Up to Last Week This Week Up to This Week Next Week Plan

Total To ( ~ 24th Aug ) (25th - 31th Aug) ( ~ 31th Aug) (1st - 7th Sept.)
Items Unit
Complete Plan Actual Plan Target Actual Plan Actual
(B-A) (B-A) (B-A') (B-A) BMS Target Con.
BMS (A) (B) BMS (A) Con. (A') (B) BMS (A) (B)
Concrete Works
Podium M3 24.701 19.088 12.841 -6.247 120 342 16 -104 -326 19.208 12.857 -6.351 220 466
Tower 1 M3 55.586 26.707 22.116 -4.591 800 774 815 15 41 27.507 22.931 -4.576 800 750
Tower 2 M3 53.155 16.373 13.259 -3.114 700 373 396 -304 23 17.073 13.655 -3.418 700 290
Tower 3 M3 34.704 16.790 13.936 -2.854 389 539 431 42 -108 17.179 14.367 -2.812 389 539
TOTAL M3 168.146 78.959 62.152 -16.807 2.009 2.028 1.658 -351 -370 80.968 63.810 -17.158 2.109 2.045