO FEMA-1 23FX-2401 Mechanical 35 Days FEMA Task 23FX-2401 MECH-SAP 5 SPM 35 D
513 SAPCO FEMA-1 23FX-2401 Mechanical 1 Months FEMA Task 23FX-2401 MECH-SAP 5 SPM 1 M

358122780.xlsx Page 38 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
514 SAPCO FEMA-1 23FX-2401 Mechanical 3 Months FEMA Task 23FX-2401 MECH-SAP 5 SPM 3 M
515 SAPCO FEMA-1 23FX-2401 Mechanical 1 Weeks FEMA Task 23FX-2401 MECH-SAP 5 SPM 1 W
516 SAPCO FEMA-1 23FX-2401 Mechanical 2 Weeks FEMA Task 23FX-2401 MECH-SAP 5 SPM 2 W
517 SAPCO FEMA-1 23FX-2401 Mechanical 4 Years FEMA Task 23FX-2401 MECH-SAP 5 SPM 4 Y
518 SAPCO FEMA-1 23FX-2401 Mechanical 5 Years FEMA Task 23FX-2401 MECH-SAP 5 SPM 5 Y
519 SAPCO FEMA-1 23FX-2410 Mechanical 1 Months FEMA Task 23FX-2410 MECH-SAP 5 SPM 1 M
520 SAPCO FEMA-1 23FX-2410 Mechanical 3 Months FEMA Task 23FX-2410 MECH-SAP 5 SPM 3 M
521 SAPCO FEMA-1 23FX-2410 Mechanical 1 Years FEMA Task 23FX-2410 MECH-SAP 5 SPM 1 Y
522 SAPCO FEMA-1 23FX-2410 Mechanical 5 Years FEMA Task 23FX-2410 MECH-SAP 5 SPM 5 Y
523 SAPCO FEMA-1 23FX-2410 Mechanical 10 Years FEMA Task 23FX-2410 MECH-SAP 5 SPM 10 Y
524 SAPCO FEMA-1 23FX-2420 Mechanical 1 Months FEMA Task 23FX-2420 MECH-SAP 5 SPM 1 M
525 SAPCO FEMA-1 23FX-2420 Mechanical 3 Months FEMA Task 23FX-2420 MECH-SAP 5 SPM 3 M
526 SAPCO FEMA-1 23FX-2420 Mechanical 1 Years FEMA Task 23FX-2420 MECH-SAP 5 SPM 1 Y
527 SAPCO FEMA-1 23FX-2420 Mechanical 5 Years FEMA Task 23FX-2420 MECH-SAP 5 SPM 5 Y
528 SAPCO FEMA-1 23FX-2420 Mechanical 10 Years FEMA Task 23FX-2420 MECH-SAP 5 SPM 10 Y
529 SAPCO FEMA-1 23FX-2500 Mechanical 35 Days FEMA Task 23FX-2500 MECH-SAP 5 SPM 35 D
530 SAPCO FEMA-1 23FX-2500 Mechanical 2 Years FEMA Task 23FX-2500 MECH-SAP 5 SPM 2 Y
531 SAPCO FEMA-1 23FX-2500 Mechanical 5 Years FEMA Task 23FX-2500 MECH-SAP 5 SPM 5 Y
532 SAPCO FEMA-1 23FX-2501 Mechanical 1 Months FEMA Task 23FX-2501 MECH-SAP 5 SPM 1 M
533 SAPCO FEMA-1 23FX-2501 Mechanical 2 Years FEMA Task 23FX-2501 MECH-SAP 5 SPM 2 Y
534 SAPCO FEMA-1 23FX-2501 Mechanical 5 Years FEMA Task 23FX-2501 MECH-SAP 5 SPM 5 Y
535 SAPCO FEMA-1 23FX-2701 Mechanical 3 Months FEMA Task 23FX-2701 MECH-SAP 5 SPM 3 M
536 SAPCO FEMA-1 23FX-2701 Mechanical 6 Months FEMA Task 23FX-2701 MECH-SAP 5 SPM 6 M
537 SAPCO FEMA-1 23FX-2701 Mechanical 1 Years FEMA Task 23FX-2701 MECH-SAP 5 SPM 1 Y
538 SAPCO FEMA-1 23FX-2701 Mechanical 2 Years FEMA Task 23FX-2701 MECH-SAP 5 SPM 2 Y
539 SAPCO FEMA-1 23FX-2701 Mechanical 5 Years FEMA Task 23FX-2701 MECH-SAP 5 SPM 5 Y
540 SAPCO FEMA-1 23K-7401A Mechanical 3 Months FEMA Task 23K-7401A MECH-SAP 5 SPM 3 M
541 SAPCO FEMA-1 23K-7401A Mechanical 6 Months FEMA Task 23K-7401A MECH-SAP 5 SPM 6 M
542 SAPCO FEMA-1 23K-7401A Mechanical 1 Years FEMA Task 23K-7401A MECH-SAP 5 SPM 1 Y
543 SAPCO FEMA-1 23K-7401A Mechanical 3 Years FEMA Task 23K-7401A MECH-SAP 5 SPM 3 Y
544 SAPCO FEMA-1 23K-7401A Mechanical 5 Years FEMA Task 23K-7401A MECH-SAP 5 SPM 5 Y
545 SAPCO FEMA-1 23K-7401B Mechanical 3 Months FEMA Task 23K-7401B MECH-SAP 5 SPM 3 M
546 SAPCO FEMA-1 23K-7401B Mechanical 6 Months FEMA Task 23K-7401B MECH-SAP 5 SPM 6 M
547 SAPCO FEMA-1 23K-7401B Mechanical 1 Years FEMA Task 23K-7401B MECH-SAP 5 SPM 1 Y
548 SAPCO FEMA-1 23K-7401B Mechanical 3 Years FEMA Task 23K-7401B MECH-SAP 5 SPM 3 Y
549 SAPCO FEMA-1 23K-7401B Mechanical 5 Years FEMA Task 23K-7401B MECH-SAP 5 SPM 5 Y
550 SAPCO FEMA-1 23M-1410 Mechanical 3 Days FEMA Task 23M-1410 MECH-SAP 5 SPM 3 D
551 SAPCO FEMA-1 23M-1410 Mechanical 35 Days FEMA Task 23M-1410 MECH-SAP 5 SPM 35 D
552 SAPCO FEMA-1 23M-1410 Mechanical 105 Days FEMA Task 23M-1410 MECH-SAP 5 SPM 105 D
553 SAPCO FEMA-1 23M-1410 Mechanical 1 Months FEMA Task 23M-1410 MECH-SAP 5 SPM 1 M
554 SAPCO FEMA-1 23M-1410 Mechanical 1 Years FEMA Task 23M-1410 MECH-SAP 5 SPM 1 Y
555 SAPCO FEMA-1 23M-1410 Mechanical 3 Years FEMA Task 23M-1410 MECH-SAP 5 SPM 3 Y
556 SAPCO FEMA-1 23M-1410 Mechanical 5 Years FEMA Task 23M-1410 MECH-SAP 5 SPM 5 Y
557 SAPCO FEMA-1 23M-1420 Mechanical 1 Months FEMA Task 23M-1420 MECH-SAP 5 SPM 1 M
558 SAPCO FEMA-1 23M-1420 Mechanical 3 Months FEMA Task 23M-1420 MECH-SAP 5 SPM 3 M
559 SAPCO FEMA-1 23M-1420 Mechanical 1 Years FEMA Task 23M-1420 MECH-SAP 5 SPM 1 Y
560 SAPCO FEMA-1 23M-1420 Mechanical 3 Years FEMA Task 23M-1420 MECH-SAP 5 SPM 3 Y
561 SAPCO FEMA-1 23M-1420 Mechanical 5 Years FEMA Task 23M-1420 MECH-SAP 5 SPM 5 Y
562 SAPCO FEMA-1 23M-1721 Mechanical 3 Months FEMA Task 23M-1721 MECH-SAP 5 SPM 3 M
563 SAPCO FEMA-1 23M-1721 Mechanical 1 Years FEMA Task 23M-1721 MECH-SAP 5 SPM 1 Y
564 SAPCO FEMA-1 23M-1721 Mechanical 2 Years FEMA Task 23M-1721 MECH-SAP 5 SPM 2 Y
565 SAPCO FEMA-1 23M-2410 Mechanical 1 Months FEMA Task 23M-2410 MECH-SAP 5 SPM 1 M
566 SAPCO FEMA-1 23M-2410 Mechanical 3 Months FEMA Task 23M-2410 MECH-SAP 5 SPM 3 M
567 SAPCO FEMA-1 23M-2410 Mechanical 1 Years FEMA Task 23M-2410 MECH-SAP 5 SPM 1 Y
568 SAPCO FEMA-1 23M-2410 Mechanical 3 Years FEMA Task 23M-2410 MECH-SAP 5 SPM 3 Y
569 SAPCO FEMA-1 23M-2410 Mechanical 5 Years FEMA Task 23M-2410 MECH-SAP 5 SPM 5 Y
570 SAPCO FEMA-1 23M-2420 Mechanical 1 Months FEMA Task 23M-2420 MECH-SAP 5 SPM 1 M

