Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 152

Description Unit Rate

Site Management Cost for concrete works item 125,000.00


Site management Cost for Finishing works item 125,000.00
Transport / Logistics item 250,000.00
Boundary wall production item 3,700.00
Dewatering item 35,000.00
Excavation cub.mtr 575.00
Backfilling item 18,500.00
Lean concrete (50mm Thick) cub.mtr 9,000.00
Damp Proofing item 15,000.00

Concrete cub.mtr 15,550.00


Steel Deformed Bar 25mm mtr 100.00
Steel Deformed Bar 20mm mtr 75.00
Steel Deformed Bar 16mm mtr 60.00
Steel Deformed Bar 12mm mtr 30.00
Steel Deformed Bar 10mm mtr 20.00
Steel Round Bar 6mm mtr 10.00
Formwork sq.mtr 400.00
Formwork.. sq.mtr 275.00
150mm Thick Solid Block Wall Below Ground Level sq.mtr 380.00
120mm Thick Solid Block Parapet wall sq.mtr 400.00
100mm Thick Solid Block Exterior walls sq.mtr 290.00
100mm Thick Hollow Block Interior sq.mtr 290.00
Plastering 20mm Thick Exterior sq.mtr 275.00
Plastering 13mm Thick Interior sq.mtr 245.00
38mm Thk Cement Screed sq.mtr 230.00
Flooring 65mm thick sq.mtr 375.00
75mm Thick Ground Slab cub.mtr 15,550.00
600x600 Homogeneous Tiles on General areas sq.mtr 1,200.00
300x300 Ceramic Tiles on Toilet Floors sq.mtr 1,000.00
300x450 Ceramic Tiles on Toilet Walls sq.mtr 1,000.00
300x600 Ceramic Tiles on Staircase sq.mtr 1,000.00

6mm Thick ceiling sq.mtr 1,350.00


Kitchen Cupboard (concrete works) item 23,500.00

D1 - 2100 X 2833 nos 4,050.00


D1A - 2100 X 1400 nos 7,500.00
D2 - 2100 X 850 nos 4,050.00
D2A - 2100 X 850 nos 3,250.00
D2B - 2100 X 2679 nos 3,000.00
D2C - 2100 X 3235 nos 4,000.00
D3 - 2100 X 1600 nos 5,000.00
D3A - 3400 X 1600 nos 2,000.00
D4 - 2100 X 750 nos 1,500.00
FG1 - 2100 X 4832 nos 2,000.00
FG2 - 2100 X 2833 nos 2,500.00
FG3 - 2100 X 3165 nos 3,000.00
FG4 - 1100 X 4949 nos 3,500.00
FG5 - 3000 X 4700 nos 6,500.00
FG6 - 1100 X 4949 nos 6,500.00
FG7 - 3000 X 2830 nos 1,200.00
FG8 - 3000 X 3850 nos 1,200.00
FG9 - 3000 X 7369 nos 3,125.00
W1 - 700 X 600 nos 4,650.00
W2 - 700 X 3600 nos 1,850.00
nos 9,500.00
Ground Floor Ceiling works nos 9,500.00
nos 9,501.00
Exterior Fire Proof Cladding sq.mtr 1,550.00
Painting on Exterior Surfaces of Wall sq.mtr 100.00
Putty & Painting on interior surfaces of wall sq.mtr 100.00
Putty & Painting on ceiling / sofits of slab sq.mtr 100.00
Connecting to MWSC sewer mains item 4,000.00
Sewerage/waste water main connection nos 5,000.00
Inspection chamber nos 4,500.00
Water meter for whole building nos 2,500.00
Well water pump nos 15,000.00
Plumbing works inc.pipe line accessories for whole building nos 75,000.00
Plumbing works internal nos 30,000.00
WC nos 6,500.00
Muslim shower nos 5,600.00
Wash basin nos 380.00
Wash basin tap nos 380.00
Toilet paper holder nos 340.00
Towel hook nos 340.00
Soap holder nos 150.00
Mirror set nos 2,400.00
Shower nos 350.00
Tap nos 150.00
Floor trap nos 205.00
Electrical Meter item 5,500.00
Electrical main connection item 12,500.00
Electrical wiring to Lights and Fans points 400.00
Electrcal wiring to socket outlets points 400.00
Energy Saving Lights 25W (ceiling mounted) nos 650.00
Energy Saving Lights 25W (Wall mounted) nos 650.00
Spot light nos 1,250.00
13A single socket outlet nos 100.00
13A double socket outlet nos 125.00
15A socket outlet nos 150.00
One way switch nos 100.00
Two way switch nos 115.00
One way switch (one Gang) nos 75.00
One way switch (2 Gang) nos 110.00
One way switch (3 Gang) nos 135.00
One way switch (4 Gang) nos 165.00
Light Dimmer nos 275.00
Outdoor down light nos 1,000.00
Flourescent Luminaire 4' nos 950.00
Fan regulator nos 350.00
Ceiling Fan nos 1,000.00
AC 12000BTU nos 18,000.00
Heater nos 3,500.00
TV/cable outlet nos 650.00
Data/Network outlet nos 650.00
Distribution Board nos 5,000.00
Main Panel board nos 95,000.00

