Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

TECHNOLOGY FOCUS

Production Facilities

Every year, SPE organizes more than 30 conferences worldwide. Critical issues of Hisham Saadawi, SPE, is Vice
current interest to the oil industry are reflected in the SPE papers presented at these President (Engineering) for Abu Dhabi
conferences. When selecting papers for this feature, I was not surprised that many Company for Onshore Oil Operations
papers deal with topics related to safety in facilities design and to asset integrity. (ADCO). He has more than 30 years
With recent publicized accidents and the industrys continuing concern about
its public image, operating companies are focusing on process safety and improv- experience in the design, construction,
ing asset integrity, and are addressing these issues early in facilities design. startup, and operation of oil- and gas-
Indeed, it can be argued that enhancing safety performance and dealing with processing facilities. Saadawis current
the increased environmental risks remain the key challenges facing the industry areas of interest include multiphase
today. Some concepts relevant to these topics are briefly outlined. pumping, CO2 enhanced oil recovery,
Asset integrity can be defined as the ability of the asset to perform its required
technical safety, as well as training and
function effectively and efficiently while managing health, safety, and the envi-
ronment. In this context, asset integrity refers to hydrocarbon systems and development. He is a recipient of the
includes support systems and infrastructure, such as platform structures. 2011 SPE Regional Projects, Facilities,
Critical safety elements are those systems and equipment that prevent, control, and Construction Award. Saadawi is a
or mitigate major accidents. They include elements such as pressure-relief valves, 20102011 SPE Distinguished Lecturer
shutdown systems, fire- and gas-detection systems, and firefighting equipment. and an SPE course instructor. He has
Safety instrumented systems (SISs)since its publication in 2003, the
International Electrotechnical Commission (IEC) 61511 standard is becoming the served on several committees and sub-
basis for the specifications and implementation of SISs in the oil industry. Initially, committees of SPE conferences and
the industry was relatively slow to adopt this standard. A dilemma facing operat- workshops, and he serves on the JPT
ing companies is what to do about the existing shutdown safety systems that were Editorial Committee. Saadawi holds a
installed before 2003 and that are not in compliance with IEC 61511. PhD degree in mechanical engineering
Papers selected for this feature along with those recommended for additional
from the University of Manchester, UK,
reading highlight industry progress in these issues. I hope that they will be of
interest to you. JPT and is a Chartered Engineer in the UK.

Production Facilities additional reading


available at OnePetro: www.onepetro.org

SPE 146240 The Practical Application of Process Safety Principles To


Determine and Monitor Asset Integrity of Oil and Gas Facilities by John
Hopkins, WGPSN.

SPE 141174 Replacement of Existing ESD Valves With New SIL Rated
ESD Valves: A Case Study of Production Optimization and Enhancement of
Process Safety and Integrity in Kuwait Oil Company by Sadoun Mutar Bezea
Al-Khaledi, Kuwait Oil Company, et al.

SPE 137461 Corrosion Management of a Worldwide Existing Pipeline


Network by Michel Bonis, Total S.A., et al.

