Professional Documents
Culture Documents
Critical Analysis of The Flisa Bridge Henry Tung: Department of Architecture and Civil Engineering, University of Bath
Critical Analysis of The Flisa Bridge Henry Tung: Department of Architecture and Civil Engineering, University of Bath
Critical Analysis of The Flisa Bridge Henry Tung: Department of Architecture and Civil Engineering, University of Bath
Henry Tung
Abstract: This paper describes the design, construction process and aesthetic evaluation of the Flisa Bridge in
Hedmark, Norway. References are made to the Eurocode for timber bridge construction in assessing designed
loadings of the bridge; details of the connections, other elements of the bridge and the construction process are
assessed in the paper. A comparison of timber bridges with steel and other construction materials for bridge
construction is also included.
Figure 1: the old Flisa Bridge Figure 2: Location of the Flisa Bridge
Figure 5: Drive through view of the bridge The width of the carriageway is 6.5m, and so the
number of notional lanes is 2, with the width of each
3 Loadings: lane being 3m and the remaining width being 0.5m.
(According to EN 1991-2, if a carriage way is divided
This section analyses the self-weight, the
into two parts, then only one numbering should be used
superimposed dead load, live loading and other types
for the two lanes.) There is also a 2.5 metres wide LM 3 takes into account the unusual heavy
pedestrian footway next to the road. vehicles which may, on rare occasions be present on
the bridge. The type of special vehicle allowed in
particular routes depends on authorisation of the
European highway network or the nature of the
individual project defined by the client; and since the
details are unknown, the heaviest loading according to
the Eurocode will be included in this report. Special
vehicles are modelled as high axle loads of magnitudes
ranging from 150 to 240KN; the heaviest vehicle
specified in the standards weights 3600KN and is
represented by 15 axle loads, each of 240KN
magnitude. Contact area of the wheels is taken as
1.20m by 0.15m and there is 0.3 m space within each
wheel. The influence area of the special vehicle is
represented by the green rectangle on the lanes, this
Figure 6: Dimensions of the notional lanes area is specified by giving 25m before and after the
vehicle; the area outside the influence is subjected to
3.2.1 Vertical loadings: loadings defined in load model 1, Fig. 9.
Loading values:
Axle loads (QQk) = 0.8 x 300KN = 240 KN
UDL (qqk) = 1 x 9 KN/m = 9 KN/m
udl (qrqrk)= 1 x 2.5 KN/m = 2.5 KN/m
3.3 Horizontal loading: is calculated to be 11.7ms-1; wind load factor (C) is 2.6
and the reference area is taken as the area of the
3.3.1 Breaking and acceleration forces: footway, which is 452.5m2. This gives s total wind
Breaking forces (Q1k) acts as a longitudinal force force perpendicular to the bridge span to be 100 KN,
at the surface level which is estimated to be greater 0.55 KN/m.
than 180Q but less than 900KN; and should be Wind forces exerted in the y-direction (along the
calculated by the equation: bridge span) is usually the less problematic component
Q1k = 0.6Q1(2Q1k)+0.1q1q1kw1L (1) due to the much higher bending capacity at this axis.
For a truss bridge, the wind load is taken as 50% wind
Which gives Q1k to be 828 KN; between 180Q force in the x-direction, giving a total wind force of
and 900KN. 50KN in the y-direction.
Wind forces in the z-direction could also be
3.3.2 Parapet loading: estimated using equation 2; using the coefficient of lift
This accounts for the horizontal and vertical forces (Cf,x) and new reference area (Aref,z). This gives a wind
transferred to the bridge deck by vehicle restraint load in the z-axis to be 0.69 KN/m. it is stated that the
members. Since the parapets are rigidly bolted to the forces of is only significant if it is of the same order as
crossbeams beneath the deck, they would be designed he dead load of the bridge (34 KN/m), hence uplift is
to carry heavy horizontal load in the case of collision. insignificant.
According to Eurocode, collision forces are Wind loading in the x-direction is resisted by the
expected to act either 1 m above the level of the wind trusses at the top of the truss girders, which
carriage way or 0.1 m below the top of the parapets, braced the structure but still provided a minimum head
which ever one to be lower and on a line of length room of 5.99m according to highway regulations.
