Professional Documents
Culture Documents
Formating
Formating
SUMMARY SHEET
BOQ - SUMMARY
No. Description Amount
1 SITE MANAGEMENT
Site management cost for concrete works 125,000.00
Site management cost for Finishing works 125,000.00
2 GROUND WORKS
Ground works 385,157.40
3 FOUNDATION WORK
Concrete Works 274,892.90
4 GROUND FLOOR
Concrete Works 664,451.50
Masonry , plastering & finishing work 3,613,834.40
5 FIRST FLOOR
Concrete Works 672,191.00
Masonry , plastering & finishing work 1,014,218.50
6 MISCELLANEOUS WORK 345,000.00
TOTAL FOR CONCRETE 2,121,692.80
TOTAL FOR MASONRY, PLASTERING & FINISHING 4,753,052.90
TOTAL FOR MISCELLANEOUS WORK 345,000.00
6% OF G.S.T 433,184.74
DURATION
Building completion
SUMMARY SHEET
BOQ - SUMMARY
Amount
250,000.00
385,157.40
274,892.90
4,278,285.90
1,686,409.50
345,000.00
7,219,745.70
433,184.74
7,652,930.44
MAIN MATERIALS
SN Details
Note: The BOQ is given based on the Main Materials Prices Below,
MAJOR MATERIALS
1.00 CEMENT BAG MRF 95.00
1.01 SAND BAG MRF 40.00
1.02 AGGRIGATE BAG MRF 40.00
1.03 6mm Dia. PLAIN STEEL BAR 6 METER MRF 31.00
1.04 10mm Dia. DEFORMED STEEL BAR 6 METER MRF 74.00
1.05 12mm Dia. DEFORMED STEEL BAR 6 METER MRF 105.00
1.06 16mm Dia. DEFORMED STEEL BAR 6 METER MRF 198.00
1.07 20mm Dia. DEFORMED STEEL BAR 6 METER MRF 280.00
1.08 25mm Dia. DEFORMED STEEL BAR 6 METER MRF 460.00
1.09 12mm Plywood MRF 340.00
1.10 Timber (2" x 6" x 12') MRF 235.00
1.11 Municipality Solid Blocks (2"x4"x8") MRF 2.00
1.12 Municipality Hollow Blocks (6"x4"x12") MRF 5.50
VIEW BUILDERS PVT LTD
Ma.Vahffaru, Buruzumagu,
Male' - Maldives
Exepected Pro
M.MUDHOO
2 Ground Works
Masonry works for Boundry protection
Dewatering & Excavation
Dewatering & Lean Concrete
3 Concrete Works
Foundation Raft Concrete
Foundation Beam Concrete
Lift, Stair & Columns up to First Slab
Damp proofing And Masonry works at Below Ground
First Slab Beams & Slab
First floor Columns, Lift & Stair
Second Slab Beam & Slab
Second floor Columns, Lift & Stair
Third Slab Beam & Slab
Third floor Columns, Lift & Stair
Fourth Slab Beam & Slab
Fourth floor Columns, Lift & Stair
Fifth Slab Beam & Slab
Fifth floor Columns, Lift & Stair
Sixth Slab Beam & Slab
Sixth floor Columns, Lift & Stair
Seventh Slab Beam & Slab
Seventh floor Columns, Lift & Stair
Terrace Slab Beam & Slab
Terrace floor Columns & Lift
Roof Slab Beam & Slab
5 Finishing Works
Ground Floor - ( Including Penal Board & 2 Booster Pump)
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Terrace (Including Lift)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
399,141.23
407,114.58
407,114.58
407,114.58
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
384,077.94
384077.94
384,077.94
#REF!
#REF!
#REF!
