CHANGE ORDER

JO No. : 16 - 7763
Customer : CH Perez Brothers Consultancy Corp. Control No. : C01 - 7763
Address : Suite 3A & 3B St. Mary's Bldg., Date : 3-Oct-16
#5 Central Ave., Quezon City Tel. No. :
Project : HMRID Property Development Fax No. :
Location : AFO RSBS East Service Road KM 21 Taguig CP No. :

NUMBER OF SETS NUMBER OF DIMENSIONS DESCRIPTION


PANELS PER SET Height Width

Revision on RUD Installation Orientation (17 sets of RUD ) from FIXED TYPE (Box Included and Plate to plate Included) to OPEN TYPE
(Plus Box and Plus Guide).

REMARKS:

SEE ATTACHED REVISED DRAWING DETAIL

Requested by: Received by Production: Received by Accounting:


VERIFICATION
FABRICATION

KENNETH G. WENCESLAO

Due Date: No. of Days for Fabrication: Payment:

Checked by: Approved by: Approved by:


FILIPINAS ASIA SHUTTER DOOR CORP.
43 YEARS OF EXPERIENCE IN MANUFACTURING QUALITY ROLL-UP DOORS
KM. 23 ORTIGAS AVE., EXTENSION, CAINTA RIZAL
Email: filasiashutterdoorcorp@yahoo.com.ph
Gmail: filasiashutterdoorcorp@gmail.com

CHARGE SLIP
JOB ORDER NO. : 16 - 7763
PROJECT NAME : HMRID
REPORTED BY : JUNJUN LORA

Date: 10/3/2016 Description:


Remarks:

Cannot install Roll up doors due to shortage on width.

Amount to be Charged:

Charge to:

Recommendation:

Fabricate and replace new set of roll up doors.

Computation: Agreement:

Agreed by:

Prepared by: Approved by:


KENNETH WENCESLAO
Accounting: