Laporan Bulanan August 2016
Laporan Bulanan August 2016
11
Aug 2016
I. PROJECT DESCRIPTION
TOWER 2 (OFFICE)
LAND AREA :-
Page 1 / 73
Monthly Progress Report No.11
Aug 2016
Design Consultant :
Geo Teknik : PT Geo Prima
Road & Drainage : PT Aramsa Infrayasa
Architect : PT Airmas Asri
Structures : PT Haerte Widyatama Konsultan
MEP : PT Hamparan Prima Mandiri
Faade : Paul Adam Facades
Landscaping : PT Bouganvillea Cipta
Special Lighting : Hadi Komara& Associates
Traffic : PT Pamintori Cipta
Quantity Surveyor (QS) : PT Wilde Woollard Indonesia
AMDAL : PT. Delta Proling Pratama
Direct Contractors
1. Package of Package Pelebaran Jalan : PT Pembangunan Perumahan (PP)
2. Package of Bored Pile Works : PT Handal Subur Lautan (HSL)
3. Package of Diaphragm Wall : PT Indopora (IPR)
4. Package of Excavation Works : PT Sinar Jaya Andalas Nusantara (SJAN)
5. Package of Ground Anchor : PT Dinamika (DSS)
6. Package of Dewatering : PT Tarumanegara Bumiyasa
7. Package of Capping beam : PT Duta Karya Rekatama (DKR)
8. Package of Strutting beam : PT Mitra Jaya Raharja (MJR)
9. Vanity Top Table : tba
10. Exterior Stone Work (install) : tba
11. External Stone Work (Hardscape) : tba
12. Interior Wall Lobby (Main Lobby GF & Typical Lift Lobby) : tba
13. Special Ceiling works Lobby : tba
14. Landscape works : tba
15. Pool & Water features (Finishes) : tba
16. Kitchen Units : N/A
17. Marble Installation : tba
Page 2 / 73
Monthly Progress Report No.11
Aug 2016
Direct Supplier
1. Marble : tba
2. Sanitary wares : PT. Surya Pertiwi
3. Generator sets : PT. Altrak 1978
4. Transformers : PT. ABB Sakti Industri
5. Cooling Towers : tba
6. Pumps to VAC and Plumbing : tba
7. Fire Pumps : PT. Baskara Prima Sarana
8. Fans : tba
9. Water Heaters : tba
10. VRV/Single AC Split system : tba
11. Special Lighting : tba
12. MV Switchgear : PT. ABB Sakti Industri
13. LV Switchgear : tba
14. Street Lighting : tba
15. Audio/Video Entry Phone : tba
16. CCTV : tba
17. Sound/PAS system : tba
18. Precast Piles : N/A
19. Lifts : PT. Mitsubishi Jaya Elevator & Escalator
PC Rates to LTJO
1. Ready Mix Concrete
2. Steel Reinforcement bar
3. Aerated block works
4. Homogeneous Tiles
5. Ceramic Tiles
Page 3 / 73
Monthly Progress Report No.11
Aug 2016
1. Organization Chart
Page 4 / 73
Monthly Progress Report No.11
Aug 2016
2. Staffing Schedule
Dated : 31 Jul 2016
Duration 2015 2016 2017 2018
No Position Name Start Finish Remarks
(Month) 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06
1/Jul/2015 30/Jun/2018 36 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 Project Manager Yunseung Jun
1/Jul/2015 13 2 2 2 2 2 2 2 2 2 2 2 2 2
15/Aug/2015 30/Jun/2018 35 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Engineering Manager Minhwan Ko
30/Jul/2015 13 2 2 2 2 2 2 2 2 2 2 2 2 2
1/Jul/2015 30/Jun/2018 36 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Cost / Planning Manager Hyungjik Nam
1/Jul/2015 13 2 2 2 2 2 2 2 2 2 2 2 2 2
30/Sep/2015 30/Jun/2018 34 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Design Manager Han Il Cha
12/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
31/Aug/2015 30/Jun/2018 35 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Construction Coordinator Sangchul Baik
15/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
31/Aug/2015 31/May/2018 35 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 GA Manager Hyun Young Park
30/Jul/2015 13 2 2 2 2 2 2 2 2 2 2 2 2 2
30/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Senior MEP Manager Byung Jin Lee
2/Jan/2016 7 2 2 2 2 2 2 2
30/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 Deputy Project Manager Kwanghyu Lee
23/Nov/2015 8 2 2 2 2 2 2 2 2
1/Aug/2015 30/May/2018 34 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
10 Construction Manager Yayan Sofyan
24/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
10/May/2016 31/Jan/2018 29 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
11 Site Manager Tower 3 Yarmen
3 2 2 2
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 Site Manager
15/Jun/2016 0
1/Dec/2015 30/Apr/2018 29 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
13 Site Manager Tower 2 Agus Gunawan
28/Sep/2015 9 2 2 2 2 2 2 2 2 2
1/Nov/2015 30/Apr/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
14 Site Manager Podium Sutejo RESIGNED
28/Sep/2015 6 2 2 2 2 2 2
Site Engineering 0
17 Evrialdy
Manager 1/Dec/2015 8 2 2 2 2 2 2 2 2
1/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
18 Security Manager Nurcholis
28/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
Secretary / 0
24 Rifan Hermawan
Administration 3/Feb/2016 3 2 2 2 2 2 2
Secretary / 0
25 Retno Wulandari Adelina
Administration 15/Feb/2016 6 2 2 2 2 2 2
Secretary / 0
26 Putri Rizqy Amaliah
Administration 28/Jan/2016 7 2 2 2 2 2 2 2
15/Sep/2015 30/Apr/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
27 Quality Control Manager Bambang Widiyanto
8/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
21/Jul/2016 0
28 QC Engineering Sakhrudi
1 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
29 Quality Control Eka Indra
7/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Nov/2015 31/06/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
30 Quality Control Khaeron
19/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
Page 5 / 73
Monthly Progress Report No.11
Aug 2016
1/Jan/2016 31/06/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
32 Quality Control Adiyta Novali
16/Nov/2015 9 2 2 2 2 2 2 2 2 2
30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
33 Quality Control Asep Amin Nurdin
22/Apr/2016 4 2 2 2 2
0
34 Quality Control Hariyanto
11/Jan/2016 7 2 2 2 2 2 2 2
0
35 Quality Control Tua Siagian
7/Dec/2015 8 2 2 2 2 2 2 2 2
0
36 Quality Control Marlan Nugraha RESIGNED
30/Sep/2015 16/Nov/2015 3 2 2 2
0
37 Quality Control Moch. Mashari RESIGNED
16/Nov/2015 4 2 2 2 2
0
38 QC Inspector Adhy Ghuna
17/Feb/2016 6 2 2 2 2 2 2
0
39 QC MEP Sunardi
18/Jan/2016 7 2 2 2 2 2 2 2
0
40 QC MEP Amif Tahudin
15/Feb/2016 6 2 2 2 2 2 2
1/Aug/2015 31/04/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
41 Safety Manager Budi Sastra
3/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 30/Apr/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
42 Safety Man Victor Sihombing
7/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
43 Safety Supervisor Aji Ismayan RESIGNED
7/Sep/2015 30/Dec/2015 4 2 2 2 2
1/Dec/2015 31/May/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
44 Safety Man M. Cakra Satria
25/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Dec/2015 30/May/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
45 Safety Man Arif Yudiana
12/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
19/Jul/2016 30/May/2018 29 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
46 Safety Man TBA
0
1/Jan/2016 30/May/2018 29 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
47 Safety Officer Wiwin Sudarmo
1/Nov/2015 9 2 2 2 2 2 2 2 2 2
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
48 Safety Officer Jumari Slamet Riyadi
16/Mar/2016 5 2 2 2 2 2
0
49 Safety Patrol TBA
0
01/006/2016 30/May/2018 29 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
50 Safety Patrol Fakhrizal
2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
51 Chief ARC&STR Drafter Bayuadi Aspinanto RESIGNED
3/Aug/2015 11 2 2 2 2 2 2 2 2 2 2 2
13/May/2016 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
52 Drafter Design Triyanto
3 2 2 2
1/Jul/2015 30/02/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
53 Drafter STR Deny
26/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
54 Drafter STR Dedi Hamzah
28/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
55 Senior Arch. Drafter Muhammad Nurcahya
4/Jan/2016 7 2 2 2 2 2 2 2
0
56 Senior Drafter Cahya Budi Wibawa RESIGNED
3 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
57 Drafter ARC Jero Vaku Dewa RESIGNED
9-Nov-15 4 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
58 Site Engineer Christoph Noiya
16/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
59 Electrical Draftsman Safi Anam
1/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
60 Mechanical Draftsman Dodi Fassah
17/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
Page 6 / 73
Monthly Progress Report No.11
Aug 2016
0
62 Drafter Rahmat Padmawijaya
15/Feb/2016 6 2 2 2 2 2 2
