The document outlines a method of work for a trial section of road widening. It involves 1) installing traffic signs, 2) cutting asphalt edges, 3) excavating shoulders to a depth and width, 4) hauling and disposing excavated material, 5) preparing and compacting the subgrade, 6) testing the subgrade density, 7) hauling and dumping granular or rock material, 8) installing geotextile and geogrid layers, 9-11) spreading and compacting the material in layers, and 12,17) testing the material density.
The document outlines a method of work for a trial section of road widening. It involves 1) installing traffic signs, 2) cutting asphalt edges, 3) excavating shoulders to a depth and width, 4) hauling and disposing excavated material, 5) preparing and compacting the subgrade, 6) testing the subgrade density, 7) hauling and dumping granular or rock material, 8) installing geotextile and geogrid layers, 9-11) spreading and compacting the material in layers, and 12,17) testing the material density.
The document outlines a method of work for a trial section of road widening. It involves 1) installing traffic signs, 2) cutting asphalt edges, 3) excavating shoulders to a depth and width, 4) hauling and disposing excavated material, 5) preparing and compacting the subgrade, 6) testing the subgrade density, 7) hauling and dumping granular or rock material, 8) installing geotextile and geogrid layers, 9-11) spreading and compacting the material in layers, and 12,17) testing the material density.
1. Installation of Trafic Signs at trial of widening work
location. 2. Cutting the asphalt existing (50 cm from the edge) by using asphalt cutter to prevent damage in adjoining asphalt when excavation by using excavators begins (as separator). 3. Excavation of shoulder by using Excavator, depth 60 cm and width 350 380 cm. 4. Excavated materials hauled and disposed by using dump truck to disposal area ( material from the result of excavation that can still be used will be reused). 5. Preparation and compaction on the sub grade of excavation area by using Vibratory Roller (8 10 x passing), compacting process will be implemented in Optimum Water Content. 6. Sand Cone Test at the sub grade to find out the value of the density. 7. Hauling Selected Granular or Rock Material from Quarry going to project location by Dump Truck. 8. Installation of Geotextile below the Selected Granular or Geogrid below the Rock Material. 9. Dump the Selected Granular or Rock Material from the Dump Truck at Widening Area. 10. Spreading the Selected Granular or Rock Material by using Motor Grader (cross fall 5 %).Thickness 30 cm. 11. Compacting Selected Granular or Rock Material by Vibratory Roller (8 10 x passing). 12. Sand Cone /CBR Test at Selected Granular or Rock Material to find out the value of the density. 13. Installation of geogrid on GSE. 14. Dump the Selected Granular or Rock Material from the Dump Truck at Widening Area. 15. Spreading the Selected Granular or Rock Material by using Motor Grader (cross fall 5 %).Thickness 30 cm. 16. Compacting Selected Granular or Rock Material by Vibratory Roller (8 10 x passing).Thickness 24 cm. 17. Sand Cone /CBR Test at Selected Granular or Rock Material to find out the value of the density.