Professional Documents
Culture Documents
New Centralized Adaptive Under Frequency Load Shedding Algorithms
New Centralized Adaptive Under Frequency Load Shedding Algorithms
New Centralized Adaptive Under Frequency Load Shedding Algorithms
44
II. CENTRALIZED ADAPTIVE UFLS SCHEMES
In this section two centralized adaptive UFLS algorithms are In the following two subsections centralized adaptive
proposed. The first algorithm is response-based while the UFLS algorithms of this work are introduced.
second is a combination of event-based and response-based A. The Completely Response Based Method
methods.
It is worth mentioning that in response based system In this method the algorithm proposed in [12] is used to
protection schemes, response of the system to disturbances is estimate the magnitude of disturbance, i.e. the imbalance
used in decision making. Input signals of the system in this between generation and consumption. In this algorithm the
method may be voltage, frequency or any other signal of the swing equations of all generators are used to estimate the
system. Under frequency load shedding and under voltage magnitude of disturbance. For this purpose the ith generator
load shedding schemes are popular methods in this class. On ( i=1N, where N is the number of generators ) swing
the other hand in event based method decision is based on the equation is written as follows:
state of specific elements in the system such as important 2H i df i
transmission lines or generators. This method usually requires = Pm i Pe i = Pi
f n dt (1)
a communication link to transmit the state of important
elements to the control center and under frequency relays. For where Pmi is the mechanical turbine power in pu, Pei is the
example one of the methods proposed in this work is partially electrical power in pu, Pi is the imbalance between
event based. In this method UFLS scheme is based on the generation and consumption in pu, Hi is the inertia constant in
outage of generators. Whenever a generator is tripped a signal seconds, fi is the frequency in Hz, and fn is its rated value. By
is transmitted to the control center. The decision making adding swing equations for all generators of the system the
system in the control center determines the amount of load to following equation is obtained for the total imbalance: [12]
be shed based on the location of the tripped generator. The N
45
for a period of 0.2 s load of that bus will be dropped. Since with the conventional load shed scheme. This is particularly
this step is independent of frequency, to avoid overfrequency, important for major disturbances such as outage of important
maximum permissible amount of load to be shed in this step tie lines or complete outage of a power plant including many
must be limited between 10-15 percent of total load. If generating units. For such cases, although the conventional
candidate loads to be shed exceed the limit the priority is load shed scheme might operate and disconnect the selected
given to the loads with low VQ margins, according to the loads in a sequence one after another, but the system could
ranking of step 1. become eventually unstable due to late response of the load
4) Calculation of frequency and its rate of change at the shed scheme. Detailed description about setting UFLS
terminals of all generators of the system. parameters using df/dt may be found in [14],[15].
5) Transmitting the calculated parameters of step 4 to the
B. Combination of Event Based and Response Based Methods
control center through a high speed communication link.
6) Calculation of P, fc and dfc/dt in the control center, This algorithm is similar to A except for the methods of
according to (2)-(4). calculating P and Pshed. In this method instead of using (2)
7) If P exceeds a threshold value, part of system load for calculation of P, an event based method is used. In this
algorithm when a generator is tripped, a signal is sent to the
must be shed. The threshold value ( Pthr ) is the maximum
control center instantly, so it is known which generator is
amount of imbalance between generation and load for which
tripped and what amount of generation is reduced. This is also
frequency does not reach a specified value, for instance 49 Hz correct for tie line outages. The required amount of load to be
in the 50 Hz systems. This value is 350 MW for the simulated shed could be determined considering the amount of
system of this work. The amount of load to be shed is generation outage and also the permissible system frequency
calculated using (6). decline. The 13 steps of A are also applicable to this algorithm
Pshed = 1.05 * (P Pthr ) and there is no difference between the algorithms in this
(6)
regard, except for step 7. In the latter method the revised form
Following a generator outage the system rapidly encounters
of (9) is used to calculate Pshed according to (7).
voltage decline and, due dependence of loads upon voltage,
total system load is suddenly decreased. Therefore the value of Pshed = P Pthr (7)
P, calculated by (2), would be less than active power of the Since in this method the value of P is directly achieved, it
tripped generator. In order to compensate for this, and other is generally greater than the value calculated by (5). Therefore,
uncertainties in modeling, the right side of (6) has been in order to perform the load shedding more optimally and to
multiplied by 1.05. avoid overfrequency, there is no need to multiply the right side
8) In this step the loads to be shed are selected. The first of (7) by 1.05.
