Date : 5/2/2013

| LOGO | Project : Hotel Panghegar


HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS6B Area meeting

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 2.725 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 400 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (400)
= 1194.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 806.288 kgm

Mu 806.29
Mn = = 1007.86 kgm
0.8
Koefisien Ketahanan Rn;
Mn 100786
Rn = = 9.14 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.914 = 0 , didapat = 0.001870

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0, 545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 1.96 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 1.96
= = 6.93 atau 7.0
Ab 0.2827
Required U6 - 166.67 mm
use : M6 - 150 + D10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (1007.86 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai M6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 2725
fr saat stripping : 2.71 Mpa B= 1250
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 1.725 m
q1x = 240 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 120.00 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -15.00 kgm
Output model SAP a b
MAB = MBA = 27.78 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 41.67 kgm
Ig = 0.5*1/12*B*t = 26666666.67 mm4
3

Mcrack = fr*Ig/y = 1806666.667 Nmm = 1.807 kNm = 180.7 kgm > Mmax = 41.67 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 41.67
= = 52.0875 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.65 m
q1x = 523.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 261.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -11.77 kgm Output model SAP


MAB= 1.92 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 17.658 kgm
Ig = 0.5*1/12*L*t = 3
58133333.33 mm4
Mcrack = fr*Ig/y = 3938533.333 Nmm = 3.939 kNm = 393.9 kgm > Mmax = 17.658 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 17.658
= = 22.0725 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 252.44124 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.545 m
b = (L-2a) = 1.635 m
q1x =t*B*2400 = 240 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -35.64 kgm Output model SAP


MAB = 41.77 kgm 41.77
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 53333333.33 mm4
Mcrack = fr.Ig/y = 3613333.333 Nmm = 3.613 kNm = 361.3 kgm > Mmax = 41.77 kgm ( O
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 41.77
= = 52.2125 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.3625 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 179.700125 kgm
Mmax 179.7001
Mn = = = 224.63 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =1194.4 x 2.725^2 = 985.46294 kgm
9 9
Mu 985.463
Mn = = 1231.83 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 123182.87
= 11.17 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.117 = 0 , didapat = 0.002297
Dengan memperhitungkan min dan max, diambil nilai = 0.0028
Luas tulangan yang dibutuhkan, As = x b x d = 2.41 cm2
Digunakan baja tulangan M6 - 150 + D10 - 600 ;
As = 3.308 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 1871.476 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 166.67 mm

mm
mm
mm
120.00 kg/m

b a
B
kgm > Mmax = 41.67 kgm ( OK)

25 mm

261.60 kg/m

b a

kgm > Mmax = 17.658 kgm (.. OK)

55 mm

240.00 kg/m
b a

kgm > Mmax = 41.77 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
D10 - 600 mm

M6 - 150 mm + D10 - 600 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS1A Area residential

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.725 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1203.900 kgm

Mu 1203.90
Mn = = 1504.87 kgm
0.8
Koefisien Ketahanan Rn;
Mn 150487
Rn = = 13.65 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.365 = 0 , didapat = 0.002824

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.97 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.97
= = 10.51 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + D10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (1504.87 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai M6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3725
fr saat stripping : 2.71 Mpa B= 1100
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.725 m
q1x = 211.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 105.60 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -13.20 kgm
Output model SAP a b
MAB = MBA = 79.52 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 119.28 kgm
Ig = 0.5*1/12*B*t = 23466666.67 mm4
3

Mcrack = fr*Ig/y = 1589866.667 Nmm = 1.59 kNm = 159 kgm > Mmax = 119.28 kgm

Check terhadap momen yang terjadi :


Mn = Mmax 119.28
= = 149.1 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.5 m
q1x = 715.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 357.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -16.09 kgm Output model SAP


