NO. MATERIAL KETERANGAN SAT. BAAMANG - MB.

KETAPANG
I BATA, BATU DAN PASIR
1 Bata Merah uk. 5 x 11x 22 cm bh 875,00
2 Bata beton ringan ex Citicon uk. 10 x 20 x 60 cm bh 17.250,00
3 Batu kali Batu belah pondasi m3 656.250,00
4 Batu Split Pecah Mesin 1/2 m3 468.750,00
5 Batu Split Pecah Mesin 3/5 m3 468.750,00
6 Batu Split Pecah Mesin 0,5/1 m3 468.750,00
7 Pasir Beton m3 187.500,00
8 Pasir Pasang m3 187.500,00
9 Pasir Urug m3 112.500,00
10 Tanah Urug m3 112.500,00
11 Tanah Urug Pilihan m3 187.500,00
12 Aspal Pen 60/70 Kg 15.062,50

II BAHAN PEREKAT
1 Semen (50 Kg) Semen Indonesia/Gresik zak 87.500,00
Semen (40 Kg) Semen Indonesia/Gresik zak 70.000,00
Kg 1.750,00
2 Semen Warna Semen Indonesia kg 14.000,00
3 Filler Kg 1.750,00

III BAHAN BAJA :


1 Besi Beton U-24 KS Kg 11.875,00
2 Besi Beton U-39 KS kg 11.875,00
3 Besi Hollow Galvanis (Pagar) KS M2 573.000,00
4 Besi Hollow Stainless ( Pagar) m2 948.000,00
5 Rangka atap baja ringan Baja Ringan m2 159.625,00
6 Kawat beton Kawat Beton kg 17.500,00
7 Kawat Bronjong (0,5x1x2) Pcs/Lbr 343.750,00
8 Geotextile 200gr/M2 200 gr / m2 M2 20.625,00
9 Wiremesh Polos (U32) M6 Kg 13.012,50
10 Karet Eva Lbr 62.500,00

IV BAHAN KAYU
1 Balok Kayu Klas I/Ulin Ulin m3 7.031.250,00
Papan Kayu Kelas I / Ulin Ulin m3 13.175.000,00
2 Balok Kayu Klas II Lanan m3 3.750.000,00
Papan Kayu Kelas II Lanan m3 3.750.000,00
3 Papan/Balok Kayu Klas III Meranti m3 2.562.500,00
4 Papan/Balok Kayu Klas IV/Campuran Bekisting m3 2.125.000,00
5 Dolken/ Knopel dia 8 s/d 10 cm p. 4 m btg 15.000,00
6 Kayu Galam 10-12 P = 4 m btg 20.000,00
7 Kayu Galam 10-12 P = 3 m btg 15.000,00

V BAHAN ALUMINIUM
1 Kusen Almunium 3" m' 80.000,00
2 Rangka Jendela Almunium m' 75.000,00
3 Rangka Pintu Almunium m' 118.750,00
4 Kusen & Pintu PVC toilet - unt 331.250,00
5 Engsel 3", ex Belucci bh 36.750,00
7 Handle pintu Dekson/Belucci bh 209.375,00
8 Selinder Dekson/Belucci bh 156.250,00
9 Door Stoper bh 43.750,00
10 Door closer bh 159.375,00
11 Slot Tanam Dekson / Gerber bh 173.500,00
12 Kait Angin Belucci bh 28.750,00
13 Grendel Kodai 4"/Belucci bh 9.250,00

VI BAHAN PELAPIS :
1 Triplek t. 3 mm Uk 120x240 cm lbr 69.375,00
2 Triplex t. 4 mm Uk 120x240 cm lbr 88.125,00
3 Triplex t. 9 mm Uk 120x240 cm lbr 181.250,00

VII BAHAN LANTAI & DINDING KERAMIK


1 Keramik 30/30 ex Masterina/DK m2 70.375,00
2 Granite Tile 60/60 ex Granito tile m2 203.125,00
3 Plint Keramik 10/30 cm Biasa bh 13.750,00
4 Plint Granitetile 10/40 cm Granit bh 20.000,00

