Professional Documents
Culture Documents
PR-1076 - Isolation of Process Equipment Procedure
PR-1076 - Isolation of Process Equipment Procedure
Document ID PR-1076
Security Unrestricted
Revision 6.0
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part
of this document may be disclosed to others or reproduced, stored in a retrieval system, or
transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise)
without prior written consent of the owner.
i Document Authorisation
Authorised For Issue May 2012
ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of all
revisions prior to these are held on file by the issuing department.
TABLE OF CONTENTS
1 Introduction........................................................................................................................... 7
1.1 Background..................................................................................................................... 7
1.2 Purpose........................................................................................................................... 7
1.3 Distribution / Target Audience.......................................................................................... 7
1.4 Changes to the Document............................................................................................... 7
1.5 Step-out Approval............................................................................................................ 7
1.6 ALARP............................................................................................................................. 7
2 Roles and Responsibilities.................................................................................................... 8
3 Isolation of Process Equipment........................................................................................... 10
3.1 Scope............................................................................................................................ 10
3.2 Terminology................................................................................................................... 10
3.2.1 Major Work.............................................................................................................. 10
Table 1 Minimum Isolation Requirements............................................................................11
3.2.2 Minor Work.............................................................................................................. 12
3.2.3 Battery Limits.......................................................................................................... 12
3.2.4 Baseline Isolation Standard....................................................................................12
3.2.5 Boundary Isolation.................................................................................................. 12
3.2.6 Hydrocarbon Services.............................................................................................12
3.2.7 Hazardous Substance / Service..............................................................................12
3.2.8 Non-Hazardous Service.......................................................................................... 12
3.2.9 H2S / Toxic System.................................................................................................. 13
3.3 Guidance Notes for Isolation......................................................................................... 13
3.3.1 Issue of PTW to Permit Holder...............................................................................13
3.3.2 Positive Isolation of Equipment for Maintenance....................................................13
3.3.3 Removal and Replacement of Relief Valves on Live Systems.............................13
3.3.4 Isolation of Moving Machinery................................................................................14
3.3.5 Isolation of Vessels.................................................................................................14
3.3.6 Isolation of Tanks.................................................................................................... 14
3.3.7 Isolation of Equipment Containing H2S...................................................................14
3.3.8 Use of Breathing Apparatus....................................................................................15
3.3.9 Immobilising Devices..............................................................................................15
3.4 General Exceptions....................................................................................................... 15
3.5 Precautionary Considerations for Isolation....................................................................15
3.6 Typical Isolation and De-isolation Process....................................................................17
Figure 1 Process Equipment Isolation Process...................................................................17
Appendix 1 Positive Isolation Arrangements...........................................................................20
Appendix 2 Abbreviations........................................................................................................ 25
Appendix 3 Tank Pressure / Vacuum Valve Changeout...........................................................26
Appendix 4 Reference Material............................................................................................... 30
Page 5 PR-1076 - Isolation of Process Equipment Printed 14/07/17
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
1 Introduction
1.1 Background
Whenever process plant, equipment or systems require to be taken out of service for
major maintenance, repair or modification, then positive mechanical isolations shall be
provided between the process plant, equipment or system and any potential hazardous
energy source. Positive Mechanical Isolations requires the insertion of a spade / blind
in the line, or the removal of a spool (if required), downstream of the last tight isolation
valve to physically isolate the potential energy source.
IMPORTANT: A double block and bleed arrangement on its own is not
considered positive mechanical isolation without the insertion of a spade /
blind.
1.2 Purpose
The purpose of this procedure is to provide a safe and consistent method for the
isolation of process equipment prior to and during maintenance / modification / repair.
1.6 ALARP
ALARP is the acronym for As Low As Reasonably Practicable which simplified means,
reducing the risk to a level at which the cost and effort (time and trouble) of further risk
reduction are grossly disproportionate to the risk reduction achieved. Full Compliance
to PDO Standards and Procedures is a key element in achieving ALARP.