358122780.xlsx Page 39 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
571 SAPCO FEMA-1 23M-2420 Mechanical 3 Months FEMA Task 23M-2420 MECH-SAP 5 SPM 3 M
572 SAPCO FEMA-1 23M-2420 Mechanical 1 Years FEMA Task 23M-2420 MECH-SAP 5 SPM 1 Y
573 SAPCO FEMA-1 23M-2420 Mechanical 3 Years FEMA Task 23M-2420 MECH-SAP 5 SPM 3 Y
574 SAPCO FEMA-1 23M-2420 Mechanical 5 Years FEMA Task 23M-2420 MECH-SAP 5 SPM 5 Y
575 SAPCO FEMA-1 23M-2721 Mechanical 3 Months FEMA Task 23M-2721 MECH-SAP 5 SPM 3 M
576 SAPCO FEMA-1 23M-2721 Mechanical 6 Months FEMA Task 23M-2721 MECH-SAP 5 SPM 6 M
577 SAPCO FEMA-1 23M-2721 Mechanical 1 Years FEMA Task 23M-2721 MECH-SAP 5 SPM 1 Y
23MX-1702 Mechanical 3 Months FEMA
578 SAPCO FEMA-1 23MX-1702 MECH-SAP 5 SPM 3 M
Task
23MX-1702 Mechanical 6 Months FEMA
579 SAPCO FEMA-1 23MX-1702 MECH-SAP 5 SPM 6 M
Task
580 SAPCO FEMA-1 23MX-1702 Mechanical 1 Years FEMA Task 23MX-1702 MECH-SAP 5 SPM 1 Y
581 SAPCO FEMA-1 23MX-1702 Mechanical 2 Years FEMA Task 23MX-1702 MECH-SAP 5 SPM 2 Y
582 SAPCO FEMA-1 23MX-1702 Mechanical 5 Years FEMA Task 23MX-1702 MECH-SAP 5 SPM 5 Y
23MX-1716 Mechanical 3 Months FEMA
583 SAPCO FEMA-1 23MX-1716 MECH-SAP 5 SPM 3 M
Task
23MX-1716 Mechanical 6 Months FEMA
584 SAPCO FEMA-1 23MX-1716 MECH-SAP 5 SPM 6 M
Task
585 SAPCO FEMA-1 23MX-1716 Mechanical 1 Years FEMA Task 23MX-1716 MECH-SAP 5 SPM 1 Y
586 SAPCO FEMA-1 23MX-1716 Mechanical 2 Years FEMA Task 23MX-1716 MECH-SAP 5 SPM 2 Y
587 SAPCO FEMA-1 23MX-1716 Mechanical 5 Years FEMA Task 23MX-1716 MECH-SAP 5 SPM 5 Y
23MX-1718 Mechanical 1 Months FEMA
588 SAPCO FEMA-1 23MX-1718 MECH-SAP 5 SPM 1 M
Task
23MX-1718 Mechanical 3 Months FEMA
589 SAPCO FEMA-1 23MX-1718 MECH-SAP 5 SPM 3 M
Task
23MX-1718 Mechanical 6 Months FEMA
590 SAPCO FEMA-1 23MX-1718 MECH-SAP 5 SPM 6 M
Task
591 SAPCO FEMA-1 23MX-1718 Mechanical 5 Years FEMA Task 23MX-1718 MECH-SAP 5 SPM 5 Y
23MX-1825 Mechanical 1 Months FEMA
592 SAPCO FEMA-1 23MX-1825 MECH-SAP 5 SPM 1 M
Task
23MX-1825 Mechanical 3 Months FEMA
593 SAPCO FEMA-1 23MX-1825 MECH-SAP 5 SPM 3 M
Task
23MX-1825 Mechanical 6 Months FEMA
594 SAPCO FEMA-1 23MX-1825 MECH-SAP 5 SPM 6 M
Task
595 SAPCO FEMA-1 23MX-1825 Mechanical 5 Years FEMA Task 23MX-1825 MECH-SAP 5 SPM 5 Y
23MX-2716 Mechanical 3 Months FEMA
596 SAPCO FEMA-1 23MX-2716 MECH-SAP 5 SPM 3 M
Task
23MX-2716 Mechanical 6 Months FEMA
597 SAPCO FEMA-1 23MX-2716 MECH-SAP 5 SPM 6 M
Task
598 SAPCO FEMA-1 23MX-2716 Mechanical 1 Years FEMA Task 23MX-2716 MECH-SAP 5 SPM 1 Y
599 SAPCO FEMA-1 23MX-2716 Mechanical 2 Years FEMA Task 23MX-2716 MECH-SAP 5 SPM 2 Y
600 SAPCO FEMA-1 23MX-2716 Mechanical 5 Years FEMA Task 23MX-2716 MECH-SAP 5 SPM 5 Y
23MX-2718 Mechanical 1 Months FEMA
601 SAPCO FEMA-1 23MX-2718 MECH-SAP 5 SPM 1 M
Task
23MX-2718 Mechanical 3 Months FEMA
602 SAPCO FEMA-1 23MX-2718 MECH-SAP 5 SPM 3 M
Task
23MX-2718 Mechanical 6 Months FEMA
603 SAPCO FEMA-1 23MX-2718 MECH-SAP 5 SPM 6 M
Task
604 SAPCO FEMA-1 23MX-2718 Mechanical 5 Years FEMA Task 23MX-2718 MECH-SAP 5 SPM 5 Y
23MX-3310 Mechanical 3 Months FEMA
605 SAPCO FEMA-1 23MX-3310 MECH-SAP 5 SPM 3 M
Task
23MX-3310 Mechanical 6 Months FEMA
606 SAPCO FEMA-1 23MX-3310 MECH-SAP 5 SPM 6 M
Task
607 SAPCO FEMA-1 23MX-3310 Mechanical 1 Years FEMA Task 23MX-3310 MECH-SAP 5 SPM 1 Y
608 SAPCO FEMA-1 23MX-3310 Mechanical 2 Years FEMA Task 23MX-3310 MECH-SAP 5 SPM 2 Y
609 SAPCO FEMA-1 23MX-3310 Mechanical 5 Years FEMA Task 23MX-3310 MECH-SAP 5 SPM 5 Y
23MX-3320 Mechanical 3 Months FEMA
610 SAPCO FEMA-1 23MX-3320 MECH-SAP 5 SPM 3 M
Task
23MX-3320 Mechanical 6 Months FEMA
611 SAPCO FEMA-1 23MX-3320 MECH-SAP 5 SPM 6 M
Task
612 SAPCO FEMA-1 23MX-3320 Mechanical 1 Years FEMA Task 23MX-3320 MECH-SAP 5 SPM 1 Y
613 SAPCO FEMA-1 23MX-3320 Mechanical 2 Years FEMA Task 23MX-3320 MECH-SAP 5 SPM 2 Y
614 SAPCO FEMA-1 23MX-3320 Mechanical 5 Years FEMA Task 23MX-3320 MECH-SAP 5 SPM 5 Y
23MX-3430 Mechanical 3 Months FEMA
615 SAPCO FEMA-1 23MX-3430 MECH-SAP 5 SPM 3 M
Task
23MX-3430 Mechanical 6 Months FEMA
616 SAPCO FEMA-1 23MX-3430 MECH-SAP 5 SPM 6 M
Task
617 SAPCO FEMA-1 23MX-3430 Mechanical 1 Years FEMA Task 23MX-3430 MECH-SAP 5 SPM 1 Y
618 SAPCO FEMA-1 23MX-3430 Mechanical 2 Years FEMA Task 23MX-3430 MECH-SAP 5 SPM 2 Y
619 SAPCO FEMA-1 23MX-3430 Mechanical 5 Years FEMA Task 23MX-3430 MECH-SAP 5 SPM 5 Y
23MX-3520 Mechanical 3 Months FEMA
620 SAPCO FEMA-1 23MX-3520 MECH-SAP 5 SPM 3 M
Task
23MX-3520 Mechanical 6 Months FEMA
621 SAPCO FEMA-1 23MX-3520 MECH-SAP 5 SPM 6 M
Task
622 SAPCO FEMA-1 23MX-3520 Mechanical 1 Years FEMA Task 23MX-3520 MECH-SAP 5 SPM 1 Y
623 SAPCO FEMA-1 23MX-3520 Mechanical 2 Years FEMA Task 23MX-3520 MECH-SAP 5 SPM 2 Y
624 SAPCO FEMA-1 23MX-3520 Mechanical 5 Years FEMA Task 23MX-3520 MECH-SAP 5 SPM 5 Y
625 SAPCO FEMA-1 23P-1100 Mechanical 1 Months FEMA Task 23P-1100 MECH-SAP 5 SPM 1 M
626 SAPCO FEMA-1 23P-1100 Mechanical 2 Months FEMA Task 23P-1100 MECH-SAP 5 SPM 2 M
627 SAPCO FEMA-1 23P-1100 Mechanical 6 Months FEMA Task 23P-1100 MECH-SAP 5 SPM 6 M