66 JPT DECEMBER 2011


PRODUCTION FACILITIES

Twelve Steps To Engineering Safe Oil and Gas Facilities

The safety of an onshore facility is bly lead to equipment failure, personnel tive that the piping system be designed
a function of how safely the facil- injuries, and environmental damage. properly. Because upstream oil and gas
ity was designed. People are injured, The full-length paper details 12 key facilities are not covered specifically by
and sometimes killed, when explosions, areas for facility designers and engineers codes, it is the users responsibility to
fires, and toxic-gas releases occur at oil- to include when designing facilities for select the applicable piping code. Codes
and gas-producing facilities that were safe operation. The following is a short for process piping and for materials used
designed without including measures summary of these areas that should in H2S-containing environments in oil
that could have prevented such inci- enable designing and building safe and gas production are applicable.
dents. The safety of people and equip- facilities that reduce the risk of major
ment must be considered and included incidents. See the full-length paper for Proper Pressure Vessel. Pressure ves-
along every step in the engineering and citing of applicable recommended prac- sels are generally defined as those hav-
design of oil and gas facilities. tices, codes, and standards. ing an internal pressure greater than
15 psig and an inside diameter great-
Introduction Design-Standards Policy. Each pro- er than 6 in. The US Department of
Many wellsites, tank batteries, and pro- ducing company, no matter how small, Labor Occupational Safety and Health
duction facilities are at risk because of must implement a policy regarding the Administration (OSHA) set rules that
design or installation errors. These errors use of industry design standards that require pressure vessels used in flam-
may have occurred when the facility was can be articulated to the production mable- and combustible-liquid service
built or because the facility had been and operations groups regarding how to be built in accordance with the code
enlarged or upgraded through the years. surface facilities should be built. Setting for unfired pressure vessels set forth
Lack of proper engineering design can a design policy to use industry stan- by the American Society of Mechanical
lead to equipment failure, lost produc- dards will reduce the risk of injury to Engineers (ASME).
tion, human injury, or harm to the envi- personnel or the occurrence of an envi- The manufacturers nameplate,
ronment. Design and equipment selec- ronmental event at the facility. Most which should remain affixed perma-
tion will affect the safety and health of industry standards and regulations nently to the pressure vessel, must
perhaps generations of workers who will were developed in response to safety- display the U stamp as an indica-
be working on and near the equipment. related events and continually evolve to tion that the design, fabrication, and
incorporate lessons learned from other testing were conducted in accordance
Safe Facilities safety-related events. Building a facility with that code. To maintain the integ-
When designing a facility for a discov- to industry standards provides the user rity of pressure vessels, they must be
ery, companies may choose to make with industry-accepted safety criteria. inspected periodically. Vessels repaired
sure that all facilities are designed and or rerated as a result of an inspection,
operated in accordance with standards Site Layout for Safety. One of the should have an additional nameplate
and good engineering practices and first tasks when building a new facility added with an R stamp displayed.
with regulatory requirements. The other is to lay it out on the pad properly. In
choice is to make decisions that inevita- planning the equipment layout, one Picking the Proper Tank. According to
must obtain a plot plan of the site and OSHA, there are two types of tanks used
This article, written by Senior Technology a list of the equipment to be installed. in upstream oil and gas operations. Low-
Editor Dennis Denney, contains high- Start with placement of the most-haz- pressure tanks have a maximum allow-
lights of paper SPE 141974, Twelve ardous items on the sitevents; flares; able working pressure (MAWP) of 0.5
Steps To Engineering Safe Oil and fired process equipment; engines and to 15 psig, with OSHA requirements that
Gas Facilities, by J.E. Johnstone, rotating equipment; separators, tanks, are very similar to those for pressure ves-
SPE, and J.V. Curfew, SPE, Contek and unfired vessels; and site offices, sels. Atmospheric tanks have an MAWP
Solutions, prepared for the 2011 SPE electronic control equipment, batteries, of 0 to 0.5 psig and must be used only for
Americas E&P Health, Safety, Security, and electrical switchgear. storage of crude petroleum.
and Environmental Conference, Houston,
2123 March 2011. The paper has not Design Piping Properly. To design a Specifying Rotating Equipment for
been peer reviewed. safe and reliable facility, it is impera- Safety. Centrifugal pumps can be used

For a limited time, the full-length paper is available free to SPE members at www.jptonline.org.

JPT DECEMBER 2011 67


in severe service (defined as hydro- state and federal laws and codes. In able concentrations of gases, vapors, or
carbon liquids in a high-temperature addition to safety, state and federal liquids normally are prevented by posi-
environment) or can be used in less- regulations cover environmental con- tive mechanical ventilation; or loca-
rigorous service where intrinsic reli- siderations. A concern that should be tions adjacent to a Class-I, Division-1
ability and high-temperature service addressed early in the design is whether location where ignitable concentrations
are not required. The discharge piping a relief system is necessary or if atmo- might be communicated occasionally.
of the pumps should be equipped with spheric vents are acceptable. This deci- Many sites have been observed at
a relief valve to prevent overpressuring sion should be made primarily on the which low-voltage automation systems
of downstream piping, a check valve basis of the type of fluids being handled have been installed; however, these sys-
to prevent backflow, and a high-/low- and public exposure. tems often are not rated for classified
pressure switch to alert operators in the Relief-system design begins with areas. In many instances, this equip-
event of a problem with the discharge. criteria for individual relief devices. ment has been used in other industries
In light-hydrocarbon or -crude service, Initial considerations are set pressure, and has not yet been rated for hazard-
a shut-in valve should be installed allowable overpressure, and relief- ous locations. Personnel also need to
on the pump inlet. This safety device capacity requirements. Overpressure recognize that carrying a nonclassi-
can close off flow to the pump in the is the pressure increase beyond the fied device into a classified area is in
event of a leak or fire downstream of set pressure of the primary relieving violation of code.
the pump. device. For single-relief-device sys-
Internal-combustion reciprocating tems, the set pressure of the device Instrumentation and Control Sys-
gas engines follow standards for report- can be no higher than the MAWP of tem. Instrument alarms and shutdown
ing engine-horsepower ratings. Engine the system. For multiple-device sys- systems provide the first level of safety
ratings are degraded by ancillary equip- tems, supplemental devices may be in the event that a process upset has
ment (e.g., fans and pumps), altitude, set higher than the MAWP, the exact occurred. Control systems that use pro-
ambient temperature, and fuel compo- set pressure being determined by the grammable-logic controllers, distribut-
sition. The engineer should work with purpose for the additional capacity of ed-control systems, and supervisory-
the engine manufacturer to determine the device. Normally, the allowable control and data-acquisition systems
the available horsepower in accordance overpressure is 10% of the set pressure have improved facility safety greatly
with those standards. Engines should and is a consideration when evaluating by enabling advanced logic in safety
have shutdown systems for situations the size for a relief device. Depending systems and by making it easier to
that will harm the engine or associ- on the relieving scenario, the overpres- add alarm and shutdown points. Safety
ated processes. sure can vary from 10 to 21%. systems can be examined in terms of
Reciprocating compressors are cat- levels of protection to prevent or mini-
egorized as low- to moderate-speed Electrical-Area Classification. Elec- mize the effects of equipment failure
compressors (typically in the 300- trical equipment is used increasingly to within the process. Generally, facilities
to 700-rev/min range) or as high- automate remote facilities. Solar panels are built to have at least two levels of
speed compressors (typically 900 have brought electricity to remote pro- protection. Having two levels of safety
to 1,800 rev/min and used in field duction facilities, and personnel are enables safe operation in the event
compression applications). All pres- carrying more electronic equipment, that one of the protection means fails
sure vessels connected to compressors such as cell phones and lap-top com- to operate as designed. The two levels
must be protected with relief valves puters, which usually are nonclassi- should be independent and in addition
on the compressors. Generally, these fied, as part of their work. Along with to the control devices being used in the
relief valves are placed on the inlet the increase in the number of electri- normal process operation.
scrubber(s) and downstream of each cal devices is the need to ensure that
stage of compression. installed equipment meets the require- Personnel Safety. Personnel safety at
Electric-motor enclosure types, insu- ments of hazardous locations. the oil and gas site must be examined
lation systems, and ratings for winding- Hazardous locations generally are to ensure that employees do not place
temperature rise must be specified to classified in one of two divisions for the themselves at risk while performing
standards for general-purpose indus- oil and gas industry. Class-I, Division-1 routine operations and to ensure that
trial alternating-current squirrel-cage locations are defined as locations where the site conforms to OSHA require-
induction motors. Within these stan- ignitable concentrations of flammable ments. OSHA regulations provide
dards, descriptions are provided for gases or vapors can exist under nor- excellent guidance when designing
various classifications of protection for mal operations, may exist frequent- walking surfaces, exit routes, stairways,
motor enclosures. In general, there ly because of repair or maintenance ladders, elevated platforms, and equip-
are two primary categoriesopen and or because of leakage, or may exist ment guarding.
totally enclosed. because of equipment breakdown that
simultaneously causes the equipment Process-Hazard Analysis. A process-
Relief-System Design. The purpose of to become a source of ignition. hazard analysis is a systematic method
a relief system is to protect piping and Class-I, Division-2 locations are to identify and analyze potential haz-
equipment from excessive overpres- defined as locations where volatile flam- ards associated with a facility. The goal
sure. Relief devices must comply with mable liquids or flammable gases or of the analysis should be to recommend
the appropriate ASME vessel codes, vapors exist, but normally are confined necessary design changes to make
and relief systems must comply with within closed containers; where ignit- the facility safe during abnormal or

68 JPT DECEMBER 2011


unplanned operating conditions. Each Recommended practices, codes, and After the facilities are built, there are
facility should be designed to ensure standards for building safe facilities two steps that should be taken. The first
that personnel, the environment, and are readily available. Most of these is conducting some type of process-
equipment are safe if control equip- items were first conceived after a major hazard analysis to ensure that all of the
ment fails (e.g., liquid-dump valves and incident and have continued to evolve. needed safety systems are in place and
pressure regulators), human operating Engineers and operations personnel that the operations personnel are not
errors occur (e.g., turning the wrong need to take time to acquaint them- placed at risk. The second step is to con-
valve or tank overflows), or mechanical selves with these recommended prac- duct a prestartup safety review to ensure
equipment fails (e.g., compressor-valve tices, codes, and standards to be com- that the piping, tanks, engines, pumps,
or pump-seal failure). The design also fortable with their use. and compressors have been installed
should account for risk from natural as planned. JPT
causes (e.g., rain, freezing weather, or
change of wind direction).
Results of the process-hazard anal-
ysis should include findings, a risk
ranking of the findings, and recom-
mendations to resolve those findings.
Recommendations should be followed
up with a list showing the party respon-
sible for making corrections and the
time frame in which the corrections
must be made.
Additions or changes to the facil-
ity that might affect safety or materi-
ally change the process-hazard analysis
must be reviewed. Companies often
use a management-of-change pro-
cess to ensure that changes do not
degrade safety systems already in place
at the facility.

Design Verification and Commission-


ing. The prestartup safety review is
a formal process to ensure that each
component and system in a facility is
checked thoroughly and is ready to be
brought into service. It is customary to
use checklists so that nothing is over-
looked and so that signoff can be per-
formed as each section is completed.
The checklists focus attention on each
key item and usually assign respon-
sibility for completion. It is impor-
tant that all disciplines be involved so
that no detail is overlooked. Therefore,
checklists are as extensive as necessary
for the particular facility, but not so
detailed that they become cumbersome
and ineffective. In the signoff process,
any individual or group has the ability
to delay startup until the issue of con- Whatever abrasive, high-pressure, high-
cern is resolved. volume operation you have planned
for your completion, youre going to
want packing thats up to the task.
Summary Our well service packing solutions are
Many incidents and injuries can be engineered to keep you up and running
through it all. Count on us.
prevented if production facilities are www.TuffBreed.com
designed properly. The first step is to
obtain management buy-in that all
injuries are preventable and that the
companys facilities should be built to
good industry practices and regula-
tory requirements.