0.5m. The height of the parapet is approximately 1.2m; During designing, issues were raised as to decide what
hence take the height of collision to act at 1m height. the best way of transferring the lateral loads to the piers
would be, the two options were either increase the
3.3.3 Collision forces on the curb: thickness of all the truss components or add lateral steel
There are no barriers between the road and the supports; the latter was chosen to maintain the slender
pavement, so it is quite possible that a vehicle may appearance of the trusses and U-shaped steel supports
collide with the curb. In such case, the collision force area installed at the piers.
would be transferred from the curb to the structural
members which for the Flisa Bridge, this would be 4 Strength analysis of the bridge
glulam beams underneath the pavement and the steel I
beam directly next to the curb. According to Eurocode The strength analysis in the paper is done
a horizontal force of 100 KN would act at 0.05m below according to Eurocode EN1995-1-1, Ref [5] (Design of
the top of the curb; a vertical force of 0.75Q1Qk = 180 timber structures) and EN 1995-2, Ref [4] (Design of
KN acts simultaneously at the top of the curb. timber structures- bridges).
The deck plate is sawn laminated timber made
3.4 Wind loading: from Norwegian pine; according to ultimate limit state
According to EN 1991-1-4; wind forces are treated design, the entire system strength of the laminated deck
as forces from three major directions, annotated as axis as a result of the combination of laminations should be
x, y, and z. Wind forces from the x-direction assessed. The system bending strength is given by:
(perpendicular to direction of bridge span) can be
calculated by the equation: Fm,d,deck = ksys x fm,d,lam (3)
Fw = 0.5 x x Vb2 x C x Aref,x (2) Similarly the system shear strength is:
Where the density of air () is taken as 1.25 Kg/m3 Fv,d,deck = ksys x fv,d,lam (4)
according to the national annex; basic wind speed (Vb)
To calculate the system strength factor (ksys), the for areas subjected to concentrated loads; pre-stressed
number of lamination needs to be specified, this is steel bars are located at 600mm intervals and stressed
given by the equation: up to 140KN, thus giving p,min a value of 1.05N/mm2.
The thickness of laminations (h) is 48mm; the design
n = bef / blam (5)
shear force (Fv,ed) is taken to be 9N/mm. The term on
The width of the individual lamination (blam) is the right hand side of the equation becomes 11.6N/mm,
48mm; while the value of bef is calculated to be 0.81m. and the relation stated above is satisfied.
This gives n a value of ~17. The value of Ksys is then
taken from a chart in EN 1995-1-1; for n > 10, Ksys = 5 Vibration
1.2 for pre-stressed laminated timber. If the ultimate
Vibration caused by pedestrian loading
bending strength of pine is taken as roughly 123
Acceleration due to pedestrian loadings could be
N/mm2, then applying the system factor gives the
calculated providing the fundamental natural frequency
system bending strength (Fm,d,deck) 147.6 N/mm2.
of the bridge is known. The value of vertical natural
Similarly applying Ksys to the shear strength of the
frequency (fvert) should be 5 Hz < fvert < 75 Hz. The
individual laminations perpendicular to the grains,
natural frequency of the bridge could be estimated by
which is estimated to be about 690 N/mm2, then the
the equation:
system shear strength is about 828 N/mm2.
Timber decks takes into account a dispersion of Wn = (nl)2 x (EI/ml4)1/2 (7)
concentrated loads according to EN 1995-2, Fig. 10.
The stress at the middle of the deck is calculated by Where Wn is the fundamental natural frequency, E
applying dispersion angles () for different layers of is the youngs modulus of the deck, I is the second
moment of area, l being the length of the span, m is the
the deck. The value of in the pavement is taken as
45o and that of the timber perpendicular to the grain is bridge mass per unit length and (nl)2 is a boundary
15o. Using load model 2 from the loading section bw condition factor. As the bridge deck is supported every
5.6 m, the connection could be treated as one end
would be 0.6m; after dispersion bw,middle is 0.76m.