Staircase Railing item 18,000.00


Balcony Railing item 7,500.00
Railing above Parapet wall item 18,500.00

50x175 Timber Rafters @ 900c/c mtr 200.00


38x50 Timber battens @ 600c/c mtr 165.00
50x150 Timber member @ side walls mtr 175.00
Roof Truss mtr 4,500.00
25x200 Timber Fascia mtr
50x50 Timber Memberance for Valley Gutter Support mtr
50x175 Timber Memberance Raters Support mtr
Lysaght Roor covering sq.mtr 500.00
GI pipe dim 75mm mtr

Passenger lift (6pax) Mitsubishi item 865,000.00


MWSC booster pump item 65,000.00
Electric main panel board with meters item 135,000.00
Main powerline from STELCO substation to panel baord item 150,000.00
MWSC Water meter connection item 60,000.00
Total Electrical work item 60,000.00
Total Electrical work in ground floor item 45,000.00
Total Electrical work item 60,000.00
Total Electrical work(two bed room appartments) item 95,000.00
Total Electrical work in terrace item 50,000.00
STO PETROL SHED
CLIENT:

SUMMARY SHEET

BOQ - SUMMARY
No. Description Amount
1 SITE MANAGEMENT
Site management cost for concrete works 125,000.00
Site management cost for Finishing works 125,000.00
2 GROUND WORKS
Ground works 385,157.40
3 FOUNDATION WORK
Concrete Works 274,892.90
4 GROUND FLOOR
Concrete Works 664,451.50
Masonry , plastering & finishing work 3,613,834.40
5 FIRST FLOOR
Concrete Works 672,191.00
Masonry , plastering & finishing work 1,014,218.50
6 MISCELLANEOUS WORK 345,000.00
TOTAL FOR CONCRETE 2,121,692.80
TOTAL FOR MASONRY, PLASTERING & FINISHING 4,753,052.90
TOTAL FOR MISCELLANEOUS WORK 345,000.00

SUB TOTAL 7,219,745.70

6% OF G.S.T 433,184.74

GRAND TOTAL 7,652,930.44

DURATION
Building completion

V.I.V Private Limited Page 4 of 152


STO PETROL SHED
CLIENT:

SUMMARY SHEET

BOQ - SUMMARY
Amount
250,000.00

385,157.40

274,892.90

4,278,285.90

1,686,409.50

345,000.00

7,219,745.70

433,184.74

7,652,930.44

V.I.V Private Limited Page 5 of 152


PROJECT: #REF!
CLIENT: #REF!

MAIN MATERIALS
SN Details

Note: The BOQ is given based on the Main Materials Prices Below,

Price on Date: 1st March 2009


Main Supplier: STO Conctruction Materials,

MAJOR MATERIALS
1.00 CEMENT BAG MRF 95.00
1.01 SAND BAG MRF 40.00
1.02 AGGRIGATE BAG MRF 40.00
1.03 6mm Dia. PLAIN STEEL BAR 6 METER MRF 31.00
1.04 10mm Dia. DEFORMED STEEL BAR 6 METER MRF 74.00
1.05 12mm Dia. DEFORMED STEEL BAR 6 METER MRF 105.00
1.06 16mm Dia. DEFORMED STEEL BAR 6 METER MRF 198.00
1.07 20mm Dia. DEFORMED STEEL BAR 6 METER MRF 280.00
1.08 25mm Dia. DEFORMED STEEL BAR 6 METER MRF 460.00
1.09 12mm Plywood MRF 340.00
1.10 Timber (2" x 6" x 12') MRF 235.00
1.11 Municipality Solid Blocks (2"x4"x8") MRF 2.00
1.12 Municipality Hollow Blocks (6"x4"x12") MRF 5.50
VIEW BUILDERS PVT LTD
Ma.Vahffaru, Buruzumagu,
Male' - Maldives

Exepected Pro
M.MUDHOO

ITEM DESCRIPTION Apr-10 May-10


1 Demolition
Demolition #REF!

2 Ground Works
Masonry works for Boundry protection
Dewatering & Excavation
Dewatering & Lean Concrete

3 Concrete Works
Foundation Raft Concrete
Foundation Beam Concrete
Lift, Stair & Columns up to First Slab
Damp proofing And Masonry works at Below Ground
First Slab Beams & Slab
First floor Columns, Lift & Stair
Second Slab Beam & Slab
Second floor Columns, Lift & Stair
Third Slab Beam & Slab
Third floor Columns, Lift & Stair
Fourth Slab Beam & Slab
Fourth floor Columns, Lift & Stair
Fifth Slab Beam & Slab
Fifth floor Columns, Lift & Stair
Sixth Slab Beam & Slab
Sixth floor Columns, Lift & Stair
Seventh Slab Beam & Slab
Seventh floor Columns, Lift & Stair
Terrace Slab Beam & Slab
Terrace floor Columns & Lift
Roof Slab Beam & Slab

4 Masonry, Plastering Wiring, Plumbing & Screeding


Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Terrace

5 Finishing Works
Ground Floor - ( Including Penal Board & 2 Booster Pump)
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Terrace (Including Lift)

BOQ ACTUAL AMOUNT #REF! -


ADMIN & MANAGEMENT COST #REF! -

TOTAL FOR BOQ ACTUAL AMOUNT & MANAGEMENT COST #REF! -


e

Exepected Progress Values / Forecasted


M.MUDHOO (EIGHT STOREY BUILDING)

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!

#REF! #REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF!


Phone: +960 332 9467
Fax: +960 332 9468
email:projects@viewbuilders.com.mv, Url:www.viewbuilders.com.mv

Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
399,141.23
407,114.58
407,114.58
407,114.58
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
384,077.94
384077.94
384,077.94
#REF!
#REF!

