Professional Documents
Culture Documents
3bow-String Girder - Design Construction Aspects PDF
3bow-String Girder - Design Construction Aspects PDF
CONSTRUCTION ASPECTS
By
Anamul Haque Sr DEN/IV/ALD
Sandeep Kumar Sr DEN/II/IZN
Anisur Rehman Dy CE/Br/HQ/Hajipur
Bow string Girder spans of Thane Creek Bridges
The new bridge across Thane creek was required to be constructed parallel to existing
main line bridge which is more than 100 year old constructed with stone masonry for
laying the new corridors between Thane Turbhe Nerul / Vashi commuter line
project. Bridge No.33/1A is located immediately after Thane station and consists of
three clear spans of 30 m each. Bridge No. 33/2A is located across Thane creek and
consists of 5 clear spans of 30 m and one end span of 7.5 m PSC, except for RUB span
of bridge No.33/1A and navigational spans of bridge No.33/2A. Prestressed box girders
of 2.1 m depth resting on neoprene bearing with RCC plate piers have been adopted.
RCC footings rest on good basalt rock was available at shallow depths in creek bed. In
case of RUB span of bridge No.33/1A where sufficient vertical clearance is to be
provided for the passage of light vehicular traffic as per the requirement of Thane
Municipal Corporation and in case of navigational span of bridge No. 33/2A where the
necessary vertical clearance is to be provided as per requirement of inland waterway
authority, a bow string girder type of structure has been considered most suitable, both
from structural and aesthetics point of view.
The construction of 3 spans of bridge No. 33/1A and 32/A across Thane Creek is
a part of a commuter line Project from Thane-Turbhe Nerul/Vashi. The construction of
two bridges are on East side of existing arch bridges which are more than 100 year old,
constructed with stone masonry existing bridges are having UCR foundations.
Existing bridge has one navigational clear span of 24.2 m with vertical clearance
6.96m from MHWS (Mean High Water of Spring tides). As indicated by Port
Authorities, that in July 1976, Government of Maharashtra has appointed a Committee
of Technical Experts on the Engineering feasibility of THE THANE CREEK-ULHAS
RIVER-BASSEIN CREEK-DHARAMTAR CREEK-ISLAND WATERWAY
PROJECT, MAHARASHTRA PROJECT. They have recommended providing two
navigational spans of 30 m and vertical clearance of 9.0 m at all tide levels. However it
was possible to provide two spans for navigational purpose but vertical clearance cant
be increased because of near by Thane yard, where gradient of track cannot be increased.
Hence Port Authorities has agreed that same vertical clearance as available in existing
bridge can be provided and in due course they will dredge the present bed to a depth of
3.0m.
As the hangers are tension members of the Bow String Bridge, these are the most
important and crucial members of the girder. Therefore to protect these hangers from
any damage due to derailment of trains, the fender boxes have been provided at 3.5m
height from Rail Level on each hangers of central arch.
Design Approach
For this bridge, additional vertical clearance was required to be provided in three
spans. Hence design approach was to develop a structural configuration, which will
require minimum depth 1500 mm between rail top to soffit of structure for the long
span of 32 m with MBG loading. Since rail, ballast etc. takes up depth of 750mm,
structural depth of only 750 mm is available. Live load defection permissible as per IRS
Concrete Bridge Code is only span/1000, it was therefore necessary to have
configuration stiff enough to keep live load deformations under check, without
increasing dead load & depth below rail. Structure should also have adequate fatigue
strength and durability. Actual design was done as per relevant Railway loading
standards & codes.
Three bowstring girders of 32 m span with limited depth of 750 mm only were
designed to support two tracks whereas normal depth requirement with PSC box girder
was 2.5m. A single-track loading is 50% higher than a two-lane roadway loading, central
bowstring girder is thus carrying equivalent of a 3-lane roadway loading.
Salient Features
a) Chosen form improves durability as most of the structure is in compression.
c) Partial shock absorbing system provided on hangers to reduce the damage due
to accident.
Normal precautions like provision of checkrails etc. has been made as safety
against derailment. Additionally on the central hanger, structural steel buffer
boxes have been provided at an appropriate level, which can absorb some of the
impact in case any of the bogies come to rest against the hangars. Spacing of
hangars is such that at least 4-5 hangars will share the load.
Construction Aspects
In order to reduce the construction joints in beams, slabs and arches it has
been concreted in a single pour of 247 cum covering end cross beams,
longitudinal beams, deck slab and end part of arch (3 m height). Special floating
type of shuttering to cover 3m height of arch was erected. Malamine based
superplasticiser Sikament 500M2 with a dose of 1.2% by weight of cement was
used which gives a slump of 120 mm even after 3 hrs and initial setting time
increased to 6 hrs keeping w/c ratio of 0.37. Concreting sequence was so planned
that new concrete is poured before previously laid concrete achieves initial
setting. Hence cold joints were completely avoided. Hangars were cast with
minimum joints by concreting in 2.0 m lifts. All construction joints have been
sealed with epoxy mortar. The reinforcement bars have been given anticorrosive
treatment as per CECRI and hangar bars were treated with fusion-bonded epoxy.
To make the deck slab water proof, 10 mm thick mastic asphalt and 30
mm thick fiber reinforced concrete of M30 grade has been provided. The fiberlon
nylon fibers were used as reinforcement to avoid shrinkage cracks and higher
impact resistance.
..