New Centralized Adaptive Under Frequency Load Shedding Algorithms

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

New Centralized Adaptive Under Frequency

Load Shedding Algorithms


M. Sanaye Pasand, Senior Member, IEEE and H. Seyedi

or sudden load increase. The loads to be shed by this system


Abstract-- In this paper two centralized adaptive Under are constant load feeders and are not selected adaptively. In
Frequency Load Shedding algorithms are proposed and other words always the same loads are dropped from the
analyzed. The objective of these methods is to simultaneously system, regardless of the location of disturbance. In this
protect power systems against frequency instability as well as
method loads are classified in three groups of non-vital, semi-
voltage instability, following combinational disturbances. After
some events in power systems frequency starts to recover, while vital and vital loads [11]. The trend is to shed non-vital loads.
the system collapses due to voltage instability. This situation may However in severe conditions semi-vital loads may also be
occur due to high dependence of loads upon voltage, low shed. Obviously this constant non-adaptive load shed scheme
frequency settings of under frequency relays, slow operation of is not the most efficient one and may cause some problems in
under frequency relays and inappropriate selection of either the system. As an example, outage of a major generating unit
amount or location of loads to be shed by conventional UFLS
in the power system may cause transfer of high amount of
relays. The load shedding algorithms of this paper attempt to
overcome the above mentioned shortcomings of conventional power in long distances which can reduce voltage stability
UFLS method. Performances of the proposed algorithms are margin of the system. In this situation occurrence of another
evaluated by application of adaptive algorithms to the distributed contingency may cause voltage instability, though the system
and dynamic simulated model of a real power system test case. is stable in terms of frequency. After occurrence of the system
disturbance, frequency initially decreases and then it might
Index Terms Adaptive UFLS, Centralized UFLS, Voltage return back to its near normal value, but system might become
stability.
unstable due to voltage problem. The return of frequency is
due to load dependency on voltage and frequency. Therefore,
I. INTRODUCTION
modeling the dependency of load upon voltage and frequency

O NE of the major challenges of electric utilities in recent


years is power system blackout. For instance the
blackouts of Greece, Italy, North America, Sweden and
is of essential importance. In this research work this
dependency has been considered using appropriate load
models.
Denmark, Iran and many others have been mentioned in the Conventional UFLS schemes are generally implemented in a
literature [1]-[5]. In fact, due to both economical and decentralized, i.e. distributed, protection system. In this
technological restrictions, it is not possible to completely approach the decision to shed load is made using the local
prevent these blackouts. However, with the aid of some frequencies measured at the location of relays. However, in
protection and control strategies, frequency and severity of recent years, application of centralized load shedding
these blackouts may be reduced [6]. One of the important algorithms to enhance adaptability of the schemes has been
protection strategies used for this purpose is a class of proposed in some publications [12].
protection schemes known as System Protection Schemes In one of the algorithms, proposed in the present paper, the
[7],[8]. method of [12] is used to calculate the amount of imbalance
System protection schemes are protection strategies designed between generation and load. However in the present work a
to detect a particular system condition that is known to cause new approach is proposed to select the loads that must be
unusual stress to the power system, and to take some kind of shed. Another advantage of this algorithm, compared with that
predetermined action to counteract the observed condition in a of [12], is that in this approach time delay and frequency
controlled manner [9]. One of the most commonly used types settings of the load shedding system is a function of df/dt. This
of system protection schemes, generally accepted after the way the load shedding algorithm is adapted to the intensity of
northeastern blackout of 1965, is Under Frequency Load disturbance. This system could help preserve integrity of the
Shedding (UFLS) scheme [10]. system after extremely large disturbances.
Conventional UFLS system is designed to recover the balance In the second algorithm of this work, instead of the method of
of generation and consumption following a generator outage [12], an event based method is used to calculate the amount of
imbalance between generation and consumption.
Majid Sanaye Pasand (msanaye@ut.ac.ir) and Heresh Seyedi The two proposed algorithms are tested on the simulated
(hereshseyedi@yahoo.com) are with the School of ECE, University of model of Khorasan network, one of the important utilities in
Tehran, Iran. the Iranian interconnected grid.
978-1-4244-1583-0/07/$25.00 2007 IEEE