BILL OF QUANTITIES
Site Management Cost for concrete works item 1.00 125,000.00 125,000.00
Site management Cost for Finishing works item 1.00 125,000.00 125,000.00
TB Beam 41,985.00
Concrete cub.mtr 2.70 15,550.00 41,985.00
Column(s) C1 19,437.50
Concrete cub.mtr 1.25 15,550.00 19,437.50
Column(s) C1 87,702.00
Concrete cub.mtr 5.64 15,550.00 87,702.00
Beam(s) B1 40,430.00
Concrete cub.mtr 2.60 15,550.00 40,430.00
Beam(s) B2 99,520.00
Concrete cub.mtr 6.40 15,550.00 99,520.00
Tiling 214,154.00
600x600 Homogeneous Tiles on General areas sq.mtr 128.17 1,200.00 153,804.00
300x300 Ceramic Tiles on Toilet Floors sq.mtr 4.65 1,000.00 4,650.00
300x450 Ceramic Tiles on Toilet Walls sq.mtr 46.20 1,000.00 46,200.00
300x600 Ceramic Tiles on Staircase sq.mtr 9.50 1,000.00 9,500.00
Cladding 327,332.00
Exterior Fire Proof Cladding sq.mtr 95.50 1,550.00 148,025.00
Column(s) C1 87,702.00
Concrete cub.mtr 5.64 15,550.00 87,702.00
Staircase 29,730.00
Concrete cub.mtr 1.40 15,550.00 21,770.00
Steel Deformed Bar 10mm mtr 197.00 20.00 3,940.00
Formwork sq.mtr 10.05 400.00 4,020.00
Balcony 12,375.00
Concrete cub.mtr 0.50 15,550.00 7,775.00
Steel Deformed Bar 10mm mtr 44.00 20.00 880.00
Formwork sq.mtr 9.30 400.00 3,720.00
Tiling 125,046.00
600x600 Homogeneous Tiles on General areas sq.mtr 59.03 1,200.00 70,836.00
Cladding 287,345.00
Exterior Fire Proof Cladding sq.mtr 95.50 1,550.00 148,025.00
Ceiling 139,320.00
6mm Thick ceiling sq.mtr 103.20 1,350.00 139,320.00
15 MISCELLANEOUS 345,000.00
7,219,745.70
LENTH
1 2 3 4 5 6
ST1 7.1
ST2 7.1
ST3B 7.1
ST3A 2.5
ST1
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 20 4 7.1 0.9 32 35.2 92.4 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 20 2 2 4 4.4
20 4 1.5 6 6.6
Top reinforcement
Dia Nos L lapping total
Through 20 4 7.1 0.9 32 35.2
ST2
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 3 7.1 0.75 23.55 25.905 82.445 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 16 2 2 4 4.4
16 4 1.5 6 6.6
Top reinforcement
Dia Nos L lapping total
Through 16 4 7.1 0.75 31.4 34.54
ST3B
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 4 7.1 0.75 31.4 34.54 113.08 1
Through 12 2 7.1 0.55 15.3 16.83 16.83
Support 16 4 2 8 8.8
16 8 1.5 12 13.2
Top reinforcement
Dia Nos L lapping total
Through 16 4 7.1 0.75 31.4 34.54
ST3A
Bottom reinforcement
Dia Nos L lapping total 10% Nos
Through 16 4 2.5 0 10 11 25.3 1
Through 12 2 0 0.55 1.1 1.21 1.21
Support 0
0
Top reinforcement
Dia Nos L lapping total
Through 16 4 2.5 0.75 13 14.3
Mid span 0 0
Rings
10 9 2.16 19.44 21.384 38.808
10 9 1.76 15.84 17.424
0 0
Total 230.4
10% 253.44 270.27
ST2 RAFT SLAB REINFORCEMENT FOUNDATION RAFT SL
Description Dia Nos length lapping total Nos L
Bottom
main 12 32 1.2 38.4 1 6.5
distribute 12 5 6.7 0.55 36.25
TOP main 0
distribute 0
0
0 total
0
Total 74.65