358122780.xlsx Page 40 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
628 SAPCO FEMA-1 23P-1100 Mechanical 1 Years FEMA Task 23P-1100 MECH-SAP 5 SPM 1 Y
629 SAPCO FEMA-1 23P-1100 Mechanical 3 Years FEMA Task 23P-1100 MECH-SAP 5 SPM 3 Y
630 SAPCO FEMA-1 23P-1100 Mechanical 5 Years FEMA Task 23P-1100 MECH-SAP 5 SPM 5 Y
631 SAPCO FEMA-1 23P-1150 Mechanical 3 Months FEMA Task 23P-1150 MECH-SAP 5 SPM 3 M
632 SAPCO FEMA-1 23P-1150 Mechanical 5 Years FEMA Task 23P-1150 MECH-SAP 5 SPM 5 Y
633 SAPCO FEMA-1 23P-1160 Mechanical 3 Months FEMA Task 23P-1160 MECH-SAP 5 SPM 3 M
634 SAPCO FEMA-1 23P-1160 Mechanical 5 Years FEMA Task 23P-1160 MECH-SAP 5 SPM 5 Y
635 SAPCO FEMA-1 23P-1721 Mechanical 1 Months FEMA Task 23P-1721 MECH-SAP 5 SPM 1 M
636 SAPCO FEMA-1 23P-1721 Mechanical 2 Months FEMA Task 23P-1721 MECH-SAP 5 SPM 2 M
637 SAPCO FEMA-1 23P-1721 Mechanical 6 Months FEMA Task 23P-1721 MECH-SAP 5 SPM 6 M
638 SAPCO FEMA-1 23P-1721 Mechanical 2 Weeks FEMA Task 23P-1721 MECH-SAP 5 SPM 2 W
639 SAPCO FEMA-1 23P-1721 Mechanical 1 Years FEMA Task 23P-1721 MECH-SAP 5 SPM 1 Y
640 SAPCO FEMA-1 23P-1721 Mechanical 3 Years FEMA Task 23P-1721 MECH-SAP 5 SPM 3 Y
641 SAPCO FEMA-1 23P-1721 Mechanical 5 Years FEMA Task 23P-1721 MECH-SAP 5 SPM 5 Y
642 SAPCO FEMA-1 23P-1722 Mechanical 5 Years FEMA Task 23P-1722 MECH-SAP 5 SPM 5 Y
643 SAPCO FEMA-1 23P-1722 Mechanical 5 Years FEMA Task 23P-1722 MECH-SAP 5 SPM 5 Y
644 SAPCO FEMA-1 23P-1726 Mechanical 1 Months FEMA Task 23P-1726 MECH-SAP 5 SPM 1 M
645 SAPCO FEMA-1 23P-1726 Mechanical 2 Months FEMA Task 23P-1726 MECH-SAP 5 SPM 2 M
646 SAPCO FEMA-1 23P-1726 Mechanical 6 Months FEMA Task 23P-1726 MECH-SAP 5 SPM 6 M
647 SAPCO FEMA-1 23P-1726 Mechanical 1 Years FEMA Task 23P-1726 MECH-SAP 5 SPM 1 Y
648 SAPCO FEMA-1 23P-1726 Mechanical 5 Years FEMA Task 23P-1726 MECH-SAP 5 SPM 5 Y
649 SAPCO FEMA-1 23P-1726 Mechanical 6 Months FEMA Task 23P-1726 MECH-SAP 5 SPM 6 M
650 SAPCO FEMA-1 23P-1726 Mechanical 2 Weeks FEMA Task 23P-1726 MECH-SAP 5 SPM 2 W
651 SAPCO FEMA-1 23P-1726 Mechanical 3 Years FEMA Task 23P-1726 MECH-SAP 5 SPM 3 Y
652 SAPCO FEMA-1 23P-1726 Mechanical 5 Years FEMA Task 23P-1726 MECH-SAP 5 SPM 5 Y
653 SAPCO FEMA-1 23P-2721 Mechanical 1 Months FEMA Task 23P-2721 MECH-SAP 5 SPM 1 M
654 SAPCO FEMA-1 23P-2721 Mechanical 2 Months FEMA Task 23P-2721 MECH-SAP 5 SPM 2 M
655 SAPCO FEMA-1 23P-2721 Mechanical 6 Months FEMA Task 23P-2721 MECH-SAP 5 SPM 6 M
656 SAPCO FEMA-1 23P-2721 Mechanical 2 Weeks FEMA Task 23P-2721 MECH-SAP 5 SPM 2 W
657 SAPCO FEMA-1 23P-2721 Mechanical 1 Years FEMA Task 23P-2721 MECH-SAP 5 SPM 1 Y
658 SAPCO FEMA-1 23P-2721 Mechanical 3 Years FEMA Task 23P-2721 MECH-SAP 5 SPM 3 Y
659 SAPCO FEMA-1 23P-2721 Mechanical 5 Years FEMA Task 23P-2721 MECH-SAP 5 SPM 5 Y
660 SAPCO FEMA-1 23P-2722 Mechanical 5 Years FEMA Task 23P-2722 MECH-SAP 5 SPM 5 Y
661 SAPCO FEMA-1 23P-3310 Mechanical 1 Months FEMA Task 23P-3310 MECH-SAP 5 SPM 1 M
662 SAPCO FEMA-1 23P-3310 Mechanical 3 Months FEMA Task 23P-3310 MECH-SAP 5 SPM 3 M
663 SAPCO FEMA-1 23P-3310 Mechanical 6 Months FEMA Task 23P-3310 MECH-SAP 5 SPM 6 M
664 SAPCO FEMA-1 23P-3310 Mechanical 1 Years FEMA Task 23P-3310 MECH-SAP 5 SPM 1 Y
665 SAPCO FEMA-1 23P-3310 Mechanical 3 Years FEMA Task 23P-3310 MECH-SAP 5 SPM 3 Y
666 SAPCO FEMA-1 23P-3320 Mechanical 1 Months FEMA Task 23P-3320 MECH-SAP 5 SPM 1 M
667 SAPCO FEMA-1 23P-3320 Mechanical 3 Months FEMA Task 23P-3320 MECH-SAP 5 SPM 3 M
668 SAPCO FEMA-1 23P-3320 Mechanical 6 Months FEMA Task 23P-3320 MECH-SAP 5 SPM 6 M
669 SAPCO FEMA-1 23P-3320 Mechanical 1 Years FEMA Task 23P-3320 MECH-SAP 5 SPM 1 Y
670 SAPCO FEMA-1 23P-3320 Mechanical 3 Years FEMA Task 23P-3320 MECH-SAP 5 SPM 3 Y
671 SAPCO FEMA-1 23P-3430 Mechanical 1 Months FEMA Task 23P-3430 MECH-SAP 5 SPM 1 M
672 SAPCO FEMA-1 23P-3430 Mechanical 2 Weeks FEMA Task 23P-3430 MECH-SAP 5 SPM 2 W
673 SAPCO FEMA-1 23P-3430 Mechanical 1 Years FEMA Task 23P-3430 MECH-SAP 5 SPM 1 Y
674 SAPCO FEMA-1 23P-3430 Mechanical 3 Years FEMA Task 23P-3430 MECH-SAP 5 SPM 3 Y
675 SAPCO FEMA-1 23P-3430 Mechanical 5 Years FEMA Task 23P-3430 MECH-SAP 5 SPM 5 Y
676 SAPCO FEMA-1 23P-3430 Mechanical 1 Months FEMA Task 23P-3430 MECH-SAP 5 SPM 1 M
677 SAPCO FEMA-1 23P-3430 Mechanical 2 Months FEMA Task 23P-3430 MECH-SAP 5 SPM 2 M
678 SAPCO FEMA-1 23P-3430 Mechanical 6 Months FEMA Task 23P-3430 MECH-SAP 5 SPM 6 M
679 SAPCO FEMA-1 23P-3430 Mechanical 3 Years FEMA Task 23P-3430 MECH-SAP 5 SPM 3 Y
680 SAPCO FEMA-1 23P-3430 Mechanical 5 Years FEMA Task 23P-3430 MECH-SAP 5 SPM 5 Y
681 SAPCO FEMA-1 23P-3431 Mechanical 1 Months FEMA Task 23P-3431 MECH-SAP 5 SPM 1 M
682 SAPCO FEMA-1 23P-3431 Mechanical 3 Months FEMA Task 23P-3431 MECH-SAP 5 SPM 3 M
683 SAPCO FEMA-1 23P-3431 Mechanical 6 Months FEMA Task 23P-3431 MECH-SAP 5 SPM 6 M
684 SAPCO FEMA-1 23P-3431 Mechanical 1 Years FEMA Task 23P-3431 MECH-SAP 5 SPM 1 Y

