Professional Documents
Culture Documents
2G 3G RFQ Document 01122012 Final V4
2G 3G RFQ Document 01122012 Final V4
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 1 of 86
Page 1
87
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 2 of 86
1. Project Scope......................................................................................................................... 5
2. GENERAL HIGHLIGHTS.....................................................................................................6
3. Commercial Guidelines........................................................................................................7
-3.2 License Pooling 10
-3.3 Equipment Price Variation 10
-3.4 Prices validity 10
-3.5 RAN specific requirements 11
3.5.1 All inclusive bundle SW:..........................................................................................11
3.5.2 Purchasing KPI Commitment.................................................................................11
-3.6 Transport specific requirements 12
3.6.1 Data Equipment........................................................................................................12
-3.7 Support specific requirements 12
3.7.1 Spare Parts Management (SPMS)............................................................................12
-3.8 Training 13
-3.9 RAN Proffessional Service 14
4 Terms..................................................................................................................................... 14
-4.1 Cost of Response Preparation 14
-4.2 Response Ownership 14
5 Presentation of proposals..................................................................................................15
6 Evaluation of proposals.....................................................................................................16
7 Terms of presenting proposals.........................................................................................16
8 Milestones............................................................................................................................ 18
9 Disputes................................................................................................................................ 18
10 Termination and Assignment............................................................................................18
11 Network Model for Scenario 1.........................................................................................19
-11.1 General requirements 19
-11.2 2G Network model 21
11.2.1 BTS.......................................................................................................................... 21
11.2.2 BSC.......................................................................................................................... 30
11.2.3 TC............................................................................................................................ 31
11.2.4 TRX upgrade.......................................................................................................... 33
-11.3 3G network Model 33
11.3.1 Node B.................................................................................................................... 33
11.3.2 RNC......................................................................................................................... 37
11.3.3 CE............................................................................................................................ 37
11.3.4 HSPA....................................................................................................................... 38
12 Network Model & requirement for Scenario 2.............................................................38
-12.1 General Requirements 38
-12.2 2G RAN network model 40
12.2.1 General Requirements.........................................................................................40
12.2.2 Radio Parameters.................................................................................................41
12.2.3 Coverage polygon and site data base...............................................................42
12.2.4 2G Radio capacity parameters and traffic mix...............................................43
Page 2
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 3 of 86
12.2.5 Deliverables:.......................................................................................................... 45
-12.3 3G RAN network model 50
12.3.1 General Requirements.........................................................................................50
12.3.2 Radio Parameters.................................................................................................51
12.3.3 Coverage polygon and site data base...............................................................53
12.3.4 Number of subs per Year:...................................................................................54
12.3.5 CS and PS Traffic..................................................................................................54
12.3.6 CE & HSPA............................................................................................................ 55
12.3.7 RNC requirements...............................................................................................56
12.3.8 Deliverables:.......................................................................................................... 56
-12.4 CW network model 60
12.4.1 2G swap and 3G site collocated with 2G.........................................................60
12.4.2 New sites................................................................................................................ 63
13 Hardware specification and Software features.............................................................65
14 OMC & network performance tool..................................................................................68
15 Project Implementation Plan.......................................................................................................68
16 Services Scope.................................................................................................................... 70
-16.1 GENERAL HIGHLIGHTS 70
-16.2 Service classification 71
16.2.1 Calibration............................................................................................................. 72
16.2.2 Planning................................................................................................................. 72
16.2.3 Dimensioning.........................................................................................................73
16.2.4 Site acquisition.....................................................................................................74
16.2.5 Site Survey............................................................................................................. 74
16.2.6 Installation & CW.................................................................................................74
16.2.7 Commissioning and Configuration....................................................................75
16.2.8 Integration............................................................................................................. 75
16.2.9 Drive test................................................................................................................ 75
16.2.10 Optimisation.......................................................................................................... 76
16.2.11 Maintenance Level 2 and Level 3 Support:.....................................................76
16.2.12 First Line Maintenance (FLM):..........................................................................76
16.2.13 Network Operations (NOC)................................................................................77
16.2.14 Supervision:........................................................................................................... 78
16.2.15 Spare Parts Management....................................................................................78
16.2.16 Events handling and capacity extension/Reduction......................................78
16.2.17 Customer complaints...........................................................................................79
16.2.18 Warehousing.......................................................................................................... 80
16.2.19 Dismantling, Packing and Transportation.......................................................80
17 Rollback................................................................................................................................ 80
18 System Acceptance and Penalties...................................................................................80
-18.1 Acceptance procedure80
-18.2 KPI acceptance 81
-18.3 Penalties 81
19 Transmission........................................................................................................................ 81
Page 3
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 4 of 86
20 HUMAN RESOURCE.................................................................................................................... 85
21 Training.................................................................................................................................... 85
22 On job training.......................................................................................................................... 85
23 Exit management plan................................................................................................................ 86
Page 4
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 5 of 86
1. Project Scope
Djezzy has amended the RFQ for Tender for Tender for Supply of HSPA+ Solution
sent on 3rd of November 2011 and Tender for 2G Equipment (Supply/Swap) sent
on the 21st of March 2012. Tendering parties are requested to offer two separate
proposals and quotations for 2G SUPPLY/SWAP and 3G/HSPA+ implementation based
on:
Scenario 1:
CAPEX based modernization; normal quotation approach using fixed BoQ approach
delivered by Djezzy in BoQ Annex 01- 2G modernization BOQ, Annex 02- 3G
RAN & CW BoQ and Annex 03-TX BoQ.
Bidder shall provide dimensioning of necessary network elements as per the defined
network model.
The tendering party shall be responsible for delivering the 3G project in turnkey for
year 1.
The Tendering Party shall provide their own network design for both 2G and
3G for 48 wilaya as per the defined area polygons over the five years.
Page 5
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 6 of 86
Following the provided traffic mix, tendering party will present a proposal
with required number of sites, configuration per site, and site location so as
to satisfy required coverage and capacity needs.
Tendering Party may propose to utilize all or part of the provided site list
according to the defined network model
In case of shutting down any 2G site the tendering party should present the
plots and how traffic of this site will be carried.
The Tendering Party shall provide their own MW backhaul network design for
both 2G and 3G for 48 wilaya over the five years.
2. GENERAL HIGHLIGHTS
The tendering party should fill Annex 21- Compliance Matrix with all
individual clauses, indicating the level of compliance with each clause, and
providing related explanation.
All the quoted equipment must be single RAN capable starting from day one.
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 7 of 86
Network is further split into 6 zones as indicated in Annex 04- Network zone
split, the Evolution of the zones over the years, considering new roll-outs,
has to be done with Djezzy consent. Djezzy reserves the right to change the
zonal definition up on Djezzy requirements.
The Winning party shall provide a live trial of at least 1 BSC, 1TC, NMS and
Two BTSs of configuration (Macro (S222 G + S222 D), Micro S220) within
one month of the tendering party selection date.
The Winning party shall provide a live trial of at least NMS, 1 RNC and Two
NodeB (indoor & DBS) of configuration (S111, CE 256) within One month of
the tendering party selection date.
The wining party should commit on having half of the needed 2G and
3G equipment for year 1 (both scenarios) ready for shipment within
one month of the tendering party selection.