#REF! #REF! #REF! 791,192.52 #REF! #REF! #REF!


#REF! #REF! #REF! 12,717.06 #REF! #REF! #REF!

#REF! #REF! #REF! 803,909.58 #REF! #REF! #REF!


#REF!
#REF!

#REF!
BILL OF QUANTITIES

No Description Unit Qty Rate Amount Total


1 SITE MANAGEMENT 250,000.00

Site Management Cost for concrete works item 1.00 125,000.00 125,000.00
Site management Cost for Finishing works item 1.00 125,000.00 125,000.00

2 GROUND WORKS 385,157.40

Boundary wall production item 62.80 3,700.00 232,360.00


Dewatering item 1.00 35,000.00 35,000.00
Excavation cub.mtr 65.00 575.00 37,375.00
Backfilling item 1.00 18,500.00 18,500.00
Lean concrete (50mm Thick) cub.mtr 5.21 9,000.00 46,922.40
Damp Proofing item 1.00 15,000.00 15,000.00

3 FOUNDATION WORKS 274,892.90


Foundation Footing F1 17,882.50
Concrete cub.mtr 1.15 15,550.00 17,882.50

Foundation Footing F2 97,809.50


Concrete cub.mtr 6.29 15,550.00 97,809.50

Foundation Footing F3 53,927.40


Concrete cub.mtr 3.47 15,550.00 53,927.40

Foundation Footing F4 23,636.00


Concrete cub.mtr 1.52 15,550.00 23,636.00

Foundation Footing F5 20,215.00


Concrete cub.mtr 1.30 15,550.00 20,215.00

TB Beam 41,985.00
Concrete cub.mtr 2.70 15,550.00 41,985.00

Column(s) C1 19,437.50
Concrete cub.mtr 1.25 15,550.00 19,437.50

4 GROUND FLOOR 4,278,285.90


4A Concrete Works 664,451.50

Column(s) C1 87,702.00
Concrete cub.mtr 5.64 15,550.00 87,702.00

Beam(s) B1 40,430.00
Concrete cub.mtr 2.60 15,550.00 40,430.00

Beam(s) B2 99,520.00
Concrete cub.mtr 6.40 15,550.00 99,520.00

Floor Slab 417,517.50


Concrete cub.mtr 26.85 15,550.00 417,517.50

V.I.V Private Limited Page 15 of 152


Staircase 19,282.00
Concrete cub.mtr 1.24 15,550.00 19,282.00

4B Finishing Works 3,613,834.40

Masonry & Plastering 349,552.80


100mm Thick Solid Block Exterior walls sq.mtr 244.00 290.00 70,760.00
100mm Thick Hollow Block Interior sq.mtr 194.76 290.00 56,480.40
Plastering 20mm Thick Exterior sq.mtr 244.00 275.00 67,100.00
Plastering 13mm Thick Interior sq.mtr 633.52 245.00 155,212.40

Floor Screed 2,095,899.60


75mm Thick Ground Slab cub.mtr 132.82 15,550.00 2,065,351.00
38mm Thk Cement Screed sq.mtr 132.82 230.00 30,548.60

Tiling 214,154.00
600x600 Homogeneous Tiles on General areas sq.mtr 128.17 1,200.00 153,804.00
300x300 Ceramic Tiles on Toilet Floors sq.mtr 4.65 1,000.00 4,650.00
300x450 Ceramic Tiles on Toilet Walls sq.mtr 46.20 1,000.00 46,200.00
300x600 Ceramic Tiles on Staircase sq.mtr 9.50 1,000.00 9,500.00

Doors & Windows 100,275.00


D2A - 2100 X 850 nos 7.00 3,250.00 22,750.00
D4 - 2100 X 750 nos 4.00 1,500.00 6,000.00
W1 - 700 X 600 nos 8.00 4,650.00 37,200.00
W2 - 700 X 3600 nos 1.00 1,850.00 1,850.00
FG5 - 3000 X 4700 nos 2.00 6,500.00 13,000.00
FG6 - 1100 X 4949 nos 1.00 6,500.00 6,500.00
FG7 - 3000 X 2830 nos 2.00 1,200.00 2,400.00
FG8 - 3000 X 3850 nos 1.00 1,200.00 1,200.00
FG9 - 3000 X 7369 nos 3.00 3,125.00 9,375.00

Putty & Painting 76,634.00


Putty & Painting on interior surfaces of wall sq.mtr 633.52 100.00 63,352.00
Putty & Painting on ceiling / sofits of slab sq.mtr 132.82 100.00 13,282.00

Cladding 327,332.00
Exterior Fire Proof Cladding sq.mtr 95.50 1,550.00 148,025.00

Ceiling Works 179,307.00


6mm Thick ceiling sq.mtr 132.82 1,350.00 179,307.00

Hydraulics & Drainage 207,680.00


Sewerage/waste water main connection nos 1.00 5,000.00 5,000.00
Inspection chamber nos 2.00 4,500.00 9,000.00
Water meter for whole building nos 1.00 2,500.00 2,500.00
Well water pump nos 1.00 15,000.00 15,000.00
Plumbing works inc.pipe line accessories for whole building nos 1.00 75,000.00 75,000.00
Plumbing works internal nos 1.00 30,000.00 30,000.00
Connecting to MWSC sewer mains item 1.00 4,000.00 4,000.00
WC nos 4.00 6,500.00 26,000.00
Muslim shower nos 4.00 5,600.00 22,400.00
Shower nos 4.00 350.00 1,400.00
Wash basin nos 4.00 380.00 1,520.00