Apply similar concept to the other side gives bw,middle a pinned and one end fixed, the value of (nl)2 is thus
depth of 0.67m. So the stressed area under a single 15.42, which gives a natural frequency of:
wheel becomes 0.67 x 0.76m2 = 0.5m2. Load model 2 Wn = 15.42 x (13.5 x 109 x 6 x 10-5/ 3400 x 5.64)1/2
specifies an axle load of 320KN, 160KN per wheel, so = 7.6 Hz
the stress half way down the deck is 160 / 0.5 =
320KN/m2 (0.32N/mm2). The compressive strength of A rough estimated value of 7.6 Hz for natural
pine (European Scots pine) perpendicular to grains frequency is within the comfort zone for occupants
could be taken as 7.5 N/mm2, so this compressive stated above. As stated in Eurocode, acceleration due to
stress from Load model 2 is acceptable. pedestrian loading does not require checking if the
fundamental frequency is above 5 Hz. However since
this is a very rough estimation and the value obtained is
fairly close to the limit, we shall assume the natural
frequency as 5 Hz to calculate the associate vertical
acceleration.
avert,1 = 100 x M x (8)
M is the product of the mass per unit length of the
bridge and the length of the used span (as the deck is
supported every 5.6m). is the damping ratio, for a
structure with mechanical joints, its value is taken as
0.015. Which gives avert a magnitude of 0.35ms-2. If
there are several people on the bridge, the associated
acceleration is given by:
Figure 10: The dispersion of concentrated loads avert = 0.23 x avert,1 x n x kvert (9)
Stress laminated decks need to be checked for the n is taken as 13 for a distinct group of pedestrians
possibility of slippage between the laminations. To and kvert from the code is 0.33; thus giving the
show that no inter-laminar slip occurs; this relation acceleration to be 0.35ms-2.
should be satisfied:
Fv,ed < D x p,min x h (6) 6 Construction process, prefabrication
Coefficient of friction (D) is given as 0.23 in the The bridge was constructed in a relatively short
Eurocode for sawn timber to sawn timber interfaces period of time; the old bridge was closed to traffic and
below 12% moisture content in the direction parallel to construction began on Nov 2002, the new bridge was
grains. Minimum long term compressive stress (p,min) opened to traffic on 5th June 2003.
from pre-stressing should be no less than 0.35N/mm2
The superstructure of the bridge such as the timber give a span of 5.6m; 5.6m is the maximum length of
truss girders and cross beams were new and mainly available sawn timber in Norway.
prefabricated; the existing dressed stone piers were in
good conditions, they were kept and new concrete tops
ware cast on top of the piers. The prefabricated parts
had to be lifted into place from positions in the river;
and so a temporary embankment was made at places
where the water level was the shallowest; for this
reason construction of the bridge had to be carried out
during the winter when the water level was at its
lowest. The embankment extended 120m from the west
and only 50m from the right side of the embankment
was opened to allow the flow of the river.
The prefabrication process involves:
1. Glulam timber beams made
2. Members are jointed by bolting with dowels,
timber to timber joints usually involves two Figure 12: Pre-stressed bars (at 140KN) in the deck
steel plates embedded in the timber and also
outside the member with steel bolts inserted So in November 2002, traffic of the old bridge was
to hold the joint in place closed and work was done to strengthen the existing
3. Parts are assembled together to see if they fit piers; new steel piles are installed to carry the increased
and if the total length of the bridge is correct design load for the new bridge, the reason steel piles
4. The components are taken apart and then are used was because they do not require the use of a
impregnated with creosote, Figs. 11, 15 large pile rig, which might have been too heavy for the
5. Transportation of timber girders to site deck of the old bridge. Strengthening of the piers had to
be done on the old bridge because it would have been
easier to insert the piles before the temporary
embankment is in place. When the piles are installed,
demolition of the steel truss structure began;
prefabrication of the new timber superstructure also
started. When the old bridge was removed, work on the
substructure began; concrete abutments were poured,
the concrete top of the piers were removed with care so
to not damage the stone piers, new concrete was poured
on top of the piers for the bearings to sit on.