0 F
63 Drafter Bagas Wisodo RESIGNED
1 2
0
64 Drafter Hendra Gunawan RESIGNED
10/Dec/2015 3 2 2 2
0
65 Drafter MEP Satriyo Miharno
25/Jan/2016 7 2 2 2 2 2 2 2
0
66 Chief BBS Andjar Rachmad
1/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 31/Dec/2017 28 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
67 BBS R. Poerwo
9/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 31/Dec/2017 28 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
68 BBS Mangara Manurung
1/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 31/Dec/2017 28 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
69 BBS Moh. Sahri RESIGNED
1/Sep/2015 4 2 2 2 2
1/Sep/2015 30/Apr/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
70 QS Manager Yus Fadlillah
1/Jul/2015 13 2 2 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
71 QS Senior Dekmark Tampubolon
21/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/Mar/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
73 Quantity Surveyor Guntur I. Sahputra
1/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/Mar/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
74 Quantity Surveyor Dzul Fikri Rasyidi MUTATION
2/Oct/2015 6 2 2 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
75 Quantity Surveyor Aan Pujiandi
9/Nov/2015 8 2 2 2 2 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
76 Quantity Surveyor Hendra Yudha Kamal MUTATION
4/Jan/2016 3 2 2 2
0
77 Quantity Surveyor Rijon Siahaan
29/Dec/2015 8 2 2 2 2 2 2 2 2
0
78 Quantity Surveyor Afina Khalida Rahma
10/Feb/2016 6 2 2 2 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
79 Cost Controller Alva Prita Damayanti MUTATION
5/Oct/2015 5 2 2 2 2 2
0
80 Cost Controller Yulianto Dwi Putro
18/Dec/2015 8 2 2 2 2 2 2 2 2
0
81 Ast Cost Controller Fadillah Gaffar
9/Nov/2015 9 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
82 Scheduler Stefanus Agung
28/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 30/Jun/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
83 STR. Chief Supervisor 1 Imam Syafi'i RESIGNED
28/Aug/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 31/Jul/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
84 STR. Chief Supervisor 3 Fariz Mahdi
5/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/Dec/2015 30/Oct/2017 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
85 STR. Chief Supervisor 2 Hery Aria Sandi
18/Jan/2016 7 2 2 2 2 2 2 2
1/Oct/2015 31/May/2017 20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
86 BBS Miftahul Huda
18/Jan/2016 7 2 2 2 2 2 2 2
1/Jul/2015 30/Apr/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
87 Supervisor STR 1 Pahala Tampubolon RESIGNED
21/Sep/2015 6 2 2 2 2 2 2
1/Jul/2015 30/Apr/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
88 Supervisor STR 1 Diding
3/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 31/Jul/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
89 Supervisor STR 3 Zainal
7/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 31/Jul/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
90 Supervisor STR 3 Asep Hifdayat RESIGNED
5/Oct/2015 6 2 2 2 2 2 2
1/Sep/2015 31/Jan/2017 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
91 Rebar Supervisor Joko Prasetyo
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/Sep/2015 31/Jan/2017 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
92 Supervisor STR 1 Hasanudin RESIGNED
1/Aug/2015 7 2 2 2 2 2 2 2
Page 7 / 73
Monthly Progress Report No.11
Aug 2016
1/Dec/2015 30/Oct/2017 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
94 Supervisor Formwork Nixon Tobing
1/Feb/2016 6 2 2 2 2 2 2
1/Dec/2015 30/Oct/2017 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
95 Supervisor STR 2 TBA
0
1/Dec/2015 30/Apr/2017 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
96 Rebar Supervisor Masruhi
9/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Dec/2015 30/Apr/2017 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
97 Supervisor STR 3 Suprayitno Heri Seto
28/Dec/2015 8 2 2 2 2 2 2 2 2
1/Dec/2015 30/Sep/2017 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
98 Rebar Supervisor Kurnia Fajar Islamto
1/Dec/2015 8 2 2 2 2 2 2 2 2
0
99 Rebar Supervisor Suroso RESIGNED
15/Feb/2016 5 2 2 2 2 2
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
100 Rebar Supervisor Sartim Gotawa
1/Nov/2015 10 2 2 2 2 2 2 2 2 2 2
0
101 Supervisor Finishing Bambang Harsono
11/May/2016 3 2 2 2
1/Dec/2015 30/May/2017 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
102 Asst Surveyor Warnadi
3/May/2016 3 2 2 2
1/Dec/2015 30/May/2017 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
103 Supervisor Casting M Fuad Hasan
3 2 2 2
16/May/2016 30/May/2017 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
104 Spv. Finishing Widoyo
3 2 2 2
16/May/2016 30/May/2017 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
105 Surveyor Imam Taufan
3 2 2 2
16/May/2016 31/Jan/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
106 Surveyor Fajar Fuadi
3 2 2 2
21/May/2016 30/Apr/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
107 Senior Surveyor Kartius Rumapea
3 2 2 2
21/May/2016 30/Jun/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
108 Asst. Mechanic Harry Siahaan
3 2 2 2
6/Jun/2016 30/Jun/2018 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
109 Spv Finishing Petrus
2 2 2
9/Jun/2016 31/Jan/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
110 Chief Surveyor Heri Sunarto
2 2 2
9/Jun/2016 30/Apr/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
111 Ass Survey Muhammad Husnan
2 2 2
1/Oct/2016 30/Jun/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
112 Supervisor Struktur Sugiyanto
2 2 2
18/Jul/2016 30/Dec/2017 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
113 Spv Concrete Makmur
1 2
18/Jul/2016 30/Dec/2017 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
114 CM Finishing Sigit
1 2
21/Jul/2016 30/Dec/2017 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
115 SM Finishing Kusnen
1 2
1/Sep/2016 30/Apr/2018 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
116 Supervisor Arch. 3 TBA
0
1/Sep/2016 30/Apr/2018 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
117 Supervisor Arch. 3 TBA
0
1/Sep/2016 30/Apr/2018 18 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
118 Supervisor Arch. 3 TBA
0
1/Dec/2016 30/Apr/2018 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
119 Supervisor Arch. 2 TBA
0
1/Dec/2016 30/Apr/2018 17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
120 Supervisor Arch. 2 TBA
0
1/Jun/2016 30/Jun/2018 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
121 Supervisor Arch. Podium TBA
0
1/Aug/2016 30/Apr/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
122 Supervisor Arch. Podium TBA
0
23/Jul/2016 0
123 Spv Concrete Roby
1 2
1/Aug/2016 30/Apr/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
124 Supervisor Arch. Podium TBA
0
15/Jul/2015 31/May/2018 35 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
125 Chief Surveyor Masrizal RESIGNED
1/Sep/2015 4 2 2 2 2
Page 8 / 73
Monthly Progress Report No.11
Aug 2016
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
127 Surveyor Heriyanto RESIGNED
9/Sep/2015 3 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
128 Surveyor M. Ridwan
21/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
1/Oct/2015 30/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
129 Surveyor Joseph
12/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
1/Mar/2016 30/Apr/2018 26 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
130 Surveyor Andar Tambunan
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/Mar/2016 30/Apr/2018 26 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
131 Surveyor Solihin
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/Mar/2016 30/Apr/2018 26 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
132 Surveyor Darwit
18/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Mar/2016 30/Apr/2018 26 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
133 Surveyor Ilham
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/May/2016 31/May/2018 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
134 Surveyor Rohman
1/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/May/2016 31/May/2018 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
