BILL OF ENGINEERING MEASUREMENT& EVALUATION-2

PROJECT TITLE;-EXTERNAL LOAD CABLES FROM GENERATOR HOUSE TO EACH BUILDING/MAIN DIST.PANEL

S/NO DESCRIPTIONS QTY UNIT RATE TOTAL

A LOAD CABLES AND ACCESSORIES

1 2-COREX10.0MM PVC/SWA/PVC ARMOURED CABLE[NIGERCHIN] 42 MTR. 950.00 39900.00

FROM MV SWITCH BOARD TO THE MOSQUE

2 4-COREX10.0MM PVC/SWA/PVC ARMOURED CABLE[NIGERCHIN] 52 MTR. 1,750.00 91000.00

FROM MV SWITCH BOARD TO GUEST CHARLET/B.QTRS

3 4-COREX16.0MM PVC/SWA/PVC ARMOURED CABLE[NIGERCHIN] 73 MTR. 2,750.00 200750.00

FROM MV SWITCH BOARD TO CHILDREN CHARLET

4 4-COREX25.0MM PVC/SWA/PVC ARMOURED CABLE[NIGERCHIN] 75 MTR. 3,500.00 262500.00

FROM MV SWITCH BOARD TO MAIN BUILDING

5 4-COREX50.0MM PVC/SWA/PVC ARMOURED CABLE[NIGERCHIN] 25 MTR. 4,850.00 121250.00

AS LOAD CABLE FOM PHCN

6 150MMX225MM PLASTIC ADAPTABLE BOX 6 NO 2,500.00 15000.00

AS LOAD CABLE FOM PHCN

7 75MM DIAM.UPVC TIGER PIPE/ACCESSORIES SUCH AS 45 NO 5,250.00 236,250.00

SOCKETS ETC

SUB-TOTAL _ _ _ 966650.00

B MAIN DISTIBUTION PANEL

LABOUR CHARGES SHALL INCLUDE DIGGING IN

LATERITE 300X600MM CABLE ROUTE ,LAYING OF LOT SUM 193330.00

PVC PIPES,LAYING OF CABLE OF VARYING SIZES,

TERMINATION OF ARMOURED CABLES ETC

LABOUR CHARGES

LABOUR CHARGES SHALL INCLUDE DIGGING IN