358122780.xlsx Page 41 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
685 SAPCO FEMA-1 23P-3431 Mechanical 3 Years FEMA Task 23P-3431 MECH-SAP 5 SPM 3 Y
686 SAPCO FEMA-1 23P-3520 Mechanical 1 Months FEMA Task 23P-3520 MECH-SAP 5 SPM 1 M
687 SAPCO FEMA-1 23P-3520 Mechanical 3 Months FEMA Task 23P-3520 MECH-SAP 5 SPM 3 M
688 SAPCO FEMA-1 23P-3520 Mechanical 6 Months FEMA Task 23P-3520 MECH-SAP 5 SPM 6 M
689 SAPCO FEMA-1 23P-3520 Mechanical 1 Years FEMA Task 23P-3520 MECH-SAP 5 SPM 1 Y
690 SAPCO FEMA-1 23P-3520 Mechanical 3 Years FEMA Task 23P-3520 MECH-SAP 5 SPM 3 Y
691 SAPCO FEMA-1 23P-3701 Mechanical 1 Months FEMA Task 23P-3701 MECH-SAP 5 SPM 1 M
692 SAPCO FEMA-1 23P-3701 Mechanical 6 Months FEMA Task 23P-3701 MECH-SAP 5 SPM 6 M
693 SAPCO FEMA-1 23P-3701 Mechanical 1 Years FEMA Task 23P-3701 MECH-SAP 5 SPM 1 Y
694 SAPCO FEMA-1 23P-3701 Mechanical 3 Years FEMA Task 23P-3701 MECH-SAP 5 SPM 3 Y
695 SAPCO FEMA-1 23P-3701 Mechanical 5 Years FEMA Task 23P-3701 MECH-SAP 5 SPM
696 SAPCO FEMA-1 23P-3701 Mechanical 2 Months FEMA Task 23P-3701 MECH-SAP 5 SPM 2 M
697 SAPCO FEMA-1 23P-3701 Mechanical 6 Months FEMA Task 23P-3701 MECH-SAP 5 SPM 6 M
698 SAPCO FEMA-1 23P-3701 Mechanical 2 Weeks FEMA Task 23P-3701 MECH-SAP 5 SPM 2 W
699 SAPCO FEMA-1 23P-3701 Mechanical 1 Years FEMA Task 23P-3701 MECH-SAP 5 SPM 1 Y
700 SAPCO FEMA-1 23P-3701 Mechanical 3 Years FEMA Task 23P-3701 MECH-SAP 5 SPM 3 Y
701 SAPCO FEMA-1 23P-3701 Mechanical 5 Years FEMA Task 23P-3701 MECH-SAP 5 SPM 5 Y
702 SAPCO FEMA-1 23P-4001 Mechanical 1 Months FEMA Task 23P-4001 MECH-SAP 5 SPM 1 M
703 SAPCO FEMA-1 23P-4001 Mechanical 2 Months FEMA Task 23P-4001 MECH-SAP 5 SPM 2 M
704 SAPCO FEMA-1 23P-4001 Mechanical 6 Months FEMA Task 23P-4001 MECH-SAP 5 SPM 6 M
705 SAPCO FEMA-1 23P-4001 Mechanical 5 Years FEMA Task 23P-4001 MECH-SAP 5 SPM 5 Y
706 SAPCO FEMA-1 23P-4001 Mechanical 1 Months FEMA Task 23P-4001 MECH-SAP 5 SPM 1 M
707 SAPCO FEMA-1 23P-4001 Mechanical 2 Weeks FEMA Task 23P-4001 MECH-SAP 5 SPM 2 W
708 SAPCO FEMA-1 23P-4001 Mechanical 1 Years FEMA Task 23P-4001 MECH-SAP 5 SPM 1 Y
709 SAPCO FEMA-1 23P-4001 Mechanical 3 Years FEMA Task 23P-4001 MECH-SAP 5 SPM 3 Y
710 SAPCO FEMA-1 23P-4001 Mechanical 5 Years FEMA Task 23P-4001 MECH-SAP 5 SPM 5 Y
711 SAPCO FEMA-1 23P-4101 Mechanical 1 Months FEMA Task 23P-4101 MECH-SAP 5 SPM 1 M
712 SAPCO FEMA-1 23P-4101 Mechanical 2 Months FEMA Task 23P-4101 MECH-SAP 5 SPM 2 M
713 SAPCO FEMA-1 23P-4101 Mechanical 6 Months FEMA Task 23P-4101 MECH-SAP 5 SPM 6 M
714 SAPCO FEMA-1 23P-4101 Mechanical 2 Weeks FEMA Task 23P-4101 MECH-SAP 5 SPM 2 W
715 SAPCO FEMA-1 23P-4101 Mechanical 1 Years FEMA Task 23P-4101 MECH-SAP 5 SPM 1 Y
716 SAPCO FEMA-1 23P-4101 Mechanical 3 Years FEMA Task 23P-4101 MECH-SAP 5 SPM 3 Y
717 SAPCO FEMA-1 23P-4101 Mechanical 5 Years FEMA Task 23P-4101 MECH-SAP 5 SPM 5 Y
718 SAPCO FEMA-1 23P-4102 Mechanical 1 Months FEMA Task 23P-4102 MECH-SAP 5 SPM 1 M
719 SAPCO FEMA-1 23P-4102 Mechanical 2 Months FEMA Task 23P-4102 MECH-SAP 5 SPM 2 M
720 SAPCO FEMA-1 23P-4102 Mechanical 6 Months FEMA Task 23P-4102 MECH-SAP 5 SPM 6 M
721 SAPCO FEMA-1 23P-4102 Mechanical 2 Weeks FEMA Task 23P-4102 MECH-SAP 5 SPM 2 W
722 SAPCO FEMA-1 23P-4102 Mechanical 1 Years FEMA Task 23P-4102 MECH-SAP 5 SPM 1 Y
723 SAPCO FEMA-1 23P-4102 Mechanical 3 Years FEMA Task 23P-4102 MECH-SAP 5 SPM 3 Y
724 SAPCO FEMA-1 23P-4102 Mechanical 5 Years FEMA Task 23P-4102 MECH-SAP 5 SPM 5 Y
23PK-6003A Mechanical 3 Months FEMA
725 SAPCO FEMA-1 23PK-6003A MECH-SAP 5 SPM 3 M
Task
726 SAPCO FEMA-1 23PK-6003A Mechanical 1 Years FEMA Task 23PK-6003A MECH-SAP 5 SPM 1 Y
727 SAPCO FEMA-1 23PK-6003A Mechanical 2 Years FEMA Task 23PK-6003A MECH-SAP 5 SPM 2 Y
728 SAPCO FEMA-1 23PK-6003A Mechanical 5 Years FEMA Task 23PK-6003A MECH-SAP 5 SPM 5 Y
23PK-6003B Mechanical 3 Months FEMA
729 SAPCO FEMA-1 23PK-6003B MECH-SAP 5 SPM 3 M
Task
730 SAPCO FEMA-1 23PK-6003B Mechanical 1 Years FEMA Task 23PK-6003B MECH-SAP 5 SPM 1 Y
731 SAPCO FEMA-1 23PK-6003B Mechanical 2 Years FEMA Task 23PK-6003B MECH-SAP 5 SPM 2 Y
732 SAPCO FEMA-1 23PK-6003B Mechanical 5 Years FEMA Task 23PK-6003B MECH-SAP 5 SPM 5 Y
23PK-6103A Mechanical 3 Months FEMA
733 SAPCO FEMA-1 23PK-6103A MECH-SAP 5 SPM 3 M
Task
734 SAPCO FEMA-1 23PK-6103A Mechanical 1 Years FEMA Task 23PK-6103A MECH-SAP 5 SPM 1 Y
735 SAPCO FEMA-1 23PK-6103A Mechanical 2 Years FEMA Task 23PK-6103A MECH-SAP 5 SPM 2 Y
736 SAPCO FEMA-1 23PK-6103A Mechanical 5 Years FEMA Task 23PK-6103A MECH-SAP 5 SPM 5 Y
23PK-6103B Mechanical 3 Months FEMA
737 SAPCO FEMA-1 23PK-6103B MECH-SAP 5 SPM 3 M
Task
738 SAPCO FEMA-1 23PK-6103B Mechanical 1 Years FEMA Task 23PK-6103B MECH-SAP 5 SPM 1 Y
739 SAPCO FEMA-1 23PK-6103B Mechanical 2 Years FEMA Task 23PK-6103B MECH-SAP 5 SPM 2 Y
740 SAPCO FEMA-1 23PK-6103B Mechanical 5 Years FEMA Task 23PK-6103B MECH-SAP 5 SPM 5 Y
23PK-6103C Mechanical 3 Months FEMA
741 SAPCO FEMA-1 23PK-6103C MECH-SAP 5 SPM 3 M
Task

