Professional Documents
Culture Documents
Earned Value & P6: A New Perspective On Project Performance and P6 Usage. Clearing Up Myths About EV
Earned Value & P6: A New Perspective On Project Performance and P6 Usage. Clearing Up Myths About EV
Prepared by:
Elaine Britt Krazer, PMP REMINDER
Align Projects, LLC Check in on the
COLLABORATE mobile app
WELCOME!
BUDGET $5M
SCHEDULE 5 MONTHS
WITH ONE MILE PER MONTH
EXAMPLE
GAK!
Whiskey Tango
Foxtrot!
EARNED VALUE
It is about integrity,
Have you spent what you said you would BY THIS TIME?
Have you completed what you said you would BY THIS TIME?
IF we continue this trend, will we deliver what we said we would
OVER TIME?
Requires then,
A time-phased plan (schedule)
A spend plan over time (cost loaded schedule)
Regular intervals of progress reporting (status updates on cost
and schedule)
A report of physical, actual accomplished work & what remains?
A schedule that reflects actuals and planned information (exact
mirror of project work)
P6 REQUIREMENTS FOR EV
Pre Work
Global Settings
All subsequent settings
REMINDER
Check in on the
COLLABORATE mobile app
Pre Work GET READY!
EPS-OBS alignment
Security
Summary data needs
Efficiency
Admin settings
Project and WBS templates (settings)
Resources, Roles
Codesa few is better than many
UDFnone is better than some
Costs prep
Risks, issues decision
Other settingsAIM!
SPI = EV / PV
EV Calculations in P6
BAC
Uses Baseline Budgeted (Planned) Values or BAC depending
on settings at Enterprise level in Admin
If the 'Earned Value Calculation' is set to 'Budgeted Values with
Planned dates' or 'Budgeted Values with Current Dates':
BAC = BL Budgeted Labor Cost + BL Budgeted Non-Labor Cost + BL
Budgeted Material Cost + BL Budgeted Expense Cost.
If the 'Earned Value Calculation' is set to 'At Completion Values
with Current Dates':
BAC = BL At Completion Labor Cost + BL At Completion Non-Labor
Cost + BL At Completion Material Cost + BL At Completion Expense
Cost
Portfolio EV
Earned Value in P6
We appreciate your feedback and insight
Oracle Partner
www.AlignProjects.com