V.I.V Private Limited Page 16 of 152


Wash basin tap nos 4.00 380.00 1,520.00
Toilet paper holder nos 4.00 340.00 1,360.00
Towel hook nos 4.00 340.00 1,360.00
Soap holder nos 4.00 150.00 600.00
Mirror set nos 4.00 2,400.00 9,600.00
Tap nos 4.00 150.00 600.00
Floor trap nos 4.00 205.00 820.00

Electrical Works 45,000.00


Total Electrical work in ground floor item 1.00 45,000.00 45,000.00

Metal Works 18,000.00


Staircase Railing item 1.00 18,000.00 18,000.00

5 FIRST FLOOR 1,686,409.50


5A Concrete Works 672,191.00

Column(s) C1 87,702.00
Concrete cub.mtr 5.64 15,550.00 87,702.00

Roof Beam(s) B1 68,109.00


Concrete cub.mtr 4.38 15,550.00 68,109.00

Roof Beam(s) B2 16,638.50


Concrete cub.mtr 1.07 15,550.00 16,638.50

Roof Beam(s) B3 40,119.00


Concrete cub.mtr 2.58 15,550.00 40,119.00

Floor Slab 417,517.50


Concrete cub.mtr 26.85 15,550.00 417,517.50

Staircase 29,730.00
Concrete cub.mtr 1.40 15,550.00 21,770.00
Steel Deformed Bar 10mm mtr 197.00 20.00 3,940.00
Formwork sq.mtr 10.05 400.00 4,020.00

Balcony 12,375.00
Concrete cub.mtr 0.50 15,550.00 7,775.00
Steel Deformed Bar 10mm mtr 44.00 20.00 880.00
Formwork sq.mtr 9.30 400.00 3,720.00

5B Finishing Works 1,014,218.50

Masonry & Plastering 149,467.50


100mm Thick Solid Block Exterior walls sq.mtr 87.00 290.00 25,230.00
100mm Thick Hollow Block Interior sq.mtr 98.00 290.00 28,420.00
Plastering 20mm Thick Exterior sq.mtr 96.30 275.00 26,482.50
Plastering 13mm Thick Interior sq.mtr 283.00 245.00 69,335.00

Floor Screed 24,375.00


Flooring 65mm thick sq.mtr 65.00 375.00 24,375.00

Tiling 125,046.00
600x600 Homogeneous Tiles on General areas sq.mtr 59.03 1,200.00 70,836.00

V.I.V Private Limited Page 17 of 152


300x300 Ceramic Tiles on Toilet Floors sq.mtr 5.97 1,000.00 5,970.00
300x450 Ceramic Tiles on Toilet Walls sq.mtr 33.00 1,000.00 33,000.00
300x600 Ceramic Tiles on Staircase sq.mtr 15.24 1,000.00 15,240.00

Doors & Windows 62,350.00


D1 - 2100 X 2833 nos 1.00 4,050.00 4,050.00
D1A - 2100 X 1400 nos 1.00 7,500.00 7,500.00
D2 - 2100 X 850 nos 1.00 4,050.00 4,050.00
D2A - 2100 X 850 nos 5.00 3,250.00 16,250.00
D2B - 2100 X 2679 nos 1.00 3,000.00 3,000.00
D2C - 2100 X 3235 nos 1.00 4,000.00 4,000.00
D3 - 2100 X 1600 nos 1.00 5,000.00 5,000.00
D4 - 2100 X 750 nos 4.00 1,500.00 6,000.00
FG1 - 2100 X 4832 nos 2.00 2,000.00 4,000.00
FG2 - 2100 X 2833 nos 2.00 2,500.00 5,000.00
FG4 - 1100 X 4949 nos 1.00 3,500.00 3,500.00

Putty & Painting 44,430.00


Painting on Exterior Surfaces of Wall sq.mtr 96.30 100.00 9,630.00
Putty & Painting on interior surfaces of wall sq.mtr 283.00 100.00 28,300.00
Putty & Painting on ceiling / sofits of slab sq.mtr 65.00 100.00 6,500.00

Cladding 287,345.00
Exterior Fire Proof Cladding sq.mtr 95.50 1,550.00 148,025.00

Ceiling 139,320.00
6mm Thick ceiling sq.mtr 103.20 1,350.00 139,320.00

Hydraulics & Drainage 80,385.00


Plumbing works internal nos 1.00 30,000.00 30,000.00
WC nos 3.00 6,500.00 19,500.00
Muslim shower nos 3.00 5,600.00 16,800.00
Shower nos 3.00 350.00 1,050.00
Wash basin nos 3.00 380.00 1,140.00
Wash basin tap nos 3.00 380.00 1,140.00
Toilet paper holder nos 3.00 340.00 1,020.00
Towel hook nos 3.00 340.00 1,020.00
Soap holder nos 3.00 150.00 450.00
Mirror set nos 3.00 2,400.00 7,200.00
Tap nos 3.00 150.00 450.00
Floor trap nos 3.00 205.00 615.00