358122780.xlsx Page 42 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
742 SAPCO FEMA-1 23PK-6103C Mechanical 1 Years FEMA Task 23PK-6103C MECH-SAP 5 SPM 1 Y
743 SAPCO FEMA-1 23PK-6103C Mechanical 2 Years FEMA Task 23PK-6103C MECH-SAP 5 SPM 2 Y
744 SAPCO FEMA-1 23PK-6103C Mechanical 5 Years FEMA Task 23PK-6103C MECH-SAP 5 SPM 5 Y
745 SAPCO FEMA-1 23R-1310 Mechanical 15 Days FEMA Task 23R-1310 MECH-SAP 5 SPM 35 D
746 SAPCO FEMA-1 23R-1310 Mechanical 35 Days FEMA Task 23R-1310 MECH-SAP 5 SPM 35 D
747 SAPCO FEMA-1 23R-1310 Mechanical 70 Days FEMA Task 23R-1310 MECH-SAP 5 SPM 70 D
748 SAPCO FEMA-1 23R-1310 Mechanical 6 Months FEMA Task 23R-1310 MECH-SAP 5 SPM 6 M
749 SAPCO FEMA-1 23R-1310 Mechanical 2 Years FEMA Task 23R-1310 MECH-SAP 5 SPM 2 Y
750 SAPCO FEMA-1 23R-1310 Mechanical 5 Years FEMA Task 23R-1310 MECH-SAP 5 SPM 5 Y
751 SAPCO FEMA-1 23R-1320 Mechanical 15 Days FEMA Task 23R-1320 MECH-SAP 5 SPM 35 D
752 SAPCO FEMA-1 23R-1320 Mechanical 35 Days FEMA Task 23R-1320 MECH-SAP 5 SPM 35 D
753 SAPCO FEMA-1 23R-1320 Mechanical 70 Days FEMA Task 23R-1320 MECH-SAP 5 SPM
754 SAPCO FEMA-1 23R-1320 Mechanical 6 Months FEMA Task 23R-1320 MECH-SAP 5 SPM 6 M
755 SAPCO FEMA-1 23R-1320 Mechanical 2 Years FEMA Task 23R-1320 MECH-SAP 5 SPM 2 Y
756 SAPCO FEMA-1 23R-1320 Mechanical 5 Years FEMA Task 23R-1320 MECH-SAP 5 SPM 5 Y
757 SAPCO FEMA-1 23R-2310 Mechanical 15 Days FEMA Task 23R-2310 MECH-SAP 5 SPM 35 D
758 SAPCO FEMA-1 23R-2310 Mechanical 35 Days FEMA Task 23R-2310 MECH-SAP 5 SPM 35 D
759 SAPCO FEMA-1 23R-2310 Mechanical 70 Days FEMA Task 23R-2310 MECH-SAP 5 SPM
760 SAPCO FEMA-1 23R-2310 Mechanical 6 Months FEMA Task 23R-2310 MECH-SAP 5 SPM 6 M
761 SAPCO FEMA-1 23R-2310 Mechanical 2 Years FEMA Task 23R-2310 MECH-SAP 5 SPM 2 Y
762 SAPCO FEMA-1 23R-2310 Mechanical 5 Years FEMA Task 23R-2310 MECH-SAP 5 SPM 5 Y
763 SAPCO FEMA-1 23R-2320 Mechanical 15 Days FEMA Task 23R-2320 MECH-SAP 5 SPM 35 D
764 SAPCO FEMA-1 23R-2320 Mechanical 35 Days FEMA Task 23R-2320 MECH-SAP 5 SPM 35 D
765 SAPCO FEMA-1 23R-2320 Mechanical 70 Days FEMA Task 23R-2320 MECH-SAP 5 SPM
766 SAPCO FEMA-1 23R-2320 Mechanical 6 Months FEMA Task 23R-2320 MECH-SAP 5 SPM 6 M
767 SAPCO FEMA-1 23R-2320 Mechanical 2 Years FEMA Task 23R-2320 MECH-SAP 5 SPM 2 Y
768 SAPCO FEMA-1 23R-2320 Mechanical 5 Years FEMA Task 23R-2320 MECH-SAP 5 SPM 5 Y
769 SAPCO FEMA-1 23Z-1410 Mechanical 35 Days FEMA Task 23Z-1410 MECH-SAP 5 SPM 35 D
770 SAPCO FEMA-1 23Z-1410 Mechanical 3 Months FEMA Task 23Z-1410 MECH-SAP 5 SPM 3 M
771 SAPCO FEMA-1 23Z-1410 Mechanical 1 Years FEMA Task 23Z-1410 MECH-SAP 5 SPM 1 Y
772 SAPCO FEMA-1 23Z-1410 Mechanical 5 Years FEMA Task 23Z-1410 MECH-SAP 5 SPM 5 Y
773 SAPCO FEMA-1 23Z-1420 Mechanical 35 Days FEMA Task 23Z-1420 MECH-SAP 5 SPM 35 D
774 SAPCO FEMA-1 23Z-1420 Mechanical 3 Months FEMA Task 23Z-1420 MECH-SAP 5 SPM 3 M
775 SAPCO FEMA-1 23Z-1420 Mechanical 1 Years FEMA Task 23Z-1420 MECH-SAP 5 SPM 1 Y
776 SAPCO FEMA-1 23Z-1420 Mechanical 5 Years FEMA Task 23Z-1420 MECH-SAP 5 SPM 5 Y
777 SAPCO FEMA-1 23Z-1500 Mechanical 35 Days FEMA Task 23Z-1500 MECH-SAP 5 SPM 35 D
778 SAPCO FEMA-1 23Z-1500 Mechanical 3 Months FEMA Task 23Z-1500 MECH-SAP 5 SPM 3 M
779 SAPCO FEMA-1 23Z-1500 Mechanical 1 Years FEMA Task 23Z-1500 MECH-SAP 5 SPM 1 Y
780 SAPCO FEMA-1 23Z-1500 Mechanical 3 Years FEMA Task 23Z-1500 MECH-SAP 5 SPM 3 Y
781 SAPCO FEMA-1 23Z-1500 Mechanical 5 Years FEMA Task 23Z-1500 MECH-SAP 5 SPM 5 Y
782 SAPCO FEMA-1 23Z-1601 Mechanical 35 Days FEMA Task 23Z-1601 MECH-SAP 5 SPM 35 D
783 SAPCO FEMA-1 23Z-1601 Mechanical 3 Months FEMA Task 23Z-1601 MECH-SAP 5 SPM 3 M
784 SAPCO FEMA-1 23Z-1601 Mechanical 6 Months FEMA Task 23Z-1601 MECH-SAP 5 SPM 6 M
785 SAPCO FEMA-1 23Z-1601 Mechanical 1 Weeks FEMA Task 23Z-1601 MECH-SAP 5 SPM 1 W
786 SAPCO FEMA-1 23Z-1601 Mechanical 3 Years FEMA Task 23Z-1601 MECH-SAP 5 SPM 3 Y
787 SAPCO FEMA-1 23Z-1601 Mechanical 5 Years FEMA Task 23Z-1601 MECH-SAP 5 SPM 5 Y
788 SAPCO FEMA-1 23Z-1601 Mechanical 35 Days FEMA Task 23Z-1601 MECH-SAP 5 SPM 35 D
789 SAPCO FEMA-1 23Z-1602 Mechanical 35 Days FEMA Task 23Z-1602 MECH-SAP 5 SPM 35 D
790 SAPCO FEMA-1 23Z-1602 Mechanical 3 Months FEMA Task 23Z-1602 MECH-SAP 5 SPM 3 M
791 SAPCO FEMA-1 23Z-1602 Mechanical 6 Months FEMA Task 23Z-1602 MECH-SAP 5 SPM 6 M
792 SAPCO FEMA-1 23Z-1602 Mechanical 1 Weeks FEMA Task 23Z-1602 MECH-SAP 5 SPM 1 W
793 SAPCO FEMA-1 23Z-1602 Mechanical 2 Years FEMA Task 23Z-1602 MECH-SAP 5 SPM 2 Y
794 SAPCO FEMA-1 23Z-1602 Mechanical 3 Years FEMA Task 23Z-1602 MECH-SAP 5 SPM 3 Y
795 SAPCO FEMA-1 23Z-1602 Mechanical 5 Years FEMA Task 23Z-1602 MECH-SAP 5 SPM 5 Y
796 SAPCO FEMA-1 23Z-1610 Mechanical 40 Days FEMA Task 23Z-1610 MECH-SAP 5 SPM 40 D
797 SAPCO FEMA-1 23Z-1610 Mechanical 3 Months FEMA Task 23Z-1610 MECH-SAP 5 SPM 3 M
798 SAPCO FEMA-1 23Z-1610 Mechanical 6 Months FEMA Task 23Z-1610 MECH-SAP 5 SPM 6 M

358122780.xlsx Page 43 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
799 SAPCO FEMA-1 23Z-1610 Mechanical 1 Weeks FEMA Task 23Z-1610 MECH-SAP 5 SPM 1 W
800 SAPCO FEMA-1 23Z-1610 Mechanical 1 Years FEMA Task 23Z-1610 MECH-SAP 5 SPM 1 Y
801 SAPCO FEMA-1 23Z-1610 Mechanical 2 Years FEMA Task 23Z-1610 MECH-SAP 5 SPM 2 Y
802 SAPCO FEMA-1 23Z-1610 Mechanical 5 Years FEMA Task 23Z-1610 MECH-SAP 5 SPM 5 Y
803 SAPCO FEMA-1 23Z-1610 Mechanical 10 Years FEMA Task 23Z-1610 MECH-SAP 5 SPM 10 Y
804 SAPCO FEMA-1 23Z-1611 Mechanical 3 Months FEMA Task 23Z-1611 MECH-SAP 5 SPM 3 M
805 SAPCO FEMA-1 23Z-1611 Mechanical 6 Months FEMA Task 23Z-1611 MECH-SAP 5 SPM 6 M
806 SAPCO FEMA-1 23Z-1611 Mechanical 40 Months FEMA Task 23Z-1611 MECH-SAP 5 SPM
807 SAPCO FEMA-1 23Z-1611 Mechanical 1 Weeks FEMA Task 23Z-1611 MECH-SAP 5 SPM 1 W
808 SAPCO FEMA-1 23Z-1611 Mechanical 1 Years FEMA Task 23Z-1611 MECH-SAP 5 SPM 1 Y
809 SAPCO FEMA-1 23Z-1611 Mechanical 2 Years FEMA Task 23Z-1611 MECH-SAP 5 SPM 2 Y
810 SAPCO FEMA-1 23Z-1611 Mechanical 5 Years FEMA Task 23Z-1611 MECH-SAP 5 SPM 5 Y
811 SAPCO FEMA-1 23Z-1612 Mechanical 3 Months FEMA Task 23Z-1612 MECH-SAP 5 SPM 3 M
812 SAPCO FEMA-1 23Z-1612 Mechanical 6 Months FEMA Task 23Z-1612 MECH-SAP 5 SPM 6 M
813 SAPCO FEMA-1 23Z-1612 Mechanical 40 Months FEMA Task 23Z-1612 MECH-SAP 5 SPM
814 SAPCO FEMA-1 23Z-1612 Mechanical 1 Weeks FEMA Task 23Z-1612 MECH-SAP 5 SPM 1 W
815 SAPCO FEMA-1 23Z-1612 Mechanical 1 Years FEMA Task 23Z-1612 MECH-SAP 5 SPM 1 Y
816 SAPCO FEMA-1 23Z-1612 Mechanical 2 Years FEMA Task 23Z-1612 MECH-SAP 5 SPM 2 Y
817 SAPCO FEMA-1 23Z-1612 Mechanical 5 Years FEMA Task 23Z-1612 MECH-SAP 5 SPM 5 Y
818 SAPCO FEMA-1 23Z-1613 Mechanical 3 Months FEMA Task 23Z-1613 MECH-SAP 5 SPM 3 M
819 SAPCO FEMA-1 23Z-1613 Mechanical 6 Months FEMA Task 23Z-1613 MECH-SAP 5 SPM 6 M
820 SAPCO FEMA-1 23Z-1613 Mechanical 40 Months FEMA Task 23F-1622-23Z-1613 MECH-SAP 5 SPM
821 SAPCO FEMA-1 23Z-1613 Mechanical 1 Weeks FEMA Task 23Z-1613 MECH-SAP 5 SPM 1 W
822 SAPCO FEMA-1 23Z-1613 Mechanical 1 Years FEMA Task 23Z-1613 MECH-SAP 5 SPM 1 Y
823 SAPCO FEMA-1 23Z-1613 Mechanical 2 Years FEMA Task 23Z-1613 MECH-SAP 5 SPM 2 Y
824 SAPCO FEMA-1 23Z-1613 Mechanical 5 Years FEMA Task 23Z-1613 MECH-SAP 5 SPM 5 Y
825 SAPCO FEMA-1 23Z-1620 Mechanical 35 Days FEMA Task 23Z-1620 MECH-SAP 5 SPM 35 D
826 SAPCO FEMA-1 23Z-1620 Mechanical 1 Months FEMA Task 23Z-1620 MECH-SAP 5 SPM 1 M
827 SAPCO FEMA-1 23Z-1620 Mechanical 2 Months FEMA Task 23Z-1620 MECH-SAP 5 SPM 2 M
828 SAPCO FEMA-1 23Z-1620 Mechanical 6 Months FEMA Task 23Z-1620 MECH-SAP 5 SPM 6 M
829 SAPCO FEMA-1 23Z-1620 Mechanical 1 Years FEMA Task 23Z-1620 MECH-SAP 5 SPM 1 Y
830 SAPCO FEMA-1 23Z-1620 Mechanical 5 Years FEMA Task 23Z-1620 MECH-SAP 5 SPM 5 Y
831 SAPCO FEMA-1 23Z-1621 Mechanical 35 Days FEMA Task 23Z-1621 MECH-SAP 5 SPM 35 D
832 SAPCO FEMA-1 23Z-1621 Mechanical 1 Months FEMA Task 23Z-1621 MECH-SAP 5 SPM 1 M
833 SAPCO FEMA-1 23Z-1621 Mechanical 2 Months FEMA Task 23Z-1621 MECH-SAP 5 SPM 2 M
834 SAPCO FEMA-1 23Z-1621 Mechanical 6 Months FEMA Task 23Z-1621 MECH-SAP 5 SPM 6 M
835 SAPCO FEMA-1 23Z-1621 Mechanical 1 Years FEMA Task 23Z-1621 MECH-SAP 5 SPM 1 Y
836 SAPCO FEMA-1 23Z-1621 Mechanical 5 Years FEMA Task 23F-1622-23Z-1621 MECH-SAP 5 SPM 5 Y
837 SAPCO FEMA-1 23Z-1622 Mechanical 35 Days FEMA Task 23F-1622-23Z-1622 MECH-SAP 5 SPM 35 D
838 SAPCO FEMA-1 23Z-1622 Mechanical 1 Months FEMA Task 23Z-1622 MECH-SAP 5 SPM 1 M
839 SAPCO FEMA-1 23Z-1622 Mechanical 2 Months FEMA Task 23Z-1622 MECH-SAP 5 SPM 2 M
840 SAPCO FEMA-1 23Z-1622 Mechanical 6 Months FEMA Task 23Z-1622 MECH-SAP 5 SPM 6 M
841 SAPCO FEMA-1 23Z-1622 Mechanical 1 Years FEMA Task 23Z-1622 MECH-SAP 5 SPM 1 Y
842 SAPCO FEMA-1 23Z-1622 Mechanical 5 Years FEMA Task 23Z-1622 MECH-SAP 5 SPM 5 Y
843 SAPCO FEMA-1 23Z-1720 Mechanical 3 Months FEMA Task 23Z-1720 MECH-SAP 5 SPM 3 M
844 SAPCO FEMA-1 23Z-1720 Mechanical 6 Months FEMA Task 23Z-1720 MECH-SAP 5 SPM 6 M
845 SAPCO FEMA-1 23Z-1720 Mechanical 1 Years FEMA Task 23Z-1720 MECH-SAP 5 SPM 1 Y
846 SAPCO FEMA-1 23Z-1720 Mechanical 3 Years FEMA Task 23Z-1720 MECH-SAP 5 SPM 3 Y
847 SAPCO FEMA-1 23Z-1720 Mechanical 5 Years FEMA Task 23Z-1720 MECH-SAP 5 SPM 5 Y
848 SAPCO FEMA-1 23Z-1850 Mechanical 3 Months FEMA Task 23Z-1850 MECH-SAP 5 SPM 3 M
849 SAPCO FEMA-1 23Z-1850 Mechanical 1 Years FEMA Task 23Z-1850 MECH-SAP 5 SPM 1 Y
850 SAPCO FEMA-1 23Z-1850 Mechanical 3 Years FEMA Task 23Z-1850 MECH-SAP 5 SPM 3 Y
851 SAPCO FEMA-1 23Z-1850 Mechanical 5 Years FEMA Task 23Z-1850 MECH-SAP 5 SPM 5 Y
852 SAPCO FEMA-1 23Z-2410 Mechanical 35 Days FEMA Task 23Z-2410 MECH-SAP 5 SPM 35 D
853 SAPCO FEMA-1 23Z-2410 Mechanical 3 Months FEMA Task 23Z-2410 MECH-SAP 5 SPM 3 M
854 SAPCO FEMA-1 23Z-2410 Mechanical 1 Years FEMA Task 23Z-2410 MECH-SAP 5 SPM 1 Y
855 SAPCO FEMA-1 23Z-2410 Mechanical 5 Years FEMA Task 23Z-2410 MECH-SAP 5 SPM 5 Y