JPT DECEMBER 2011 69


PRODUCTION FACILITIES

Independent Verification of Safety-Critical Elements

The main objectives of independent ing technologies and practices used UK Offshore Installations
verification are to help substantiate in the offshore industry to update the (Safety Case) Regulation
that current oil and gas best prac- requirements and evaluate compliance. Lord Cullens report was adopted in
tices are used; to provide assurance The maintenance of detailed regula- 1992 in The Offshore Installations
that facilities have been designed to tory requirements on how to construct (Safety Case) Regulationslater re-
operate safely throughout their life- safe installations or operate them prop- vised in 2005and several support-
time; and to ensure that all health, erly is resource intensive, and these ing regulations. Named the Safety
safety, and environmental risks requirements lag behind best indus- Case Regulations (SCR), it describes a
have been managed to acceptable try practices. framework of activities that are either
and as-low-as-reasonably-practicable The owner of offshore installations required or implied to demonstrate the
(ALARP) levels. Independent verifica- must be completely knowledgeable in safety of installations. The duty holder
tion anticipates the lack of applicable the regulations (or lack thereof) of each demonstrates its intention to manage
laws or standards, especially in new country in which it operates. its installations safely through safety
environments. This approach, initially The owner of offshore installations cases and by proving achievement of
introduced in the UK after the Piper is responsible only for complying with the regulators goals. Key steps that
Alpha disaster in 1988, is becoming an individual regulatory requirements. support the safety case are presented in
industry standard. Particularities of each offshore in- the following subsections.
stallation are not considered and, as
Introduction such, may not be analyzed as a whole, Identification of Major-Accident
A prescriptive approach to safety and within the context in which they Hazards (MAHs). To define the safety
environmental management of offshore operate. goals for an installation, the first step
installations relies on a selection of Complex working situations occur comprises identifying MAHs. The SCR
specific regulatory requirements devel- on offshore installations, possibly creat- defines a major accident as:
oped for all phases from design to ing dangerous conditions that must be Fire, explosion, or the release of a
decommissioning, which are imposed examined carefully and organized in dangerous substance involving death
by a regulator. The owners of the off- the best way possiblethe details of or serious personal injury
shore installations must follow exist- which cannot be foreseen in a prescrip- Any event involving major damage
ing standards, practices, guidelines, tive approach. to the structure of the installation or
and procedures. The same regulator loss of its stability
will evaluate the compliance through Goal-Setting Approach Collision of a helicopter with the
review, auditing, and inspections of The goal-setting approach was intro- installation
plans, permits, and related documents. duced through Lord Cullens 1990 Accidents linked to diving activities
Relying on this approach alone has report on the Piper Alpha disaster. Any other event arising from a
revealed several disadvantages. Instead of imposing rules, the regula- work activity involving death or serious
The regulator must understand and tor proposed specific quantifiable goals personal injury to five or more persons
be capable of keeping up with evolv- that the offshore installations owners The duty holder can extend this defi-
must meet. Hence, the owners have nition with additional requirements,
This article, written by Senior Technology flexibility on how they will meet these such as environmental concerns or
Editor Dennis Denney, contains highlights goals. An important change is that the economical or reputation effects.
of paper SPE 136392, Independent responsibility for managing safety and
Verification of Safety-Critical Elements, environmental aspects rests on the Strategy for Risk Reduction. UK regu-
by Julien Marty, Sophie Theys, SPE, duty holder, which is either the owner lations require a hierarchy of strategies
Christian Bucherie, Andy Bolsover, or the operator of the offshore instal- for managing and reducing risk from
and Philippe Cambos, Bureau Veritas, lation. The goal-setting approach does MAHs and adherence to the ALARP
prepared for the 2010 SPE Russian Oil & not exclude prescriptive regulations. principles. Hence, this step comprises
Gas Technical Conference and Exhibition, Often, hybrid solutions use elements finding ways to reasonably reduce the
Moscow, 2628 October. The paper has from both goal-setting and prescrip- risk for each MAH. A typical risk-
not been peer reviewed. tive approaches. management hierarchy prioritizes risk-

For a limited time, the full-length paper is available free to SPE members at www.jptonline.org.