135 Surveyor Rijal RESIGNED
14/Aug/2015 10 2 2 2 2 2 2 2 2 2 2
1/May/2016 31/May/2018 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
136 Surveyor Loniko Sitorus
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
137 Surveyor Marisi Sirait MUTATION
17/Feb/2016 4 2 2 2 2
0
138 Surveyor Edy Sarwono RESIGNED
11/Feb/2016 5 2 2 2 2 2
0
139 Surveyor Gokma Simanungkalit
10/Dec/2015 8 2 2 2 2 2 2 2 2
0
140 Ast Surveyor Dwito Hendro RESIGNED
20/Jan/2016 5 2 2 2 2 2
0
141 Ast Surveyor Friderik Abednego S.
28/Jan/2016 7 2 2 2 2 2 2 2
0
142 Ast Surveyor Anhari
7/Dec/2015 8 2 2 2 2 2 2 2 2
1/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
144 Mech. Engineer Kaswanto
18/Jan/2016 7 2 2 2 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
145 Mech. Engineer TBA
0
1/Apr/2016 31/Jan/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
146 Mechanic Nurwahid
16/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
1/Jul/2016 30/Apr/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
147 MEP Supervisor Adi David Sihombing
1/Sep/2015 5 2 2 2 2 2
1/Nov/2016 30/Jun/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
148 MEP Supervisor Andrian Lubis
4/Jan/2016 7 2 2 2 2 2 2 2
1/Nov/2015 30/Apr/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
149 Electrical Manager Priyo Sudewo
1/Dec/2015 8 2 2 2 2 2 2 2 2
0
150 MEP Supervisor Sofi Firmansyah
10/Feb/2016 6 2 2 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
151 Elec. Manager TBA
0
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
152 Elec. Engineer Sugeng Widodo
1/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
1/Nov/2015 30/Jun/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
153 Elec. Engineer TBA
0
9/Jun/2016 30/Jan/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
154 Chief Mekanik Lundu Sitohang
2 2 2
9/Jun/2016 30/Apr/2018 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
155 Ass Mekanik Febrianto Hutahaean RESIGNED
1 2
1/Oct/2016 30/Jun/2018 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
156 Elec. Supervisor 2 TBA
0
1/Nov/2015 30/Apr/2018 30 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
157 Supervisor ME Taufik Jauhari RESIGNED
22/Feb/2016 1 2
1/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
158 Material Assist. Aep Saefulloh
14/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
Page 9 / 73
Monthly Progress Report No.11
Aug 2016
0
160 Cashier Hermansyah Saad
8/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
Human Resources 0
161 Hulman Tobing
Supervisor 30/Nov/2015 8 2 2 2 2 2 2 2 2
1/Oct/2015 31/May/2018 32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
162 General Affairs Sabda
11/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
0
163 General Affairs Yohanes
21/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
0
164 Human Resources Ahmad Yuri RESIGNED
1/Oct/2015 2 2 2
0
165 Document Controller Diana
1/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
0
166 Document Controller Glory Afriani
15/Dec/2015 8 2 2 2 2 2 2 2 2
Assistant Document 0
167 Anzar
Controller 15/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
168 Assistant Surveyor Ricard Ricardo
2/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
169 Assistant Surveyor Bariyono RESIGNED
1/Oct/2015 6 2 2 2 2 2 2
0
170 Assistant Surveyor Umam
14/Aug/2015 12 2 2 2 2 2 2 2 2 2 2 2 2
0
171 Chief Material Control Sutomo
1/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
172 Material Control Natal Tambunan
14/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
0
173 Material Control Zainal Abidin
14/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
0
174 Material Control Sriyanto
19/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
175 Material Control Rominton S
13/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
176 Material Control Kasdovan Antonius
29/Sep/2015 11 2 2 2 2 2 2 2 2 2 2 2
0
177 Material Control Marlon Sitorus
12/Nov/2015 9 2 2 2 2 2 2 2 2 2
0
178 Material Control Prima Adianta Barus
22/Dec/2015 8 2 2 2 2 2 2 2 2
0
179 Material Checker Irwan Suyudi
21/Dec/2015 8 2 2 2 2 2 2 2 2
0
180 Material Control Andi Setiadi RESIGNED
22/Dec/2015 1 2
0
181 Mechanic Irwan Puji
17/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
182 Mechanic Budi Prayogo
17/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
183 Mechanic Cholis Muchlisin
6/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
184 Assitant Mechanic Deki Santoso
13/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
Page 10 / 73
Monthly Progress Report No.11
Aug 2016
0
186 Assitant Mechanic Luis Adam
20/Nov/2015 9 2 2 2 2 2 2 2 2 2
0
187 Assitant Mechanic Jekson Silalahi
22/Oct/2015 10 2 2 2 2 2 2 2 2 2 2
0
188 Spv Cleaning Tower 1 Sandro Imanuel
18/Feb/2016 6 2 2 2 2 2 2
0
189 QA Engineer Yudia Akbar
18/Feb/2016 6 2 2 2 2 2 2
0
190 Spv Cleaning Tower 3 Adiputra Simanjuntak
18/Feb/2016 6 2 2 2 2 2 2
0
192 Senior Scheduller Harryson Tampubolon
7/Mar/2016 5 2 2 2 2 2
0
193 Drafter Muhammad Nur Fadhillah
1/Mar/2016 5 2 2 2 2 2
0
194 Quantity Surveyor Rectifa Rio
7/Mar/2016 5 2 2 2 2 2
0
195 Site Engineer X. Muhammad RESIGNED
1/Mar/2016 3 2 2 2
0
196 Architectural Draftsman Hendy Prasetyo
7/Mar/2016 5 2 2 2 2 2
0
197 Quality Tester Dony Panjaitan
1/Mar/2016 5 2 2 2 2 2
0
198 Tower 1 Inspection Mgr Kentas Rubiyono
1/Mar/2016 5 2 2 2 2 2
0
199 BBS Production Sugiastono RESIGNED
1/Mar/2016 1 2
0
202 Assistant Surveyor Micarlos
7/Mar/2016 5 2 2 2 2 2
0
203 Drafter (Formwork) Umam
7/Mar/2016 5 2 2 2 2 2
0
204 Supervisor (Form work) Muhammad Soleh
7/Mar/2016 5 2 2 2 2 2
0
205 Supervisor (Stairs) Saiful Riza
7/Mar/2016 5 2 2 2 2 2
0
206 Supervisor (Conc'c) Royen MUTATION
7/Mar/2016 4 2 2 2 2
0
207 Supervisor (Conc'c) Adrian
7/Mar/2016 5 2 2 2 2 2
0
208 Supervisor (Form work) Supriyanto
7/Mar/2016 5 2 2 2 2 2
0
209 Safety Officer Suhaya RESIGNED
7/Mar/2016 1 2
0
210 Assistant Surveyor Rio Rikianyah
17/Mar/2016 5 2 2 2 2 2
0
211 Assistant Surveyor bayu ariyadi
24/Mar/2016 5 2 2 2 2 2
Electrical Engineering 0
