Item Description Qty. Unit Cost % Accomplishment Amount
Item Description Qty. Unit Cost % Accomplishment Amount
Item Description Qty. Unit Cost % Accomplishment Amount
PROJECT:
BUILDER:ROQUE VILLAJUAN
DATE COVERED:
DATE PREPARED
SEPTIC
Excavation & Laying 1 lot 2,700.00 90% 80% 10% 270.00
249.107143
Total for 10 units
Area
193.75