44
II. CENTRALIZED ADAPTIVE UFLS SCHEMES
In this section two centralized adaptive UFLS algorithms are In the following two subsections centralized adaptive
proposed. The first algorithm is response-based while the UFLS algorithms of this work are introduced.
second is a combination of event-based and response-based A. The Completely Response Based Method
methods.
It is worth mentioning that in response based system In this method the algorithm proposed in [12] is used to
protection schemes, response of the system to disturbances is estimate the magnitude of disturbance, i.e. the imbalance
used in decision making. Input signals of the system in this between generation and consumption. In this algorithm the
method may be voltage, frequency or any other signal of the swing equations of all generators are used to estimate the
system. Under frequency load shedding and under voltage magnitude of disturbance. For this purpose the ith generator
load shedding schemes are popular methods in this class. On ( i=1N, where N is the number of generators ) swing
the other hand in event based method decision is based on the equation is written as follows:
state of specific elements in the system such as important 2H i df i
transmission lines or generators. This method usually requires = Pm i Pe i = Pi
f n dt (1)
a communication link to transmit the state of important
elements to the control center and under frequency relays. For where Pmi is the mechanical turbine power in pu, Pei is the
example one of the methods proposed in this work is partially electrical power in pu, Pi is the imbalance between
event based. In this method UFLS scheme is based on the generation and consumption in pu, Hi is the inertia constant in
outage of generators. Whenever a generator is tripped a signal seconds, fi is the frequency in Hz, and fn is its rated value. By
is transmitted to the control center. The decision making adding swing equations for all generators of the system the
system in the control center determines the amount of load to following equation is obtained for the total imbalance: [12]
be shed based on the location of the tripped generator. The N

algorithm could be extended for outage of tie lines as well. N


2 H i
df c df
[13] P = Pi = i =1
= c
The main features of the proposed methods of this paper i =1 fn dt dt (2)
which distinguish them from conventional method are as the where
following: N N
1) The methods are centralized, therefore there may be fc = Hifi H i
various useful parameters available in the decision i =1 i =1 , (3)
making process. N
2
2) In these methods, in contrast to the conventional
method, voltage of sub-transmission buses has a very
=
fn
H
i =1
i
(4)
important role in the load shedding system, although
there is no need to transmit the measured voltage of fc is the frequency of the equivalent inertial center. Using
busbars to the control center. This way the load the above equations, magnitude of the disturbance is
shedding scheme is sensitive to both frequency and estimated. This value may be used by the UFLS system to
voltage. This characteristic enables the load shed determine the amount of load that must be shed. In order to
scheme to prevent voltage collapse as well as calculate P the estimated values of df/dt at the generator
frequency instability in numerous cases. terminals must be transmitted to the control center.
3) Intelligent selection of loads to be shed is another In this paper a centralized UFLS algorithm, based on the
important feature of the proposed methods. In these above principles, is proposed. This method includes 13 steps:
algorithms loads to be shed are connected to the 1) The first step is to rank all sub-transmission buses of the
buses with low voltages and low voltage stability VQ system in the control center according to their VQ margins.
margins. This characteristic has the highest impact on This ranking may be updated every 10-15 minutes according
the robustness of these methods during combinational to the updated topology of the system.
disturbances. 2) In each sub-transmission substation of the system the
4) In the proposed methods the amount of load to be voltage is measured by voltage transformers. According to the
shed is determined adaptively and it is completely magnitude of positive sequence voltage one of the following
proportional to the magnitude of disturbance. This signals is transmitted to the control center. In (5) ftr is
way the problems of under-shedding and over- frequency of the transmitted signal through the channel.
shedding existing in the conventional UFLS method
are overcome. f 1 if V 0.8
f 2 if 0.8 < V < 0.85
5) In the adaptive methods of this work, frequency
settings and time delay settings are selected f tr =
f 3 if 0.85 V < 0.9
adaptively according to the magnitude of disturbance.
For large disturbances, high frequency settings and
f 4 if V 0.9 (5)
minimum possible time delays are used. This way a This way the control center is aware of the magnitude of
fast response is obtained for large disturbances and, voltage in each sub-transmission bus of the system.
as the results of simulations verify, several voltage 3) Using (5) whenever voltage of a bus falls below 0.8 pu
collapses may be prevented.

