Section A

General Conditions and Preliminaries


Item Description Unit Quantity Quantity Rate Amount
Allow for perliminaries and complying with condition of contract as follows

1 Site Management cost(including site staff,progress reports,monthly progress photographs

2 Taking Levels and setting out of works


Levels / Asbuilt
Alignment

3 Complying with all regulations and paying all fees,deposits,etc for temporary water and
electric supplies,testing & commisioning etc
4 Protection and / or making good of existing road , drains,etc

5 Provide all temporary buildings ( including site office , labour quarters, store, etc

6 Provide scaffolding

7 Provide all plants and equipment necessary

8 Provide all insurance policies

9 Safety , health and welfare of work people and work sites

10 Contribution to CIDB

11 Timber hoarding to 1.8 m ht using painted plywood as screen and timber structures as
support , if or where indicated
12 Removal of debris
Remarks
Section B
Piling ( All Provisional) Quoted Actual
Item Description Unit Quantity Quantity Rate
1 Allow for the provision of all necessary piling equipment plant and tools
for their transportation to the site , assembling and removal off site after completion
of operations

2 Allow for moving and handling piping equipment about the site as and whenever
necessary for the whole operation , including temporary platforms to ensure smooth
operations of piping works

3 Supply transport , handle , pitch , unload around the site and drive the following 1152m 1000m
precast reinforced concrete ( Grade 45) piles to the satisfaction of the engineer
including driving of extension of lengthened piles

4 Piling recods

5 Load test (PDA) 2 500 1000

6 Cutting off surpluss length of precast piles at levels indicated on the drawings or as 64
instructed , prepare pile heads to receive pilecaps and remove form site
Amount Remarks
Section C
Substructure ( Work Below lowest floor finish ) Quoted Actual
Item Description Unit Quantity Quantity Rate Amount
1 Excavation works
All excavation works including removing surplus earth from site
a) Footings m3 39.1 48.72
b) Ground Beam m3 72.4 24.94
c) Warehouse floor slab m3 660 659.26
d) Apron and driveway m3 662 240.52
e) Pipeculvert drain m3 93.8
f) Brick sump m3 34.6

1a Hacking of concrete at concrete slab area

2 Reinforced concrete
Reinforced concrete including all neccesary reinforcement and formwork
Footings / pile caps
a) Concrete grade 30 m3 10.5 27.6
b) Sawn formwork m2 53.6 139.2
c) Reinforcement kg 1077 3601.6

3 Stump ( P-1,2,4)
a) Concrete grade 30 m3 4 34.5
b) Sawn formwork m2 38.5 174
c) Reinforcement kg 1026 4759.84

4 Ground Beams
a) Concrete grade 30 m3 22.7 22.67
b) Sawn formwork m2 201.5 201.52
c) Reinforcement kg 3339 7000

5 Concrete Floor
Reinforced concrete including layer of damp proof membrane and all
neccesary formwork and fabric reinforcements as per drawing and
specification
a) 200 mm concrete grade 30 m3 329.7

b) Sawn formwork m2 48.7

c) Reinforcement ( Y10-2) kg 33500

d) DPC m2 1648

6 Apron & driveway floor slab


a) 200mm concrete grade 30 m3 331

b) Reinforcement ( BRC A7-2 layer) m2 1655

7 Lean concrete
50 mm thk lean concrete
a) Footing / pile caps m3 4
b) Ground beams m3 4
c) Ground slab

8 Hardcore
200 mm thk hardcore as specified rammed consolidated and blinded with sand to
receive concrete
a) Ware house ground floor m2 1648
b) Apron & driveway m2 1655
Remarks

Recommended Item
Section D
Roof Finished and rain water goods Quoted Actual
Item Description Unit Quantity Quantity Rate
1 Steelstructure including column , rooftruss , tie rods, fascia truss, gutter awning,crane runway,
tip beam & jack roof truss 107864.43
a) Portal Frame/bay (Attachment 1) 62056.40
b) Rooftruss(Attachment 2) 8345.59
c) Jack Roof truss(Attachment 4) 1144.80
d) Tie Beams(Attachment 5) 6988.00
e) Fascia truss(Attachment 6) 350.00
f) Gutter awning
g) Sag bar and channel(Attachment 7) 426.00
h) Overhead crane(Attachment 8) 28553.64
j) Wind bracing(Attachment 9)
k) Gusset plate
l) Bolt and nuts

2 Roof covering and rainwater goods ( Metal roofing 0.47mm thk Ajiya or equivalent )
a) Warehouse m2 1996.00 1814.66
b) Wall m2 1348.00 1312.5
c) Flashing m2 183.00
d) Capping m2 214.00
e) Awning(Top) m2 815.00 528
f) Stainless steel gutter (0.75mm) m 82.00
g) uPVC rainwater downpipe m 224.00
h) Alum framing louvre nos 2.00

3 Painting Ls
Amount Remarks

No material spec given

N/A
Section E
Other Works Quoted Actual
Item Description Unit Quantity Quantity Rate Amount
1 Any other works not mentioned above but shall be deemed necessary for the overall
completion of the works to provide / submit details
a) 300 mm pipe culvert drain
b) Brick sump ( 600mm x 600mm)
c) Power float (warehouse floor)
d) Power float (apron & driveway)
e) Painting carpark line

2 Firesystem / hose reel system


a) Break glass & bell
Emergency light
Armoured cable with junction ( 135m x 7 core x 1.5mm)
Hose reel pipe ( 102m - 50mm)
GIB underground pipe (12m - 50mm)
Dropper pipe (18m - 25mm)
Hose reel drum (3 sets)
ABC dry powder fire extinguisher (9kg - 5nos)
Testing & Commisioning
Submit and approval

3 Electrical work / lighting


Lighting point using ( 2 x 1.5mm)
36w bare channel fluorescent light (awning walkway area)
13 A twin switch socket
TPN isolator point ( 30A-60A-200A)
HPS High Bay (250w)
Floodlight (400w)
Underground form TNB substation 200 TPN distribution board
Testing & Commissioning
Double girder electric overhear traveling crane
Remarks