358122780.xlsx Page 44 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE


SCHEDULING START OF ACTUAL
SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* PERIOD CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
856 SAPCO FEMA-1 23Z-2420 Mechanical 35 Days FEMA Task 23Z-2420 MECH-SAP 5 SPM 35 D
857 SAPCO FEMA-1 23Z-2420 Mechanical 3 Months FEMA Task 23Z-2420 MECH-SAP 5 SPM 3 M
858 SAPCO FEMA-1 23Z-2420 Mechanical 1 Years FEMA Task 23Z-2420 MECH-SAP 5 SPM 1 Y
859 SAPCO FEMA-1 23Z-2420 Mechanical 5 Years FEMA Task 23Z-2420 MECH-SAP 5 SPM 5 Y
860 SAPCO FEMA-1 23Z-2500 Mechanical 35 Days FEMA Task 23Z-2500 MECH-SAP 5 SPM 35 D
861 SAPCO FEMA-1 23Z-2500 Mechanical 3 Months FEMA Task 23Z-2500 MECH-SAP 5 SPM 3 M
862 SAPCO FEMA-1 23Z-2500 Mechanical 1 Years FEMA Task 23Z-2500 MECH-SAP 5 SPM 1 Y
863 SAPCO FEMA-1 23Z-2500 Mechanical 3 Years FEMA Task 23Z-2500 MECH-SAP 5 SPM 3 Y
864 SAPCO FEMA-1 23Z-2500 Mechanical 5 Years FEMA Task 23Z-2500 MECH-SAP 5 SPM 5 Y
865 SAPCO FEMA-1 23Z-2601 Mechanical 35 Days FEMA Task 23Z-2601 MECH-SAP 5 SPM 35 D
866 SAPCO FEMA-1 23Z-2601 Mechanical 3 Months FEMA Task 23Z-2601 MECH-SAP 5 SPM 3 M
867 SAPCO FEMA-1 23Z-2601 Mechanical 6 Months FEMA Task 23Z-2601 MECH-SAP 5 SPM 6 M
868 SAPCO FEMA-1 23Z-2601 Mechanical 1 Weeks FEMA Task 23Z-2601 MECH-SAP 5 SPM 1 W
869 SAPCO FEMA-1 23Z-2601 Mechanical 2 Years FEMA Task 23Z-2601 MECH-SAP 5 SPM 2 Y
870 SAPCO FEMA-1 23Z-2601 Mechanical 3 Years FEMA Task 23Z-2601 MECH-SAP 5 SPM 3 Y
871 SAPCO FEMA-1 23Z-2601 Mechanical 5 Years FEMA Task 23Z-2601 MECH-SAP 5 SPM 5 Y
872 SAPCO FEMA-1 23Z-2602 Mechanical 35 Days FEMA Task 23Z-2602 MECH-SAP 5 SPM 35 D
873 SAPCO FEMA-1 23Z-2602 Mechanical 3 Months FEMA Task 23Z-2602 MECH-SAP 5 SPM 3 M
874 SAPCO FEMA-1 23Z-2602 Mechanical 6 Months FEMA Task 23Z-2602 MECH-SAP 5 SPM 6 M
875 SAPCO FEMA-1 23Z-2602 Mechanical 1 Weeks FEMA Task 23Z-2602 MECH-SAP 5 SPM 1 W
876 SAPCO FEMA-1 23Z-2602 Mechanical 2 Years FEMA Task 23Z-2602 MECH-SAP 5 SPM 2 Y
877 SAPCO FEMA-1 23Z-2602 Mechanical 3 Years FEMA Task 23Z-2602 MECH-SAP 5 SPM 3 Y
878 SAPCO FEMA-1 23Z-2602 Mechanical 5 Years FEMA Task 23Z-2602 MECH-SAP 5 SPM 5 Y

Notes: * Fields are mandatory


** mandatory only if for creation
*** mandatory only if for change/delete
insert rows as required
signatures required on last page only

Requested by: Approved by(end-user Supervisor): Approved by (Superintendent): Updated in SAP by:

___________________________ ___________________________ ___________________________ ___________________________


(Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date)