The supplier must ensure the confidentiality of all the data within this RFQ,
the tendering party shall take all the necessary measures to protect and
forbid any security hazard that may affect the confidentiality of the data.
Page 7
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 8 of 86
3. Commercial Guidelines
Tendering parties are requested to use the lowest price catalogue exists in
Vimpelcom group including 2013 contractual discounts as a base line for the
quotation per subsystem in response to this RFQ, keeping in mind that equipment
sub-items that already exist in Vimpelcom Catalogue should be quoted with exactly
similar item codes and description. However if the price used in the last submission
of Tender for Tender for Supply of HSPA+ Solution sent on 3rd of November 2011
and Tender for 2G Equipment (Supply/Swap) sent on the 21st of March are more
economical, the bidder must applied it (linked to the price list) including all
incentives and discounts. The tendering party should add on top of it the new
discounts and incentives in order to be commercially competitive in this RFQ.
Any new item that will be provided by the vendors needs to be highlighted in the
quotation/BoQ shopping list, and the tendering party to provide within one week
after technical/commercial submission a benchmarking exercise for all new line
items to explain/justify the offered price level for these new line items in comparison
to the corresponding items in the catalogue that were providing similar/close
functionality and capacity
For the bidders that have existing group catalogue with VimpelCom in Euro and will
be used in part or in total to answer the scope of this tender, a conversion rate of 1
Euro=1.26USD to be used when submitting the commercial proposal.
The prices for the services part must be quoted in Algerian local currency.
The prices will be fixed for the 2 areas, but the tenders are encouraged to offer
additional incentive flat discounts to be applied on the different areas indicated in
the TCO annex 01- 2G modernisation BoQ, Annex 02- 3G RAN & CW BoQ and Annex
03- TX BoQ.
Page 8
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 9 of 86
to add any kind of missing items or services that it finds necessary to have a full
complete workable solution. The forgetfulness of this quotation will imply the
acceptance of these costs in charge of the winning bidder.
The tendering party commits and declares that its offered products will work
perfectly, also in terms of integrity, in Djezzy operations HW & SW environment and
that, in every case, the same Vendor wont ask additional payments, nor will be
considered excluded from the commitments of this Contract or POs, pleading
misinterpretation, lack, or inadequacy of information relating to Djezzy HW & SW
environment.
For Economical offers submissions (TCO Sheets), Tendering parties are requested to
abide to such templates and formulas, other kinds of format will be rejected, any
update required or errors discovered in such templates need to be reported to
Djezzy procurement during the Q&A window for correction and re-distribution.
Discounts mechanism
Discounts: includes yearly flat aggregated discounts offered on Top of the catalog
base line unit price List and shows the overall discounts for HW & SW per year per
unit item.
Page 9
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 10 of 86
The proposed discounts by the bidders over the TCO life time shall not be linked to
the calendar year of such TCO sheet rather being applicable taking into account the
effective date of the contract as a starting point for TCO discounts application.
Vouchers and Special discounts will not be considered into the commercial
evaluation rather might result into losing scores due to commercial requirements
noncompliance from the bidders side, the Tendering Parties should not offer any
types of discounts beyond the below categories:
Price Book : discounts that have incremental slope one year after the
other.
All the quantity either forecasted per year or will be calculated by the bidders in
line with the requested traffic profiles in the entire RFQ scope and responses, are
only for illustration purposes and will be used to develop the overall commercial
evaluation and ranking for the bidders, meaning that such quantity are not
committed from Djezzy.
Djezzy will have the full freedom to decide where and on which base station (either
2G or 3G) to implement/relocate the purchased all inclusive S/W bundle remotely by
means of NMS with no extra fees charged by the tendering party except if there is
extra professional services requested to be performed from the tendering party side
and acknowledged/accepted by Djezzy.
Tendering party will have the full freedom to monitor the entire active number of
Cell carriers/TRXs on the network level to make sure that it doesnt exceed the
purchased licenses.
Page 10
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 11 of 86
The Prices resulting as an outcome to this tender shall survive the expiry of the
contract and shall not be subject to any variation due to increases in production
costs, fluctuations in exchange rates and the living expenses or any reason, or
inflation indicator, even in case of contract renewals.
Vendors to commit in general that the prices in Djezzy moving forward for all
technologies included into the scope of this tender will not be subjected to any price
increase regardless of the expiry of any contractual agreement that includes the
discounts and incentives mutually agreed between Djezzy and the winning supplier
In the presence of significant price reductions in the market, the Prices set out in
the contractual agreement following this tender, although they had not to rise,
however, must be renegotiated downward if Djezzy requested it, in other words,
Djezzy reserves the right to re-negotiate the prices set forth as an outcome to this
tender and its related contractual agreement on annual basis and based on
benchmarking process with fair market price.
Page 11
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 12 of 86
The all-inclusive bundle is a maximum fixed amount of $ value that Djezzy will pay
per Cell Carrier for 3G or Active TRX for 2G for purchasing any type of H/W
activation S/W ( i.e. LTU, RTU,..etc) or SW features and covers all known and
unknown RAN and OSS S/W for the current and all future SW release, including the
S/W upgrade fee itself from one Version to another.
In the Free design BoQ templates, Annex 01- Network modernisation BOQ
021212_Free Design.xlsx, Annex 02- 3G RAN CW BoQ 021212_Free Design.xlsx
and Annex 03- TX BoQ 021212_Free Design.xlsx, the vendor shall provide a yearly
purchasing KPI for CapEx, CapEx Maintenance and OpEx as detailed in the sheets.
Support fees to be provided Free of Charge for first 3 years starting acceptance
date for any new purchased equipment.
The support should include only the SW support part (As H/W is covered under
Page 12
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 13 of 86
SPMS part) including but not limited to help line, software update, Technical
Support, report handling and on-site support. Detailed support description and SLA
is explained in the technical/Support document
The support cost should not include the R&R cost as it is part of the SPMS
For Support pricing rules, the tendering party should provide the following:
If the pricing rules in a year resulted is hitting the CAP value, the cap value will
apply, otherwise, the pricing rule applies for the support calculations
The bidders are requested to quote for spare parts management program (SPMS),
with the following guide lines:
- Each vendor will own the spare parts needed for the provided subsystem
- Each vendor will be responsible of keeping the spare log updated and repaired
and provide the needed warehousing facility in way that is coherent with the
SLA requirements if any
Page 13
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 14 of 86
3.8 Training
Tendering Party is requested to provided Free Of Charge training all over the RFQ
period and recommended by the tendering party as mandatory know how skill to be
gained by Djezzy personnel to be able to get familiar with the technoclogy offered
by the vendor either from design, planning, operation and maintenance,...etc
prospectives
For additional training that might be requested, the tendering parties are requested
to classify the training and the corresponding tariff into the below category:
Price/Trainer Per day in case training venue is managed by Djezzy; and such
fee to be inclusive of all travel/living and accommodation expenses for the
trainer.
Page 14
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 15 of 86
4 Terms
Response Errors
Recipients are solely responsible for any errors or omissions contained in their
responses. If the Recipient identifies a misstatement, the Recipient may at its effort
and expense submit a replacement Response provided the replacement Response
fully complies with the RFP and provided the replacement Response is delivered
within the Closing Date and Time. Recipients will not be allowed to alter Response
after the Closing Date and Time. However, if a Recipient identifies a material
misstatement after the deadline for submission, the Recipient must notify the
Page 15
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 16 of 86
Operator in writing. In the event the Response contains an error in cost, time or
other calculations, quoted items shall prevail. In case of inconsistencies between
various sections in the response the Operator retains the right to select the option,
which shall be applied and valid for the Response.