Kitchen kupboard (including pipe lines) 23,500.00


Kitchen Cupboard (concrete works) item 1.00 23,500.00 23,500.00

Electrical Works 60,000.00


Total Electrical work item 1.00 60,000.00 60,000.00

Metal Works 18,000.00


Staircase Railing item 1.00 18,000.00 18,000.00

15 MISCELLANEOUS 345,000.00

MWSC Water meter connection item 1.00 60,000.00 60,000.00

V.I.V Private Limited Page 18 of 152


Electric main panel board with meters item 1.00 135,000.00 135,000.00
Main powerline from STELCO substation to panel baord item 1.00 150,000.00 150,000.00

7,219,745.70

V.I.V Private Limited Page 19 of 152


FOUNDATION

LENTH
1 2 3 4 5 6
ST1 7.1
ST2 7.1
ST3B 7.1
ST3A 2.5

ST1
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 20 4 7.1 0.9 32 35.2 92.4 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 20 2 2 4 4.4
20 4 1.5 6 6.6
Top reinforcement
Dia Nos L lapping total
Through 20 4 7.1 0.9 32 35.2

Mid span 20 4 2.5 10 11


Rings
10 33 2.26 74.58 82.038 220.704
10 33 1.76 58.08 63.888
10 33 2.06 67.98 74.778

ST2
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 3 7.1 0.75 23.55 25.905 82.445 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 16 2 2 4 4.4
16 4 1.5 6 6.6
Top reinforcement
Dia Nos L lapping total
Through 16 4 7.1 0.75 31.4 34.54

Mid span 16 4 2.5 10 11


Rings
10 66 1.86 122.76 135.036 135.036
0 0
0 0

ST3B
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 4 7.1 0.75 31.4 34.54 113.08 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 16 4 2 8 8.8
16 8 1.5 12 13.2
Top reinforcement
Dia Nos L lapping total
Through 16 4 7.1 0.75 31.4 34.54

Mid span 16 8 2.5 20 22


Rings
10 33 2.16 71.28 78.408 142.296
10 33 1.76 58.08 63.888
0 0

ST3A
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 4 2.5 0 10 11 25.3 1
Through 12 2 0 0.55 1.1 1.21 1.21
Support 0
0
Top reinforcement
Dia Nos L lapping total
Through 16 4 2.5 0.75 13 14.3

Mid span 0 0
Rings
10 9 2.16 19.44 21.384 38.808
10 9 1.76 15.84 17.424
0 0

ST1 RAFT SLAB REINFORCEMENT FOUNDATION RAFT SL


Description Dia Nos length lapping total Nos L
Bottom
main 12 52 2.2 114.4 1 6.5
distribute 12 16 6.7 0.55 116
TOP main 0
distribute 0
0
0 total
0

Total 230.4
10% 253.44 270.27
ST2 RAFT SLAB REINFORCEMENT FOUNDATION RAFT SL
Description Dia Nos length lapping total Nos L
Bottom
main 12 32 1.2 38.4 1 6.5
distribute 12 5 6.7 0.55 36.25
TOP main 0
distribute 0
0
0 total
0

Total 74.65
10% 82.115 98.945

ST3B RAFT SLAB REINFORCEMENT FOUNDATION RAFT SL


Description Dia Nos length lapping total Nos L
Bottom
main 12 37 1.7 62.9 1 6.5
distribute 12 8 6.7 0.55 58
TOP main 0
distribute 0
0
0 total
0

Total 120.9
10% 132.99 149.82

ST3A RAFT SLAB REINFORCEMENT FOUNDATION RAFT SL


Description Dia Nos length lapping total Nos L
Bottom
main 12 7 1 7 1 1.2
distribute 12 5 1.35 0 6.75
TOP main 0
distribute 0
0
0 total
0

Total 13.75
10% 15.125 16.335

TB BEAM
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 12 11.4 0.75 145.8 160.38
Support 0 0
Mid span 0 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 12 11.4 0.75 145.8 160.38 320.76
0
Mid span 0 0
Rings
6 336 0.92 0 309.12 340.032 340.032
FOUNDATION TO GROUND FLOOR

columns C1
Dia Nos length total No of colu TOTAL 10%
16 8 1.75 14 42 46.2 Nos
6 9 1.02 9.18 3
6 9 0.68 6.12 3
45.9 50.49

columns C2
Dia Nos length total No of colu TOTAL 10%
12 8 1.75 14 98 107.8 Nos
6 9 0.82 7.38 7
7
6 9 0.58 5.22 88.2 97.02
0

STAIRCASE REINFORCEMENT
Discription DIA Nos L lapping L in m 10% Nos
Main rod 10 18 1.5 0 27 29.7 1
distribute 10 20 0.95 0 19 20.9 50.6

GROUND FLOOR

columns C1
Dia Nos length lapping total No of colu TOTAL 10%
16 4 3 12
16 4 3 0.75 15 81 89.1
6 18 1.02 18.36
3
6 18 0.68 12.24
0
0 91.8 100.98

columns C2
Dia Nos length lapping total No of colu TOTAL 10%
12 4 3 12
12 4 3 0.9 15.6 193.2 212.52
6 18 0.82 14.76 7
6 18 0.58 10.44
0 176.4 194.04

STAIRCASE REINFORCEMENT
Discription DIA Nos L lapping L in m 10% Nos
Main rod 10 18 6 1.1 127.8 140.58 196.68 1
distribute 10 60 0.85 0 51 56.1 17

TERRACE FLOOR
columns C2
Dia Nos length lapping total No of colu TOTAL 10%
12 4 3 12
12 4 3 0.9 15.6 110.4 121.44
6 18 0.82 14.76 4
6 18 0.58 10.44
0 100.8 110.88

