The determination of the critical path of a project requires three steps which are summarized along the
following lines and discussed in the remainder of this article.:
Activity slack
The amount of slack (or float) associated with each activity is used to denote the free time of each activity
within the ESS and LSS. It denotes the amount of time each activity can be delayed without violating the
entire project duration. The slack of an activity can be calculated as the difference between its latest start
and earliest start time, or alternatively, as the difference between its latest and earliest finishing time.
Activities with zero slack cannot be delayed without affecting the entire project duration and are called
critical activities. The critical path consists of a path of critical activities and is given by activities A, B, E
and F.
Activities that lie on the critical path cannot be delayed without delaying the entire project duration. Since
time is an important objective in scheduling, the critical path is where the project manager has to focus
on. It helps the manager to calculate the minimum length of time in which the project can be completed,
and which activities should be prioritized to complete by that project deadline. In order to finish a project
on time, the critical path calculations help the project manager to focus on the essential activities to which
attention and resources should be devoted. It provides an effective basis for the scheduling and
monitoring of project progress.