45
for a period of 0.2 s load of that bus will be dropped. Since with the conventional load shed scheme. This is particularly
this step is independent of frequency, to avoid overfrequency, important for major disturbances such as outage of important
maximum permissible amount of load to be shed in this step tie lines or complete outage of a power plant including many
must be limited between 10-15 percent of total load. If generating units. For such cases, although the conventional
candidate loads to be shed exceed the limit the priority is load shed scheme might operate and disconnect the selected
given to the loads with low VQ margins, according to the loads in a sequence one after another, but the system could
ranking of step 1. become eventually unstable due to late response of the load
4) Calculation of frequency and its rate of change at the shed scheme. Detailed description about setting UFLS
terminals of all generators of the system. parameters using df/dt may be found in [14],[15].
5) Transmitting the calculated parameters of step 4 to the
B. Combination of Event Based and Response Based Methods
control center through a high speed communication link.
6) Calculation of P, fc and dfc/dt in the control center, This algorithm is similar to A except for the methods of
according to (2)-(4). calculating P and Pshed. In this method instead of using (2)
7) If P exceeds a threshold value, part of system load for calculation of P, an event based method is used. In this
algorithm when a generator is tripped, a signal is sent to the
must be shed. The threshold value ( Pthr ) is the maximum
control center instantly, so it is known which generator is
amount of imbalance between generation and load for which
tripped and what amount of generation is reduced. This is also
frequency does not reach a specified value, for instance 49 Hz correct for tie line outages. The required amount of load to be
in the 50 Hz systems. This value is 350 MW for the simulated shed could be determined considering the amount of
system of this work. The amount of load to be shed is generation outage and also the permissible system frequency
calculated using (6). decline. The 13 steps of A are also applicable to this algorithm
Pshed = 1.05 * (P Pthr ) and there is no difference between the algorithms in this
(6)
regard, except for step 7. In the latter method the revised form
Following a generator outage the system rapidly encounters
of (9) is used to calculate Pshed according to (7).
voltage decline and, due dependence of loads upon voltage,
total system load is suddenly decreased. Therefore the value of Pshed = P Pthr (7)
P, calculated by (2), would be less than active power of the Since in this method the value of P is directly achieved, it
tripped generator. In order to compensate for this, and other is generally greater than the value calculated by (5). Therefore,
uncertainties in modeling, the right side of (6) has been in order to perform the load shedding more optimally and to
multiplied by 1.05. avoid overfrequency, there is no need to multiply the right side
8) In this step the loads to be shed are selected. The first of (7) by 1.05.
candidates to be shed are the loads which their buses have
voltages between 0.8 and 0.85. If the amount of load shedding III. MODELING A TEST SYSTEM
would exceed Pshed, calculated by (6), then the priority is given In order to test the performance of the proposed load
to the buses with low VQ margins according to the ranking of shedding algorithm the HV network of Khorasan province in
step 1. Iran is simulated in a power system analysis tool. The
9) If the amount of load to be shed by the criterion of step 8 Khorasan province network is a grid with seventy two 132 kV
is less than Pshed the loads with bus voltages between 0.85 and and 400 kV buses. This network is connected to the main grid
0.9 are the next candidates. Again if the amount of load through a 400 kV tie line. Total load of this system is about
shedding would exceed Pshed, the priority is given to the buses 2500 MW and its single line diagram is depicted in Fig. 1.
with low VQ margins in the ranking of step 1. The following models are used for power system
10) If the amount of load to be shed by the criteria of steps components of the simulated network:
8 and 9 is still less than Pshed the remaining required loads to 1. The fourth order model is used for system generators in
be shed are selected among the loads with low VQ margins of this study [16], [17].
step 1. 2. The simplified governor model of [17] is used.
11) In order to avoid over-shedding and overfrequency 3. The IEEE type DC1 model is used for AVR modeling
problems, if during 1 second before a generator or tie line [16], [17].
outage some loads had been shed by step 3, these loads would 4. The EPRI load model is used for loads [16]. In this
be considered in load shedding. model dependence of loads upon voltage and frequency
12) After the loads to be shed are selected if |dfc/dt| is less is considered.
than a certain value, related to large disturbances, frequency Conventional UFLS scheme is designed using the method
and time delays settings are similar to the conventional of [18].
scheme.
13) If |dfc/dt| is so large that the event is considered to be a
large disturbance all selected loads will be shed in one step
without any intentional delay and with a higher frequency
setting compared with the first step of the conventional
method. It speeds up the necessary load shed operation and
prevents probable system instability due to delays associated

46
fc
50.1
fc Conventional
50 fc Centralized

49.9

frequency (Hz)
49.8

49.7

49.6

49.5

49.4

49.3
0 20 40 60 80 100 120 140 160
time (cycles)

Fig. 2: fc for event 1.