For more details refer to ALARP Definition
3.1 Scope
This procedure covers the mandatory administration and mechanical isolation of
process equipment prior to maintenance or engineering work.
For major maintenance or engineering work the minimum requirement for process
equipment shall be;
shut down;
depressurised to atmospheric pressure;
drained and flushed (if required);
freed of flammable or toxic gases
Positive isolation shall be applied once the above have been completed between any
adjacent systems that may, or may not, remain live during the work.
3.2 Terminology
Systems containing
flashing liquids above
ANSI 300, (Note 4) i.e.
ANSI 600 and above.
Examples:
As a pre-cursor for major work;
Breaking flanges for draining of depressurised systems;
Insertion of blinds between flanges on depressurised systems;
Working on instrumentation lines.
NOTE: For Minor work the valve isolation will require to be appropriate to address the
risk i.e. double block and bleed for H2S or pressurised lines, and demonstrated tight.
The electrical, air, steam, hydraulic or other source of energy to the moving machinery,
both flow and return circuits, shall be isolated from the drive unit and the drive unit
secured immobile before work commences.
Isolation of moving machinery from process fluids shall be accomplished by tight
valves and spades or blinds on the equipment side of inlet and outlet lines in order that
maintenance may be carried out while the surrounding facilities remain live. Where
H2S is present in the process stream double block and bleed and swung blind is the
minimum mandatory requirement.
Machinery brakes and brake locks are to be applied and the clutch (if applicable) is to
be disengaged.
Spades / blinds shall be installed on the downstream side of the inlet block
valve and the upstream side of the outlet block valve. Where practical these
spades / blinds should be mounted directly on the flange. Where H 2S is present
in the process stream double block and bleed and swung blind is the minimum
mandatory requirement. Non-compliance shall be in accordance with PR-
1001e Operations Procedure Temporary Variance.
NOTE: Refer to Table 1 for recommendations regarding isolation requirements.
Adequate isolation and purging shall be proven by a direct measurement (using gas
detector) for both hydrocarbons and the toxic component concerned (usually H 2S).
Further work such as opening the equipment for inspection will be carried out wearing a
personal H2S monitor and escape set. Refer to PR-1148 Entry into a Confined Space
for conditions allowing entry into a confined space.
10) Actuated valves shall only be used as part of the positive isolation if the fail
safe condition is closed and all motive power to the valve has been physically
disconnected from the actuator.
WARNING: Reliance on switches shall not be acceptable under any
circumstances.
11) Double block and bleed arrangements provide positive isolation when used in
conjunction with spades or blinds.
Where the insertion of spades and blinds in conjunction with double block and
bleed is considered impractical i.e. not possible to break containment or
suitable spading and blinding locations not available, the use of the double
block and bleed may be authorised by the Production Coordinator provided a
variance is raised in accordance PR-1001e Operations Procedures
Temporary Variance.
For minor work, such as replacing a faulty instrument on a vessel a single
demonstrated tight valve may be allowed if authorised by the Production
Coordinator. For toxic and high pressure applications double block and bleed
shall be considered a minimum requirement. Where the piping and valve
arrangement of process equipment does not allow this to be met a variance
shall be raised in accordance with PR-1001e Operations Procedures
Temporary Variance. In addition the work shall be completed during a working
shift, all valves employed for isolation shall be demonstrated tight and the
work site shall not be left unattended while the work is in progress.
For work of longer duration or where fittings and accessories remain removed
for an appreciable period, e.g. overnight or longer, spades or blinds shall be
employed to provide positive isolation.
12) For long term 1 isolations where a piece of equipment, or a system, is taken out
of service for a considerable period, e.g. months, yet the adjacent plant
remains live, it is essential that proper records are kept. (e.g. spade / blind /
valve checklist) and a record kept of the status of the isolation and its
continuing integrity. This should be carried out on an Extended Period Isolation
and verified regularly.