6 Presentation of proposals
The Recipients proposals should enclose the following documents signed and
sealed by the Recipient on all papers:
General Part:
2 CDs with the complete RFP, Price list is MS Excel, Response in WinWord,
Compliance matrix in MS Excel. Supporting Technical documentation in WinWord or
PDF format.
02 CDs with the complete RFP separating the financial part from technical part,
Price list isMSExcel, Response in WinWord, Compliance Matrix in MS Excel.
Supporting Technical documentation in WinWord or PDF format,2 detailed BOM
files ,one unquoted (addressedto the technical )and another one quoted (to the
procurement ).the file format should be in Excel.
Page 16
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 17 of 86
7 Evaluation of proposals
The present RFP does not bind the Operator in any way whatsoever. The Operator
for the latter reserves itself the right to study the different files submitted by the
Recipients and to
conclude contract negotiations for the object of this RFP in its totality or parts
thereof, with any, several or no company, as it sees fit. The Operator also retains the
right to only enter a contract for parts of the offered solution.
Moncef AHLOUCHE
Page 17
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 18 of 86
Mr : Moncef Ahlouche
Additional information
Page 18
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 19 of 86
9 Milestones
Milestone Dates
10 Disputes
The Parties shall attempt to amicably resolve any dispute in connection with this
Agreement. If the Parties cannot resolve any dispute by mutual agreement within
sixty (60) days following a Partys reception of a written dispute notification by the
other Party, then the dispute shall be finally settled under the Rules of Conciliation
and Arbitration.
The Operator shall have the discretionary right to assign at any time and with
immediate effect the agreement with the Recipient to any other person or entity,
public or private.
Page 19
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 20 of 86
The Operator shall have the right to disqualify any vendor immediately if the
submitted offers didnt comply with any of the above terms and conditions.
c. Critical boards for all quoted equipments must be redundant. (BSC, RNC &
OSS).
d. For spare, tendering party should consider 10% from BSC/RNC equipment
and 7% from BTS/NodeB equipment.
h. In the below section, the network model is provided for each zone. The zones
are defined in Annex 04- Network zone split Site type definition mentioned
in the network model is provided in Annex 05- Site type.
Page 20
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 21 of 86
i. The tendering party is requested to quote only the extra needed equipment
or services for 2G in case of:
j. The tendering party is requested to quote only the extra needed equipment or
services for 3G in case of:
k. For TRX upgrade, the tendering party should assume 4 TRX per module to be
active.
l. For BSC configuration, the tendering party should consider the below details
PCU
Abis TC
TRXs Traffic Cells BHCA (PDCH
connection connection
MCS9)
<=180 <=27 348
Low <=400 <=100 <=480000 30
0
<=320 <=32 686
Medium <=800 <=200 <=680000 60
0
High >1000 >4500 >200 >960000 >60 >45 1024
m. For RNC configuration, the tendering party should consider at least 2010
Mbps and 21100 Erlang simultaneously.
n. The tendering party should consider 80% utilization as dimensioning rule for
RNC, BSC, TC and OSS. (Extra 20% should be considered as margin to
Page 21
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 22 of 86
12.2.1 BTS
The table below includes the incremental number of sites to be swapped over five
years:
Zone Indoor 6 86 0 39 52
1
Existing 2G Micro 2 2 8 15 50
Outdoor 13 9 0 12 23
Indoor 0 0 28 20 0
Outdoor 0 0 8 7 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 0 0 0 0
3G
Outdoor
DBS 0 0 2 0 0
Indoor 141 20 0 0 0
Outdoor 54 7 0 0 0
Existing 2 G wich
Indoor
will be collocated
DBS 0 0 0 0 0
with 3G
Outdoor
DBS 0 3 0 0 0
Outdoor 0 0 0 39 35
Page 22
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 23 of 86
Indoor
DBS 0 0 0 8 7
day 1
Outdoor
DBS 0 0 0 1 1
Zone Indoor 11 21 0 56 73
2
Existing 2G Micro 26 0 8 48 84
Outdoor 2 2 0 15 22
Indoor 0 153 16 27 0
Outdoor 0 18 3 6 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 8 0 0 0
3G
Outdoor
DBS 0 1 1 0 0
Indoor 102 27 0 0 0
Outdoor 29 6 0 0 0
Existing 2 G wich
Indoor
will be collocated
DBS 0 0 0 0 0
with 3G
Outdoor
DBS 0 4 0 0 0
Page 23
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 24 of 86
Indoor
DBS 0 0 0 5 4
Outdoor
DBS 0 0 0 3 3
Zone Indoor 4 18 0 40 50
3
Existing 2G Micro 53 3 8 90 153
Outdoor 6 0 0 14 7
Indoor 0 237 95 21 0
Outdoor 0 86 31 8 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 15 0 0 0
3G
Outdoor
DBS 0 2 6 3 0
Indoor 39 21 0 0 0
Outdoor 16 8 0 0 0
Existing 2 G wich
Indoor
will be collocated
DBS 0 0 0 0 0
with 3G
Outdoor
DBS 0 0 0 0 0
Indoor 0 0 0 4 6
DBS
Page 24
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 25 of 86
Outdoor
DBS 0 0 0 1 1
Indoor 3 133 0 40 33
Existing 2G Micro 21 0 4 22 50
Outdoor 0 32 0 26 22
Indoor 0 0 175 0 0
Outdoor 0 0 73 0 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 0 6 0 0
3G
Outdoor
DBS 0 0 7 0 0
Indoor 95 15 0 0 0
Zone
4 Outdoor 47 8 0 0 0
Existing 2 G wich
Indoor
will be collocated
DBS 0 0 0 0 0
with 3G
Outdoor
DBS 0 1 0 0 0
Indoor 0 0 0 78 123
Outdoor 0 0 0 34 52
Outdoor
DBS 0 0 0 1 1
Page 25
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 26 of 86
Indoor 74 11 0 66 40
Existing 2G Micro 18 0 4 25 50
Outdoor 20 8 0 19 7
Indoor 0 69 110 24 0
Outdoor 0 7 23 5 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 2 4 3 0
3G
Outdoor
DBS 0 2 3 0 0
Indoor 8 22 0 0 0
Zone
5 Outdoor 3 5 0 0 0
Existing 2 G wich
Indoor
will be collocated
DBS 0 0 0 0 0
with 3G
Outdoor
DBS 0 0 0 0 0
Outdoor 0 0 0 35 29
Outdoor
DBS 0 0 0 2 1
Page 26
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 27 of 86
Micro 15 0 5 18 31
Outdoor 16 6 0 11 5
Indoor 0 0 64 24 0
Outdoor 0 0 17 7 0
