WEEKLY CONSTRUCTION PROGRESS REPORT_#01

Period Covered: W6 - July 06, 2017 to July 12, 2017

I. PROJECT INFORMATION

Project Title: Construction of C5 South Link Expressway Project Project ID: 16C5

Project Location: City of Paraaque, Taguig & Pasay Days 35/730


Elapsed: Calendar Day(s)
Contract Start: June 02, 2017 Contract June 02, 2019 Revised
Completion Contract
Date: Completion:
Project Contract P1,087,000,000.00 Variation Revised
Amount: Order: Contract
Amount:
Project Client: Cavitex Infrastructure Corporation Aguinaldo Blvd.

II. SAFETY REPORT

A. Man-Hour Summary
LAST WEEK THIS WEEK TO DATE

B. Site Safety Statistics

INCIDENT EXPERIENCE SUMMARY LAST WEEK THIS WEEK INCEPTION-TO-DATE

1) First Aid Treatment


2) Property Damage
3) Fire Incident
4) Near Miss
5) Environmental Incident
6) Others

Note: Provide brief description of accidents/ Incidents:

C. Status of Safety, Health & Environment Compliance

Note: List down of all applicable laws including local ordinances and resolutions with relevance
to Safety, Health & Environment encountered within the project period (e.g. Project Safety &
Health Program was approved by DOLE last January 01, 1999)
D. Safety, Health & Environment Activities, Issues and Concern

Note: Provide highlights & lowlights activities for the week. Attach also some photos.

III.QUALITY REPORT