Such isolations shall be audited and checked for integrity at a frequency
defined by the Production Coordinator.
13) All process isolations shall be recorded on the Process Isolation Wall.
14) All electrical isolations must be done in accordance with SP-1108 - Electrical
Safety Operational Procedures.
The most important rule for isolation of equipment is Stick to the Procedures. For
guidance, the schematic diagrams in Appendix 1 should be used for reference to
typical isolation arrangements.
1
Depending on the type of long term isolation moth balling may be considered.
Page 16 PR-1076 - Isolation of Process Equipment Printed 14/07/17
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
1. The Permit Applicant Shall complete the relevant sections of the PTW certificate
and define the isolation requirements on an As Built drawing (PEFS).
The marked up As Built drawing and the PTW shall be submitted to the
Responsible Supervisor.
2. The Responsible Supervisor shall review and discuss the PTW and isolation
requirements with the Permit Applicant. The positive isolation proposed on the
marked up As-Built drawing shall comply to this procedure and SP-1125
Specification for the Isolation of Process Equipment. Where compliance has been
demonstrated the PTW shall be authorised by the Responsible Supervisor.
3. Isolations that do not comply with this procedure shall require to have a variance
raised against them in accordance with PR-1001e Operations Procedures
Temporary Variance. The Production Supervisor and the Permit Applicant shall
agree the minimum isolation that can be used to address the risks. The Risk
Assessment and the variance shall be reviewed, endorsed and authorised by the
DTL and Operations Manager before further work can be planned.
4. The authorised PTW with the marked up As Built drawing shall be handed to the
Permit Holder who shall give them to the Area Authority.
The Area Authority shall complete the Mechanical Isolation Certificate from the
approved positive isolation on the As Built drawing. isolation 2 as detailed on the
Mechanical / Electrical Isolation Certificate authorised by the responsible
Supervisor.
IMPORTANT NOTE: No PTW shall be validated by Area Authority until the
required isolation process is completed.
Mechanical isolations that are to be put in place shall be listed on the Mechanical
Isolation Certificate or Mechanical Isolation Continuation Sheet and attached to the
PTW. These certificates shall be used to verify that all mechanical isolations have
been removed.
NOTE: Electrical and Safeguarding Instrumentation isolations are recorded on
separate Certificates and Forms and are attached to the PTW accordingly..
Positive isolation shall require having spades or blinds / spectacle blinds placed
into the lines. This shall involve breaking pipework at flanges and shall be recorded
in a specific procedure / method study for the work.
All precautions and safety points shall be recorded in the Safety Plan before any
breaks are made to the system / equipment integrity
5. The Area Authority shall witness all gas freeing and gas testing operations.
The work required to be undertaken can be progressed as soon as the isolation has
been established, checked and the PTW is issued.
The Area Authority shall validate the PTW and hand it to the Permit Holder to
undertake the work.
6. If the equipment is required to be test run this should be carried out under a De-
Isolation for Test (DFT) procedure using the reverse side of the Mechanical and /
or Electrical Isolation Certificates
2
All isolated valves, spades, blinds etc, shall be tagged with the 3 Part Tag. The 2 nd part of the
tag shall be attached to the PTW and the 3 rd part of the tag shall be placed on the PTW board.
The valve spade etc, should be secured with pro-lock fittings.
Page 18 PR-1076 - Isolation of Process Equipment Printed 14/07/17
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
7. Depending on the length that the isolations will be applied, integrity checks shall be
defined. The integrity checks shall be carried out by the Area Authority and
Production Supervisor who will ensure that the isolations are correct and intact.
The positive isolation shall be checked before the PTW is revalidated.
Any violations shall be reported to Production Coordinator and a fountain
Incident raised. The work will be stopped until an investigation has been
carried out.