Existing 2 G wich
Indoor
is collocated with
DBS 0 0 3 0 0
3G
Outdoor
DBS 0 0 1 0 0
Indoor 35 24 0 0 0
Outdoor 8 6 0 0 0
6
Existing 2 G wich
Indoor
will be collocated
DBS 0 4 0 0 0
with 3G
Outdoor
DBS 1 0 0 0 0
Outdoor 0 0 0 42 38
Outdoor
DBS 0 0 0 7 2
The table below includes the incremental number of 2G sites to be swapped from
Indoor to outdoor over five years:
Page 27
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 28 of 86
Swap from
Zone Existing 2 S4
Indoor to 5 2 10 8 8
1 G 44
Outdoor
Swapfrom
Zone Existing 2 S4
Indoor to 5 2 10 8 8
2 G 44
Outdoor
Swap from
Zone Existing 2 S4
Indoor to 5 2 8 5 5
3 G 44
Outdoor
Swap from
Zone Existing 2 S4
Indoor to 6 2 8 10 5
4 G 44
Outdoor
Swap from
Zone Existing 2 S4
Indoor to 5 2 5 12 10
5 G 44
Outdoor
Swap from
Zone Existing 2 S4
Indoor to 5 2 10 8 5
6 G 44
Outdoor
Total 31 12 51 51 41
The table below includes the incremental number of the new sites over five years:
Topolog
Zone Year1 Year2 Year3 Year4 Year5
y
Zone 1 Indoor 95 86 25 35 32
Page 28
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 29 of 86
Outdoo
r 34 35 1 12 10
Indoor 56 61 8 19 16
Zone 2 Outdoo
r 83 74 14 25 23
Indoor 33 32 5 19 15
Zone 3 Outdoo
r 58 38 12 25 23
Indoor 29 30 7 12 11
Zone 4 Outdoo
r 55 46 13 19 18
Indoor 48 53 6 19 16
Zone 5 Outdoo
r 65 63 9 22 18
Indoor 31 34 8 9 8
Zone 6 Outdoo
r 56 62 20 21 21
12.2.2 BSC
The table below shows the incremental number of BSCs (new and to be swapped)
over five years:
Page 29
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 30 of 86
Low 1 1 1 1 1
BSCs Mediu
Zone 1 Existing m 1 1 2 2 1
High 3 5 4 4 4
Low - - - - -
BSCs Mediu
Zone 2 Existing m - - - - -
High 6 6 6 7 6
Low - 1 1 1 1
BSCs Mediu
Zone 3 Existing m 4 5 4 4 4
High 2 5 5 5 5
Low 1 2 2 2 1
BSCs Mediu
Zone 4 Existing m 4 6 5 5 6
High 1 2 2 2 2
Mediu 1 2 1 2 1
Page 30
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 31 of 86
Existing High 5 6 5 5 6
Low 1 2 1 1 2
BSCs Mediu
Zone 6 Existing m 1 2 2 2 1
High 3 4 3 3 4
12.2.3 TC
The table below shows the incremental number of TCs (new and to be swapped)
over five years
Creation
Zone 1 (Ater) 195 61 66 30 28
MSC
Locations 6 6 6 6 6
Creation
Zone 2 (Ater) 285 75 81 22 26
MSC
Locations 6 6 6 6 6
Page 31
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 32 of 86
Creation
Zone 3 (Ater) 121 73 87 13 80
MSC
Locations 4 4 4 4 4
Creation
Zone 4 (Ater) 121 20 50 21 11
MSC
Locations 7 7 7 7 7
Creation
Zone 5 (Ater) 349 53 68 14 19
MSC
Locations 6 6 6 6 6
Creation
Zone 6 (Ater) 136 18 18 1 4
MSC
Locations 7 7 7 7 7
Page 32
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 33 of 86
The table below includes the incremental number of the TRX upgrade over five
years
12.3.1 Node B
The table below includes the incremental number of the nodeB over five years
Zone 1 Indoor 28 20 0 0
DBS 2 0 0 0
Page 33
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 34 of 86
Outdo
modernized 2G
or 0 44 7 0 0
DBS 0 10 3 0 0
Indo
or 0 0 0 127 114
DBS 0 0 0 9 8
Indo
or 153 16 27 0 0
3G collocated with current
Outdo
existing 2G
or 18 3 6 0 0
DBS 9 1 0 0 0
Indoor 0 102 27 0 0
DBS 0 7 4 0 0
Outdo
5G starting from day 1
or 0 0 0 27 23
DBS 0 0 0 8 7
Page 34
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 35 of 86
Indo
or 237 95 21 0 0
3G collocated with current
Outdo
existing 2G
or 86 31 8 0 0
DBS 17 6 3 0 0
Indo
or 0 39 21 0 0
3G collocated with
Outdo
Zone 3 modernized 2G
or 0 13 8 0 0
DBS 0 3 0 0 0
Indo
or 0 0 0 73 94
DBS 0 0 0 5 7
DBS 13 0 0 0
Outdo 0 40 8 0 0
or
Page 35
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 36 of 86
DBS 0 7 1 0 0
Indo
or 0 0 0 78 123
5G starting from day 1 Outdo
or 0 0 0 34 52
DBS 0 0 0 6 9
3G pure new site DBS 0 0 4 2 2
Total 0 403 28 120 186
Indoor 69 110 24 0 0
3G collocated with current existing
Outdoor 7 23 5 0 0
2G
DBS 4 7 3 0 0
Indoor 0 8 21 0 0
3G collocated with modernized 2G Outdoor 0 2 5 0 0
Zone 5
DBS 0 1 0 0 0
Indoor 0 0 0 160 135
5G starting from day 1 Outdoor 0 0 0 35 29
DBS 0 0 0 10 9
3G pure new site DBS 0 0 4 2 2
Total 80 151 62 207 175
Indoor 29 24 0 0
3G collocated with current existing
Outdoor 9 7 0 0
2G
DBS 3 0 0 0
Indoor 0 35 24 0 0
3G collocated with modernized 2G Outdoor 0 8 6 0 0
Zone 6
DBS 0 1 4 0 0
Indoor 0 0 0 164 147
5G starting from day 1 Outdoor 0 0 0 42 38
DBS 0 0 0 11 10
3G pure new site DBS 0 0 4 1 1
Total 0 85 69 218 196
Page 36
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 37 of 86
12.3.2 RNC
The table below includes the incremental number of the RNC over five years
Zone 1 0 1 1 0 1
Zone 2 1 0 2 0 0
Zone 3 1 0 2 0 0
Zone 4 0 1 1 0 1
Zone 5 1 0 1 0 1
Zone 6 0 1 1 0 1
Total 3 3 8 0 4
The tendering party need to calculate the needed RNC according to their capacity
considering the provided data in section 3.1.
12.3.3 CE
- All supplied CE Hardware should support HSPA+.
- All NodeB S111, should have in terms of HW 256 CE for Uplink and 256 CE
for Downlink, SW 128 CE for uplink and 128 CE for downlink.
- All NodeB S222, should have in terms of HW and SW 256 CE for uplink and
256 CE for downlink.
Page 37
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 38 of 86
- All NodeB S333, should have in terms of HW and SW 356 CE for uplink and
356 CE for downlink.
- All above CE configuration are for R99 and for HSPA CE should be considered
separately.
12.3.4 HSPA
The HSPA will be deployed starting from year 1 as indicated in below table, and it
represents the HSPA activation for total cumulative installed Node B per year.
The Tendering Party should consider the network model given in this section as a guideline for the
Djezzy quotation of his response to this RFQ.
Vendor is free to propose any or all enhancements in the design to optimize the investment &
returns.
In case of shutting down any 2G site the tendering party should present the plots and how traffic
Page 38
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 39 of 86
All the supplied plots should be based on updated digital maps with a release of at least 2011 and
a resolution of 5m (dense urban), 20m (urban), and 50m (rural).