candidates to be shed are the loads which their buses have
voltages between 0.8 and 0.85. If the amount of load shedding III. MODELING A TEST SYSTEM
would exceed Pshed, calculated by (6), then the priority is given In order to test the performance of the proposed load
to the buses with low VQ margins according to the ranking of shedding algorithm the HV network of Khorasan province in
step 1. Iran is simulated in a power system analysis tool. The
9) If the amount of load to be shed by the criterion of step 8 Khorasan province network is a grid with seventy two 132 kV
is less than Pshed the loads with bus voltages between 0.85 and and 400 kV buses. This network is connected to the main grid
0.9 are the next candidates. Again if the amount of load through a 400 kV tie line. Total load of this system is about
shedding would exceed Pshed, the priority is given to the buses 2500 MW and its single line diagram is depicted in Fig. 1.
with low VQ margins in the ranking of step 1. The following models are used for power system
10) If the amount of load to be shed by the criteria of steps components of the simulated network:
8 and 9 is still less than Pshed the remaining required loads to 1. The fourth order model is used for system generators in
be shed are selected among the loads with low VQ margins of this study [16], [17].
step 1. 2. The simplified governor model of [17] is used.
11) In order to avoid over-shedding and overfrequency 3. The IEEE type DC1 model is used for AVR modeling
problems, if during 1 second before a generator or tie line [16], [17].
outage some loads had been shed by step 3, these loads would 4. The EPRI load model is used for loads [16]. In this
be considered in load shedding. model dependence of loads upon voltage and frequency
12) After the loads to be shed are selected if |dfc/dt| is less is considered.
than a certain value, related to large disturbances, frequency Conventional UFLS scheme is designed using the method
and time delays settings are similar to the conventional of [18].
scheme.
13) If |dfc/dt| is so large that the event is considered to be a
large disturbance all selected loads will be shed in one step
without any intentional delay and with a higher frequency
setting compared with the first step of the conventional
method. It speeds up the necessary load shed operation and
prevents probable system instability due to delays associated
46
fc
50.1
fc Conventional
50 fc Centralized
49.9
frequency (Hz)
49.8
49.7
49.6
49.5
49.4
49.3
0 20 40 60 80 100 120 140 160
time (cycles)
Voltage (P.U.)
Jlgerokh_132
(Voltage (per unit))
Bardskn_132
0.6 (Voltage (per unit))
Dargaz_132
(Voltage (per unit))
0.4 SangBast_132
(Voltage (per unit))
Istghazd_132
(Voltage (per unit))
0.2 Khjrabi_132
(Voltage (per unit))
Mehrgan_132
0 (Voltage (per unit))
Sabzvar_132
0 20 40 60 80 100 120 140 160 (Voltage (per unit))
time (Cycles) Abusaid_132
(Voltage (per unit))
Jlgerokh_132
(Voltage (per unit))
0.6 Bardskn_132
(Voltage (per unit))
Dargaz_132
(Voltage (per unit))
0.4 SangBast_132
(Voltage (per unit))
Fig. 1: Single line diagram of Khorasan province network. Istghazd_132
0.2 (Voltage (per unit))
Khjrabi_132
(Voltage (per unit))
In this section two disturbances are applied to the simulated time (Cycles)
(Voltage (per unit))
Abusaid_132
(Voltage (per unit))
system. Performances of the conventional and proposed Fig. 4: Voltages of some busbars for event 1 and centralized methods.
centralized adaptive UFLS systems following the disturbances
are analyzed. B. Event2: Outage of Toos-Neyshaboor 400 kV line plus
A. Event1: Outage of Gas Units of Neyshaboor Plant outage of Toos power plant
The first event is outage of gas units of Neyshaboor power In this case at first Toos-Neyshaboor 400 kV line is tripped
plant with 390 MW generation. For this event, since the due to a fault at the middle of the line. After 500 ms Toos
amount of generation outage is not so large and also the power plant is disconnected from the system. Again the
system load decreases due to voltage decline, the conventional conventional method is not able to protect the system and
UFLS relays do not operate and the system collapses due to voltage collapse occurs.
voltage instability. However operation of both centralized The first centralized method is also not capable of
methods prevents voltage collapse. This operation is due to protecting the system in view of the fact that after occurrence
under voltage load shedding by step 3 of section II.A. The of the fault, as depicted in Fig.5, an abrupt change is observed
amount of load shed by the centralized methods is 200 MW. in the value of P. This sudden change may be the
Fig. 2 shows frequency of the equivalent inertial center ( fc ) consequence of closeness of the fault to major power plants of
for this event and different load shedding algorithms. Figs. 3 the system i.e. Toos and Neyshaboor power plants. The
and 4 depict voltages of several busbars for conventional and amount of load to be shed calculated by (6) is about 1500
centralized methods respectively. Since in this event operation MW. Shedding this amount of load, the system will
of the centralized methods is performed by under voltage experience cascading outage of generators due to
units, responses of the two centralized methods are identical. overfrequency.