Assembly of the first section began on February
2003; the order of assembly was:
1. Prefabricated parts transported to the site, the
truss walls are connected to the wind trusses,
the steel cross beams are connected to the
truss girders by cables
2. The connected bridge sections are craned into
Figure 11: Preliminary assembly after prefabrication position; first the central section, then the end
at Moelven Limtre factory section on the west side is lifted to join the
abutments and the centre span; and the arch
The maximum length of the member sizes are section on the east craned into position last,
restricted by the sizes of the creosote impregnation Fig 13,14
tanks, the upper and lower chord of the truss girders 3. Once the truss walls are in place, the stress
are divided into several parts of maximum length 28m. laminated sawn timber are laid to create the
The bridge deck was composed of stress laminated bridge deck. Then parapets are installed
timber; planks of sawn timber of dimension 48 x 4. Finally the copper cladding on the top surface
223mm are clamped together at their wide surface and of glulam trusses, asphalt and Topeka are laid
pre-stressed with high strength steel rods of 15mm on top of the sawn timber deck
diameter stressed up to 140KN, Fig 12. During Assembly of the bridge finished on early spring of
construction, the beams are placed side by side with 2003, and the bridge was opened to traffic on 5th June
each other, then holes are drilled on the wide faces of 2003. Removal of the temporary embankment began
the joists; once they are put together in place steel rods once the truss walls were assembled, as work began on
are pushed through the holes and tensioned. The steel the deck, the embankment were being gradually lifted
rods are spaced 600mm to give better sharing of the up and transported away; so at the time the bridge was
load and the timber spans between the crossbeams to opened in spring and the water level raised, the
embankment was below water level.
possible to replace these members when the bridge is in
service and so they must be designed to last the
expected lifespan. It is quite difficult for glulam
members to achieve a full impregnation with only one
treatment. Sapwood is first treated with chrome, copper
and arsenic (CCA) salt solution before it is flattened
and glued, after the glulam members are made and
preliminary assembly is carried out; the parts are then
taken to an impregnation cell and treated with creosote
to reduce cracking and make the glulam water
repellent.
7.1 Vandalism
The problem with vandalism of a timber bridge is
one of the more common maintenance required issues.
This usually happens to the railings of the bridge
which could be resolved by wither repainting or
replacing parts of the railings. There had been no
reports showing graffiti or other forms of vandalism at
the Flisa Bridge. The timber used in the bridge are
mostly impregnated with creosote and possess a dark Figure 16: The use of piles to provide lateral stability
colour, so minor damages on the parapets or railings to stone piers
are less obvious; and being a truss bridge, there are no
The original abutments were too small and had to
large continuous surfaces which makes it less likely to
be rebuilt; a new, larger concrete abutment was cast in
be the target of graffiti painters. Most components on
situ. The abutments are designed to carry vertical loads;
the bridge except for the glulam trusses are replaceable
the horizontal loads from the bridge deck are carried by
during the service life of the bridge; so the parts such
concrete friction plates behind the abutments at both
as the sawn deck of the pavement or parapets could be
ends, Fig 17. The concrete friction plates slope at a
quite easily maintained if damaged.
gradient of 1 in 8 and of a total area of 115.1m2.
7.2 Creep
Creep is observed in timber bridges as a result of
sustained loading and cyclic moisture change in the
timber which can cause sagging in the deck. Creep and
shrinkage of the wood from drying out can cause the
pre-stress steel bars inside the deck to reduce in its pre-
stress forces. Because of initial creep, the pre-
tensioned steel bars needed further tightening a year
after construction.
8 Foundation:
Using timber as the main construction material for
the bridge reduces the dead load of the new structure
which allows re-use of some of the old foundations;
avoided some expensive and time consuming
foundation work. The abutments and piers built for the
old bridge were made of high quality dressed stones on
pile foundations and are still in good conditions after
100 years. The old bridge was only held one lane so Figure 17: Plan and elevation of friction plate
the new bridge which is designed to carry full traffic
loads would exert larger loads to the foundations; extra 9 Temperature
steel piles were bored into the bedrock to strengthen
the piers. Thermal expansion of the bridge deck could be
The old piers were strong in the vertical direction, roughly estimated by the equation:
but weak in the lateral direction; using steel piles of L = L x x T (10)
diameter 120mm at the side of the piers increases its
resistance to lateral load, Fig 16. Similar methods of Where the linear thermal expansion coefficient
using piles bored into soil to provide stability and along the grain () is taken to be 3.5 x 10-6 /K, Ref. [2];
cradle the stone structure is used for the building of the change in temperature (T) is taken as the
wharfs. The steel piles provide extra lateral stability maximum temperature difference between summer and
and increase the bearing capacities of the piers. winter in 2008 and 2009, which is about 57.4 K. This
gives an associated expansion of 25mm. This can then
be converted into resulting strain by dividing the
expansion by total length of the bridge, which gives
and equivalent strain of 2 x 10-4. If the abutments were detailing and preserving timber; such as the Evenstad
to resist horizontal movements and the restrained strain Bridge in Hedmark, Norway.