SahlAbad_132
Voltage (Voltage (per unit))
Gholaman_132
1.2 (Voltage (per unit))
Ferdos_132
(Voltage (per unit))
1 Pardis_132
(Voltage (per unit))
Salehabd_132
(Voltage (per unit))
0.8

Voltage (P.U.)
Jlgerokh_132
(Voltage (per unit))
Bardskn_132
0.6 (Voltage (per unit))
Dargaz_132
(Voltage (per unit))
0.4 SangBast_132
(Voltage (per unit))
Istghazd_132
(Voltage (per unit))
0.2 Khjrabi_132
(Voltage (per unit))
Mehrgan_132
0 (Voltage (per unit))
Sabzvar_132
0 20 40 60 80 100 120 140 160 (Voltage (per unit))
time (Cycles) Abusaid_132
(Voltage (per unit))

Fig. 3: Voltages of some busbars for event 1 and conventional method.


SahlAbad_132
Voltage (Voltage (per unit))
1.2 Gholaman_132
(Voltage (per unit))
Ferdos_132
(Voltage (per unit))
1 Pardis_132
(Voltage (per unit))
Salehabd_132
0.8 (Voltage (per unit))
Voltage (P.U.)

Jlgerokh_132
(Voltage (per unit))
0.6 Bardskn_132
(Voltage (per unit))
Dargaz_132
(Voltage (per unit))
0.4 SangBast_132
(Voltage (per unit))
Fig. 1: Single line diagram of Khorasan province network. Istghazd_132
0.2 (Voltage (per unit))
Khjrabi_132
(Voltage (per unit))

IV. RESULTS OF SIMULATIONS 0 Mehrgan_132


(Voltage (per unit))
0 50 100 150 200 Sabzvar_132

In this section two disturbances are applied to the simulated time (Cycles)
(Voltage (per unit))
Abusaid_132
(Voltage (per unit))
system. Performances of the conventional and proposed Fig. 4: Voltages of some busbars for event 1 and centralized methods.
centralized adaptive UFLS systems following the disturbances
are analyzed. B. Event2: Outage of Toos-Neyshaboor 400 kV line plus
A. Event1: Outage of Gas Units of Neyshaboor Plant outage of Toos power plant
The first event is outage of gas units of Neyshaboor power In this case at first Toos-Neyshaboor 400 kV line is tripped
plant with 390 MW generation. For this event, since the due to a fault at the middle of the line. After 500 ms Toos
amount of generation outage is not so large and also the power plant is disconnected from the system. Again the
system load decreases due to voltage decline, the conventional conventional method is not able to protect the system and
UFLS relays do not operate and the system collapses due to voltage collapse occurs.
voltage instability. However operation of both centralized The first centralized method is also not capable of
methods prevents voltage collapse. This operation is due to protecting the system in view of the fact that after occurrence
under voltage load shedding by step 3 of section II.A. The of the fault, as depicted in Fig.5, an abrupt change is observed
amount of load shed by the centralized methods is 200 MW. in the value of P. This sudden change may be the
Fig. 2 shows frequency of the equivalent inertial center ( fc ) consequence of closeness of the fault to major power plants of
for this event and different load shedding algorithms. Figs. 3 the system i.e. Toos and Neyshaboor power plants. The
and 4 depict voltages of several busbars for conventional and amount of load to be shed calculated by (6) is about 1500
centralized methods respectively. Since in this event operation MW. Shedding this amount of load, the system will
of the centralized methods is performed by under voltage experience cascading outage of generators due to
units, responses of the two centralized methods are identical. overfrequency.

47
P algorithm is generally less than conventional scheme.
500

VI. REFERENCES
0
0 10 20 30 40 50 60 70 80 90 [1] C. Vournas, " Technical summary on the Athens and southern Greece
blackout of July 12, 2004 ", National Technical University of Athens
-500
Report
P (MW)

