1st Semester CMR - Samberga Plant
1st Semester CMR - Samberga Plant
Other sectorial
Requirements All relevant permits to concerned
Mandated by agencies have been applied and
Other agencies approved.
To be complied
with
Annex 3-1
PRO-FORMA PROPONENT COMPLIANCE MONITORING REPORT (CMR)
Semi-annual Module 5 of SMR
EMP and The EMPs formed part of the Updating the EMPs may not be
updates as submitted ECCs application necessary considering that
deemed documents. mitigating measures applicable
necessary during the operational stage of
the projects are subsumed in the
other ECCs condition which was
complied/being complied with.
Conduct of
compliance and Quarterly Self-Monitoring Reports Validation of the SMR formed
impact self (SMR) is being submitted to part of the PCO monitoring
monitoring EMB- Reg 3. activities.
Institutional
arrangements An environmental Unit is tasked
necessary for to ensure the implementation of
implementation necessary environmental
of environ- management measures.
mental
management
measures
Watershed Comprehensive site Devt project
Development within the barangay is being
and monitored/validated by the
Management company.
Standard DENR
requirement on N/A Project has just started operation
Abandonment stage.
Compliance Social Among others, being
with EMP development implemented by the company Other measures describe in the
Program (SDPs) under its SDP for the semester EMPs were subsumed in the
includes the following: conditions stipulated in the ECCs.
1. Give to the host barangay any
solicitation asked.
2. Donate whatever is needed
during to any if not all
barangay activities.
Complaints Management Plan
No complaint related to project
operation was received during
this quarter.
Accountability qualified
personnel are charge with the The monitoring capabilities of the
routine monitoring of the PCO is enhanced/ strengthened
project activities in terms of during seminars, meeting/
education, training, knowledge training/ workshop/drills.
and experience of the
environmental team
A. Compliance Monitoring
B. Impact Monitoring
No adverse impact to the environment being a non-environmental critical project.
i. Summary of Previous Monitoring
No relevant issue monitored during the previous monitoring