212 Frikelly Silaban
MEP 2/May/2016 3 2 2 2
0
213 Assistant Surveyor Deri Hermansyah
29/Mar/2016 5 2 2 2 2 2
0
214 Drafter Structure Design Hafizur Rahman
1/Apr/2016 4 2 2 2 2
0
215 Safety Manager Nuridin
13/Jun/2016 2 2 2
Page 11 / 73
Monthly Progress Report No.11
Aug 2016
0
217 Drafter MEP P.Bambang p Adi
1/Apr/2016 4 2 2 2 2
0
218 Supervisor Structure Anna Dandy DS RESIGNED
11/Apr/2016 2 2 2
0
219 Asst. Mechanic Zaenal Arifin
15/Apr/2016 4 2 2 2 2
0
220 Asst Document Control M Abi Syahbani
2/May/2016 3 2 2 2
0
221 Architect Engineering Nicholas Atmajaya
16/May/2016 2 2 2
Plan 6 10 26 54 65 79 87 88 92 96 100 105 109 111 111 118 118 120 120 117 117 117 113 108 107 104 104 102 99 99 93 88 86 78 53 23
TOTAL LTJO STAFF
Actual 5 22 56 90 97 114 122 139 153 152 165 169 167 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
To be Assisgned
Newly Resigned
Page 12 / 73
Monthly Progress Report No.11
Aug 2016
Project Elapse Time : 31 July 2016 = 304 days / 974 days = 31.21%
% Elapse Time
304 Days
31.21 %
Total Period
Current Period
974 Days
Page 13 / 73
Monthly Progress Report No.11
Aug 2016
Quantity
Sub Up to
No Work Description Unit This Up to This Progress Remarks
Contractor Total Last
Month Month
Month
Stripping Heads of Bore Pile
1 LTJO NOS 1.207 1.138 10 1.148 96%
1000 & 800
PT. Catur Putra
2 Excavation M3 29.068 21.638 606 22.244 77%
Manunggal
SandBedding/
4 LTJO M2 34.906 26.826 3.846 30.672 88%
Lean Concrete
Page 14 / 73
Monthly Progress Report No.11
Aug 2016
Page 15 / 73
Monthly Progress Report No.11
Aug 2016
Staircase 7 1 1
Ramp 8 2 11
BW-1
Slab 443 7 62
Beam 160 6 32
Column 83 6 20
B-1
Staircase + SW 70 5 17
Ramp
BW-1
Slab 355 5 41
Beam 207 17 42
L2
***Above plan and quantity is based on 2nd Catch up schedule submitted on Jun, 2016
Page 16 / 73
Monthly Progress Report No.11
Aug 2016
The table below shows the Contractors Major Plan on Next Month (Aug).
*** On the submitted 2nd cacth up schedule, block work is planned to be started from August, 2016
Page 17 / 73
Monthly Progress Report No.11
Aug 2016
TO COMPLETE CONCRETING : Zone P1-9~P1-11 SLAB B4, Zone P1-1 SLAB B3, Zone P1-3 SLAB GF ; Zone P3-4~P3-6 SLAB
B5, Zone P3-2 SLAB B4~B3, Zone P3-1 SLAB B2~B1 ; Zone P2-1 SLAB B4~B2; Zone P2-2 SLAB GF
Page 18 / 73
Monthly Progress Report No.11
Aug 2016
TO COMPLETE CONCRETING : Zone T1-1~T1-4 SLAB L6~L8 ; Zone T1-1~T1-3 SLAB L9 ; Zone T1-1 SLAB L10 ; Zone T3-3
SLAB L4, ZONE T3-1~T3-3 SLAB L5~L8, ZONE T3-1 SLAB L9, Zone T2-1 & T2-4 SLAB L2, Zone T2-2 & T2-3 SLAB L3, Zone
T2-1~T2-4 SLAB L4, Zone T2-1~T2-3 SLAB L5, Zone T2-1 SLAB L6
Page 19 / 73
Monthly Progress Report No.11
Aug 2016
2) Tower 2
a. L2Zone T2-1 until T2-4 completed of formwork, rebar and concrete for beam
and slab
b. L3Zone T2-2 completed of formwork, rebar and concrete for beam and slab
c. GFZone P2-1 until P2-3, completed of formwork, rebar and concrete for
beam and slab
3) Tower 3
a. L4Zone T3-3 completed formwork, rebar and concrete for beam and slab
b. L5Zone T3-1 until T3-3, completed formwork, rebar and concrete for beam
and slab
c. L6 Zone T3-1 until T3-3, completed formwork, rebar and concrete for beam
and slab
d. L7 Zone T3-1 until T3-2, completed formwork, rebar and concrete for beam
and slab, Zone T3-3, completed formwork, rebar for beam and slab
e. B5 & B4Zone P3-2 completed formwork, rebar and concrete for beam and
slab
4) * Greatech
a) Tower 1 : Wiring cable installation lighting and power outlet at Basement 1
Angelo & Bella, Wiring cable installation lighting and power outlet at Basement 2
Angelo & Bella, Wiring cable installation lighting and power outlet at Basement 3
Angelo & Bella, Wiring cable installation lighting and power outlet at Basement 4
Angelo & Bella, Wiring cable installation lighting and power outlet at Basement 5
Angelo & Bella, Sleeve pipe for Installation EL& EC 4th Floor area T3,T4, Sleeve
pipe for Installation EL& EC 5th Floor area T2,T3,T4, Sleeve pipe for Installation
EL& EC 6th Floor area T1,T2,T3,T4, Sleeve pipe for Installation EL& EC 7th Floor
area T1,T2, Column & Wall installation EL & EC 5th Floor area T2,T3, Column &
Wall installation EL & EC 6th Floor area T1,T2,T3,T4, Column & Wall installation
EL & EC 7th Floor area T1,T2,T3,T4, Column & Wall installation EL & EC 8th
Floor area T1,T2,T3, In slab conduit for EL & EC Installation Basement 5 area P9
Page 20 / 73
Monthly Progress Report No.11
Aug 2016
c) Tower 3 : Wiring cable installation lighting and power outlet at Basement 1 Area
T1,T2,T3, Wiring cable installation lighting and power outlet at Basement 2 area
T1,T2,T3,P3, Wiring cable installation lighting and power outlet at Basement 3
area T1,T2,T3,P3, Wiring cable installation lighting and power outlet at Basement
4 area T1,T2,T3P1,P2, Wiring cable installation lighting and power outlet at
Basement 5 area T1,T2,T3P1,P3, Sleeve pipe for Installation EL& EC 3th Floor
area T1,T2,T3, Sleeve pipe for Installation EL& EC 4rd Floor area T1,T2,T3,
Sleeve pipe for Installation EL& EC 5th Floor area T1 T2,T3, Column & Wall
installation EL & EC 4th Floor area T1,T2,T3, Column & Wall installation EL & EC
5th Floor area T1,T2,T3, Column & Wall installation EL & EC 6th Floor area
T1,T2,T3
5) * Jayantara
a) Tower 1 : Installation Hydrant & Splinker Floor B3, Installation Hydrant &
Splinker Floor B2, Installation Hydrant & Splinker Floor B1, Installation sleeve FF
& Plumbing Floor B1 zone P3, Installation sleeve FF & Plumbing 6th Floor zone
T3, Installation sleeve FF & Plumbing 6th Floor zone T2, Installation sleeve FF
Floor B4 Zone P9, Installation sleeve FF & Plumbing 7th Floor zone T1,
Installation sleeve FF & Plumbing 6th Floor zone T4, Installation Hydrant &
Splinker Floor B1, Installation sleeve FF and Plumbing Floor B3 Zone P1,
Installation sleeve FF & Plumbing 7th Floor zone T4, Installation sleeve FF &
Plumbing 7th Floor zone T3, Installation sleeve FF & Plumbing 8th Floor zone T4,
Installation sleeve FF & Plumbing 8th Floor zone T3, Installation sleeve FF &
Plumbing 8th Floor zone T2, Installation sleeve FF & Plumbing 9th Floor zone T1,
Installation sleeve FF & Plumbing 9th Floor zone T2, Installation sleeve FF &
Plumbing 9th Floor zone P10, Installation sleeve FF & Plumbing 9th Floor zone
P11
b) Tower 2 : Installation Hydrant & Splinker Floor B3, Installation Hydrant &
Splinker Floor B4, Installation Hydrant & Splinker Floor B2, Sparing Retening Wall
zone P2, P3, Installation sleeve FF Floor GF Zone P3, Installation sleeve
Plumbing 2nd floor zone T2, Installation sleeve FF Floor GF Zone P1, Installation
sleeve Plumbing 3th floor area Toilet zone T3, Installation sleeve FF Floor GF
Zone P2
c) Tower 3 : Installation Hydrant & splinker Floor B3, Installation Hydrant &
splinker Floor B4, Installation Hydrant & splinker Floor B2, Installation sleeve FF &
Plumbing 4th Floor zone T3, Installation sleeve FF & Plumbing 4th Floor zone T2,
Installation sleeve FF & Plumbing 4th Floor zone T1, Installation sleeve FF &
Plumbing 5th Floor zone T1, Installation sleeve FF & Plumbing Floor B4 zone P2,
Installation Discharge sumpit ( DSP 09 ) Floor B5 Zone P4, P5, P6, Installation
sleeve FF & Plumbing 5th Floor zone T2, Installation sleeve FF & Plumbing 5th
Floor zone T2, T3, Installation Discharge sumpit ( DSP 09 ) Floor B5 Zone P4, P5,
Page 21 / 73
Monthly Progress Report No.11
Aug 2016
P6, Installation sleeve FF & Plumbing Floor B3 zone P2, Installation sleeve FF &
Plumbing 6th floor zone T3
6) * SKJ
a. Wiring FA & Hydrant Tower 1, Tower 2, Tower 3 ( Up to B2 )
b. Wiring FA & Hydrant T1 ( Up to B1 )
1-2. QA/QC
a. Tower 1
1) Inspection of column, SW, beam and slab 5th FL angello tower zone 2
2) Inspection of column, SW, beam and slab 5th FL bella tower zone 3
3) Inspection of column, SW, beam and slab 5th FL bella tower zone 4
4) Inspection of column, SW, beam and slab 6th FL angello tower zone 1
5) Inspection of column, SW, beam and slab 6th FL angello tower zone 2
6) Inspection of column, beam and slab foundation B5 Podium 12 tower 1
b. Tower 2
1) Inspection of column, SW, beam and slab 2nd FL tower 2 zone 2
2) Inspection of column, beam and slab B1 Podium 1 tower 2
3) Inspection of column, beam and slab B1 Podium 2 tower 2
4) Inspection of column, beam and slab B1 Podium 3 tower 2
c. Tower 3
1) Inspection of column, SW, beam and slab 3rd FL chianti tower zone 3
2) Inspection of column, SW, beam and slab 4th FL chianti tower zone 1
3) Inspection of column, SW, beam and slab 4th FL chianti tower zone 2
d. Reporting
1. Report concrete casting of Jul 2016
2. Report concrete crushing test of Jul 2016
3. Material delivery to site of Jul 2016
4. Report rebar test of Jul 2016
Summary and detail of QA/QC reports are provided on X.HSE & QA/QC Reports
1-3. Safety
Page 22 / 73
Monthly Progress Report No.11
Aug 2016
Page 23 / 73
Monthly Progress Report No.11
Aug 2016
2) Tower 2
a. L3Zone T2-1, T2-2 & T2-3, completed of formwork, rebar and concrete for
beam and slab
b. L4Zone T2-1 until T2-4, completed of formwork, rebar and concrete for beam
and slab
c. L5Zone T2-1 until T2-2, completed of formwork, rebar and concrete for beam
and slab
d. B2 until GFZone P2-1 ( ramp ), completed of formwork, rebar and concrete
for beam & slab
3) Tower 3
a. L7Zone T3-3, completed formwork, rebar and concrete for beam and slab
b. L8Zone T3-1 Until T3-3 completed formwork, rebar and concrete for beam
and slab
c. L9Zone T3-1 Until T3-3 completed formwork, rebar and concrete for beam
and slab
d. L10Zone T3-1 Until T3-3 completed formwork, rebar and concrete for beam
and slab
e. L11Zone T3-1 Until T3-3 completed formwork, rebar and concrete for beam
and slab
f. L12Zone T3-1 completed formwork, rebar and concrete for beam and slab
Page 24 / 73
Monthly Progress Report No.11
Aug 2016
g. B4 until B3Podium Zone P3-4 until P3-6 completed formwork, rebar and
concrete for beam and slab
h. B2 until GFPodium Zone P3-1 until P3-2 completed formwork, rebar and
concrete for beam & slab
i. L4-L8 finishing work Block Wall Installed and L4 finishing work plastering
4) * Greatech
c) Tower 3 : Installation Hydrant & Splinker Floor B4, Installation Hydrant &
Splinker Floor B3, Installation Hydrant & Splinker Floor B2, Installation sleeve FF
& Plumbing Floor B4 zone P3, Installation sleeve FF & Plumbing Floor B5 zone
Page 25 / 73
Monthly Progress Report No.11
Aug 2016
T2, Installation sleeve FF & Plumbing 7th Floor zone T3, Installation sleeve FF &
Plumbing 7th Floor zone T2, Installation sleeve FF & Plumbing 7th Floor zone T1,
6) * SKJ
a. Wiring FA & Hydrant Tower 1, Tower 2, Tower 3 ( Up to L2 )
b. Wiring FA & Hydrant Tower 1 ( Up to L3 )
1-2. QA/QC
A. Tower 1
1. Inspection of column, SW, beam and slab 6th FL bella tower zone 3
2. Inspection of column, SW, beam and slab 6th FL bella tower zone 4
3. Inspection of column, SW, beam and slab 7th FL angello tower zone 1
4. Inspection of column, SW, beam and slab 7th FL angello tower zone 2
5. Inspection of column, SW, beam and slab 7th FL bella tower zone 3
6. Inspection of column, SW, beam and slab 7th FL bella tower zone 4
7. Inspection of column, SW, beam and slab 8th FL angello tower zone 1
8. Inspection of column, SW, beam and slab 8th FL angello tower zone 2
9. Inspection of column, SW, beam and slab 8th FL bella tower zone 3
10. Inspection of column, SW, beam and slab 8th FL bella tower zone 4
11. Inspection of column, SW, beam and slab 9th FL angello tower zone 1
12. Inspection of column, SW, beam and slab 9th FL angello tower zone 2
13. Inspection of column, SW, beam and slab 9th FL bella tower zone 3
14. Inspection of column, SW, beam and slab 10th FL angello tower zone 1
B. Tower 2
C. Tower 3
1. Inspection of column, SW, beam and slab 4th FL chianti tower zone 3
Page 26 / 73
Monthly Progress Report No.11
Aug 2016
2. Inspection of column, SW, beam and slab 5th FL chianti tower zone 1
3. Inspection of column, SW, beam and slab 5th FL chianti tower zone 2
4. Inspection of column, SW, beam and slab 5th FL chianti tower zone 3
5. Inspection of column, SW, beam and slab 6th FL chianti tower zone 1
6. Inspection of column, SW, beam and slab 6th FL chianti tower zone 2
7. Inspection of column, SW, beam and slab 6th FL chianti tower zone 3
8. Inspection of column, SW, beam and slab 7th FL chianti tower zone 1
9. Inspection of column, SW, beam and slab 7th FL chianti tower zone 2
10. Inspection of column, SW, beam and slab 7th FL chianti tower zone 3
11. Inspection of column, SW, beam and slab 8th FL chianti tower zone 1
12. Inspection of column, SW, beam and slab 8th FL chianti tower zone 2
13. Inspection of column, SW, beam and slab 8th FL chianti tower zone 3
14. Inspection of column, SW, beam and slab 9th FL chianti tower zone 1
15. Inspection of column, beam and slab foundation B5 podium 4, 5, 6 chianti tower
16. Inspection of column, beam and slab B4 podium 2 chianti tower
17. Inspection of column, beam and slab B3 podium 2 chianti tower
18. Inspection of column, beam and slab B2 podium 1 chianti tower
19. Inspection of column, beam and slab B1 podium 1 chianti tower
D. Reporting
1-3. Safety
1) Safety Talk Meeting (Will be perform on every Friday from 08.00 to 08.30 AM)
2) Regular internal safety meeting in LTJOs meeting room
3) General House Keeping
4) Protection on the required hazard / harmfull area
5) Conduction of Trainings and Safety induction for new employees
6) Inspection Lifting Equipment, Tower Crane, Scaffolding, Medical Kit, Webbing
Sling, Hand Tools, PPE, Fire Extinguisher, Genset, Electrical Distribution Board
and etcs.
7) Warn and maintain for the hygiene condition of the Canteen
8) Conducting for HSEs training
9) Monitoring of pouring concrete on column and shearwall at Tower 1, 2 & 3
10) Monthly Safety Patrol with EPH
Page 27 / 73
Monthly Progress Report No.11
Aug 2016
Make no delays on progress according LTJO will focus on Tower 2& Tower 3 to
1
to submitted catch up schedule part 2. catch up schedule part 2..
EPH shall finalize the negotiation and
Finish negotiation meeting and award
award the tile supplier and faade
tile supplier and faade Subcontractor
2 Subcontractor for stick system not to
for Stick System (T1&T3) and Unitized
make any delays on LTJO finishing
System (T2)
works.
LTJO and EPH needs to discuss detail
and further discussion regarding
Further discussion regarding basement
3 basement carpark handover such as
carpark handover.
handover carpark floor, area, usage
condition and so on.
LTJO needs to take care labours to
Normalizing the Site after Hari Raya Idul
4 normalize the Site after the long Hari
Fitri.
Raya Idul Firtri.
Page 28 / 73
Monthly Progress Report No.11
Aug 2016
Page 29 / 73
Monthly Progress Report No.11
Aug 2016
Page 30 / 73
Monthly Progress Report No.11
Aug 2016
Page 31 / 73
Monthly Progress Report No.11
Aug 2016
Page 32 / 73
Monthly Progress Report No.11
Aug 2016
1. HSE REPORTS
1-1. SAFETY STATISTIC
MT Average
Major Major >3 Days 1-3 Days First Near Hours Working
Description Fatal beyond No. Of
PD Non PD Away Away Aid Miss Lost Hours
First Aid Employees
Page 33 / 73
Monthly Progress Report No.11
Aug 2016
Mandays Average
Manhours
No Position Up to
This Up to this Juli 2016
Last Jul-16
Month Month
Month
I STAFF
1 Project Manager 243 15 258 150 1,00
Page 34 / 73
Monthly Progress Report No.11
Aug 2016
Mandays Average
Manhours
No Position Up to
This Up to this Juli 2016
Last Jul-16
Month Month
Month
28 MEP Manager 194 15 209 150 1,00
II WORKER
Page 35 / 73
Monthly Progress Report No.11
Aug 2016
Mandays Average
Manhours
No Position Up to
This Up to this Juli 2016
Last Jul-16
Month Month
Month
20 Mdr Holis 78 - 78 - 0,00
38 HARDINER 6 - 6 - 0,00
A. PT. SAMYOUNG -
3. ELECTRICAL WORKER -
3. ELECTRICAL WORKER -
Page 36 / 73
Monthly Progress Report No.11
Aug 2016
Mandays Average
Manhours
No Position Up to
This Up to this Juli 2016
Last Jul-16
Month Month
Month
C. GREATECH ARTHANINDO -
3. ELECTRICAL WORKER -
3. ELECTRICAL WORKER -
3. ELECTRICAL WORKER
3. ELECTRICAL WORKER
Page 37 / 73
Monthly Progress Report No.11
Aug 2016
1) HSE Induction
No Company Works No. of Inducted
1 Mandor Daryono Bekisting 119
2 Mandor Sugiyanto Bekisting 84
3 Mandor Sajam Bekisting 95
4 Mandor Tarlan Finishing 112
5 PT. Berca Hardaya Perkasa Electrical 19
6 Mandor Warsono Rebar 47
7 Mandor Suparji Rebar 31
8 Mandor Sunarto Rebar 35
9 Mandor Basuki Cleaning & Proteksi 11
10 Mandor Kohar Cleaning & Proteksi 13
11 Mandor Abdullah 18
11 LTJO STAFF 8
12 PT. Jaya Teknik Indonesia Electrical 2
TOTAL 594
1) All Works could be excecuted after permitted and accepted safe condition
(HSE Approved Working Permit)
2) Checking lifting equipment, transport equipment and hand tools on a regular
basis
3) Protection of power cable lines with strung on poles
4) Providing garbage disposal / trash bin in each of the tower crane cabin
Page 38 / 73
Monthly Progress Report No.11
Aug 2016
Inspection Pesseger Hoist 2 at Juli 19, 2016 Fogging is done 3x a week in each tower
Joint Safety Patrol at Juli 23, 2016 Sterilisasi Mess Worker 2x a month
Page 39 / 73
Monthly Progress Report No.11
Aug 2016
Page 40 / 73
Monthly Progress Report No.11
Aug 2016
Page 41 / 73
Monthly Progress Report No.11
Aug 2016
Inhouse training penggunaan kabel dan steker yang Inspection dan tagging equipment and handtools
aman
Page 42 / 73
Monthly Progress Report No.11
Aug 2016
Inspection Scaffolding once a week Inspection pesseger hoist 3A in tower 1 at Juli 28,
2016
Page 43 / 73
Monthly Progress Report No.11
Aug 2016
Inhouse training bekerja di ketinggian at juli 23, Give pusihment for worker not use helmet and
2016 smoking in area project
Page 44 / 73
Monthly Progress Report No.11
Aug 2016
2. QA/QC REPORTS
NCR / NCN 80 45 35
SDR 17 11 6
SVR 29 14 15
Legend :
NCR :Non Conformance Record
NCN :Non Conformance Notice
SDR :Surveillance Deficiency Report
SVR :Safety Violation Report
Page 45 / 73
Monthly Progress Report No.11
Aug 2016
Result
Delivery Date Bending test
No Kode Dia BJTS No. MDS Fy Fu Ratio Status
Date Testing Elongation %
(kg/mm) (kg/mm) (Fu/Fy) Angle Bending
Crack
Bending Dia.