70 JPT DECEMBER 2011


management actions. The strategy to verification can be defined as a system the Canada-New Foundland Offshore
reduce risk must ensure the following. of independent and competent scrutiny Petroleum Resources gathered all regu-
All staff understand their exposure of the suitability of SCEs throughout lations in December 2009 under the
to risk and are aware of emergency the asset life cycle. The whole process Canada Oil and Gas Operations Act
responses of identifying SCEs, producing PSs, (COGOA). Previously, the National
All risks are eliminated, controlled, and performing assurance is monitored Energy Board established a goal-setting
or mitigated to levels that are ALARP and verified by an independent compe- approach that was declined in each
All MAHs and risks are monitored tent person (ICP). The duty holder is of the provinces and territories with
and managed through a systematic responsible to select the independent offshore installations. Still, the prov-
approach verification body (IVB) and screen its inces have established implementation
ICPs. Verification is a sampling process acts following the COGOA that have
Identifying Safety-Critical Elements and includes document review, checks a more-prescriptive nature. In addi-
(SCEs). To avoid MAHs or to mitigate by calculation, physical examination, tion, the issuance of a certificate of
them, the duty holder will develop a testing, or witnessing of tests, audit, fitness for each installation by a certi-
list of SCEs applicable to its installa- and confirmation of records during the fying authority (five of them are cited)
tion. The SCEs are defined as parts life of the asset. is required.
of the installation or its operational
organization for which their failure Other Commonwealth Countries Other Adopted Approaches
could cause or contribute substantially Australia has been regulating offshore While the UK, Australia, and New
to a major accident, and their purpose installations since 1967, and the lat- Zealand require the acceptance of a
is to prevent or limit the effect of a est update to safety management has safety case and the intervention of
major accident. been ratified and published under the an IVB, other countries have opted
name of Offshore Petroleum (Safety) for varying solutions to ensure that
Production of Performance Stan- Regulations 2009 (OPSR). The prin- safety and environmental management
dards (PSs). The next step comprises ciples behind the Australian OPSR are are taking place. Also, companies that
expressing, in qualitative or quantita- very similar to those of the UK SCR, in historically have been linked to UK
tive terms, the performance required that OPSR requires the following. activities may opt for the goal-setting
for each SCE. This can relate to items An owner or titleholder must nom- approach as an integral part of their
of equipment, persons, or procedures. inate one person for each facility safety-management system.
These PSs define the following criteria The safety case must be accepted
for each SCE. by the safety authorityincludes the Country. Norway considers the accep-
Functionality same steps of hazards identification, tance of a safety case or similar docu-
Availability risks assessment, technical measures to ment by a regulator as a very resource-
Reliability reduce risk, and monitoring of continu- demanding exercise and, accordingly,
Survivability ous improvements and implementation does not require that step. However,
Interdependency The ALARP concept is used Norway does require the same risk
It is in the PSs that the duty holder Revisions of the safety case are per- assessment and description of how
can set prescriptive requirements, and formed every 5 years the operator intends to control identi-
they can be standards with which the The safety case must contain a fied risks. These documented assess-
SCE should conform. detailed description of the safety-man- ments and calculations must be avail-
agement system that accounts for all able to the Norwegian government
Assurance. The duty holder will per- hazards and risks to personnelnot (Petroleum Safety Authority, the State
form assurance activities to confirm just for major-accident events (equiva- Pollution Control Agency, or the
that the installation meets the require- lent to the UK MAH). Hence, a large Health Directorate) at any time. The
ments of individual PSs during design part of the safety case should be dedi- operator can, however, elect individu-
and throughout the operational life- cated to occupational health and safety, ally to perform a safety case and have
time of the installation. At the design including diving operations. it verified by an independent body.
stage, such assurance is undertaken Similarly, New Zealand has formal- Traditionally, the USA has had no
by the duty holder through the use ized the need for a health, safety, legal requirements for a safety- and
of appropriate codes and standards, and environment case as described in environmental-management sys-
best practices, risk-based approaches, Schedule 4 of its Health and Safety in tem. Instead, its national regulator
design reviews, peer checks and senior- Employment (Petroleum Exploration suggested programs based on the
engineer approvals, and third-party and Extraction) Regulations 1999. American Petroleum Institute (API)
interventions by suitably qualified, Again, the inclusion of potential Recommended Practice 75 (API RP 75).
experienced, and competent persons. hazards to/from the environment API RP 75 recommends a manage-
Assurance activities during the opera- extends the goal-setting approach ment program that covers 11 areas
tional phase include inspection, test, beyond hazards to persons. Self- especially management of changes in
and maintenance. monitoring and -reporting are the rec- personnel and facilities, establishment
ommended practice. of operating procedures, and a strong
Verification. Underpinning the safety In Canada, the National Energy emphasis in establishing goals and
case will be the verification scheme, a Board, the Canada-Nova Scotia performance measures. Its application
mandatory part of the UK SCR. The Offshore Petroleum Resources, and is limited to well drilling, servicing,

