Professional Documents
Culture Documents
The Case of Shop Painting Going To Waste: Cases From The F-Files
The Case of Shop Painting Going To Waste: Cases From The F-Files
N
ew steel rake arm compo-
nents were installed in
steel clarifier tanks at a
wastewater treatment plant in the east-
ern U.S. and finish coated on site during
2005. The rake arm components were
reported to have been shop primed with
one coat of epoxy coating and then
stored off site for an extended period of
time before delivery to the treatment
plant and installation.
The product data sheet for the epoxy
coating recommended a dry film thick-
ness (DFT) of 4 to 10 mils per coat
applied to an SSPC-SP 10 (Near-White
Blast Cleaning) prepared surface.
Further information related to the shop
painting and storage of the steel compo-
nents was not available. Fig. 2
Fig. 1
Once the shop-coated steel was
assembled in the various tanks,
Figs. 1-3: Various photos of typical coating failure
two finish coats of a different on steel components. All photos courtesy of KTA-
manufacturers epoxy coating Tator, Inc.
were applied to the shop-applied
primer. The product data sheet had delaminated, and a red primer was
for the epoxy finish coat recom- visible (Figs. 13). Areas of failure were
mended 5 to 8 mils DFT per coat. typically only several square inches in
The steel surfaces of the assem- size, but relatively widespread through-
blies in the tanks where work was out the various tanks. There did not
first completed consisted of pres- appear to be a particular pattern to the
Fig. 3
surized water cleaning. However, failure.
the surface preparation method was were performed. An independent third Closer examination of the failed areas
later changed to brush-off blasting. party investigation of the coating failure found that the back side of the delami-
A few months after the tanks were was requested to determine the cause of nating finish also contained a red
placed into service, the new finish coats the problem. primer layer, with red primer remaining
uniform layer of the red primer, indicat- ing cuts through the coating to the sub- Testing the rake arm components
ing that the break in the system was strate with the smaller angle of the cuts throughout the tanks showed poor
either between (adhesive) or within between 30 and 45 degrees. A pressure- adhesion between the finish coat and
(cohesive) layers of the red primer coat. sensitive tape is then applied to the X- primer coat, as evidenced by 0A (worst)
Coating adhesion was evaluated fol- cut area and rapidly removed. The or 1A test ratings. The remaining
lowing Method A of ASTM D3359, adhesion is rated according to the scale primer was well adhered to the steel.
Standard Test Methods for Measuring provided in the method, with the high- The DFT of the coatings was mea-
Adhesion by Tape Test. The Method A est rating being 5A (no coating sured at various locations over steel
tape test involves making two intersect- removed). surfaces of the rake arm assemblies. The
measurements for total DFT varied
with ranges as low as 14 to 18 mils and
as high as 25 to 29 mils. The thickness
of the exposed red primer that
remained on the steel surfaces was also
measured, with DFTs ranging from 6 to
11 mils. The thickness of the finish coat
could not easily be determined in the
field since a thin layer of the primer was
also delaminating.
Representative coating samples were
collected from tank rake arm assemblies
for laboratory analysis to help deter-
mine the cause of failure. One of the
samples obtained included all coating
layers down to the steel substrate.
Have a new Surface Prep project but dont want The Laboratory Analysis
to invest in new equipment? Try renting! From Following the site visit, the samples
40k waterblasters to spinning nozzles. Blasting were submitted to the laboratory for
mowers to lances, water guns to safety wear. visual and microscopic examination
FS Solutions centers carry high quality and infrared spectroscopy. The micro-
Jetstream units for rent or purchase as scopic analysis of delaminated samples
well as all of the parts and accessories revealed three coating layers. The first
for your surface prep application. red coatthe coating that had delami-
nated from red primer that remained on
Call today for pricing the steelwas approximately 0.5 mils
thick. A light blue intermediate coat (or
and availability.
first finish coat) was 3 to 7 mils thick,
and the white top coat was also 3 to 7
mils thick.
Click our Reader e-Card at paintsquare.com/ric
Possible Explanations
10 to 11 mils thick, and the
white topcoat, 12 to 15 mils
thick. The edges of the sample Although the primer and finish coats
appeared to exhibit coating were from different manufacturers,
fracture between the second, there should not have been an inherent
darker red coat and the thin- compatibility problem between the
ner, lighter red coat (Fig. 4). The coatings. Both coatings were epoxies,
thickness of the lighter red coat but differed slightly in their composi-
was consistent with the range tionthe primer was an amine epoxy
of thickness of the red coat on and the finish was a polyamide epoxy.
the delaminated sample chips. Fig. 4: Lab microphoto showing coating fracture between When dealing with epoxies, one possi-
what appeared to be a darker red coat from a thinner, lighter
The fractured edge of the red coat.
bility for coating problems is curing
sample was further examined stresses imposed by new coats of exces-
by applying pressure at the point of that observed in the field, both from sive thickness, but the samples obtained
fracture to induce separation. The delaminating finish coat and by adhe- from the site visit did not generally
forced separation at the point of frac- sion testing. show excessive thickness. The thickness
ture resulted in the back two red coats The infrared spectroscopic analysis of of the finish coats was typically consis-
disbonding from the top three coats, the various coating layers found all mate- tent with the recommended DFT of 10
which included the white top coat, light rials were epoxy coatings. However, dif- to 16 mils for two coats.
blue intermediate coat, and the thin red ferences in the spectra obtained indicated With the coating system separating
coat. This mode of separation matched that the red primer and white/blue finish Continued
For over 20 years, Jenessco has been supplying containment to the following industries: extended period due to the hard and
Oilfield Shipyards Refineries and Power plants Paper mills And more. dense coating film that forms. Most
coating manufacturers recommend
scarifying the primer surface before
Call today for a custom quote. topcoating if exterior exposure is 30
Free fabric sample swatches available upon request.
days or longer. Although the length of
time that had elapsed between shop
priming the steel and applying the finish
coat was not established, the time peri-
jenessco.com 281.498.8833 felix@jenessco.com od was likely well in excess of one
month.
Conclusion
The cause of the failure was attributed
to exceeding the recoat time for the
epoxy primer, which did not allow the
last primer coat applied to achieve ade-
quate adhesion to the initial primer lay-
ers. A likely scenario was that the shop-
primed steel was initially coated with
two coats of epoxy primer and stored
for an extended period. Prior to ship-
ment and erection at the site, an addi-
tional thin layer of the primer was
applied, creating the weak adhesive link
in the coating system that failed after
the tanks were put into service.
JPCL
www.paintsquare.com
Click our Reader e-Card at paintsquare.com/ric