1 BJTS 40 S 13 MS 26 Mei 2016 13 40 26-May-16 26-May-16 29-Jun-16 47.203 61.047 1.293 24.276 180 5D No TRUE
2 BJTS 40 S 13 MS 07 June 2016 13 40 7-Jun-16 7-Jun-16 29-Jun-16 45.293 60.451 1.335 23.921 180 5D No TRUE
3 BJTS 40 S 13 MS 08 June 2016 13 40 8-Jun-16 8-Jun-16 29-Jun-16 45.651 61.167 1.340 24.204 180 5D No TRUE
4 BJTS 40 S 16 MS 26 Mei 2016 16 40 26-May-16 26-May-16 29-Jun-16 43.137 59.722 1.384 24.743 180 5D No TRUE
5 BJTS 40 S 16 MS 07 June 2016 16 40 7-Jun-16 7-Jun-16 29-Jun-16 42.349 60.274 1.423 21.984 180 5D No TRUE
6 BJTS 40 S 22 MS 21 Mei 2016 22 40 21-May-16 21-May-16 29-Jun-16 45.904 61.337 1.336 22.230 180 5D No TRUE
7 BJTS 40 S 22 MS 03 June 2016 22 40 3-Jun-16 3-Jun-16 29-Jun-16 43.850 59.481 1.356 20.900 180 5D No TRUE
8 BJTS 40 S 25 MS 01 June 2016 25 40 1-Jun-16 1-Jun-16 29-Jun-16 45.004 61.452 1.365 29.730 180 5D No TRUE
9 BJTS 40 S 25 MS 02 June 2016 25 40 2-Jun-16 2-Jun-16 29-Jun-16 42.285 58.912 1.393 27.260 180 5D No TRUE
10 BJTS 40 S 25 MS 07 June 2016 25 40 7-Jun-16 7-Jun-16 29-Jun-16 45.193 61.620 1.363 27.670 180 5D No TRUE
11 BJTS 40 S 29 MS 06 June 2016 29 40 6-Jun-16 6-Jun-16 29-Jun-16 46.691 65.711 1.407 27.590 180 6D No TRUE
12 BJTS 40 S 10 MS 15 June 2016 10 40 15-Jun-16 15-Jun-16 22-Jul-16 43.870 59.905 1.366 23.295 180 5D No TRUE
13 BJTS 40 S 10 MS 14 June 2016 10 40 14-Jun-16 14-Jun-16 22-Jul-16 43.366 59.098 1.363 23.584 180 5D No TRUE
14 BJTS 40 S 10 MS 24 June 2016 13 40 24-Jun-16 24-Jun-16 22-Jul-16 45.988 60.611 1.318 24.285 180 5D No TRUE
15 BJTS 40 S 13 MS 17 June 2016 13 40 17-Jun-16 17-Jun-16 22-Jul-16 43.085 59.138 1.373 23.346 180 5D No TRUE
16 BJTS 40 S 13 MS 23 June 2016 13 40 23-Jun-16 23-Jun-16 22-Jul-16 41.415 58.064 1.402 24.272 180 5D No TRUE
17 BJTS 40 S 16 MS 09 June 2016 16 40 9-Jun-16 9-Jun-16 22-Jul-16 44.555 62.716 1.408 21.613 180 5D No TRUE
18 BJTS 40 S 16 MS 23 June 2016 16 40 23-Jun-16 23-Jun-16 22-Jul-16 42.389 58.816 1.388 25.953 180 5D No TRUE
Page 46 / 73
Monthly Progress Report No.11
Aug 2016
Result
Delivery Date Bending test
No Kode Dia BJTS No. MDS Fy Fu Ratio Status
Date Testing Elongation %
(kg/mm) (kg/mm) (Fu/Fy) Angle Bending
Crack
Bending Dia.
19 BJTS 40 S 22 MS 20 June 2016 22 40 20-Jun-16 20-Jun-16 22-Jul-16 45.212 57.134 1.264 23.580 180 5D No TRUE
20 BJTS 40 S 22 MS 24 June 2016 22 40 17-Jun-16 17-Jun-16 22-Jul-16 45.259 57.755 1.276 23.240 180 5D No TRUE
21 BJTS 40 S 22 MS 25 May 2016 22 40 25-May-16 25-May-16 22-Jul-16 45.585 57.451 1.260 24.530 180 5D No TRUE
22 BJTS 40 S 25 MS 09 June 2016 25 40 9-Jun-16 9-Jun-16 22-Jul-16 45.684 65.920 1.443 23.090 180 5D No TRUE
23 BJTS 40 S 25 MS 22 June 2016 25 40 22-Jun-16 22-Jun-16 22-Jul-16 46.748 62.232 1.331 25.870 180 5D No TRUE
24 BJTS 40 S 25 MS 25 May 2016 25 40 25-May-16 25-May-16 22-Jul-16 46.241 61.922 1.339 19.780 180 5D No TRUE
25 BJTS 40 S 25 MS 17 June 2016 25 40 17-Jun-16 17-Jun-16 22-Jul-16 45.942 62.502 1.360 28.410 180 5D No TRUE
26 BJTS 40 S 25 MS 21 June 2016 25 40 21-Jun-16 21-Jun-16 22-Jul-16 46.134 61.813 1.340 26.100 180 5D No TRUE
27 BJTS 40 S 29 MS 14 June 2016 29 40 14-Jun-16 14-Jun-16 22-Jul-16 54.396 70.083 1.288 26.370 180 6D No TRUE
28 BJTS 40 S 29 MS 15 June 2016 29 40 15-Jun-16 9-Jun-16 22-Jul-16 43.835 61.465 1.402 29.600 180 6D No TRUE
Page 47 / 73
Monthly Progress Report No.11
Aug 2016
U50
Result
Delivery Date Bending test
No Kode Dia BJTS No. MDS Fy Fu Ratio Elongation Status
Date Testing
(kg/mm) (kg/mm) (Fu/Fy) % Angle Bending
Crack
Bending Dia.