10% 82.115 98.945
Total 120.9
10% 132.99 149.82
Total 13.75
10% 15.125 16.335
TB BEAM
Bottom reinforcement
columns C1
Dia Nos length total No of colu TOTAL 10%
16 8 1.75 14 42 46.2 Nos
6 9 1.02 9.18 3
6 9 0.68 6.12 3
45.9 50.49
columns C2
Dia Nos length total No of colu TOTAL 10%
12 8 1.75 14 98 107.8 Nos
6 9 0.82 7.38 7
7
6 9 0.58 5.22 88.2 97.02
0
STAIRCASE REINFORCEMENT
Discription DIA Nos L lapping L in m 10% Nos
Main rod 10 18 1.5 0 27 29.7 1
distribute 10 20 0.95 0 19 20.9 50.6
GROUND FLOOR
columns C1
Dia Nos length lapping total No of colu TOTAL 10%
16 4 3 12
16 4 3 0.75 15 81 89.1
6 18 1.02 18.36
3
6 18 0.68 12.24
0
0 91.8 100.98
columns C2
Dia Nos length lapping total No of colu TOTAL 10%
12 4 3 12
12 4 3 0.9 15.6 193.2 212.52
6 18 0.82 14.76 7
6 18 0.58 10.44
0 176.4 194.04
STAIRCASE REINFORCEMENT
Discription DIA Nos L lapping L in m 10% Nos
Main rod 10 18 6 1.1 127.8 140.58 196.68 1
distribute 10 60 0.85 0 51 56.1 17
TERRACE FLOOR
columns C2
Dia Nos length lapping total No of colu TOTAL 10%
12 4 3 12
12 4 3 0.9 15.6 110.4 121.44
6 18 0.82 14.76 4
6 18 0.58 10.44
0 100.8 110.88
B1 (1 BEAM)
Bottom reinforcement
B1 (2 BEAM)
Bottom reinforcement
B1 (3 BEAM)
Bottom reinforcement
B2 (1 BEAM)
Bottom reinforcement
B2 (2 BEAM)
Bottom reinforcement
B3 BEAM
Bottom reinforcement
CB1 BEAM
Bottom reinforcement
TERRACE
B1 (2 BEAM)
Bottom reinforcement
B1 (3 BEAM)
Bottom reinforcement
306.8 337.48
BALCONY1ST TO 3RD
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 15 0.875 0 13.125 1 2.9
distribute 10 3 2.9 0 8.7 2 1.2
main 10 12 0.875 0 10.5
distribute 10 6 1.2 0 7.2
39.525 43.4775
BALCONY4th floor
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 10 0.875 0 8.75 1 1.95
distribute 10 3 1.95 0 5.85 1 6.2
main 10 31 0.875 0 27.125
distribute 10 3 6.2 0 18.6
60.325 66.3575
parapet
REINFORCEMENT CONCRE
Description Dia Nos length lapping total Nos L
main 10 33 1.1 0 36.3 1 6.5
distribute 10 4 6.5 0 26
main 0
distribute 0
62.3 68.53
FINISHING WORK
FINISHING WORK
GROUND FLOOR
Nos L H TOTAL
100'' Solid block 2 18.48 2.6 96.096 Deduction
1 8.5 2 17
113.096
Total
Nos L H TOTAL
100'' Hollow block 1 11.98 2.6 31.148
1 2.025 3 6.075 Deduction
1 1.325 3 3.975
3 3.05 3 27.45
1 1.35 3 4.05
1 1.6 3 4.8
1 1.45 3 4.35
1 0.85 3 2.55
0
84.398
1ST floor
Area FIRST FLOOR to fifth
Nos L H TOTAL
100'' Solid block 2 12.198 2.6 63.4296 Deduction
2 6.5 2.6 33.8
97.2296
Total
Nos L H TOTAL
100'' Hollow block 0
1 12.198 3 36.594 Deduction
2 1.325 3 7.95
1 4.05 3 12.15
1 6.5 3 19.5
2 1.35 3 8.1
3 3.25 3 29.25
0
0
0
0
0
0
113.544
Terrace 100.35
floor Area TERRACE FLOOR
Nos L H TOTAL
100'' Solid block 2 12.198 2 48.792 Deduction
2 3.175 3 19.05
2 2 3 12
79.842
L B H
EXCAVATION TOTAL
ST1
ST2
ST3
ST3
ST4
LIFT AREA
ST1 ST1
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.5 0.45 1.4625 2