GROUND FLOOR BEAM


LENTH
1 2 3 4 5 6
B1 2=6.5 4=3.35 2=1.8
B2 11.2 9.4
B3 11.2
CB1 1

B1 (1 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 6.7 0.75 14.9 16.39 65.56
Mid span 0
Mid span 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 6.7 0.75 14.9 16.39
Support 0
Support 0
Rings
6 44 0.92 0 40.48 44.528 89.056

B1 (2 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 3.55 0 7.1 7.81 62.48
Mid span 0
Mid span 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 3.55 0 7.1 7.81
Support 0
Support 0
Rings
6 23 0.92 0 21.16 23.276 93.104

B1 (3 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 2 0 4 4.4 17.6
Mid span 0
Mid span 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 2 0 4 4.4
Support 0
Support 0
Rings
6 12 0.92 0 11.04 12.144 24.288

B2 (1 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 11.4 0.75 24.3 26.73 94.16
Support - 0 0
Mid span 16 2 9.5 19 20.9
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 11.4 0.75 24.3 26.73
Support 16 2 9 18 19.8
Mid span 0 0
Rings
6 90 0.92 0 82.8 91.08 91.08

B2 (2 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 9.6 0.75 20.7 22.77 80.74
Support - 0 0
Mid span 16 2 8 16 17.6
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 9.6 0.75 20.7 22.77
Support 16 2 8 16 17.6
Mid span 0 0
Rings
6 75 0.92 0 69 75.9 75.9

B3 BEAM
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 11.4 0.75 24.3 26.73 53.46
Support - 0 0
Mid span 25 2 10 20 22 44
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 11.4 0.75 24.3 26.73
Support 25 2 10 20 22
Mid span 0 0
Rings
6 56 0.92 0 51.52 56.672 56.672

CB1 BEAM
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 1 2 2.2 22
Support - 0 0
Mid span 0 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 1 0 2 2.2
Support 16 2 3 6 6.6
Mid span 0 0
Rings
6 10 0.92 0 9.2 10.12 20.24

GROUND FLOOR SLAB REINFORCEMENT GROUND FLOOR SLA


Description Dia Nos length lapping total Nos L
Bottom
main 10 81 6.65 0.45 575.1 1 12.2
distribute 10 44 12.35 0.9 583 1 1.95
44 1 44 Deduction
4 6.65 0.45 28.4 1 2.5
44 1 44 1 0.75
4 6.65 0.45 28.4 1 1
44 2.5 110
10 6.65 0.45 71
81 1 81
4 12.35 0.9 53
81 1 81
4 12.35 0.9 53
81 2.5 202.5
10 12.35 0.9 132.5
22 1 22
4 3.3 13.2
0
0
0
0
0
0
0
0
2122.1
Deductin
10 20 1.6 32
10 11 2.95 32.45
7 1.3 9.1
9 1 9
9 0.75 6.75
5 1.35 6.75
0
0
96.05
Total 2026.05
10% 2633.865

TERRACE
B1 (2 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 3.55 0 7.1 7.81 31.24
Mid span 0
Mid span 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 3.55 0 7.1 7.81
Support 0
Support 0
Rings
6 23 0.92 0 21.16 23.276 46.552

B1 (3 BEAM)
Bottom reinforcement

Dia Nos L lapping total 10%


Through 16 2 2 0 4 4.4 17.6
Mid span 0
Mid span 0
Top reinforcement 0
Dia Nos L lapping total
Through 16 2 2 0 4 4.4
Support 0
Support 0
Rings
6 12 0.92 0 11.04 12.144 24.288

ROOF SLAB REINFORCEMENT ROOF SLAB CO


Description Dia Nos length lapping total Nos L
Bottom
main 10 20 3.9 0 78 1 3.7
distribute 10 26 2.9 0 75.4
Bottom
main 10 20 3.9 0 78
distribute 10 26 2.9 0 75.4

306.8 337.48

BALCONY1ST TO 3RD
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 15 0.875 0 13.125 1 2.9
distribute 10 3 2.9 0 8.7 2 1.2
main 10 12 0.875 0 10.5
distribute 10 6 1.2 0 7.2
39.525 43.4775

BALCONY4th floor
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 10 0.875 0 8.75 1 1.95
distribute 10 3 1.95 0 5.85 1 6.2
main 10 31 0.875 0 27.125
distribute 10 3 6.2 0 18.6
60.325 66.3575

parapet
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 33 1.1 0 36.3 1 6.5
distribute 10 4 6.5 0 26
main 0
distribute 0
62.3 68.53

FINISHING WORK

Ground Below ground floor


14.896
floor Area block work

FINISHING WORK
GROUND FLOOR
Nos L H TOTAL
100'' Solid block 2 18.48 2.6 96.096 Deduction
1 8.5 2 17
113.096
Total

Nos L H TOTAL
100'' Hollow block 1 11.98 2.6 31.148
1 2.025 3 6.075 Deduction
1 1.325 3 3.975
3 3.05 3 27.45
1 1.35 3 4.05
1 1.6 3 4.8
1 1.45 3 4.35
1 0.85 3 2.55
0
84.398
1ST floor
Area FIRST FLOOR to fifth
Nos L H TOTAL
100'' Solid block 2 12.198 2.6 63.4296 Deduction
2 6.5 2.6 33.8
97.2296
Total