1 BJTS 50 S 10 MS 24 Mei 2016 10 50 24-May-16 24-May-16 29-Jun-16 52.241 69.788 1.336 23.250 90 5D No TRUE
2 BJTS 50 S 10 MS 27 Mei 2016 10 50 27-May-16 27-May-16 29-Jun-16 52.947 69.184 1.307 21.884 90 5D No TRUE
3 BJTS 50 S 10 MS 07 June 2016 10 50 7-Jun-16 7-Jun-16 29-Jun-16 52.745 70.091 1.329 22.253 90 5D No TRUE
4 BJTS 50 S 13 MS 23 Mei 2016 13 50 23-May-16 23-May-16 29-Jun-16 54.304 72.087 1.327 19.017 90 5D No TRUE
5 BJTS 50 S 13 MS 27 Mei 2016 13 50 27-May-16 27-May-16 29-Jun-16 55.378 72.445 1.308 18.635 90 5D No TRUE
6 BJTS 50 S 16 MS 23 Mei 2016 16 50 23-May-16 23-May-16 29-Jun-16 53.301 70.477 1.322 19.480 90 5D No TRUE
7 BJTS 50 S 25 MS 23 Mei 2016 25 50 23-May-16 23-May-16 29-Jun-16 53.629 70.390 1.313 23.890 90 5D No TRUE
8 BJTS 50 S 25 MS 24 Mei 2016 25 50 24-May-16 24-May-16 29-Jun-16 55.054 73.035 1.327 22.740 90 5D No TRUE
9 BJTS 50 S 29 MS 23 Mei 2016 29 50 23-May-16 23-May-16 29-Jun-16 53.802 68.856 1.280 28.480 90 6D No TRUE
Page 48 / 73
Monthly Progress Report No.11
Aug 2016
2.3 Equipments
Overall Equipment Schedule
2015 2016 2017 2018
No Description Total Remarks
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
Plan 60 2 4 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2
1 Concrete Pump
Actual 21 2 4 4 4 2 3 1 0 1 0
Plan 68 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2
2 CPB
Actual 17 3 3 3 4 4
Plan 56 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2
3 Compressor
Actual 27 1 1 3 3 3 3 7 3 3
Plan 201 3 6 6 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
4 Concrete Vibrator
Actual 80 3 7 7 7 7 8 14 14 6 7
Plan 207 2 6 9 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
5 Bar Bender
Actual 99 1 6 6 6 6 14 11 27 11 11
Plan 188 2 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
6 Bar Cutter
Actual 74 1 4 4 4 6 13 11 17 7 7
Plan 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Fuel Tank
Actual 10 1 1 1 1 1 1 1 1 1 1
Plan 125 2 3 3 4 4 4 4 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 2
8 Tower Crane
Actual 37 2 3 4 4 4 4 4 4 4 4
Plan 137 3 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 4 4 2
9 Hoist
Actual 6 2 4
Plan 94 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 Back Up
10 Genset
Actual 20 2 2 2 2 2 2 2 2 2 2
Plan 9 1 1 1 1 1 1 1 1 1
11 Mobile Crane
Actual 8 2 1 0 1 1 1 1 0 1 0
Plan 10 4 4 2
12 Excavator / BackHoe
Actual 15 6 2 2 1 1 0 0 0 2 1
Page 49 / 73
Monthly Progress Report No.11
Aug 2016
OVERALL VIEW 3
OVERALL VIEW 1
OVERALL VIEW 4
OVERALL VIEW 2
Page 50 / 73
Monthly Progress Report No.11
Aug 2016
Page 51 / 73
Monthly Progress Report No.11
Aug 2016
Page 52 / 73
Monthly Progress Report No.11
Aug 2016
Page 53 / 73
Monthly Progress Report No.11
Aug 2016
REBAR BW1 CONCRETE RAMP BASEMENT 5 REBAR SLAB LANTAI GROUND FLOOR
Page 54 / 73
Monthly Progress Report No.11
Aug 2016
Page 55 / 73
Monthly Progress Report No.11
Aug 2016
X. ATTACHMENT
1. Summary of Log for Shop Drawing, Material Approval, RFI and RFIT
2500 2256
2000
1526 Submitted
1500 Approved
1000
500 212
147 107
0
0
SHOP DRAWING MATERIAL APPROVAL RFI RFIT
Log of Shop Drawing is provided summary only (Detail of log is submitted regularly to Client)
Page 56 / 73
Monthly Progress Report No.11
Aug 2016
For Construction 4th Floor (T1 & T3), 3rd Floor (T2)
9 KK3/A020/TS/EPH/LTJO/00241 1-Jul-2016
Keyplan (Rev.1)
For Construction 5th Floor (T1 & T3), 4th Floor (T2)
10 KK3/A020/TS/EPH/LTJO/00241 1-Jul-2016
Keyplan (Rev.1)
For Construction 6th Floor (T1 & T3), 5th Floor (T2)
11 KK3/A020/TS/EPH/LTJO/00241 1-Jul-2016
Keyplan (Rev.1)
For Construction 7th Floor (T1 & T3), 6th Floor (T2)
12 KK3/A020/TS/EPH/LTJO/00241 1-Jul-2016
Keyplan (Rev.1)
32 KK3/A020/TS/EPH/LTJO/00245 14-Jul-2016
Page 57 / 73
Monthly Progress Report No.11
Aug 2016
Page 58 / 73
Monthly Progress Report No.11
Aug 2016
Page 59 / 73
Monthly Progress Report No.11
Aug 2016
4. Log of RFI
KK3-RFI-
3 Inclinometer Pipe 24-Jun-16 E 14-Jul-16
03-00145
KK3-RFI-
5 Dike Rebar Spacing 15-Jul-16
03-00147
KK3-RFI-
6 Struting Beam Releasing Tower #02 Phase #02 15-Jul-16 E 19-Jul-16
03-00148
KK3-RFI-
7 Ramp at Basement #01 Tower #03 25-Jul-16
03-00149
Page 60 / 73
Monthly Progress Report No.11
Aug 2016
KK3-RFI-
14 Zinc Sheet & Sealant Usage at Wall - Slab Joint 13-Jul-16 E 29-Jul-16
01-00033
KK3-RFI- Floor Finish Material for Lift Lobby Basement 4-1 Tower
17 14-Jul-16 E 21-Jul-16
01-00036 1
KK3-RFI-
18 Ceiling Maintenance Openings Location 18-Jul-16
01-00037
KK3-RFI-
19 Location of D13 & DW33 19-Jul-16
01-00038
Page 61 / 73
Monthly Progress Report No.11
Aug 2016
KK3-RFI-
20 Annotation CT. 1 at 3rd Floor Toilet Tower 1 19-Jul-16
01-00039
KK3-RFI-
21 Wall Thickness on Units Main Entrance 19-Jul-16
01-00040
KK3-RFI-
22 Final Reflection Ceiling Plan Typical Floor Tower 1 19-Jul-16
01-00041
Page 62 / 73
Monthly Progress Report No.11
Aug 2016
DETACHMENT OF CO AND
ELECTRONIC SOCKET INSTALLATION
5 KK3-NCN-02-00050 30-May-16 27-Jul-16
AT TOWER 3 AREA; PODIUM
BASEMENT 3; GRID T3.11
Page 63 / 73
Monthly Progress Report No.11
Aug 2016
Page 64 / 73
Monthly Progress Report No.11
Aug 2016
Page 65 / 73
Monthly Progress Report No.11
Aug 2016
Page 66 / 73
Monthly Progress Report No.11
Aug 2016
No. Ref. No. Description Date Received Latest Submit Status Reply Date of Reply Remarks
Page 67 / 73
Monthly Progress Report No.11
Aug 2016
Date
No. Ref. No. Description Remarks
Received
Standar pengecekan Kolom Vertikal dengan Waterpass dan
1 KK3/A020/SM/EPH/LTJO/033 28-Jul-16
gambar kerja
Page 68 / 73
Monthly Progress Report No.11
Aug 2016
2 MS-04-00005 List and Schedule of Method Statement Electrial Work 13-Jul-16 B 25-Jul-16
Page 69 / 73
Monthly Progress Report No.11
Aug 2016
1 KK3-MDS-03-00113 Inspection Delivered Material 59.63 ton dated 27-June-2016 14-Jul-16 27-Jun-16
Page 70 / 73
Monthly Progress Report No.11
Aug 2016
9. Log of Weather
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31
Page 71 / 73
Monthly Progress Report No.11
Aug 2016
Page 72 / 73
Monthly Progress Report No.11
Aug 2016
Page 73 / 73