PROGRESS OF MAIN ACTIVITIES A

KIBO NJOMBE PROJECT

ACTIVITY DESCRIPTION OF WORK


NO
1 NJOMBE KIBO PROJECT

EQUIPMENT
7 Equipment procurement

9 Manufacture and dispatch equipment

26 Receive documentation (Unilever)

43 Arrival at Dar es Salaam Port

60 Arrival at site

EARLIER WORKS

77 Earlier Works

79
Site establishment
83
Earthwork Mobilization
88
Fencing
92
Procurement of steel building
96
Borehole
DESIGN
101
Design

MAIN BUILDING CONSTRUCTION


106
Main Building
107
SUBSTRUCTURES (ALL PROVISIONAL)
108
Excavation
110
CONCRETE
111
Formwork
114
REINFORCEMENT
117
CONCRETE WORKS
121
FILL MATERIALS
124
Main Building superstructure
125
Main building installation
131
FLOOR
133
Masonry work
135
Plaster work
137
PAINTWORK
139
Service works

EQUIPMENT INSTALLATION
142
Equipment Installation
COMMISSIONING

159 Commissioning

FIREWOOD SHED CONSTRUCTION

162
FIRE WOOD SHED
167
CANTEEN
168
Substructure
176
Superstructure
181
Services
184
Plaster work
186
IRONMONGERY/JOINERY WORKS
188
PAINTWORK

EXTERNAL WORKS & LANDSCAPING


190
External works

CONSTRUCTION OF ADMINISTRATION BLOCK


197
Administration Building
198
Substructure
206
Superstructure
216
Building services
219
Plaster work
221
IRONMONGERY/JOINERY WORKS
223
PAINTWORK
S OF MAIN ACTIVITIES AGAINST THE NETWORK

TASK PROGRESS
Completed

On track

Delayed but critical

Delayed but not at risk

Not started

START DATE COMPLETION DATE COMPLETION %

7-Dec-16 8-Jun-16 100%

7-Dec-16 21-Apr-17 70%

5-Apr-17 12-Apr-17 0%

13-Apr-17 25-May-17 0%

9-May-17 8-Jun-17 0%

19-Dec-16 2017/26/7 80%

19-Dec-16 10-Feb-17 100%

22-Dec-16 5-Apr-17 100%

24-Mar-17 21-Jul-17 30%

7-Mar-17 26-Jul-17 40%

95%
15-Feb-17 16-May-17 100%

29-Mar-17 26-Jan-18 15%

0%

29-Mar-17 3-May-17 100%

3-Apr-17 23-May-17 25%

5-Apr-17 19-May-17 35%

5-Apr-17 22-May-17 35%

0%

2-May-17 27-Jun-17 0%

23-Jun-17 26-Jan-18 0%

27-Jul-17 26-Oct-17 0%

28-Jun-17 10-Aug-17 0%

7-Aug-17 15-Sep-17 0%

17-Aug-17 26-Sep-17 0%

8-Sep-17 17-Oct-17 0%

23-Jun-17 1-Nov-17 0%

23-Aug-17 4-Jan-18 0%

8-Dec-17 26-Jan-18 0%

29-Nov-17 31-Jan-18 0%

6-Jun-17 8-Sep-17 0%
6-Jun-17 21-Jun-17 0%

24-Jul-17 8-Sep-17 0%

9-Aug-17 22-Aug-17 0%

9-Aug-17 22-Aug-17 0%

23-Aug-17 31-Aug-17 0%

23-Aug-17 8-Sep-17 0%

11-Aug-17 5-Jan-18 0%

10-Jul-17 4-Jan-18 0%

10-Jul-17 12-Sep-17 0%

6-Sep-17 4-Jan-18 0%

6-Sep-17 31-Oct-17 0%

18-Oct-17 7-Nov-17 0%

8-Nov-17 6-Dec-17 0%

1-Nov-17 4-Jan-18 0%
STATUS

Completed

Delayed but not at risk

Delayed but not at risk

Delayed but not at risk

Delayed but not at risk

Completed

Completed

Completed

On track

On track

On track
Completed

On track

Completed

On track

On track

On track

On track

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started
Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started

Not started