induces stress, with the youngs modulus of pine being
13.5 x 104 N/mm2, this would increase the compressive
stress of the entire deck by 2.7 N/mm2, which is an
increase of 4 % of the ultimate compressive stress of
timber. In comparison to steel which would have
expanded 131 mm under the same condition and
temperature change.
The low coefficient of expansion of timber is
generally regarded as an advantage because it is
possible to omit the need for expansion joints if used in
the right orientation. As the linear coefficient of
thermal expansion perpendicular to the grain is roughly
40 x 10-6 /K, almost eleven times than that parallel to
Figure 18: The Evenstad Bridge in Hedmark, Norway;
the grain.
Built using similar techniques.
10 The use of timber
10.1 Environmental issues
Timber has recently come back in fashion as a
Timber is considered to be a more environmentally
building material; in countries such as Norway and
friendly material in comparison to steel or concrete; as
Sweden, timber is becoming a more competitive
the production of both materials produces a large
construction material comparing to steel and concrete.
amount of CO2; 1000 Kg of cement is said to produce
This is due to the better understanding of the material
approximately 800CO2; while the same amount of
property to produce better design parameters and
timber would have absorbed 1100 Kg of CO2.
joining techniques, and thus removing some of the
The main environmental issue with using timber as
negative myths about timber such as poor durability
a construction material is the creosote used in
issues.
reservation; creosote is a toxic material and is banned
For the Flisa Bridge, timber had allowed certain
from countries such s Sweden. At the Flisa Bridge,
options to be achieved such as the reuse of existing
excess creosote is believed to slowly drip into the river
stone piers even with increased number of lanes;
Glomma and the surround area on a warm day, but it is
concrete with heavier self-weight was unlikely to
argued that the negative impact is minor if the timber
provide the same result; by reusing the existing piers,
members last its design life of over 100 years.
approximately 1 million was saved from the final bill.
Steel was the alternative option but the use of de-icing
References:
salts in the winter presents severe corrosion problems,
and to achieve the 100 years design lifespan for [1] Ekeberg, PK. and Soyland, K., 2003. Flisa Bridge
structures in Norway it would have raised the cost a record-breaking timber bridge [online]
higher; timber on the other hand could use salt residues Available at:
as preservatives. http://www.thomastelford.com/journals [Accessed
Advantages of using timber as a construction February 2009]
material includes its more positive reaction to the
[2] Dinwoodie, JM., 1999. Timber: Its nature and
encounter of de-icing salts, which can be inevitable for
behaviour, second edition, pp 66.
certain locations; the possibility of avoiding the use of
expansion joints because of the lower thermal [3] BS EN1991-2, 2003. Eurocode 1: Action on
coefficient in comparison to steel; and increased structures Part 2: Traffic load on bridges. BSI
construction ease, instead of requiring a large amount
of formwork or centring, the timber trusses of the Flisa [4] BS EN1995-2, 2004. Eurocode 5: Design of timber
Bridge was simply craned into position. Most of the structures Part 2: Bridges. BSI
structural components could be pre-fabricated which [5] BS EN1995-1-1, 2004. Eurocode 5: Design of
decreased the construction time. timber structures Part 1-1: General Common rules
There are many examples of old timber bridges in and rules for buildings. BSI
poor conditions and hardly shows the possible
durability qualities. But recently developed knowledge [6] BS EN1991-1-4, 2005. Eurocode 1: Action on
and techniques provides better design standards structures Part 1-4: General actions Wind actions.
criteria, this includes better treatment to the timber, BSI
better detailing on joints, better grading of the timber [7] Nordic Road Association., 2005. NVF conference
and more advanced monitoring techniques and on timber bridges, Hamar, Norway.
equipments. These new developed techniques allow
timber to be used in more projects; other timber [8] GATE., 2006. Timber bridges new alternative
bridges had been built using similar methods for spanning, Ljubljana, Slovenia.