[2] S. Corsi, C. Sabelli, " General blackout in Italy, Sunday September 28,
-1000 2003, h. 03:28:00 ", IEEE Power Engineering Society General meeting,
2004, Vol. 2, Pages 1691-1702,
-1500
[3] " Power failure in eastern Denmark and southern Sweden on 23
September 2003, Final report on the course of events ", Elkraft System,
November 2003
-2000 [4] " Technical analysis of the August 14, 2003 blackout, What happened,
time (Cycles) why and what did we learn ? ", North American Electric Reliability
Fig. 5: P for event 2 and the first centralized method. Council, Final Report, July 23, 2004
The second centralized method is not affected by the [5] M. Sanaye Pasand, M. R. Dadashzadeh, " Iran national grid blackout,
power system protection point of view ", Developments in Power System
transmission line fault and effectively recovers system Protection, 8th IEE International Conf. April 2004, Vol. 1, Pages 20-23
frequency and voltages. [6] S. H. Horowitz, A. G. Phadke, " Boosting immunity to blackouts ",
IEEE Power and Energy Magazine, Sept./Oct. 2003
C. Discussion [7] S. Tamronglak, S. H. Horowitz, A. G. Phadke, J. S. Thorp, " Anatomy of
The following points are deduced from the case studies: power system blackouts: preventive relaying strategies ", IEEE Trans.
on Power Delivery, vol. 11, No. 2, April 1996
1) In both simulated cases conventional UFLS algorithm is [8] M. Jonson, " Protection strategies to mitigate major power system
not capable of preserving system stability. This may be the breakdowns ", Ph .D. Dissertation, Chalmers University of Technology,
consequence of its late response due to relatively low Goteborg, Sweden, 2003
[9] P. Crossley, F. Ilar, D. Karlsson, " System protection schemes in power
frequency settings and high intentional time delays. networks: existing installations and ideas for future development ",
2) Another important shortcoming of the conventional Developments in power system protection conference, No. 479, IEE
method that seriously reduces the efficiency of this algorithm 2001
[10] C. W. Taylor, " Concepts of undervoltage load shedding for voltage
is the unintelligent selection of loads to be shed. In this stability ", IEEE Trans. on Power Delivery, vol. 7, No. 2, April. 1992
method UFLS relays are installed in substations with low [11] Z. Ding, D. Cartes and S. Sirvastava, " New load shedding scheme for
degree of importance, mostly from the social or political islanded power systems ", 2006 IEEE/SMC International Conference on
System of Systems Engineering Los Angeles, CA, USA - April 2006
points of view. However if the load shedding is performed in [12] V. V. Terzija, " Adaptive underfrequency load shedding based on the
the areas suffering from low voltage several voltage collapses magnitude of the disturbance estimation ", IEEE Transactions on Power
may be prevented, as simulated cases of this work validate this Systems, Vol. 21, No. 3, Aug. 2006
[13] M. Jonson, Protection strategies to mitigate major power system
fact. breakdowns , Ph .D. Dissertation, Chalmers University of Technology,
3) Although equation (2) seems to calculate the amount of Goteborg, Sweden, 2003
imbalance between generation and consumption accurately, it [14] H. Seyedi, M. Sanaye-Pasand, M. R. Dadashzadeh, " Design and
has an important drawback which has not been considered in simulation of an adaptive load shedding algorithm using a real network
", IEEE Power India Conference, April 10-12, 2006
[12]. When location of a fault is close to large generators of [15] H. Seyedi, M. Sanaye-Pasand and M. R. Dadashzadeh, " Application of
the system equation (2) may improperly result in considerable an adaptive under frequency load shedding scheme ", International
value of P. This may consequently direct the system to Conf. on Power System Protection, Sept. 6-8, 2006, Slovenia
[16] P. S. Kundur, Power System Stability and Control, Mc Grow-Hill, Inc.
overshedding and overfrequency problems. 1993
4) In the second centralized method the problem of [17] " PSAF software users guide and reference manual, CYMSTAB for
incorrect estimation of P is resolved by using the trip signal windows ", CYME international inc., Sept. 1999
[18] J. R. Jones and W. D. Kirkland, " Computer algorithm for selection of
of the disconnected generator which is quickly transmitted to frequency relays for load shedding ", Computer Applications in Power,
the control center. Vol. 1, Jan. 1988, Pages 21-25

V. CONCLUSION VII. BIOGRAPHIES


In this paper two centralized adaptive UFLS schemes were
proposed. The objective is to protect system stability and Majid Sanaye-Pasand, graduated in electrical engineering in 1988, Tehran,
Iran, and received his M.Sc. and Ph.D. in 1994 and 1998, Calgary, Canada,
prevent voltage collapse for major system disturbances or respectively. His areas of interest include power system analysis and control,
occurrence of subsequent events after the initial disturbance. digital protective relays and application of AI. He is at present an associate
The proposed centralized algorithms select the loads to be professor at University of Tehran.
shed based on the magnitude of sub-transmission bus voltages
Heresh Seyedi, is a Ph.D. student at the school of Electrical and Computer
and also static voltage stability VQ margins of the buses. The Engineering, University of Tehran, Iran and currently a visiting scholar at the
proposed methods were applied to the simulated model of a University of Waterloo, Ontario, Canada. He graduated in electrical
real test system using distributed and dynamic modeling of the engineering in 2001 and received his M.Sc in 2003, university of Tehran, Iran.
system. The results of simulations show that the second His areas of interest include power system analysis, power system protection,
transmission line switching transients.
centralized approach proposed in this work is capable of
efficiently preserve system stability following severe
disturbances while the amount of load to be shed by this

48

You might also like