2
ST2 ST2
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.45 0.5 1.4625 2
2
ST3B ST3B
CONCRETE FORM WORK
L B H TOTAL Nos
6.5 0.45 0.5 1.4625 2
2
ST3A ST3A
CONCRETE FORM WORK
L B H TOTAL Nos
1.725 0.45 0.5 0.388125 2
2
0
0 TOTAL
total 4.55
6.0125
0
0 TOTAL
total 1.95
3.4125
0
0 TOTAL
total 2.925
4.3875
0
0 TOTAL
total 0.342
0.730125
UND FLOOR
RACE FLOOR
concrete form work
columns C2 columns C2
Nos L B H Total cub.m Nos
4 0.35 0.2 2.7 0.756 4
D FLOOR BEAM
16 6 CONCRETE FORMWORK
B1 145.64 206.448 1.620 16.20
B2 174.9 166.98 1.112 11.12
44 53.46 56.672 0.605 6.05
CB1 22 20.24 0.108 1.08
0.820625
9.527375
TERRACE
CONCRETE FORM WORK
B1 (2 BEAM) B1 (2 BEAM)
Nos L B H Total cub.m Nos
2 3.35 0.2 0.27 ### 4
5.562
48.84 0.556
70.84
CONCRETE FORMWORK
B H Total cub.m Nos L H
0.1 0.875 0.170625 2 1.95 0.875
0.1 0.875 0.5425 2 6.2 0.875
0.713125
CONCRETE FORMWORK
B H Total cub.m Nos L H
0.1 1.1 0.715 2 6.5 1.1
0 2 0 0
0.715
D1 1
Nos L H TOTAL D1A 1
D3 2
SW1 1
16.7225 W2 1
96.3735 V1 1
Nos L H TOTAL
D1 1
D2 2
D4 2
W6 1
V2 1
10.415
TOTAL 73.983
Nos L H TOTAL W1 1
W2 1
W3 2
10.8 SD1 2
86.4296
SD2 2
Nos L H TOTAL
D1 1
D2 3
D4 3
D5 1
W3 1
W4 1
16.32 W5 1
TOTAL 97.224
Nos L H TOTAL
D2 1
W2 1
2.64
77.202
LEAN
L B H
CONCRETE TOTAL
0
0
0
0
0
0
0
1.7
1.7
ST1
FORM WORK
L H TOTAL
6.5 0.45 5.85
0.5 0.45 0.45
6.3
ST2
FORM WORK
L H TOTAL
6.5 0.5 6.5
0.45 0.5 0.45
6.95
ST3B
FORM WORK
L H TOTAL
6.5 0.5 6.5
0.45 0.5 0.45
6.95
ST3A
FORM WORK
L H TOTAL
1.725 0.5 1.725
0.45 0.5 0.45
2.175
SLAB FORMWORK
Total seq.m
4.55
1.4
0
0
5.95
12.25
SLAB FORMWORK
Total seq.m
3.9
0.6
0
0
4.5
11.45
SLAB FORMWORK
Total seq.m
3.9
0.9
0
0
4.8
11.75
SLAB FORMWORK
Total seq.m
0.72
0.285
0
0
1.005
3.18
form work
columns C2
H Total seq.m
0.55 4.235
form work
columns C1
L H Total seq.m
1.2 2.7 9.72
form work
columns C2
L H Total seq.m
1.1 2.7 20.79
137.445
staircase form work
H Total seq.m
6 5.1
0.15 2.55 10.05
6 2.4
form work
columns C2
L H Total seq.m
1.1 2.7 11.88
FORM WORK
B1 (1 BEAM)
L H Total seq.m
6.5 0.27 7.02
FORM WORK
B1 (2 BEAM)
L H Total seq.m
3.35 0.27 7.24
FORM WORK
B1 (3 BEAM)
L H Total seq.m
1.8 0.27 1.94
FORM WORK
B2 (1 BEAM)
L H Total seq.m
11.2 0.27 6.05
FORM WORK
B2 (2 BEAM)
L H Total seq.m
9.4 0.27 5.08
FORM WORK
B3 BEAM
L H Total seq.m
11.2 0.27 6.05
FORM WORK
CB1 BEAM
L H Total seq.m
1 0.27 1.08
AB FORM WORK
Total seq.m
79.3
4
1.0125
1.3
6.3125
72.9875
FORM WORK
B1 (2 BEAM)
L H Total seq.m
3.35 0.27 3.62
FORM WORK
B1 (3 BEAM)
L H Total seq.m
1.8 0.27 1.94
ORMWORK
Total seq.m
9.99
ORK
Total seq.m
5.075
4.2
9.275
ORK
Total seq.m
3.4125
10.85
14.2625
ORK
Total seq.m
14.3
0
14.3
2 2 4
1.25 0.65 0.8125
0.6 0.6 0.72
2.45 1.075 5.2675
10.8 10.4285
2.72 0.9 4.896
2.64
Specification of the Finishes
Furniture Layout
TV RACK WHITE
REFRIGERATOR
X 4 BURNER
GAS RANGE
SINGLE OVEN