8. On completion of all works, commissioning and testing the process equipment can
be de-isolated3. The de-isolation should be checked off against the Mechanical
Isolation Certificate and the marked up As-Built drawings.
9. When the de-isolation is completed by the Area Authority the PTW can be closed
out by the Permit Holder.
3
This includes de-spading and re-instating blinds / spectacle blinds into their operating
positions.
Page 19 PR-1076 - Isolation of Process Equipment Printed 14/07/17
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
Appendix 2 Abbreviations
The following abbreviations are used in this Procedure.
ANSI American National Standards Institute
CDFP Corporate Discipline Focal Point
CFDH Corporate Functional Discipline Head
DFT De-isolated for Test
EPI Extended Period Isolation
ESOP Electrical Safety Operational Procedures
LC Locked Closed
LO Locked Open
NC Normally Closed
NO Normally Open
PEFS Process Engineering Flow Schematic
A man basket (intrinsically safe) shall be provided with rated lifting strops to
evacuate causalities from the tank top in emergency.
3. Preparation for Undertaking the Work
Permit to Work
The Permit Applicant and Responsible Supervisor shall comply with PR-1172
Permit to Work System and carryout a site inspection.
The Permit Applicant shall prepare an HSE Job Plan and a Rescue Plan which
shall be attached to the PTW.
A marked-up Process and Engineering Flow Scheme shall be completed to
indicate all isolations.
Tools and Spares
A new gasket, bolts, nuts and washers shall be procured for the PVV and
bagged ready for use.
Spanners and a suitable torque wrench for removing and replacing bolting.
Scrappers and brass wire brushes for cleaning and preparing the flange joint.
Solvents for cleaning (WD40) may be used provided they are suitable for the
application. Absorbent cloths for cleaning the area and mopping small spills.
All tools for the work shall be bagged and a check list provided to enable
accounting to be carried out on completion of work.
The replacement PVV shall be checked to ensure it is correct for the
application and has been tested accordingly. The flanges of the replacement
PVV shall be protected prior to lifting to the tank top.
Safety Equipment
The SCBAs and air lines for the positive pressure hoods will require to be
carried or lifted to the tank top.
Personnel working on the tank top shall be issued with Emergency Escape
Hoods for evacuation.
Lifting Equipment
A suitably rated (25ton) with sufficient jib extension will be located, preferably
up wind of the operation, on site. Suitably rated slings shall be provided to lift
the old and replacement PVV during changeout.
NOTE: Gas monitoring shall be carried out before starting the crane and
continuously throughout the operation when the crane engine is running.
Permitry
If the tank is in H 2S sour service all personnel involved in the operation shall
have an in date H2S certificate.
Personnel using breathing apparatus (SCBA) must be certificated.
SCBA or positive pressure hoods shall require to be worn by all personnel
working on the tank top while the operation of changing out the PVV is being
carried out.
Preliminary Work Prior to Removal / Replacement
a) Close inlet isolation valve and inlet ESD valve (if provided) to the tank that is
to be worked on.
b) Divert the flow to second tank (if available) by opening inlet isolation valve on
the receiving tank.
c) Reduce the level in the tank to be worked on to low low level. Overriding of
safety critical alarms and trips shall be in accordance with PR-1001c
temporary Overriding of Safeguarding Systems
d) Complete manual isolation of oil and drain outlet by closing the isolation valves
on the tank to be worked on. Record the valves and positions on the PEFS.
Update Locked Open / Lock Closed register for any normally Locked Open /
Locked Closed valves that are used. Refer to PR-1086 - Locked Valve Control
Requirements.
e) Isolate the blanket gas line (if provided) on the tank to be worked on.
f) Blow down / vent the residual gas inside the tank to be worked on to via the
flare / vent line or atmospheric vent line, to atmospheric.
NOTE: Use suitable sited pressure gauge on the tank to confirm condition.
g) PTW validated by the Area Authority
h) Hand-over the isolated tank to maintenance team.
