Aa BART
Silicon Valley Berryessa Extension
Contract Delivery Strategy
April 1, 2010
Definitions and origins for each delivery method
+ Design/8id/Build (088)
~ the traditional project delivery method,
~ the owner retains @ designer to furnish complete design services,
= ativertves and awards a separate construction contract,
— owner is responsible forthe details of design and warrants the quality
ofthe construction documents to the construction contractor, and
— cam be traced back to the Braaks Act of 1972
+ Besign/Build (D8)
project deivery method in which the ewner procures design and
‘constuction services in the same contact from 3 single legal entity,
the OB entity i able for al design ane consteuction costs,
— provides a trm-fned price (FFP) proposal, and
= introduced was Intermodal Surface Transportation Efficiency Act (1891)
and explicitly autho zed for use on federal projects nthe Federal
Acquisition Reform Act (3986)
4/1/20104/1/2010
VTA has the authority to award Design/Build
contracts using a “best value” criteria
Califoroia Public Contract Cade (PCC) affords VTA the authority to
award a design/buld contract under best value erteria
+ PCC Section 20209.6
— Use ofthe design build process wil accomelsh one ofthe following,
objectives:
+ neduce project costs
+ Expedite pret comletion
+ Prowse desi features not achicsable through the sind
method
» PCC Section 20209.8
— authorizes a transit district to award a design-build content to the
‘esponsible bidder whose proposals determined to be the best value
ese Cucnaanany mmm A BART =
DB allows construction to begin prior to the
completion of design
DESIGN/BID/BUILD
onaton
DESIGN 100%
concn
Sar
coven
cn
ae
sraintce
DESIGN/BUILD
eae twinnidimta marae BART «
Bae.Additional differences between delivery methods
Teagne ompwg roe once
ihe peta ost
con fice with rncres some spceaty otra de ce ewer canes ee,
S'Scowraly uartedome-tawic® |S tan ou cae wt eee
fae ‘apart erie te sen pase
7 Nogafcan alarsaeeae”” | > eae lista nthe seme eo
vos “hsuiing susan sree | Sigerort of asnuny pn
omsrement | [one pore sfncarecbny | re
2 Dane stans nin eaten | One alates a ak tne
osereuirg Bam Contact eam ene Deeg
ugsney kstance oss ch
fetarsioed eee thc it
The risk assessment provides an analysis of cost and
schedule implications for a DB Contracting Strategy
«Factors considered in the SVBX Comparative Risk
Assessment include, but are not limited to...
~ potential owner engineering risks
~ potential contractor engineering risks,
~ project definition {Level of Design),
~ consoldation of she civil and systerns contracting packages,
~ status & schedule or agreements, city, utility relocation, &
ROW,
~ the FFGA schedule
mnie camwanainy annum A BARE -
4/1/2010The risk analysis forecasts a $147M savings in pre-
mitigated Risk Adjusted Cost
‘* $85Min reduction in the Base Cost Estimate
~ Lower Project/Construction Management Oversight costs
~ Shorter schedule duration
+ $62Min reduced Cost Risk
~ Alocation of risk to the DB contractor
nit 30 oncoming kuttonien 6 BART,
The risk analysis forecasts a 12-mo savings in pre-
mitigated Risk Adjusted Schedule
* 6 month reduction in the Project Schedule
= Overlapping project phases and activities
= Optimal use of resources
* 6 month reduction in Schedule Risk
~ Allocation of risk to the DB contractor
sein to Sittin Mn tner tanita A BAL
frdonnte
4/1/2010The changes in Cost and Schedule Risk are a result of
the allocation of risk
+ Under design-build, several risks can be shared,
transferred or avoided
‘+ The guiding principle is that every individual risk
should be possessed by the group that can best
handle it
* DB Contractor is best able to manage:
— Design & Construction integration/interface risks
— Guideway & tation construction risks
ena cnc nimi sonennwn AZ BARE
Results Assessment Summary
‘+ $147M in Risk Adjusted Cost Savings
SSM lower Base Cost Estimate
— $62M reduction in Cost Risk
+ 12 month savings in Risk Adjusted Schedule
= 6monch shorter Project Schedule
= Smonth reduction in Schedule Risk
1+ The Risk Profile shifts ~ Management Risks are the key
Multiple design and construction risks are transferred tothe contractor
= Managernent risks are incurred by VTA but are easily mitigated if action
's taken quickly
= New epportunities arise and can be exploited if action i taken quickly
‘+ Applying lessons learned from other agencies can ald Project
Leaders in mitigation of management risks
coannonerwan enim BART, =
4/1/2010