Propagation model should be accurate and tuned model from similar clutter/market.
DJEZZY withholds the rights to review/change the design requirement and inputs at any time and
the tendering party must comply and provide the complete design as per new Djezzy
requirements and inputs.
For spare, tendering party should consider 10% from BSC/RNC equipment and 7% from
BTS/NodeB equipment.
Critical boards for quoted equipment must be redundant (BSC, RNC & OSS) 25% additional
software licences for all dimensioning elements should be provided FOC for purpose of re-homing
activities.
The Tendering party should provide a dynamic License management solution, that is to say: the
purchased licenses can be used or moved dynamically between BSCs/RNCs (for example: in case
for BTS re-homing).
The tendering party shall stock 5% of each phase equipments (this is 5% equipment are free of
charge), In case of Performance problems, the tendering party shall be given 48 hour to resolve all
the issues and rectify any design or parameters mis-adjustments, after which the tendering party
shall use this Extra 5% in order to comply immediately with Djezzy requirements at no extra cost
on Djezzy.
Page 39
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 40 of 86
For the link budget and coverage calculation the tendering party should not
consider the TRX power sharing feature.
Acceptance test agreed upon (in Chapter 7 provided within the Tender for
Supply of HSPA+ Solution sent on 3rd of November 2011 and in section
System Acceptance and penalties and Annex C - 2G new site KPIs
definitions submitted within the Tender for 2G Equipment (Supply/Swap)
sent on the 21st of March 2012) and between DJEZZY and the Tendering
Party shall be carried out by the tendering party under DJEZZY supervision
and control to accept the technical/functional specifications (HW/SW),
features, capacity and coverage requirements.
Page 40
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 41 of 86
Probability of
95% 95% 95% 90% 90%
coverage
Standard Deviation
8 dB 8 Db 8 dB 7 dB 7 dB
Margin
Interference Margin 3 3 3 3 3
Minimum Desired
-65 dBm -65 dBm -75 dBm -75 dBm -89 dBm
Signal strength
Frequency band 900/1800 MHz 900/1800 MHz 900/1800 MHz 900/1800 MHz 900/1800 MHz
Diversity Gain 3 3 3 3 3
Cable Loss 3 dB 3 dB 3 dB 3 dB 3 dB
UE Antennas Gain 0 0 0 0 0
GSM 900 : 33 dBm GSM 900 : 33 dBm GSM 900 : 33 dBm GSM 900 : 33 dBm GSM 900 : 33 dBm
Mobile power
DCS 1800: 30 dBm DCS 1800: 30 dBm DCS 1800: 30 dBm DCS 1800: 30 dBm DCS 1800: 30 dBm
MS RX Sensitivity -102 dBm -102 dBm -102 dBm -102 dBm -102 dBm
Body loss 3 dB 3 dB 3 dB 3 dB 3 dB
Penetration loss 20 dB 18 dB 15 dB 8 dB 5 dB
(*) these values will be used for link budget calculations, for coverage simulation,
Page 41
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 42 of 86
- The tendering party shall design the below south road (defined in the above
file) on turnkey basis from design till the acceptance of the last site.
- RN1-South
- RN3_South-1
Page 42
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 43 of 86
- RN3_South-2
- RN6_South
- RN47
- RN50
- RN51
- RN52
On the top of the current coverage/capacity/quality Sites, The tendering party shall
consider below additional requirement.
The tendering party will use the following traffic forecast and radio capacity
parameters for network design and dimensioning:
Page 43
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 44 of 86
The detailed traffic forecast per cell is given in the Annex 10-2G Traffic forecast
Cells
Page 44
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 45 of 86
- The tendering party has full flexibility in the split of extra capacity needs,
considering all associated constraints and cost (number of antennas per cell, load
on the mast ...). Historically, Djezzy has used, for extra capacity need, 40 % new
sites and 60% upgrade TRX.
For BSC dimensioning, additional to the above inputs, the tendering party shall
consider below BSC average traffic profile
PCU
Abis TC
TRXs Traffic Cells BHCA (PDCH
connection connection
MCS9)
<=180 <=27 348
Low <=400 <=100 <=480000 30
0
<=320 <=32 686
Medium <=800 <=200 <=680000 60
0
High >1000 >4500 >200 >960000 >60 >45 1024
13.2.5 Deliverables:
- The Tendering Party is requested to perform the design only for all polygons
as specified in Section Coverage polygon and site data base.
- The tendering party shall deliver the list of all proposed network elements
(BoM) including detailed description of configurations for 5 year.
- The used features/equipments should have been used and field proven for at
least 3 Months.
- The Tendering Party shall carry out the simulation of coverage and generate
prediction maps of the coverage polygons that have been specified.
Page 45
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 46 of 86
- The tendering party should provide the references for used digital maps with
their resolution per wilaya.
The tendering party is requested to provide the propagation model coefficient used
- The Tendering Party should clearly state the benefits and give the gain in terms of cost of the
introduction of any feature.
- The Tendering Party should share all design assumptions and parameters on the planning tool
with DJEZZY.
- The Tendering Party should share all dimensioning assumptions used for TRX upgrade and
capacity sites.
- The tendering Party should provide in excel format the Longitude and Latitude of the proposed
sites (swap and new) and the Radio Configuration for every sites in terms of: Antenna type,
Antenna Azimuth, Antenna Height, Antenna Tilt, output power and different Channels power,
EIRP
- The Tendering Party should provide cell configuration (equivalent TRX not module) over the five
years indicating also number of Time slot dedicated for PS traffic.
- The Tendering Party shall provide an UL and DL (900/1800 MHZ) Link-budget detailed calculations
excel sheet format with all formulas and for all morphologies and all available configurations
(1TRX, 2TRX, 3TRX ...).
- The tendering party shall deliver complete calculations capacities (TRX, BSC, TC, Abis, Ater, A,
Gb).
Page 46
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 47 of 86
DU U SU RU
MAPL (dbm)
Cell range (m)
Design level (dbm)
- The tendering Party shall provide the number of designed BTS, BSC per
wilaya
- The tendering Party shall provide the number of designed BTS, BSC for
roads coverage
- The tendering Party shall provide the number of TRX upgrade (equivalent
TRX not module), BTS (all proposed configuration), BSC, Ater, Gb and TC to
absorb the forecasted traffic wilaya per year.
Page 47
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 48 of 86
TRX upgrade
BTS XXX
BSC
TC
Ater
Gb
Page 48
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 49 of 86
- RxLEV plot
- C/I plot
- For each covered area the tendering party to provide a separate Morpho plot
(with no coverage) for each of the required areas.
Each of the above plots should be submitted for the 48 wilayas and for all
requested roads.
In addition to the soft copy in Mapinfo format, all plots should be submitted in
A1 format.
The name of the plot, name of the Wilaya/Road, service levels and borders
should be clear in all plots.
All plots should be signed by the Tendering Party officer empowered to bind
the Tendering Party to the provisions of this RFQ and any contract awarded
pursuant to it.
Page 49
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 50 of 86
The tendering party should use one carrier (5 MHz) for the designs provided
for year 1.
Acceptance test agreed upon (in Chapter 7 provided within the Tender for
Supply of HSPA+ Solution sent on 3rd of November 2011) between DJEZZY and the
Tendering Party shall be carried out by the tendering party under DJEZZY
supervision and control to accept the technical/functional specifications
(HW/SW), features, capacity and coverage requirements.
Page 50
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 51 of 86
Page 51
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 52 of 86
(*) This value will be used for link budget calculations, for coverage simulation,
refer to site data base
The tendering party shall provide the following technical Radio parameters for the
network dimensioning:
UL & DL Eb/No for each bearer supported and for Both pedestrian (urban
environment) and vehicular model (rural environment).
Page 52
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 53 of 86
The Tendering Party shall provide an UL and DL Link-budget with the above Radio
Parameters for the 4 environments with:
(*) Regarding TMA, the tendering party is free to propose the adequate
solution (with or without) and should clearly state the benefits from the
proposed solution compared to the other.
- The GSM site database for the existing GSM sites that can be used for site co-
location is provided in Annex 09-Djezzy Radio site DB
Page 53
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 54 of 86
The tables below indicate the CS and PS high level traffic forecast.
3G Voice NBH Y1 Y2 Y3 Y4 Y5
Zone 1 1 775 2 881 4 476 5 984
Zone 2 1 020 2 513 3 959 5 418 6 766
Zone 3 1 926 4 022 5 820 6 647 7 928
Zone 4 0 3 069 4 223 5 247 7 023
Zone 5 453 1 759 2 871 4 761 6 432
Zone 6 647 1 509 3 542 5 413
Page 54
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 55 of 86
The tendering party will use traffic forecast per polygon provided in Annex 12-3G
Traffic Forecast Polygon to determine the needed BoQ over the five years.
- All nodeBs should be hardware ready to support a minimal configuration of S222 and HSPA+
through software upgrade only.
- All NodeB should support at least in terms of HW 256 CE for Uplink and 256
CE for Downlink, SW 128 CE for uplink and 128 CE for downlink, these are
R99 CE. Tendering Party should specify and add the additional CE to support the provided
traffic mix and below HSPA deployment.
- The HSPA will be deployed starting from year 1 as indicated in below table,
and it represents the HSPA activation for total cumulative installed Node B
per year.
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 56 of 86
(*) Regarding HSPA+ activation, the tendering party should use dual
carrier solution.
- 25% additional software licences for all dimensioning elements should be provided FOC for
purpose of re-homing activities.
- The traffic at RNC level is to be calculated from users traffic derived from
the traffic mix defined for each year, the Node B site BoQ and the subscriber
number per site with a security margin of 20%, i.e.: the Max RNC traffic load
is 80%.
13.3.8 Deliverables:
- The Tendering Party is requested to perform the design only for all polygons
as specified in Section Coverage polygon and site data base.
- The tendering party shall deliver the list of all proposed network elements
(BoM) including detailed description of configurations over 5 years.
- The Tendering Party shall carry out the simulation of coverage and generate
prediction maps of the coverage polygons that have been specified.
- The tendering party should provide the references for used digital maps with
their resolution per wilaya.
Page 56
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 57 of 86
- The used features/equipments should have been used and field proven for at
least 3 Months.
- The Tendering Party should clearly state the benefits and give the gain in
terms of cost of the introduction of any feature.
- Regarding HSPA+ activation, the tendering party is free to propose the adequate solution (Dual
carrier or MIMO) and should clearly state the benefits from the proposed solution
compared to the other.
- The Tendering Party should share all design assumptions and parameters on
the planning tool with DJEZZY.
- The tendering Party should provide in excel format the Polygon_ID, Longitude
and Latitude of the sites used and the Radio Configuration for every sites in
terms of: Antenna type, Antenna Azimuth, Antenna Height, Antenna Tilt,
output power and different Channels power, EIRP
- The Tendering Party should provide a complete radio design report including
the UMTS coverage plots defining the different service levels in dBm and
UMTS simulations according to the coverage plots requirements.
Page 57
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 58 of 86
Suburban 8 95%
Rural 7 90%
- The Tendering Party shall provide the below data for the different clutter based
the given radio parameters.
DU U SU RU
Limiting service (UL or DL)
MAPL (dbm)
Cell range (m)
Design level (dbm)
- The tendering Party shall provide the number of Node B per wilaya and per
morphology.
- The tendering Party shall provide the Calculated Cell Load and number
of subs per Node B for the different morphology and based on the
traffic mix/number of subs:
Cell load
DU U SU RU
Number of subs per node B per
configuration
DU U SU RU
Page 58
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 59 of 86
For each covered area the tendering party to provide a separate Morpho plot (with
no coverage) for each of the required areas.
Each of the above plots should be submitted for the five years for the 48
Page 59
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 60 of 86
wilayas.
In addition to the soft copy in Mapinfo format, all plots should be submitted in
A1 format.
The name of the plot, name of the Wilaya, service levels and borders should
be clear in all plots.
All plots should be signed by the Tendering Party officer empowered to bind
the Tendering Party to the provisions of this RFQ and any contract awarded
pursuant to it.
a. For all action on existing sites ( Access, equipments add, equipments swap,)
for swap 2G project or 3G sharing project, the responsibility belongs to
Djezzy in term of site acquisition
c. If any problem occurs with the site owner during the intervention, the
tendering party should solve it 24 h max after the complain notification.
d. After the site works finishing, the tendering party should provide to Djezzy a
duly signed report by a judicial officer ( Huissier) with the site owner witch
Page 60
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 61 of 86
e. The tendering party has to consider that any additional space out of the
actual occupied one may generate an extra rent budget.
c. The tendering party has to provide the details of the Site preparation civil
works for 2G swap and 3G collocated sites with clear explanations,
calculation criteria and work assumptions for each part of the CW per site
based on the data provided from Djezzy in the Annex 13 -Djezzy global DB,
it must include but not limited to:
Page 61
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 62 of 86
Page 62
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 63 of 86
a. The tendering party will take in charge the acquisition of the new sites
designed and needed by him during the Swap period, or the 3G
implementation, with one year warranty after the acceptance of the site.
b. The tendering party has to provide commercial power for any new site designed before the final
acceptance of the site.
c. The tendering party should obtain all the legal necessary authorizations including but not limited
to ANF authorization, MPTIC authorization, construction permits, APC declaration, before
proceeding with the construction of the site.
d. Djezzy provides in the Annex 13 -Djezzy global DB list of sites very close to be acquired, named
in acquisition process, its recommended to use these points in the design if needed.
e. For those new designed and acquired sites, the rental amount should be approved by Djezzy, if
the proposed amount is not accepted, the payment of the acquisition service will not be granted
by Djezzy.
f. The sites acquisition process should be conducted according to the attached procedure in Annex
14- Djezzy acquisition process
g. The site candidates rejected for rental amount and/or site property documents non conformity
regarding the law, the payment of the acquisition service will not be granted by Djezzy.
h. The site is under tendering party responsibility till the acceptance. In case of failure site during
this cycle, it will be on tendering party charge.
