I) Status
II) Critical Areas & Action (Identifying the Responsibility and Time Frame)#
Page 1 of 2
4) Manufacturing including Resources
Fairtech/LNT once again put pressure on Goodrich to follow the delivery schedule as required by LNT ie.
6#1500-Joints- 2 no and 14#1500 Joints-2 no ON Priority .
As discussed with Mr. Michael Basker-GM-Technical- Goodrich Gaskets, the manufacturing schedule as follows
for 6#1500 Joints- 2 nos.
- Out of 4 Nos ordered 1 no dispatched on 18-12-14 via Prashar Road Carriers vide LR/CN No. 187029 dt 18-
12-14 and the Invoice No.GGPL/SD/INV/141001017.
- 2 nos inspection completed and packed on 27-12-14 and will be shipped by truck no.KA-04 C 6917,
LR No /CN No 187035 today is 30-12-14.
- Balance 1 no under Hydro today ie 30-12-14.
- Planned for dispatch by 6-01-15 after coating.
- + 1 Proto under welding
- Fairtech/LNT showed their unhappiness on the progress and once again insisted/pressurized Goodrich
to complete the same ASAP as required by LNT. Goodrich confirmed that they will try to complete at the
earliest.
Fairtech/LNT not agreed on this plan and showed their anger and once again put more pressure on Goodrich to
complete the order at the earliest with strict discussion with Technical and Production Team of Goodrich
Gaskets. After that Goodrich informed, they will try to complete the same before Pongal Holidays.
NOTE : Due to Heavy rain and the local strike by the Tamilnadu Government Bus Transport for couple of days
Goodrich had some problems caused impact on the schedule again.