358122780.xlsx Page 45 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE

SCHEDULING START OF ACTUAL


SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL PERIOD ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
1 29553 MECH-1 PM OF KNEADER 6M & Y PM 23Z-1410 MECH-SAP SPM
2 29554 MECH-1 PM OF COOLER SCRUBBER M & 3M PM 23E-7201 MECH-SAP SPM
3 29556 MECH-1 PM OF POLYBELT M PM 23R-1310 MECH-SAP SPM
4 29558 MECH-1 PM OF FAN/AIR COOLER 6M PM 23AB-1501 MECH-SAP SPM
5 29559 MECH-1 PM OF FAN/AIR COOLER 6M PM 23AB-1511 MECH-SAP SPM
6 29560 MECH-1 PM OF FAN/AIR COOLER 6M PM 23AB-2504 MECH-SAP SPM
7 29561 MECH-1 PM OF FAN/AIR COOLER 6M PM 23AB-2514 MECH-SAP SPM
8 29565 MECH-1 PM OF SCREW CONVEYOR OF BELT DRYER 23FX-1501 MECH-SAP SPM
9 29568 MECH-1 CROSS BLADE CRUSHER 23Z-1500 MECH-SAP SPM
10 29569 MECH-1 PM OF OSCILLATING BELT M & 3M PM 23FX-1500 MECH-SAP SPM
11 29570 MECH-1 PM OF BLOWER VENT STACK M- 3M & Y PM 23AB-1740 MECH-SAP SPM
12 29575 MECH-1 PM OF DUST FILTER 6M PM 23F-2601 MECH-SAP SPM
13 29576 MECH-1 PM OF ROTARY VALVE 2W PM 23FH-1540 MECH-SAP SPM
14 29578 MECH-1 PM OF ROTARY VALVE 2W PM 23FH-2602 MECH-SAP SPM
15 29579 MECH-1 PM OF LIW FEEDERS M PM 23FX-1701 MECH-SAP SPM
16 29581 MECH-1 PM OF COLLECTION BELT 3M PM 23FX-1400 MECH-SAP SPM
17 29584 MECH-1 PM OF ROTARY VALVE 2W PM 23FH-1650 MECH-SAP SPM
18 29590 MECH-1 PM OF FEEDING SCREW M PM 23FX-1410 MECH-SAP SPM
19 29592 MECH-1 PM OF BEARING OIL UNIT M PM 23M-2721 MECH-SAP SPM
20 29593 MECH-1 PM OF SOLID COOLER M PM 23E-1725 MECH-SAP SPM
21 29594 MECH-1 PM OF CONVEYOR SCREW M & 3M 23FX-1725 MECH-SAP SPM
22 29645 MECH-1 PM OF SIEVE (23F-1610) 23F-1610 MECH-SAP SPM
23 29646 MECH-1 PM OF SIEVE (23F-1611) 23F-1611 MECH-SAP SPM
24 29647 MECH-1 PM OF SIEVE (23F-1612) 23F-1612 MECH-SAP SPM
25 29648 MECH-1 PM OF SIEVE (23F-1613) 23F-1613 MECH-SAP SPM
26 29649 MECH-1 PM OF SIEVE (23F-1620) 23F-1620 MECH-SAP SPM
27 29650 MECH-1 PM OF SIEVE (23F-1621) 23F-1621 MECH-SAP SPM
28 29651 MECH-1 PM OF SIEVE (23F-1622) 23F-1622 MECH-SAP SPM
29 29656 MECH-1 PM OF KNEADER (23Z-1410) 23Z-1410 MECH-SAP SPM
30 29657 MECH-1 PM OF KNEADER (23Z-1420) 23Z-1420 MECH-SAP SPM
31 29658 MECH-1 PM OF KNEADER (23Z-2410) 23Z-2410 MECH-SAP SPM
32 29659 MECH-1 PM OF KNEADER (23Z-2420) 23Z-2420 MECH-SAP SPM
33 29660 MECH-1 PM OF NIBBLER (23Z-1720) 23Z-1720 MECH-SAP SPM
34 29661 MECH-1 PM OF NIBBLER (23Z-1850) 23Z-1850 MECH-SAP SPM
35 29677 MECH-1 PM OF-FAN/AIR COOLER (23AB-1501) 23AB-1501 MECH-SAP SPM
36 29678 MECH-1 PM OF-FAN/AIR COOLER (23AB-1502) 23AB-1502 MECH-SAP SPM
37 29679 MECH-1 PM OF-FAN/AIR COOLER (23AB-1503) 23AB-1503 MECH-SAP SPM
38 29680 MECH-1 PM OF-FAN/AIR COOLER (23AB-1504) 23AB-1504 MECH-SAP SPM
39 29681 MECH-1 PM OF-FAN/AIR COOLER (23AB-1505) 23AB-1505 MECH-SAP SPM
40 29682 MECH-1 PM OF-FAN/AIR COOLER (23AB-1506) 23AB-1506 MECH-SAP SPM
41 29683 MECH-1 PM OF-FAN/AIR COOLER (23AB-1507) 23AB-1507 MECH-SAP SPM
42 29684 MECH-1 PM OF-FAN/AIR COOLER (23AB-1508) 23AB-1508 MECH-SAP SPM
43 29685 MECH-1 PM OF-FAN/AIR COOLER (23AB-1509) 23AB-1509 MECH-SAP SPM
44 29686 MECH-1 PM OF-FAN/AIR COOLER (23AB-1510) 23AB-1510 MECH-SAP SPM
45 29687 MECH-1 PM OF-FAN/AIR COOLER (23AB-1511) 23AB-1511 MECH-SAP SPM
46 29688 MECH-1 PM OF-FAN/AIR COOLER (23AB-1512) 23AB-1512 MECH-SAP SPM
47 29689 MECH-1 PM OF-FAN/AIR COOLER (23AB-1513) 23AB-1513 MECH-SAP SPM
48 29690 MECH-1 PM OF-FAN/AIR COOLER (23AB-1514) 23AB-1514 MECH-SAP SPM
49 29691 MECH-1 PM OF-FAN/AIR COOLER (23AB-1515) 23AB-1515 MECH-SAP SPM
50 29692 MECH-1 PM OF-FAN/AIR COOLER (23AB-1516) 23AB-1516 MECH-SAP SPM
51 29693 MECH-1 PM OF-FAN/AIR COOLER (23AB-1517) 23AB-1517 MECH-SAP SPM
52 29694 MECH-1 PM OF-FAN/AIR COOLER (23AB-2501) 23AB-2501 MECH-SAP SPM
53 29695 MECH-1 PM OF-FAN/AIR COOLER (23AB-2502) 23AB-2502 MECH-SAP SPM
54 29696 MECH-1 PM OF-FAN/AIR COOLER (23AB-2503) 23AB-2503 MECH-SAP SPM
55 29697 MECH-1 PM OF-FAN/AIR COOLER (23AB-2504) 23AB-2504 MECH-SAP SPM

358122780.xlsx Page 46 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE

SCHEDULING START OF ACTUAL


SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL PERIOD ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
56 29698 MECH-1 PM OF-FAN/AIR COOLER (23AB-2505) 23AB-2505 MECH-SAP SPM
57 29699 MECH-1 PM OF-FAN/AIR COOLER (23AB-2506) 23AB-2506 MECH-SAP SPM
58 29700 MECH-1 PM OF-FAN/AIR COOLER (23AB-2507) 23AB-2507 MECH-SAP SPM
59 29701 MECH-1 PM OF-FAN/AIR COOLER (23AB-2508) 23AB-2508 MECH-SAP SPM
60 29702 MECH-1 PM OF-FAN/AIR COOLER (23AB-2509) 23AB-2509 MECH-SAP SPM
61 29703 MECH-1 PM OF-FAN/AIR COOLER (23AB-2510) 23AB-2510 MECH-SAP SPM
62 29704 MECH-1 PM OF-FAN/AIR COOLER (23AB-2511) 23AB-2511 MECH-SAP SPM
63 29705 MECH-1 PM OF-FAN/AIR COOLER (23AB-2512) 23AB-2512 MECH-SAP SPM
64 29706 MECH-1 PM OF-FAN/AIR COOLER (23AB-2513) 23AB-2513 MECH-SAP SPM
65 29707 MECH-1 PM OF-FAN/AIR COOLER (23AB-2514) 23AB-2514 MECH-SAP SPM
66 29708 MECH-1 PM OF-FAN/AIR COOLER (23AB-2515) 23AB-2515 MECH-SAP SPM
67 29709 MECH-1 PM OF-FAN/AIR COOLER (23AB-2516) 23AB-2516 MECH-SAP SPM
68 29710 MECH-1 PM OF-FAN/AIR COOLER (23AB-2517) 23AB-2517 MECH-SAP SPM
69 29717 MECH-1 PM OF AIR BLOWER (23AB-1530) 23AB-1530 MECH-SAP SPM
70 29718 MECH-1 PM OF AIR BLOWER (23AB-2530) 23AB-2530 MECH-SAP SPM
71 29719 MECH-1 PM OF AIR BLOWER (23AB-1541) 23AB-1541 MECH-SAP SPM
72 29720 MECH-1 PM OF AIR BLOWER (23AB-2541) 23AB-2541 MECH-SAP SPM
73 29721 MECH-1 PM OF VENT STACK BLOWER (23AB-1740) 23AB-1740 MECH-SAP SPM
74 29722 MECH-1 PM OF VENT STACK BLOWER (23AB-2740) 23AB-2740 MECH-SAP SPM
75 29723 MECH-1 PM OF VENT STACK BLOWER (23AB-7240) 23AB-7240 MECH-SAP SPM
76 29724 MECH-1 PM OF VENT STACK BLOWER (23AB-7250) 23AB-7250 MECH-SAP SPM
77 29725 MECH-1 PM OF VENT STACK BLOWER (23AB-7260) 23AB-7260 MECH-SAP SPM
78 29750 MECH-1 PM OF SOLID COOLER (23E-1725) 23E-1725 MECH-SAP SPM
79 29751 MECH-1 PM OF COOLER SCRUBBER (23E-7201) 23E-7201 MECH-SAP SPM
80 29752 MECH-1 PM OF COOLER SCRUBBER (23E-7210) 23E-7210 MECH-SAP SPM
81 29753 MECH-1 PM OF COOLER SCRUBBER (23E-7220) 23E-7220 MECH-SAP SPM
82 29754 MECH-1 PM OF COOLER SCRUBBER (23E-7230) 23E-7230 MECH-SAP SPM
83 29761 MECH-1 PM OF DUST FILTER (23F-1601) 23F-1601 MECH-SAP SPM
84 29763 MECH-1 PM OF DUST FILTER (23F-1624) 23F-1624 MECH-SAP SPM
85 29781 MECH-1 PM OF DUST FILTER (23F-2601) 23F-2601 MECH-SAP SPM
86 29800 MECH-1 PM OF ROTARY VALVE (23FH-1540) 23FH-1540 MECH-SAP SPM
87 29801 MECH-1 PM OF ROTARY VALVE (23FH-2540) 23FH-2540 MECH-SAP SPM
88 29802 MECH-1 PM OF ROTARY VALVE (23FH-1601) 23FH-1601 MECH-SAP SPM
89 29803 MECH-1 PM OF ROTARY VALVE (23FH-1602) 23FH-1602 MECH-SAP SPM
90 29805 MECH-1 PM OF ROTARY VALVE (23FH-1624) 23FH-1624 MECH-SAP SPM
91 29806 MECH-1 PM OF ROTARY VALVE (23FH-1622) 23FH-1622 MECH-SAP SPM
92 29819 MECH-1 PM OF ROTARY VALVE (23FH-2601) 23FH-2601 MECH-SAP SPM
93 29820 MECH-1 PM OF ROTARY VALVE (23FH-2602) 23FH-2602 MECH-SAP SPM
94 29829 MECH-1 PM OF ROTARY VALVE (23FH-1650) 23FH-1650 MECH-SAP SPM
95 29835 MECH-1 PM OF ROTARY VALVE (23FH-1830) 23FH-1830 MECH-SAP SPM
96 29857 MECH-1 PM OF COLLECTION BELT (23FX-1400) 23FX-1400 MECH-SAP SPM
97 29858 MECH-1 PM OF COLLECTION BELT (23FX-1401) 23FX-1401 MECH-SAP SPM
98 29859 MECH-1 PM OF COLLECTION BELT (23FX-2400) 23FX-2400 MECH-SAP SPM
99 29860 MECH-1 PM OF COLLECTION BELT (23FX-2401) 23FX-2401 MECH-SAP SPM
100 29861 MECH-1 PM OF FEEDING SCREW (23FX-1410) 23FX-1410 MECH-SAP SPM
101 29862 MECH-1 PM OF FEEDING SCREW (23FX-1420) 23FX-1420 MECH-SAP SPM
102 29863 MECH-1 PM OF FEEDING SCREW (23FX-2410) 23FX-2410 MECH-SAP SPM
103 29864 MECH-1 PM OF FEEDING SCREW (23FX-2420) 23FX-2420 MECH-SAP SPM
104 29865 MECH-1 PM OF OSCILLATING BELT (23FX-1500) 23FX-1500 MECH-SAP SPM
105 29866 MECH-1 PM OF OSCILLATING BELT (23FX-2500) 23FX-2500 MECH-SAP SPM
PM OF SCREW CONVEYOR-OF-B/DRYER
106 29867 MECH-1 23FX-1501 MECH-SAP SPM
(23FX-15
PM OF SCREW CONVEYOR-OF-B/DRYER
107 29869 MECH-1 23FX-2501 MECH-SAP SPM
(23FX-25
108 29872 MECH-1 PM OF LIW FEEDER (23FX-1701) 23FX-1701 MECH-SAP SPM
109 29874 MECH-1 PM OF LIW FEEDER (23FX-2701) 23FX-2701 MECH-SAP SPM
110 29877 MECH-1 PM OF CONVEYOR SCREW (23FX-1725) 23FX-1725 MECH-SAP SPM

