Oki Pulp & Paper - Inspection Report - Tanks
Oki Pulp & Paper - Inspection Report - Tanks
Flow Substance:
Material:
Insulation:
Check by Verified by
Notes in Defect List
Check List n/a Date Supplier Contractor Purchaser Mills
1 Identification (name plate/tagging)
2 Overall cleaning
3 Conformity with specifications and drawings
4 Material Conformity
5 Grouting inspection
6 Inside inspection and polishing
7 Welding
8 Welding records (X-ray, ultrasonic, etc)
9 Finishing
10 Lining
11 Painting
12 Piping
13 Flange Parallelism
14 Support Ladder, Platform installation
15 Agitator Installation (Separate inspection Report)
16 Earthing Connection
17 Hydrostatic Test
18 Thermal insulation
19 Authorities' Inspection reports and approvals
Note: Defect List must be always enclosec
The referred equipment has been inspected and is hereby released for commissioning.
Date Sign Contractor
S ign Supplier Sign OKI