47
P algorithm is generally less than conventional scheme.
500
VI. REFERENCES
0
0 10 20 30 40 50 60 70 80 90 [1] C. Vournas, " Technical summary on the Athens and southern Greece
blackout of July 12, 2004 ", National Technical University of Athens
-500
Report
P (MW)
[2] S. Corsi, C. Sabelli, " General blackout in Italy, Sunday September 28,
-1000 2003, h. 03:28:00 ", IEEE Power Engineering Society General meeting,
2004, Vol. 2, Pages 1691-1702,
-1500
[3] " Power failure in eastern Denmark and southern Sweden on 23
September 2003, Final report on the course of events ", Elkraft System,
November 2003
-2000 [4] " Technical analysis of the August 14, 2003 blackout, What happened,
time (Cycles) why and what did we learn ? ", North American Electric Reliability
Fig. 5: P for event 2 and the first centralized method. Council, Final Report, July 23, 2004
The second centralized method is not affected by the [5] M. Sanaye Pasand, M. R. Dadashzadeh, " Iran national grid blackout,
power system protection point of view ", Developments in Power System
transmission line fault and effectively recovers system Protection, 8th IEE International Conf. April 2004, Vol. 1, Pages 20-23
frequency and voltages. [6] S. H. Horowitz, A. G. Phadke, " Boosting immunity to blackouts ",
IEEE Power and Energy Magazine, Sept./Oct. 2003
C. Discussion [7] S. Tamronglak, S. H. Horowitz, A. G. Phadke, J. S. Thorp, " Anatomy of
The following points are deduced from the case studies: power system blackouts: preventive relaying strategies ", IEEE Trans.
on Power Delivery, vol. 11, No. 2, April 1996
1) In both simulated cases conventional UFLS algorithm is [8] M. Jonson, " Protection strategies to mitigate major power system
not capable of preserving system stability. This may be the breakdowns ", Ph .D. Dissertation, Chalmers University of Technology,
consequence of its late response due to relatively low Goteborg, Sweden, 2003
[9] P. Crossley, F. Ilar, D. Karlsson, " System protection schemes in power
frequency settings and high intentional time delays. networks: existing installations and ideas for future development ",
2) Another important shortcoming of the conventional Developments in power system protection conference, No. 479, IEE
method that seriously reduces the efficiency of this algorithm 2001
[10] C. W. Taylor, " Concepts of undervoltage load shedding for voltage
is the unintelligent selection of loads to be shed. In this stability ", IEEE Trans. on Power Delivery, vol. 7, No. 2, April. 1992
method UFLS relays are installed in substations with low [11] Z. Ding, D. Cartes and S. Sirvastava, " New load shedding scheme for
degree of importance, mostly from the social or political islanded power systems ", 2006 IEEE/SMC International Conference on
System of Systems Engineering Los Angeles, CA, USA - April 2006
points of view. However if the load shedding is performed in [12] V. V. Terzija, " Adaptive underfrequency load shedding based on the
the areas suffering from low voltage several voltage collapses magnitude of the disturbance estimation ", IEEE Transactions on Power
may be prevented, as simulated cases of this work validate this Systems, Vol. 21, No. 3, Aug. 2006
[13] M. Jonson, Protection strategies to mitigate major power system
fact. breakdowns , Ph .D. Dissertation, Chalmers University of Technology,
3) Although equation (2) seems to calculate the amount of Goteborg, Sweden, 2003
imbalance between generation and consumption accurately, it [14] H. Seyedi, M. Sanaye-Pasand, M. R. Dadashzadeh, " Design and
has an important drawback which has not been considered in simulation of an adaptive load shedding algorithm using a real network
", IEEE Power India Conference, April 10-12, 2006
[12]. When location of a fault is close to large generators of [15] H. Seyedi, M. Sanaye-Pasand and M. R. Dadashzadeh, " Application of
the system equation (2) may improperly result in considerable an adaptive under frequency load shedding scheme ", International
value of P. This may consequently direct the system to Conf. on Power System Protection, Sept. 6-8, 2006, Slovenia
[16] P. S. Kundur, Power System Stability and Control, Mc Grow-Hill, Inc.
overshedding and overfrequency problems. 1993
4) In the second centralized method the problem of [17] " PSAF software users guide and reference manual, CYMSTAB for
incorrect estimation of P is resolved by using the trip signal windows ", CYME international inc., Sept. 1999
[18] J. R. Jones and W. D. Kirkland, " Computer algorithm for selection of
of the disconnected generator which is quickly transmitted to frequency relays for load shedding ", Computer Applications in Power,
the control center. Vol. 1, Jan. 1988, Pages 21-25
48