72 JPT DECEMBER 2011


and production; pipeline facilities; cerned by the gap between what they
SPE
Bookstore
and facilities that may have significant know as common practice and what is
safety and environmental effects. The required by the country.
International Association of Drilling These developments involve Arctic
Contractors has produced goal-setting features such as climate and seasonal www.spe.org/store
guidelines specific to mobile offshore variations, water- and atmospheric-cir-
drilling units. culation patterns, and effects of cold or
However, following the Deepwater ice on materials and personnel that will
Horizon drilling-rig explosion, the change the construction and operation
USA divided management of resourc- parameters greatly as well as the work-
es, oversight on safety and environ- ing conditions. Those extreme con-
ment, and management of assets into ditions often stretch the application
separate entities. At the time of writing of industrial standards outside their NEW TITLE
the original paper, the recommended intended envelope.
practices were being changed to rules, The intervention of the IVB is rec-
requiring implementation of a safety- ommended, particularly in the case
and environment-management system of a voluntary adoption of the goal-
(SEMS) covering hazard analysis, man- setting approach. It has access to expe-
agement of change, operating proce- riences of different operators and dif-
dures, and mechanical integrity, with ferent installations in many environ-
possible needs for audits. API RP 75 mental settings, and it can be an aid to
may be turned into a prescriptive regu- the regulator unfamiliar with the goal-
lation for offshore installations. setting approach. Again, the indepen-
dent competent personnel involved in
Owner or Operator. Several com- the safety and environment verifica-
panies have adopted the goal-setting tion should be different from those
approachspecifically the safety case performing the business verification.
as described by the UK SCRfor
their offshore installations outside the Introducing the Goal-Setting Ap-
North Sea or Australia. It also may be proach Into Regulation. To intro-
applied to onshore facilities. Owners duce the goal-setting approach into
and operators that develop activities law, a country may need to consider Low Invasion Coring
in new countries gain confidence in the following.
J.B. Bloys and H.R. Warner Jr.
their project by voluntarily following The roles of the regulator and
a goal-setting approach. It helps them industry participants must be defined
maintain their exposure to risk at clearly and divided in such a way that The latest addition to SPEs Monograph Series,
similar levels, wherever they operate, the responsibilities are known from Low Invasion Coring will help readers develop
and for whichever assets and fields the outset. an understanding of how to apply the array of
they operate. It encourages their engi- The number of regulators should technologies required for successful completion
neers to think through design aspects be limited. In particular, the body of a low-invasion-coring (LIC) project. This
monograph addresses the principles of obtaining
critically instead of relying only on responsible for management of hydro-
low-invasion cores and provides essential
prescriptive requirements, especially carbon resources (hence, hydrocarbon
practical tips for engineering eld LIC projects.
when engineers are not familiar with production) should be distinct from Appendices provide detailed information on
local requirements. In these cases, the regulatory body responsible for specic core-analysis procedures.
owners and operators often follow the safety and/or environment.
Contents:1SFQMBOOJOHt-PXJOWBTJPODPSJOH
local mandatory prescriptive approach In the case of a federationsuch
CJUTFMFDUJPOt0UIFSEPXOIPMFIBSEXBSFt
but also follow, on a voluntary basis, as Russiathe regulator must ensure -PXJOWBTJPODPSJOHnVJETt3JHTJUFPQFSBUJPOT
a goal-setting approach to gain confi- that the goal-setting approach and the t$PSJOHQPPSMZDPOTPMJEBUFETBOETUPOFt$PSF
dence in their asset designs. regulatory structure agree on the same analysis
approach at all levels of the nation.
Appendices include: Summaries of selected
Observations The regulator should set essential
41&QBQFSTDPODFSOJOH-*$UFDIOPMPHJFTt4QFDJBM
Several Russian oil and gas develop- safety goals (keeping in mind that circumstancessponge coring and the use of
ments are in harsh, Arctic, offshore, the operator is entirely responsible OPOJOWBEJOHDPSFHFMt*NQBDUPGPJMCBTFENVE
and/or sensitive environments. State for implementing safety and envi- on connate water saturation and other rock
regulations covering health, safety, ronmental management) and refer properties
and environmental management are to industry guidelines and standards
in place. However, there are two main for their application. This point pre-
aspects that can be of concern. vents development of detailed and
These developments involve for- narrowly scoped regulations that can-
eign companiesoperators and con- not deal with the range of situations
tractorswho are unfamiliar with that may occur in a rapidly changing
Russian requirements and are con- industry. JPT

Visit our online bookstore at


JPT DECEMBER 2011 www.spe.org/store
PRODUCTION FACILITIES

Performance Standards for Safety-Critical Elements


Are We Doing Enough?