Nos L H TOTAL
100'' Hollow block 0
1 12.198 3 36.594 Deduction
2 1.325 3 7.95
1 4.05 3 12.15
1 6.5 3 19.5
2 1.35 3 8.1
3 3.25 3 29.25
0
0
0
0
0
0
113.544

Terrace 100.35
floor Area TERRACE FLOOR
Nos L H TOTAL
100'' Solid block 2 12.198 2 48.792 Deduction
2 3.175 3 19.05
2 2 3 12

79.842
L B H
EXCAVATION TOTAL
ST1
ST2
ST3
ST3
ST4
LIFT AREA

ST1 ST1
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.5 0.45 1.4625 2
2

ST2 ST2
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.45 0.5 1.4625 2
2

ST3B ST3B
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.45 0.5 1.4625 2
2

ST3A ST3A
CONCRETE FORM WORK
L B H TOTAL Nos
1.725 0.45 0.5 0.388125 2
2

FOUNDATION RAFT SLAB CONCRETE FOUNDATION RAFT SLAB FORMWORK


B H Total cub.m Nos L H

2 0.35 4.55 2 6.5 0.35


2 2 0.35

0
0 TOTAL
total 4.55

6.0125

FOUNDATION RAFT SLAB CONCRETE FOUNDATION RAFT SLAB FORMWORK


B H Total cub.m Nos L H

1 0.3 1.95 2 6.5 0.3


2 1 0.3

0
0 TOTAL
total 1.95

3.4125

FOUNDATION RAFT SLAB CONCRETE FOUNDATION RAFT SLAB FORMWORK


B H Total cub.m Nos L H

1.5 0.3 2.925 2 6.5 0.3


2 1.5 0.3

0
0 TOTAL
total 2.925

4.3875

FOUNDATION RAFT SLAB CONCRETE FOUNDATION RAFT SLAB FORMWORK


B H Total cub.m Nos L H

0.95 0.3 0.342 2 1.2 0.3


1 0.95 0.3

0
0 TOTAL
total 0.342

0.730125

CONCRETE FORM WORK


TB BEAM TB BEAM
Nos L B H Total cub.m Nos
3 11.2 0.2 0.4 ### 6
ON TO GROUND FLOOR COLUMN

concrete form work


columns C1 columns C1
L B H Total cub.m Nos L
0.4 0.2 0.55 0.132 3 1.2

concrete form work


columns C2 columns C2
L B H Total cub.m Nos L
0.35 0.2 0.55 0.2695 7 1.1

staircase concrete staircase form work


L B H Total cub.m Nos L
0.85 0.15 1 0.1275 2 0.85
2 0.15

UND FLOOR

concrete form work


columns C1 columns C1
Nos L B H Total cub.m Nos
3 0.4 0.2 2.7 0.648 3

concrete form work


columns C2 columns C2
Nos L B H Total cub.m Nos
7 0.35 0.2 2.7 1.323 7

staircase concrete staircase form work


L B H Total cub.m Nos L
0.85 0.15 6 0.765 1 0.85
0.85 0.25 0.17 0.614125 1.379125 20 0.85
2 0.2

RACE FLOOR
concrete form work
columns C2 columns C2
Nos L B H Total cub.m Nos
4 0.35 0.2 2.7 0.756 4

D FLOOR BEAM

16 6 CONCRETE FORMWORK
B1 145.64 206.448 1.620 16.20
B2 174.9 166.98 1.112 11.12
44 53.46 56.672 0.605 6.05
CB1 22 20.24 0.108 1.08

CONCRETE FORM WORK


B1 (1 BEAM) B1 (1 BEAM)
Nos L B H Total cub.m Nos
2 6.5 0.2 0.27 ### 4

CONCRETE FORM WORK


B1 (2 BEAM) B1 (2 BEAM)
Nos L B H Total cub.m Nos
4 3.35 0.2 0.27 ### 8
CONCRETE FORM WORK
B1 (3 BEAM) B1 (3 BEAM)
Nos L B H Total cub.m Nos
2 1.8 0.2 0.27 ### 4

CONCRETE FORM WORK


B2 (1 BEAM) B2 (1 BEAM)
Nos L B H Total cub.m Nos
1 11.2 0.2 0.27 ### 2

CONCRETE FORM WORK


B2 (2 BEAM) B2 (2 BEAM)
Nos L B H Total cub.m Nos
1 9.4 0.2 0.27 ### 2

CONCRETE FORM WORK


B3 BEAM B3 BEAM
Nos L B H Total cub.m Nos
1 11.2 0.2 0.27 ### 2

CONCRETE FORM WORK


CB1 BEAM CB1 BEAM
Nos L B H Total cub.m Nos
2 1 0.2 0.27 ### 4

GROUND FLOOR SLAB CONCRETE GROUND FLOOR SLAB FORM WORK


B H Total cub.m Nos L H

6.5 0.13 10.309 1 12.2 6.5


1 0.02 0.039 Deduction
1 2.5 1.6
1.6 0.13 0.52 1 0.75 1.35
1.35 0.13 0.131625 1 1 1.3
1.3 0.13 0.169

