Government of the District of Columbia

Department of Transportation

d. Infrastructure Project Management Division


Monday, June 26, 2017

Dear Resident/ANC/Local Businesses/Property Managers:

The District Department of Transportation (DDOT) will begin construction of LeDroit Park Green Infrastructure
project (see map on the reverse side of this sheet ) on the week of July 10, 2017 and V Street roadway resurfacing
project (mill and overlay, install Granite Curbs and Brick Gutter, repair Brick Sidewalk, install ADA Ramps ) on July
05, 2017. The Green Infrastructure work includes installing permeable pavement and bioretention to reduce
flooding in the neighborhood. It is estimated that the work will take approximately 6 months to complete,
weather permitting.

If weather conditions, schedule changes, or unforeseen issues do not permit our contractor to begin this work on
the date stated above, the new start date for construction will be listed on the EMERGENCY NO PARKING signs
posted on the poles and trees throughout the construction project site.

Residential: If the location of your trash collection is from the alley, your trash will be collected along the front of your
property until the completion of the alley project. Trash will not have to be separated. If your trashcan is too cumbersome
to handle, please use thick trash bags and place them in the public space in front of your property. This action is being
coordinated by DDOT with the Department of Public Works (DPW) - Solid Waste Team. All questions regarding trash pick-
up must be directed to DPW at 202-576-9000, e-mail: earl.simpson@dc.gov .

Commercial: For commercial properties along the alley, with smaller dumpsters, our contractors will move them aside, and
place them back in the same place after the work is completed. If you have a large dumpster, please alert your hauler to
this work activity and have them to contact DDOT at 202-671-2833, so that the contractor can work with the hauler to
mitigate any impact on your trash pick-up services.

Throughout the construction area, at least one lane of traffic will be open except for Oakdale Alley and the
northern side of Bohrer St NW where full closure will be in place. Access to the adjacent houses will also be
maintained. Curbside parking will be restricted at this location during construction hours. EMERGENCY NO
PARKING signs will be posted seventy-two (72) hours prior to the commencement of construction in your area.
All work will be conducted from 7:00 am to 7:00 pm, Monday through Saturday.

DDOT thanks you in advance for your patience and understanding during the construction; if you have any
questions or concerns, please contact me by phone or email, listed below.

Sincerely,
Tesfalem Tekle
Project Manager
tesfalem.tekle@dc.gov, 202-671-2219

District Department of Transportation 55 M Street, SE, Suite 400 Washington, DC 20003 202.673.6813 www.ddot.dc.gov
Project Areas

Roadway Resurfacing Project: Construction Start Date July 05, 2017


V St NW between 5TH St NW and 2ND St NW.

Green Infrastructure Project: Construction Start Date the week of July 10, 2017
Bohrer St NW.
U St between Bohrer ST NW and 5TH ST NW.
5TH St between W St NW and U St NW.
Elm St NW between 5TH St NW and 100 ft to the east of 3RD St NW.
V St NW between 5TH St NW and 2ND St NW.
Oakdale PL NW from the intersection with V St NW and southward along Common Good Community
garden.

District Department of Transportation 55 M Street, SE, Suite 400 Washington, DC 20003 202.673.6813 www.ddot.dc.gov