solution 1 package 3 roads 2 tenders

year comments 2012


month November December
week 48 49 50 51
start date of Consultancy
Contract EGIS 30 month end 22 Nov 23-Nov
kick off meeting 27th December 2012 27-Nov
collection of data
preliminary meeting 5 th December 2012 X
inception report X
reception of the Design
Design check
Design report
modification Design
tender preparation
Bank no objection
Quaterly report n1
Tender procedure
Tender evaluation
Bank no objection
Quaterly report 2
signature of the Contrat
Work Contract start date
Commencement date
Works
Winter period
defect liability period
Quaterly report 3
reception of the Design
Design check
Quaterly report 4
Design report
modification Design
tender preparation
Bank no objection

Tender procedure
Tender evaluation
Bank no objection
signature of the Contrat
Work Contract start date
Commencement date
Works
Winter period
defect liability period
preparation TD1 8 month
defect liability period TD1 10 months
preparation TD2 6 months
defect liability period TD2 5 months
December January February March April
52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

X X

X X

X
2013
April May June July
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

X
August September October November
32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

X
X

X
November December January February March
48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11

X
X
2014
March April May June July
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
2014
July August September October
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
tober November December January February
44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7
2015
February March April May June
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
June July
24 25 26 27 28 29 30 31 32