Item Description Qty. Unit Cost % Accomplishment Amount

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

ACCOMPLISHMENT FORM

PROJECT:
BUILDER:ROQUE VILLAJUAN
DATE COVERED:
DATE PREPARED

Item Description Qty. Unit Cost % ACCOMPLISHMENT Amount


Total to
101,712.00 Date Previous To Date
HOUSING
CONCRETING
COLUMNS 1 lot 6,900.00 20% 20% 1,380.00
ROOFBEAM 1 lot 6,175.00 0% 0% -
GR.FLR.SLAB & FOYER 1 lot 3,355.00 0% 0% -
ELEV.FLR.SLAB 1 lot 3,557.00 0% 0% -
BACKFILLING 1 lot 1,000.00 0% 0% -
CONC. STAIRS 1,500.00
MASONRY
GR.CHB LAYING 1 lot 7,190.00 50% 50% 3,595.00
ELV. CHB LAYING 1 lot 3,460.00 50% 50% 1,730.00
PLAST. INT 1 lot 11,997.00 0% 0% -
COL. COR 1 lot 2,300.00 0% 0% -
WIN.COR 1 lot 5,700.00 0% 0% -
PLAST. EXT 1 lot 13,823.00 0% 0% -

SEPTIC
Excavation & Laying 1 lot 2,700.00 90% 80% 10% 270.00

TOTAL 101,712.00 DUE TO DATE 6,975.00

249.107143
Total for 10 units
Area

ALL COST IS SUBJECTED TO 10% RETENTION PAYABLE 1 MONTH UPON COMPLETION


0.4935225

193.75

LE 1 MONTH UPON COMPLETION