Problem 1
A project network is shown below. The time in weeks for each activity are listed in the table below.
Use a forward and a backward pass to determine the critical path.
A202
A22
A20
A201
A21 Finish
A24
A204
Activity Time in
Weeks
A22 5
A23 4
A24 8
A20 4
A21 12
A203 10
A202 3
A204 2
A201 5
SG9-1
Chapter 9 Study Guide Solutions
Problem 2
A project network is shown below. The time in weeks for each activity are listed in the table below.
Use a forward and a backward pass to determine the critical path.
T202
T22
T203
Start T23
T201
T21
Finish
T24
T204
Activity Time in
Weeks
T22 8
T23 2
T24 5
T21 3
T203 7
T202 6
T204 12
T201 10
SG9-2
Chapter 9 Study Guide Solutions
Problem 3
A senior QM/MS case study project team has developed the following schedule of activities for
their project, using their best estimate of completion times. Draw the project network and find the
critical path. Can they complete the project in the 38 class days remaining until the end of the
semester?
Project Network
1 Contact 2 Write
Client Proposal
3 Obtain
Approval
Start
4Complete
5Complete Computer
Industry Programming
Literature
Review
6Write
Final
7Complete
Draft Oral Report
Finish
SG9-3
Chapter 9 Study Guide Solutions
Critical path = 1, 2, 3, 4, 6
SG9-4
Chapter 9 Study Guide Solutions
Problem 4
One of the seniors hears that if they purchase an upgrade for their programming software package,
they can complete the final draft in just 3 days and complete the programming in just 5 days. By
saving this time the group can cash in on the "deal" offered by Binkos copies and save $10 on the
printing for each day earlier the project is completed. One of the group members says they will
save $70 total (7 days * $10 day). Is this correct? How does this reduction in time for writing the
final draft effect the overall network?
1 Contact 2 Write
Client Proposal
3 Obtain
Approval
Start
4Complete
5Complete Computer
Industry Programming
Literature
Review
6Write 7Compelte
Final Oral Report
Draft
Finish
SG9-5
Chapter 9 Study Guide Solutions
Buying the software saves them 5 days total and therefore saves them $50. No, the
group member is not correct in saying the group would save $70.
SG9-6
Chapter 9 Study Guide Solutions
Problem 5
Given the following activity times and precedence, create a network and find the critical path.
Network
A202 A205
A22
Finish
A20 A201
Start A23
A21 A203
A24 A204
SG9-7
Chapter 9 Study Guide Solutions
Problem 6
1. Print CD labels
2. Print CD case labels
3. Transfer files to CD software
4. Begin CD burning
5. Stuff CD case labels
6. Attach CD labels
7. Return finished CD into CD case
Although the steps are numbered, they do not always reflect immediate precedence
relationships. Develop a table that lists the immediate predecessors for each activity.
SG9-8
Chapter 9 Study Guide Solutions
Problem 7
Given the following network with activities and times estimated in days.
Network
A D
C F
Start
B E
SG9-9
Chapter 9 Study Guide Solutions
Problem 8
Given the following network with activities and times estimated in days.
What are the estimated times and variances for the activities?
SG9-10
Chapter 9 Study Guide Solutions
Problem 9
Given the following network with activities and times estimated in days.
SG9-11