VIII BAHAN PENUTUP ATAP


1 Genteng Metal 1 x 4 tbl 25 mm Setara Sakura Roof 1 x 4 bh 30.375,00
2 Genteng Metal 2 x 4 btl 25 mm Setara Sakura Roof 2 x 4 (Elang) bh 47.125,00
3 Nok Gentang Metal Sakura Roof/setara bh 15.375,00
4 Nok Genteng Metal Sakura Roof Sakura Roof/setara bh 15.375,00
5 Seng Plat BJLS 30 L. 40 cm m' 13.750,00

IX BAHAN KACA :
1 Kaca Polos 3 mm m2 103.750,00
2 Kaca Polos 5 mm m2 153.125,00
3 Kaca Polos 8 mm m2 187.500,00

X BAHAN PAKU DAN MUR BAUT :


1 Paku 1 s/d 3 cm kg 16.250,00
2 Paku 5 s/d 10 cm kg 16.500,00
3 Paku 8 s/d 12 cm kg 16.500,00
4 Paku Skrup bh 1.250,00
5 Paku Ulin Kg 20.000,00

XI BAHAN FINISHING :
1 Cat kayu/Besi Kg 64.375,00
2 Plamir Kayu Kg 13.000,00
3 Meni kayu Altex kg 35.625,00
4 Wood Filler Jati Kg 41.875,00
5 Thinner Avian Ltr 39.750,00
6 Amplas Kayu Lbr 5.375,00
7 Kwas cat bh 6.250,00
8 Cat Tembok kw1 ex. Dulux ; Warna standard Kg 144.375,00
9 Cat Tembok kw2 ex. Vinilex ; Warna standard Kg 27.000,00
10 Plamir Tembok Kg 18.750,00
11 Lem Kayu kg 17.500,00
12 Seal tape bh 2.500,00
13 Minyak bekisting Ltr 23.750,00

XII BAHAN SANITARI


1 Wastafel LW 240 CJ ex Toto, Komplit kran & unt 581.250,00
2 Kloset duduk CW 600 J / SW 660 J Komplit & unt 2.621.875,00
3 Kloset Jongkok type CE 6 ex. Toto unt 334.375,00
4 Urinoir unt 1.125.000,00
5 Bak air fibreglass uk. 55x55x60 cm bh 234.375,00
6 Shower Spray Wassher unt 315.625,00
7 Shower Set Wassher unt 128.125,00
8 Floordrain Stainless bh 75.000,00
9 Tempat Sabun KIA bh 56.250,00
10 Kran zink Washer bh 346.875,00
11 Kitchenzink Hwaco 1L unt 875.000,00
12 Kran dinding Washer bh 296.875,00

XIII BAHAN PARTISI DINDING /PLAFOND


1 Gypsumboard t.9 mm ex. Jayaboard ; uk 120 x 240 cm lbr 96.875,00
2 List Profil 8 cm Gypsum m 26.625,00
3 Rangka plafond Metal furing termasuk paku ripet & acc m2 84.750,00

XIV BAHAN SALURAN AIR


1 Pipa PVC dia 1/2" ex. AW ; P. 4 m m' 8.475,00
2 Pipa PVC dia 3/4" ex. AW ; P. 4 m m' 10.325,00
3 Pipa PVC dia 1" ex. AW ; P. 4 m m' 13.000,00
4 Pipa PVC dia 1 " ex. AW ; P. 4 m m' 26.562,50
Pipa PVC dia 1 " ex. D ; P. 4 m m' 15.625,00
5 Pipa PVC dia 2" ex. AW ; P. 4 m m' 35.587,50
6 Pipa PVC dia 3" ex. AW ; P. 4 m m' 65.162,50
7 Pipa PVC dia 4" ex. AW ; P. 4 m m' 94.975,00
8 Stop kran dia 1" bh 81.250,00
9 Klep diameter 3/4" bh 21.875,00
10 Tangki air 1100 liter Profil Tank bh 1.515.625,00
11 Tangki air 650 liter Profil Tank bh 1.031.250,00
12 Pelampung otomatis bh 84.375,00
13 Roof Drain Metal Bh 34.375,00
14 Mesin Jet Pump kap.250 watt unt 2.375.000,00
15 Mesin Pompa air daya 125 watt Panasonic unt 756.250,00
(Lengkap otomatis )