0.820625

9.527375
TERRACE
CONCRETE FORM WORK
B1 (2 BEAM) B1 (2 BEAM)
Nos L B H Total cub.m Nos
2 3.35 0.2 0.27 ### 4

5.562
48.84 0.556
70.84

CONCRETE FORM WORK


B1 (3 BEAM) B1 (3 BEAM)
Nos L B H Total cub.m Nos
2 1.8 0.2 0.27 ### 4

ROOF SLAB CONCRETE ROOF SLAB FORMWORK


B H Total cub.m Nos L B

2.7 0.13 1.2987 1 3.7 2.7


1ST TO 3RD
CONCRETE FORMWORK
B H Total cub.m Nos L H
0.1 0.875 0.25375 2 2.9 0.875
0.1 0.875 0.21 4 1.2 0.875
0.46375

CONCRETE FORMWORK
B H Total cub.m Nos L H
0.1 0.875 0.170625 2 1.95 0.875
0.1 0.875 0.5425 2 6.2 0.875
0.713125

CONCRETE FORMWORK
B H Total cub.m Nos L H
0.1 1.1 0.715 2 6.5 1.1
0 2 0 0
0.715

14.896 0.55 8.1928

D1 1
Nos L H TOTAL D1A 1
D3 2
SW1 1
16.7225 W2 1
96.3735 V1 1

Nos L H TOTAL

D1 1
D2 2
D4 2
W6 1
V2 1

10.415
TOTAL 73.983

Nos L H TOTAL W1 1
W2 1
W3 2
10.8 SD1 2
86.4296
SD2 2
Nos L H TOTAL

D1 1
D2 3
D4 3
D5 1
W3 1
W4 1
16.32 W5 1
TOTAL 97.224

Nos L H TOTAL
D2 1
W2 1

2.64
77.202
LEAN
L B H
CONCRETE TOTAL
0
0
0
0
0
0
0
1.7
1.7

ST1
FORM WORK
L H TOTAL
6.5 0.45 5.85
0.5 0.45 0.45
6.3

ST2
FORM WORK
L H TOTAL
6.5 0.5 6.5
0.45 0.5 0.45
6.95

ST3B
FORM WORK
L H TOTAL
6.5 0.5 6.5
0.45 0.5 0.45
6.95

ST3A
FORM WORK
L H TOTAL
1.725 0.5 1.725
0.45 0.5 0.45
2.175

SLAB FORMWORK
Total seq.m

4.55
1.4
0
0
5.95

12.25

SLAB FORMWORK
Total seq.m

3.9
0.6
0
0
4.5

11.45

SLAB FORMWORK
Total seq.m

3.9
0.9
0
0
4.8

11.75

SLAB FORMWORK
Total seq.m

0.72
0.285
0
0
1.005

3.18

FORM WORK EXCAVATION


TB BEAM 0
L H Total seq.m
11.2 0.4 26.88
form work
columns C1
H Total seq.m
0.55 1.98

form work
columns C2
H Total seq.m
0.55 4.235

staircase form work


H Total seq.m
1 1.7
1 0.3 2

form work
columns C1
L H Total seq.m
1.2 2.7 9.72

form work
columns C2
L H Total seq.m
1.1 2.7 20.79

137.445
staircase form work
H Total seq.m
6 5.1
0.15 2.55 10.05
6 2.4

form work
columns C2
L H Total seq.m
1.1 2.7 11.88

FORM WORK
B1 (1 BEAM)
L H Total seq.m
6.5 0.27 7.02

FORM WORK
B1 (2 BEAM)
L H Total seq.m
3.35 0.27 7.24
FORM WORK
B1 (3 BEAM)
L H Total seq.m
1.8 0.27 1.94

FORM WORK
B2 (1 BEAM)
L H Total seq.m
11.2 0.27 6.05

FORM WORK
B2 (2 BEAM)
L H Total seq.m
9.4 0.27 5.08

FORM WORK
B3 BEAM
L H Total seq.m
11.2 0.27 6.05

FORM WORK
CB1 BEAM
L H Total seq.m
1 0.27 1.08

AB FORM WORK
Total seq.m

79.3

4
1.0125
1.3

6.3125

72.9875
FORM WORK
B1 (2 BEAM)
L H Total seq.m
3.35 0.27 3.62

FORM WORK
B1 (3 BEAM)
L H Total seq.m
1.8 0.27 1.94

ORMWORK
Total seq.m

9.99
ORK
Total seq.m
5.075
4.2
9.275

ORK
Total seq.m
3.4125
10.85
14.2625

ORK
Total seq.m
14.3
0
14.3

2.6 0.85 2.21


2.6 2.95 7.67
2.6 0.75 3.9
1.45 1.2 1.74
1.25 0.65 0.8125
0.65 0.6 0.39
16.7225

2.6 0.85 2.21


2.15 0.85 3.655
2.2 0.7 3.08
1.8 0.6 1.08
0.65 0.6 0.39
10.415

2 2 4
1.25 0.65 0.8125
0.6 0.6 0.72
2.45 1.075 5.2675
10.8 10.4285
2.72 0.9 4.896

2.6 0.85 2.21


2.15 0.85 5.4825
2.2 0.7 4.62
2.45 0.7 1.715
0.6 0.6 0.36
1.55 0.55 0.8525
1.8 0.6 1.08
16.32

2.15 0.85 1.8275


1.25 0.65 0.8125

2.64
Specification of the Finishes

Furniture Layout

NAME DESCRIPTION PHOTO

SOFA SET 3 SEATER

TV RACK WHITE

DINING TABLE WHITE/ BROWN

REFRIGERATOR

X 4 BURNER
GAS RANGE
SINGLE OVEN

BEDROOM SET WHITE

You might also like