Page 63
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 64 of 86
i. The tendering party should provide to Djezzy a duly signed report by a judicial officer ( Huissier)
with the site owner and still responsible of any complain during one year, action plan to be sent
to Djezzy 24 H after the notification of the complain.
j. The tendering party has to consider the project South Road as a special project and will be on full
turnkey bases for all the aspects, as per the following items but not limited to:
Sites acquisition
d) The sites designed and proposed by the tendering party should be defined by
typology :
Page 64
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 65 of 86
f) The proposed sites should respect the environment in term of visual impact, as
per Annex 16- Site environment integration process.
h) The tender party has to consider the project South Road as a special project
and will be on full turnkey bases for all the aspects, as per the following items
but not limited to:
Sites construction
i) The sites design for the south road has to be detailed by the tendering party
for all the materiel proposed with the data technical sheet and the calculation
notes per site.
Page 65
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 66 of 86
d. The tendering party should quote all the required 2G and 3G features that
have been requested in the Tender for Supply of HSPA+ Solution sent on
3rd of November 2011 and Tender for 2G Equipment (Supply/Swap) sent on
the 21st of March 2012.
e. The proposed equipment (SW & HW) should support LBS functionality for
both 2G & and 3G.
f. The tendering party should indicate its references where LBS is deployed for
both 2G and 3G.
h. All the provided equipments including 3rd party equipments proposed by the
tendering party should be available for purchasing order for the coming five
(05) years and should not come to the end of support within the coming ten
(10) years.
i. The Tendering Party shall provide his hardware (RNC, NodeB, BSC, BTS, TC,
TRX) and software roadmap.
j. The tendering party shall provide in details the end of production and end of
support for all provided equipment including 3rd party equipment
k. The Tendering Party shall provide a description of all network elements (BSC, TC, BTS, RNC and
nodeB) including but not limited to:
Hardware architecture
Page 66
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 67 of 86
Software architecture
Configuration alternatives
Foot print
Height
Weight
Maximum number of CE
Number of stages
No. of PDCHs
m. The tendering party shall provide all the dimensioning rules and methodology
Page 67
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 68 of 86
of the different Network elements (RNC, NodeB, CE, BSC, TC, PCU) and
interfaces (Iub, IuCS, IuPS, Abis, Ater, Gb)
The tendering party NMS and Performance tool must comply with the
capacity and Functionality required by Djezzy, Number of supported RNC,
NodeB, BSCs, BTSs, Cells and TRXs mentioned in the network model, and it
should be fully compliant with Annex 17- NMS solution.
The tendering party shall provide the dimensioning rules of the NMS.
a. High level roll out plan explaining the strategy of the 2G and the 3G for the
next five years should be submitted in excel format or PDF format.
c. The rollout plan should be submitted per year, wilaya and for both projects,
2G and 3G.
d. The rollout plan must include and indicate but not limited to:
- 2G & 3G implementation rollout including all the below details but not
limited to:
Page 68
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 69 of 86
- Equipment manufactory.
- Equipment shipment.
- Customs clearance.
- Delivery to warehouse.
- Site survey.
Acceptance.
a. The tendering party should provide details of the deployment team and link
them with the rollout plan; these teams have to be clearly identified with
official commitment from the proposed subcontractors.
b. The tender party should have a rollout management tool and provide access
to Djezzy in real time. All the rollout action must reported on this tool and
updated on spot.
c. Djezzy minimum accepted time plan related to number of sites per year is as
indicated in the Scenario 1 network model tables; however the tendering
party may offer a more aggressive plan.
Page 69
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 70 of 86
17 Services Scope
17.1 GENERAL HIGHLIGHTS
The tendering party shall be responsible for all the services mentioned below
section Service classification for both 2G and 3G.
a. Scenario 1
For 3G, The Tendering party shall be responsible for delivering project in
turnkey basis for year 1.
b. Scenario 2
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 71 of 86
The South road coverage will be delivered in turnkey basis starting from
design till the acceptance of the last site and adding 3 months handover for
FLM.
The tendering party shall take responsibility for all below services as per their
related scenario.
The Tendering party should provide a separate quotation for each service in the below list.
- Calibration
- Planning
- Dimensioning
- Site acquisition
- Site Survey
- Installation & CW
- Integration
- Drive test
- Optimisation
Page 71
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 72 of 86
- Supervision:
- Customer complaints
- Warehousing
17.2.1 Calibration
The Tendering party should provide the propagation model report per city
17.2.2 Planning
a. Scenario 1
The Tendering Party shall be responsible for 3G planning related issues, this includes
but not limited to:
Prepare the required Database for the planning tool as indicated (Digital
maps, clutter height and types).
Running the coverage maps and setting all the required radio parameters.
Page 72
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 73 of 86
b. Scenario 2
The Tendering Party shall be responsible for all the 2G and 3G planning related
issues, this includes but not limited to:
Prepare the required Database for the planning tool as indicated (Digital
maps, clutter height and types).
Running the coverage maps and setting all the required radio parameters.
The tendering party shall be responsible for setting the transmission plan,
routes and all the transmission related issues as per bellow section
Transmission
17.2.3 Dimensioning
a. Scenario 1
The dimensioning will be under Djezzy responsibility, the tendering party should
ensure the required support, dimensioning rules and documentations.
b. Scenario 2
The tendering party shall be responsible for all the dimensioning related issues that
includes but not limited to:
Page 73
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 74 of 86
b. Scenario 2
The tender party will take in charge the acquisition as defined in section CW
network model
- For 3G, please refer to Chapter 6 submitted within the Tender for Supply of
HSPA+ Solution sent on 3rd of November 2011.
- For 2G, please refer to section Service Scope and Classification submitted
within the Tender for 2G Equipment (Supply/Swap) sent on the 21st of
Page 74
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 75 of 86
March 2012.
b. Scenario 2
The civil work will be under tendering party responsibility for both 2G and
3G.
- For 3G , please refer to Chapter 6 submitted within the Tender for Supply of
HSPA+ Solution sent on 3rd of November 2011 .
For 3G, please refer to Chapter 6 submitted within the Tender for Supply of
HSPA+ Solution sent on 3rd of November 2011
For 2G, please refer to section Service Scope and Classification submitted
within the Tender for 2G Equipment (Supply/Swap) sent on the 21st of
March 2012.
17.2.8 Integration
The integration requirements for both scenarios are as below
For 3G, please refer to Chapter 6 submitted within the Tender for Supply of
HSPA+ Solution sent on 3rd of November 2011.
For 2G, please refer to section Service Scope and Classification submitted
within the Tender for 2G Equipment (Supply/Swap) sent on the 21st of
Page 75
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 76 of 86
March 2012.
For 3G, please refer to Chapter 6 submitted within the Tender for Supply of
HSPA+ Solution sent on 3rd of November 2011.
For 2G, please refer to section Service Scope and Classification submitted
within the Tender for 2G Equipment (Supply/Swap) sent on the 21st of
March 2012.
17.2.10 Optimisation
a. Scenario 1
The tendering party will be responsible for the 3G network optimization as described in Chapter
6 submitted within the Tender for Supply of HSPA+ Solution sent on 3rd of
November 2011 for the first year.
Then tendering party will be responsible for the 2G network optimization starting from first site
swap till the final acceptance of the wilaya.
b. Scenario 2
Page 76
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 77 of 86
according to Annex 19-Service Level agreement SoW for level 2 and level 3
support
For 2G, the tendering party shall provide FLM for all supplied equipment
from first site swap till the final acceptance of the wilaya. Additionally, the
tendering party should add 3 months for year 1, and 1 month for remaining
years after the final acceptance per wilaya.