Control and Hazard Outcome


Safety-critical-element (SCE) life- Prevention Mitigation (e.g., thermal, overpressure, toxic,
Barriers Barriers missiles, stability, or pollution)
cycle management involves identify-
ing major accident hazards (MAHs);
selecting SCEs by identifying structures
and plants that can cause, contribute
to, prevent, or help recover from a
Initiating Events

major accident event; and develop-


Hazards

ing the performance standards (PSs)


for the identified SCEs. It also involves
alignment of maintenance routines,
inspection and testing, performance Incident
Central
history, and other tasks required to Critical Event
maintain the SCE in a suitable con-
Causes Consequences Escalation Damages
dition. Continual monitoring of the
status of the hardware barriers and Fig. 1Scenario as a sequence of events.
performance-assurance tasks enables
the operating staff and management ed three headline events in the full- Identifying SCEs
to analyze the ongoing conformance of length paper to promote thought on The following methods are used by the
the SCEs by use of their PSs. the topic: the Montara wellhead-plat- industry to identify SCEs.
form blowout in 2009, the Deepwater
Introduction Horizon accident in 2010, and the Standard Companywide Checklist.
Although much has been achieved by Ocean Ranger semisubmersible sink- Some oil and gas operators use a com-
the oil and gas industry in terms of ing in 1982. These events suggest that, panywide checklist to identify SCEs.
reducing risk to personnel, the envi- perhaps, not enough is being done and, This method helps maintain consis-
ronment, and assets by use of SCEs therefore, more effort must be made to tency of the approach within various
and PSs, major accidents continue to reduce the number of major accident installations of the company.
happen. The concepts of SCEs and events or possibly prevent them.
PSs have been presented to prevent or Typical-Installation-Specific Check-
reduce the number of major accidents. Need for SCEs list. On the basis of existing knowl-
MAHs or major events are defined dif- Reliable Design and Engineering (Good edge of the type of installation (e.g.,
ferently in different parts of the world, Practices). SCEs and their PSs ensure floating production, storage, and
but have a common underlying theme that new installations or designs con- offloading vessels or mobile offshore
in that they can cause harm to multiple form to current good practice and reli- drilling-rig units), SCE-identification
people, cause substantial environmen- able engineering. For new installations, checklists are prepared and used for
tal damage, or cause expensive damage it is extremely important that their new installations.
to the assets. The author highlight- design be robust and that they be able
to perform their intended functions Comprehensive Risk Assessment.
This article, written by Senior Technology throughout their design life. Comprehensive risk assessment is the
Editor Dennis Denney, contains highlights best-practices approach to identify-
of paper SPE 140727, Performance Aging Installations. As current oil and ing SCEs and involves detailed iden-
Standards for Safety-Critical Elements gas installations get older, it is impor- tification of all hazards related to the
Are We Doing Enough?, by Rahul Dhar, tant to ensure that they remain capable design, construction, commissioning,
SPE, Abbott Risk Consulting, prepared for of performing intended functions in the operation, and decommissioning of the
the 2011 SPE European Conference on safest manner possible to avoid harm installation under consideration. This
Health, Safety, and Environmental in Oil to personnel or to the environment. assessment is achieved by performing
and Gas Exploration and Production, SCEs and their life-cycle-management several hazard-identification exercises
Vienna, Austria, 2224 February. The processes help achieve these goals and involving competent and experienced
paper has not been peer reviewed. reduce or prevent the major accidents. multidiscipline teams. One useful tool

For a limited time, the full-length paper is available free to SPE members at www.jptonline.org.

74 JPT DECEMBER 2011


to document information from these PSs that ensure the initial suitabil- Content of the PSs. PSs, or perfor-
hazard-identification workshops is a ity of SCEs in the design/construction/ mance-based standards, should be veri-
bowtie. Bowties are graphical rep- commissioning phase. fiable measures that provide qualitative
resentations that provide information PSs that ensure ongoing suitability targets and quantitative measures of a
related to the hazardous item/activity. of SCEs in the operational phase. prescribed minimum level of perfor-
Threats that could release a hazards PSs detail the following for each iden- mance. The major benefit of perfor-
potential are shown on the left-hand tified SCE. mance-based standards is a focus on
side, and consequences are shown on The goal of the SCE what must be done rather than on what
the right-hand side. On each threat The functional-performance re- should be done, as is the case with more-
branch, barriers are shown that are quirement for functionality, availabil- prescriptive regimes. However, with this
control measures to prevent the threat ity, reliability, and survivability system, the completeness, accuracy,
from arising. Similarly, on each conse- Dependencies on other SCEs and correctness of the content of the
quence branch, mitigation barriers and Detailed pass/fail acceptance criteria PSs are the responsibility of the person
recovery-control measures are shown by which SCE performance will be mea- who writes them. Moreover, there is no
that could reduce risk from the con- sured and recorded industrywide consensus on what should
sequences. Fig. 1 shows the barriers Reference material from which the be included as a minimum in the PS.
(SCEs) on the left and right side of a acceptance criteria are derived
central critical event. The PSs are aligned carefully to Performance Criteria. The perfor-
ensure that they relate directly to the mance criteria stipulated for SCEs are
Relationship of MAHs, SCEs, avoidance or mitigation of MAHs. A based mostly on recognized indus-
PSs, and Verification Activities verification and examination plan for try standards. However, in many
SCEs can be grouped into barriers that SCEs details the process undertaken instances, there are no clear criteria
prevent or limit the consequence of a in identifying the SCEs, preparing PSs, available in these recognized industry
major accident. Each barrier may con- verifying tasks for ensuring their suit- standards. The result is a challenge,
sist of one or more SCEs, which can ability, and arranging for maintenance which, in many cases, can be resolved
be broken down into components and of records. by use of the manufacturers informa-
finally into individual equipment-tag tion as criteria.
numbers. PSs were specified for all Challenges and Possible Solutions
identified SCEs and divided into two Several challenges could be encountered Maintenance Verification and Test
groups as follows. during SCE-life-cycle management. Frequency. In a report by the UK