XV PERALATAN ELEKTRIKAL
1 Box panel PVC isi 4 MCB ( Pakai Tutup) bh 65.625,00
2 MCB 6 A bh 62.500,00
3 MCB 4 A bh 62.500,00
4 Kabel NYM 2 x 2,5 mm2 m' 10.125,00
5 Kabel NYM 3 x 2,5 mm2 m' 12.750,00
6 Kabel telephone 4 x 0.5 mm m' 1.875,00
7 Isolasi bh 4.375,00
8 Saklar tunggal Broco bh 14.375,00
9 Saklar ganda Broco bh 18.625,00
10 Stop kontak Broco bh 15.000,00
11 Outlet TV Broco bh 31.250,00
12 Outlet Telephone Broco bh 31.250,00
13 Down light / PLC 13 W bh 84.375,00
14 Fitting plafond + lampu SL Panasonic bh 66.875,00
15 Lampu SL 11 Watt Philips bh 34.375,00
16 Lampu SL 14 Watt Panasonic bh 38.750,00

XVI BAHAN BAKAR / BBM


1 Pertalite / Non Subsidi Pertamina Ltr 9.437,50
2 Dexlite / Non Subsidi Pertamina Ltr 9.187,50
3 Minyak Pelumas / Olie Mesin Pertamina Ltr 43.750,00
4 Minyak Pelumas / Olie Hidrolik Pertamina Ltr 56.250,00
5 Minyak Pelumas / Olie Transmisi Pertamina Ltr 40.625,00
6 Grease / Gemuk Kg 62.500,00
7 Minyak bekisting Ltr 23.750,00
8 Kerosen/Minyak Tanah Ltr 10.625,00
Perhitungan harga material perkecamatan sudah termasuk pajak (PPn, PPh) Galian C, Asuransi, Resiko, Overhead dan Keuntungan
Standar perhitungan harga adalah sampai ibu kota kecamatan, untuk perhitungan perencanaan lokasi-lokasi lain yang letaknya relatif
jauh dari ibu kota kecamatan dapat menetapkan tambahan perhitungan untuk ongkos angkut atau overhead lainnya.

NO. UPAH SAT. BAAMANG - MB. KETAPANG


1 Tukang Besi Konstruksi OH 125.000,00
2 Tukang Besi Tulangan OH 125.000,00
3 Kepala Tukang Besi OH 162.500,00
4 Tukang Kayu Kasar OH 93.750,00
5 Tukang Kayu Halus OH 125.000,00
6 Kepala Tukang Kayu OH 162.500,00
7 Tukang Batu Kasar OH 125.000,00
8 Tukang Batu Halus OH 125.000,00
9 Kepala Tukang Batu OH 162.500,00
10 Tukang Cat Biasa OH 125.000,00
11 Kepala Tukang Cat OH 162.500,00
12 Tukang Listrik OH 125.000,00
13 Kepala Tukang Listrik OH 162.500,00
14 Pekerja OH 93.750,00
15 Mandor OH 162.500,00
16 Tukang Gali Tanah OH 93.750,00
17 Tukang Pancang OH 93.750,00
18 Operator OH 196.625,00
19 Pembantu Operator OH 125.000,00
20 Sopir / Driver OH 178.750,00
21 Pembantu Sopir / Driver OH 125.000,00
22 Mekanik OH 178.750,00
23 Pembantu Mekanik OH 125.000,00
Perhitungan harga upah perkecamatan sudah termasuk pajak (PPn, PPh) Galian C, Asuransi, Resiko, Overhead dan Keuntungan
Standar perhitungan harga adalah sampai ibu kota kecamatan, untuk perhitungan perencanaan lokasi-lokasi lain yang letaknya relatif
jauh dari ibu kota kecamatan dapat menetapkan tambahan perhitungan untuk ongkos angkut atau overhead lainnya.

