RawMaterialChargingDetails

Scrap Weight
Material Charging Arching Start Time After
Charged Charging Time Remarks
Bucket every charge
(Ton)

First 17 11.45 PM 11.55 PM

Arching delay due to uneven level of scrap on the top of


Second 11.24 12.35 AM 12.40 AM
furnace roof.

Arching delay due to uneven level of scrap on the top of


Third 10 01.00 AM 1.15 AM
furnace roof.

Fourth

Metallurgy Details

Quantity of Carbon Added 200 KG

Quantity of Lime Added 200 KG

Any other Material Added


Tapping Temp 1700C
Tapping Time 02.06 AM

Carbon (C) 0.44%


Final Chemical composition at the time of taping
Manganese(Mn) 0.84%