358122780.xlsx Page 47 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE

SCHEDULING START OF ACTUAL


SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL PERIOD ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
111 29890 MECH-1 PM OF SCREW CONVEYOR (23FX-1622) 23FX-1622 MECH-SAP SPM
112 29905 MECH-1 PM OF BEARING OIL UNIT (23M-2721) 23M-2721 MECH-SAP SPM
113 29906 MECH-1 PM OF BEARING OIL UNIT (23M-1721) 23M-1721 MECH-SAP SPM
114 29909 MECH-1 PM OF POLY BELT (23R-1310) 23R-1310 MECH-SAP SPM
115 29910 MECH-1 PM OF POLY BELT (23R-1320) 23R-1320 MECH-SAP SPM
116 29911 MECH-1 PM OF POLY BELT (23R-2310) 23R-2310 MECH-SAP SPM
117 29912 MECH-1 PM OF POLY BELT (23R-2320) 23R-2320 MECH-SAP SPM
118 29917 MECH-1 PM OF KNEADER G/B (23Z-1410) 23Z-1410 MECH-SAP SPM
119 29918 MECH-1 PM OF KNEADER G/B (23Z-1420) 23Z-1420 MECH-SAP SPM
120 29919 MECH-1 PM OF KNEADER G/B (23Z-2410) 23Z-2410 MECH-SAP SPM
121 29920 MECH-1 PM OF KNEADER G/B (23Z-2420) 23Z-2420 MECH-SAP SPM
122 29921 MECH-1 PM OF CROSS BLADE CRUSHER (23Z-1500) 23Z-1500 MECH-SAP SPM
123 29922 MECH-1 PM OF CROSS BLADE CRUSHER (23Z-2500) 23Z-2500 MECH-SAP SPM
124 42085 MECH-1 OIL COLLECTION FROM 23Z-1410 23Z-1410 MECH-SAP SPM
125 42086 MECH-1 OIL COLLECTION FROM 23Z-1420 23Z-1420 MECH-SAP SPM
126 42087 MECH-1 OIL COLLECTION FROM 23Z-2410 23Z-2410 MECH-SAP SPM
127 42088 MECH-1 OIL COLLECTION FROM 23Z-2420 23Z-2420 MECH-SAP SPM
128 42090 MECH-1 OIL COLLECTION FROM 23M-1721 23M-1721 MECH-SAP SPM
129 42622 MECH-1 OIL COLLECTION FROM 23M-2721 23M-2721 MECH-SAP SPM
130 42623 MECH-1 OIL COLLECTION FROM 23P-1722 23P-1722 MECH-SAP SPM
131 42624 MECH-1 OIL COLLECTION FROM 23P-2722 23P-2722 MECH-SAP SPM
132 42625 MECH-1 OIL COLLECTION FROM 23FX-1725 23FX-1725 MECH-SAP SPM
133 42617 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1610 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
134 42620 ELEC-1 23F-1610 ELEC-SAP SPE
GROUNDING(1W)
135 42841 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1611 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
136 42844 ELEC-1 23F-1611 ELEC-SAP SPE
GROUNDING(1W)
137 42845 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1612 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
138 42848 ELEC-1 23F-1612 ELEC-SAP SPE
GROUNDING(1W)
139 42849 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1613 MECH-SAP SPM
140 42626 MECH-1 OIL COLLECTION FROM 23EX-1410 23EX-1410 MECH-SAP SPM
141 42627 MECH-1 OIL COLLECTION FROM 23EX-1420 23EX-1420 MECH-SAP SPM
142 42628 MECH-1 OIL COLLECTION FROM 23EX-2410 23EX-2410 MECH-SAP SPM
143 42629 MECH-1 OIL COLLECTION FROM 23EX-2420 23EX-2420 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
144 42852 ELEC-1 23F-1613 ELEC-SAP SPE
GROUNDING(1W)
145 42853 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1620 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
146 42856 ELEC-1 23F-1620 ELEC-SAP SPE
GROUNDING(1W)
147 42857 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1621 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
148 42860 ELEC-1 23F-1621 ELEC-SAP SPE
GROUNDING(1W)
149 42861 MECH-1 TUMBLING SIEVE INSPECTION MECH (1W) 23F-1622 MECH-SAP SPM
TUMBLING SIEVE INSPTN ELEC
150 42864 ELEC-1 23F-1622 ELEC-SAP SPE
GROUNDING(1W)
151 42865 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1610 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
152 42872 ELEC-1 23Z-1610 ELEC-SAP SPE
FILTER(1W)
153 42873 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1611 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
154 42880 ELEC-1 23Z-1611 ELEC-SAP SPE
FILTER(1W)
155 42881 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1612 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
156 42888 ELEC-1 23Z-1612 ELEC-SAP SPE
FILTER(1W)
157 42889 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1613 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
158 42896 ELEC-1 23Z-1613 ELEC-SAP SPE
FILTER(1W)
159 42897 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1620 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
160 42904 ELEC-1 23Z-1620 ELEC-SAP SPE
FILTER(1W)
161 42905 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1621 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
162 42912 ELEC-1 23Z-1621 ELEC-SAP SPE
FILTER(1W)
163 42913 MECH-1 ROLLER MILL INSPECTION MECH (1W) 23Z-1622 MECH-SAP SPM
ROLLER MILL INSPECTION ELEC
164 42920 ELEC-1 23Z-1622 ELEC-SAP SPE
FILTER(1W)
165 56075 MECH-1 INSPECTION OF PSV (2Y)-2340PVSV-0117 2340PVSV-0117 MECH-SAP SPM

358122780.xlsx Page 48 of 49
CENTRAL MAINTENANCE SERVICES
MAINTENANCE PLAN DATA IN SAP
FO-MNT-CMS-17 Rev.02

ACTION REQUIRED : ADD CHANGE DELETE

SCHEDULING START OF ACTUAL


SER MAINT. TL GROUP MAINT MAINTENANCE PLANNER CALL PERIOD ADDITIONAL PM
MAINTENANCE PLAN SHORT TEXT** EQUIPMENT NO.* WORK CENTER* PRIORITY* CYCLE (Start PM START
NO. PLAN*** NO*** STRATEGY* ITEM** GROUP* HORIZON* CYCLE UNIT REMARKS
Date)* DATE*
166 62824 MECH-1 PM FOR PUMP 23P-1100 23P-1100 MECH-SAP SPM
167 62825 MECH-1 PM FOR PUMP 23P-3430 23P-3430 MECH-SAP SPM
168 62826 MECH-1 PM FOR 23P-4001 23P-4001 MECH-SAP SPM
169 62828 MECH-1 PM FOR PUMP23P-4101 23P-4101 MECH-SAP SPM
170 62830 MECH-1 PM FOR PUMP 23P-4102 23P-4102 MECH-SAP SPM
171 63384 MECH-1 PM FOR PUMP 23P-1726 23P-1726 MECH-SAP SPM
172 63386 MECH-1 PM FOR PUMP 23P-3701 23P-3701 MECH-SAP SPM
173 63415 MECH-1 PM FOR PUMP 23P-1721 23P-1721 MECH-SAP SPM
174 63416 MECH-1 PM FOR PUMP 23P-2721 23P-2721 MECH-SAP SPM
175 63417 MECH-1 PM FOR PUMP 23P-1722 23P-1722 MECH-SAP SPM
176 63418 MECH-1 PM FOR PUMP 23P-2722 23P-2722 MECH-SAP SPM
177 63427 MECH-1 PM FOR PUMP23P-1150 23P-1150 MECH-SAP SPM
178 63428 MECH-1 PM FOR PUMP 23P-1160 23P-1160 MECH-SAP SPM
179 63442 MECH-1 PM FOR PUMP 23P-3310 23P-3310 MECH-SAP SPM
180 63443 MECH-1 PM FOR PUMP 23P-3320 23P-3320 MECH-SAP SPM
181 63444 MECH-1 PM FOR PUMP 23P-3431 23P-3431 MECH-SAP SPM
182 63447 MECH-1 PM FOR PUMP 23P-3520 23P-3520 MECH-SAP SPM

Notes: * Fields are mandatory


** mandatory only if for creation
*** mandatory only if for change/delete
insert rows as required
signatures required on last page only

Requested by: Approved by(end-user Supervisor): Approved by (Superintendent): Updated in SAP by:

___________________________ ___________________________ ___________________________ ___________________________


(Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date) (Name, Signature & Date)

358122780.xlsx Page 49 of 49