NO. KLASIFIKASI BANGUNAN GEDUNG SAT. BAAMANG - MB.


KETAPANG

A. BANGUNAN GEDUNG NEGARA


a. GEDUNG NEGARA TIDAK SEDERHANA 1 M Rp 4.720.000,00
b. GEDUNG NEGARA SEDERHANA 1 M Rp 3.870.000,00

B. RUMAH NEGARA
a. RUMAH NEGARA TIPE A 1 M Rp 4.850.000,00
b. RUMAH NEGARA TIPE B 1 M Rp 4.620.000,00
c. RUMAH NEGARA TIPE C,D,E 1 M Rp 3.450.000,00

C. PAGAR BANGUNAN GEDUNG NEGARA


a. PAGAR GEDUNG NEGARA DEPAN 1 M' Rp 2.600.000,00
b. PAGAR GEDUNG NEGARA BELAKANG 1 M' Rp 1.880.000,00
c. PAGAR GEDUNG NEGARA SAMPING 1 M' Rp 1.800.000,00

D. PAGAR RUMAH NEGARA


a. PAGAR RUMAH NEGARA DEPAN 1 M' Rp 1.890.000,00
b. PAGAR RUMAH NEGARA BELAKANG 1 M' Rp 1.200.000,00
c. PAGAR RUMAH NEGARA SAMPING 1 M' Rp 1.130.000,00
PERHITUNGAN HARGA SATUAN BANGUNAN GEDUNG NEGARA (HSBGN) SEMESTER I (REVISI) TAHUN 2017 MENGACU PADA :
1. UNDANG-UNDANG REPUBLIK INDONESIA NOMOR 28 TAHUN 2002 TENTANG BANGUNAN GEDUNG
2. PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 73 TAHUN 2011 TENTANG PEMBANGUNAN BANGUNAN GEDUNG
NEGARA
3. PERATURAN MENTERI PEKERJAAN UMUM REPUBLIK INDONESIA PERATURAN MENTERI PEKERJAAN UMUM
NOMOR: 45/PRT/M/2007 TENTANG PEDOMAN TEKNIS PEMBANGUNAN BANGUNAN GEDUNG NEGARA
4. PERDA BANGUNAN GEDUNG KABUPATEN KOTAWARINGIN TIMUR NO. 6 TAHUN 2010
5. PERATURAN BUPATI KOTAWARINGIN TIMUR NO. 28 TAHUN 2015 TENTANG SISTEM DAN PROSEDUR PEMUNGUTAN
PAJAK MINERAL BUKAN LOGAM DAN BATUAN
6. HARGA SATUAN TERTINGGI BANGUNAN GEDUNG NEGARA SUDAH TERMASUK PAJAK (PPn, PPh) GALIAN C, ASURANSI,
RESIKO, OVERHEAD DAN KEUNTUNGAN
7. HARGA SATUAN TERTINGGI BANGUNAN GEDUNG NEGARA TERMASUK HARGA SATUAN MATERIAL DAN UPAH
MERUPAKAN HARGA SATUAN TERTINGGI UNTUK PERENCANAAN, TIDAK DAPAT DITETAPKAN MENJADI
HARGA PERKIRAAN SENDIRI (HPS).
8. PENETAPAN HARGA PERKIRAAN SENDIRI (HPS) DILAKUKAN OLEH MASING-MASING PPK KEGIATAN BERSANGKUTAN
YANG DILAKUKAN MELALUI METODE SURVEY HARGA DASAR.