Technology and Operational Excellence:


Keys to Sustainable Global Energy

Registration Deadline
23 January 2012

www.iptcnet.org/2011

RESCHEDULED 79 February 2012


#BOHLPL$POWFOUJPO$FOUSFBU$FOUSBM8PSMEr#BOHLPL 5IBJMBOE

SCAN ME TO
DOWNLOAD NOW
Host Organisation: Supported by: Ofcial Airline: Sponsored by:

Society of Petroleum Engineers

For more information, please contact International Petroleum Technology Conference (IPTC)
c/o SPE Asia Pacific Office (Kuala Lumpur)
Suite 23-02, Level 23, Centrepoint South, Mid Valley City Lingkaran Syed Putra, 59200 Kuala Lumpur, Malaysia
Tel: 60.3.2288.1233; 60.3.2182.3000 Fax: 60.32282.1200; 60.3.2182.3030 E-mail: iptc@iptcnet.org

JPT DECEMBER 2011 75


Health and Safety Executive, substan- lenge when the SCEs are retrofitted into ing expectations of the system custodian
tial maintenance backlog of SCEs was the overall maintenance-management and ambiguities in performance criteria,
identified. To ensure that the system system. It is important to use a system, working backward to specify only those
works, it is important to ensure that such as a traffic-light system, to monitor criteria that seem to be achievable by the
correct maintenance verification and the status (health check) of the SCE. maintenance manager, and budget con-
test frequency are allocated to the SCE. straints and lack of resources.
With the lack of industry standards Grading SCEs. Grading SCEs assists
on test frequency, standards are some- in prioritizing maintenance tasks on Availability/Reliability of SCEs. The
times assumed and then monitored for the basis of associated risks. However, best approach in specifying availability
effectiveness. The best practice is to use sometimes, the grading process itself and reliability targets for the SCEs is use
the risk-based approach to identify the can pose a challenge because the main- of a risk-based method by performing
optimum maintenance-verification and tenance team might keep delaying safety-integrity-level calculations. For
test-frequency requirements of the SCE. maintenance of a lower-graded SCE. It older installations that begin the pro-
Also, it is possible that the understand- is important to note that even the failure cess of identifying SCEs and PSs later in
ing of the technical authority with respect of lower-graded SCEs can result in a the operations phase, this information
to maintenance verification is different major accident. might be unavailable. Therefore, it is
from that of the maintenance operator recommended that operational experi-
who actually performs the tasks. To Entire Installation Becomes Safety ence be used to identify failure rates and
make the process successful, it is impor- Critical. It is important to identify SCEs that the safety-integrity-level calcula-
tant that technical-authority knowledge on the basis of MAH scenarios. The tions then be performed considering the
is passed to workers on the shop floor. tendency to include every part and all quantitative risk assessments completed
Training of the maintenance operator equipment of the installation in the SCE for the installation.
that is specific to the maintenance verifi- list should be avoided because it will
cation of the SCE should be an important defeat the purpose of the entire exercise. Passing/Failing Criteria. To avoid
part of the SCE-management process. ambiguity, PSs should have clear pass/
System-Custodian Verification. Veri- fail criteria. This method would assist
Maintenance-Management System. fication challenges include training the the verification operator in document-
Integration of SCE management into the system custodians and technical authori- ing results clearly, which could be used
overall maintenance-management sys- ties, interaction between system custo- for further analysis of the performance
tem of the installation can pose a chal- dian and maintenance operator, identify- of the SCE. JPT

Register Now
68 March 2012
San Diego, California, USA
Town & Country Resort & Convention Center
www.spe.org/events/dc

Society of Petoleum Engineers International Association


www.spe.org of Drilling Contractors
www.iadc.org

76 JPT DECEMBER 2011


If you play to win, not just any tool
will do. When the stakes are high
and the pressures on, call TAM.
Zonal isolation is what we do. No
matter your downhole challenge,
from cementing to stimulation and
anything in between, chances are,
weve seen it and solved it with
custom-engineered packers and
completion solutions. We are your
caddy, your pro and your greatest
fan in the worlds most challenging
rounds of oil and gas production.

To learn more about how


equipment matters, please visit
www.tamintl.com/equipment

www.tamintl.com

EQUIPMENT MATTERS

You might also like