For 3G, the tendering party shall provide FLM for all supplied equipment till
final acceptance for year one and during 6 months handover period.
For FLM Services, the tendering party shall follow the Scope indicated in
Annex 18-Operation and Maintenance SoW.
For non supplied shared third party equipments that includes Batteries, Rectifiers, Antennas
and feeders, generators and Power supplies, Djezzy shall take the maintenance responsibility
for them.
b. Scenario 2
For both 2G and 3G, the tendering party should provide FLM for all supplied
equipment till the project end.
For FLM Services, the tendering party shall follow the Scope indicated in
Annex 18-Operation and Maintenance SoW.
For non supplied shared third party equipments that includes Batteries,
Rectifiers, Antennas and feeders, generators and Power supplies, Djezzy shall
take the maintenance responsibility for them.
Page 77
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 78 of 86
Checking and correcting any Operation and Maintenance Unit failures or/and
alarms.
17.2.14 Supervision:
The network supervision will be under Djezzy responsibility for both
scenarios.
The tendering party shall handle the aspects of the spare parts on a SPM
style (Spare Parts Management). The tendering party shall propose his plan
for all the items related to the spare parts managements to Djezzy. Djezzy
withholds the right to ask the tendering party to add/remove or modify some
parts of his proposal.
All the aspects of the spare parts management has to comply with the rules
Page 78
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 79 of 86
a. Scenario 1
The network event handling will be under Djezzy responsibility.
b. Scenario 2
The tendering party shall be responsible for the handling of any event that is
reported by Djezzy and that needs a special coverage or capacity solutions, this
includes but not limited to:
Drive test prior to the event to select the most appropriate solution
Taking the necessary actions after Djezzy approval (i.e. Mobile shelter, adding
extra capacity to the existing 2G/3G site .).
i. one will monitor the event using his drive test tool and report any problems
or errors
ii. second team will be working from the office to monitor the KPIs and
respond to any errors reported by the team in the field.
For both scenarios, The Tendering party shall be responsible for all the aspects
related to customer complaints delivered to him by Djezzy customer care center,
this includes but not limited to:
Page 79
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 80 of 86
Analyzing the Customer complaints and identifying the problem causes and
taking the suitable actions to resolve them.
The table below states the time span allowed between the instant where the
complaint was reported till it was resolved
95% 100%
Normal Customer
complaints resolution time 48 Hours 72 Hours
Djezzy withholds the right to classify which complaint is VIP and which is not.
The tendering Party shall provide a weekly summary report of all treated
customer complaints, following a format to be agreed upon with Djezzy prior
to the commencement of project execution.
17.2.18 Warehousing
For both Scenarios, the tendering party shall provide the warehousing for the
supplied equipment. The warehousing operations must comply with Djezzy
procedures. Djezzy may/may not apply for this service.
Page 80
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 81 of 86
18 Rollback
Page 81
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 82 of 86
19.3 Penalties
The tendering party must comply with the penalties indicated in the
Annex I submitted within the Tender for Supply of HSPA+ Solution
sent on 3rd of November 2011. Additionally for Scenario 2, the tendering
party must comply with:
In case the tendering party fail to acquire required new sites as per
his proposed design or to satisfy the target KPIs and traffic within
the wilaya 2G swap project period, the tendering party should
consider like to like swap and any new need for additional site will
be with no additional cost on Djezzy.
In case the designed capacity site fails to achieve capacity
objectives (absorb 50% traffic from target cells to densify), the
tendering party shall take all necessary action to achieve the target
without additional cost on Djezzy.
In case the drive test shows that the 2G coverage is not as it was
designed and approved, then the tendering party shall take all the
necessary actions to resolve the problems at no extra cost on
Djezzy.
20 Transmission
For the General Transmission specifications and scope, please refer to Chapter 5
submitted within the Tender for Supply of HSPA+ Solution sent on the 3rd of
November 2011.
The Tendering party should consider for product offering the microwave equipment
Page 82
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 83 of 86
A) In Section: CH5/ I-Generalities/ 3. RfP Scope & Scenarios/ 3.2. Services and Deliverables:
Scenario 1: Annex-D2 was updated by Annex 03-TX BoQ.
Scenario 2:
- Free Design scope (described in Chapter 3 in the initial document) is amended
as per Section Network Model & requirement for Scenario 2 in this
amendment document to cover 5 Years and 48 Wilayas.
- Scenario 2 Free design will aim to aggregate the calculated traffics to the
nearest Core Transport sites as indicated in Annex 20-Djezzy transmission DB.
- All deliverables (Designs, Link Budgets, Topologies, Configurations...) must
comply with the relevant ITU-T/R standards in force and to be organized per
wilaya.
As per the initial document, the MW planning and the engineering work will comply to
the guidelines set described below:
1. There are two main types of objectives, namely, Quality and Availability. The
parameter usually used for the Quality Objective is SESR measured in seconds over
a period of 1 month in the worst conditions. Availability or Unavailability, whichever
preferred is calculated in terms of minutes, over a span of 1 year.
1.1. Quality Objective for MW hops
SESR = (0.002 (A+0.002) x 50/100) x 2.6 x10 seconds
A = 1% = 0.01
Quality Objective is always related to the Multi path propagation
phenomenon.
All the hops in the network must have an SESR value up to 130 seconds per
month
1.2. Unavailability objective
All the Hops must have an Availability above >99.995%.
2. Rain factor to be considered as per the submitted Backhaul Links DB in Annex 20-
Djezzy transmission DB.
Page 83
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 84 of 86
Page 84
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 85 of 86
Page 85
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 86 of 86
F) All the necessary databases for Scenario 2 Design are provided in Annex 20- Djezzy
Transmission DB.
J) Transmission Scope of work in Annex20- Djezzy Transmission DB
21 HUMAN RESOURCE
a. The Tendering party shall provide all the required highly qualified experts to handle
all the aspects of the deployment and to manage any required interoperability with
the 2G/3G network element, as well as to make sure of the good continuation of the
existing network operation.
b. The Tendering party may hire a certified subcontractor to finalize and speed up the
rollout, however the Tendering party shall be responsible for the quality of the
delivered work by such Subcontractors.
c. Djezzy shall have the right to request the change of any project team member or
sub-contracted party if the quality of deliverables of that party consistently fails to
meet Djezzy requirements.
22 Training
Please refer to Chapter 6 and annex J submitted within the Tender for Supply of HSPA+
Solution sent on 3rd of November 2011 and section Training submitted within the
Tender for 2G Equipment (Supply/Swap) sent on the 21st of March 2012.
23 On job training
.The tendering party should share with Djezzy team its knowledge and procedure
The Tendering Party shall commit to answer all Djezzy quires and supplying all the necessary
technical documents and explanation including but not limited to: planning, dimensioning,
optimization, implementation and Network operations & maintenance
The tendering party should consider to the exit management plan as part of the delivery process
and should ensure a smooth and efficient transfer back of the in-scope services, along with people,
assets and 3rd party agreement which will provide them, essentially ensure continuation of the
Page 86
Purchasing Departement / CEO Office
Title
2G & 3G RFQ Amendment
Reference Version Date Page
1.0 03/12/2012 Page 87 of 86
service levels in an interrupted manner for the duration of the disengagement. The process of the
exit is described in Annex_K submitted within the Tender for Supply of HSPA+ Solution sent on
3rd of November 2011.
End of Document
Page 87