4. Removal and Replacement
a) Bring lifting crane on site adhering by all precautions of the PTW. Position the
crane up-wind of the work site if possible.
NOTE: All lifts involving the crane shall be in accordance with the lifting plan
attached to the PTW.
b) Bring Canter on site adhering by all precautions of the PTW. Position the
Canter adjacent to the tank and within safe lifting range of the crane.
c) Make ready the replacement PVV for lifting on the back of the Canter.
d) Position the air line breathing apparatus trolley adjacent the tank. Check all
connectors and check face mask operation.
NOTE: This should be undertaken by the personnel who will require wearing the
equipment. Check the correct operation of the face mask.
e) Using the crane lift the SCBA, air hose(s) and tools to the tank top location.
f) Lift replacement PVV and blind flange to the tank top location.
g) The Area Authority wearing a SCBA shall carry out gas testing.
NOTE: The results of the gas testing shall dictate whether personnel will require to
wear SCBA or positive pressure hoods to perform preparatory work. Continuous gas
testing shall be carried out while preparatory work is being undertaken. Clean the
threads on the bolts securing the PVV. Apply solvent cleaner if required.
h) Unbolt using the appropriate spanners.
WARNING: As the tank will still contain hydrocarbons this operation and the
operation of re-bolting on completion will constitute hot-bolting and will
require the Approval of the Production Coordinator in accordance with SP-
2020 - Flange Connections Bolt Torquing and Tensioning Section 10.
i) Attach lifting strop to the PVV. Attach to crane hook in readiness of lift.
At this point a further gas test should be carried out and positive pressure hoods worn
by all personnel in the direct vicinity of the work. All other personnel should be moved
away from the PVV. A rescuer in a SCBA shall be made ready while the PVV is not in
place. For added safety all work should be undertaken if possible up wind of the
opening.
j) Un-bolt the PVV flange and carefully lift from the tank skin. Move to a suitable
laydown on the tank top.
k) Prepare the replacement PVV for lifting.
l) Clean and prepare the flange for fitting of the new gasket. Fit new gasket.
Page 28 PR-1076 - Isolation of Process Equipment Printed 14/07/17
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 6.0
Petroleum Development Oman LLC Effective: May-12
m) Lift the replacement PVV into position, ensuring that the gasket is not
damaged.
NOTE: If the replacement of the PVV is halted due to damage of misalignment that
shall cause delay, a flange can be fitted providing it is fitted with a low range
pressure gauge to monitor a pressure build up. In conjunction with the pressure
gauge, a tee piece with a valved vent facility should be fitted, with the vent to a
safe area or flare system so that any pressure build up due to temperature change
can be vented safely (See Illustration below). A documented risk assessment shall
be carried out if this method is employed. The risk assessment shall ensure that
regular monitoring of the pressure gauge and venting is carried out by operations
for the duration that this flange is in place.
n) Replace the bolting and torque down to specified torque. See Warning
following Step i).
o) Carryout a gas test around the completed job to ensure tightness. Repeat the
gas test at intervals as working pressure is established and when the tank is at
normal operating pressure.
p) Check and confirm all tools are accounted for. Lift and remove old PVV from
the tank top to the Canter.
q) Carefully lift all remaining equipment from the tank top and secure the site.
r) Hand the tank back to Operations personnel to de-isolate and commission.
UOP7
Custodian of Document Date:
Valved isolation shall be required for all Minor Work. For the purpose of this
procedure minor work will be considered as any intervention that does not require
spools or equipment being removed from a process line (including non-
hydrocarbons), or where there no Hot Work.
Examples:
As a re-cusor for major work;
Breaking flanges for draining of depressurised systems;
Insertion of blinds between flanges on depressurised systems;
Working on instrumentation lines.
NOTE: For Minor work the valve isolation will require to be appropriate to address the
risk i.e. double block and bleed for H2S or pressurised lines, and demonstrated tight.