MAB= -15.09 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 24.138 kgm
Ig = 0.5*1/12*L*t = 3
79466666.67 mm4
Mcrack = fr*Ig/y = 5383866.667 Nmm = 5.384 kNm = 538.4 kgm > Mmax = 24.138 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 24.138
= = 30.1725 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 252.44124 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.745 m
b = (L-2a) = 2.235 m
q1x =t*B*2400 = 211.2 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -58.61 kgm Output model SAP


MAB = 63.74 kgm 63.74
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 46933333.33 mm4
Mcrack = fr.Ig/y = 3179733.333 Nmm = 3.18 kNm = 318 kgm > Mmax = 63.74 kgm ( O
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 63.74
= = 79.675 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.8625 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 335.790125 kgm
Mmax 335.7901
Mn = = = 419.74 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =954.4 x 3.725^2 = 1471.4329 kgm
9 9
Mu 1471.433
Mn = = 1839.29 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 183929.12
= 16.68 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.668 = 0 , didapat = 0.003480
Dengan memperhitungkan min dan max, diambil nilai = 0.00348
Luas tulangan yang dibutuhkan, As = x b x d = 3.65 cm2
Digunakan baja tulangan M6 - 150 + D10 - 450 ;
As = 3.66 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2044.206 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
105.60 kg/m

b a
B
kgm > Mmax = 119.28 kgm ( OK)

25 mm

357.60 kg/m

b a

kgm > Mmax = 24.138 kgm (.. OK)

55 mm

211.20 kg/m
b a

kgm > Mmax = 63.74 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
D10 - 600 mm

M6 - 150 mm + D10 - 450 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS1I Area residential

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.725 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1203.900 kgm

Mu 1203.90
Mn = = 1504.87 kgm
0.8
Koefisien Ketahanan Rn;
Mn 150487
Rn = = 13.65 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.365 = 0 , didapat = 0.002824

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.97 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.97
= = 10.51 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + D10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (1504.87 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai M6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3725
fr saat stripping : 2.71 Mpa B= 1625
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.725 m
q1x = 312 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 156.00 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -19.50 kgm
Output model SAP a b
MAB = MBA = 117.47 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 176.205 kgm
Ig = 0.5*1/12*B*t = 34666666.67 mm4
3

Mcrack = fr*Ig/y = 2348666.667 Nmm = 2.349 kNm = 234.9 kgm > Mmax = 176.205 kgm

Check terhadap momen yang terjadi :


Mn = Mmax 176.205
= = 220.25625 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 1.025 m
q1x = 715.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 357.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -16.09 kgm Output model SAP


MAB= 24.05 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 36.075 kgm
Ig = 0.5*1/12*L*t = 3
79466666.67 mm4
Mcrack = fr*Ig/y = 5383866.667 Nmm = 5.384 kNm = 538.4 kgm > Mmax = 36.075 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 36.075
= = 45.09375 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 252.44124 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.745 m
b = (L-2a) = 2.235 m
q1x =t*B*2400 = 312 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -86.58 kgm Output model SAP


MAB = 94.16 kgm 94.16
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 69333333.33 mm4
Mcrack = fr.Ig/y = 4697333.333 Nmm = 4.697 kNm = 469.7 kgm > Mmax = 94.16 kgm ( O
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 94.16
= = 117.7 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.8625 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 335.790125 kgm
Mmax 335.7901
Mn = = = 419.74 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =954.4 x 3.725^2 = 1471.4329 kgm
9 9
Mu 1471.433
Mn = = 1839.29 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 183929.12
= 16.68 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.668 = 0 , didapat = 0.003480
Dengan memperhitungkan min dan max, diambil nilai = 0.00348
Luas tulangan yang dibutuhkan, As = x b x d = 3.65 cm2
Digunakan baja tulangan M6 - 150 + D10 - 450 ;
As = 3.66 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2044.206 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
156.00 kg/m

b a
B
kgm > Mmax = 176.205 kgm ( OK)

25 mm

357.60 kg/m

b a

kgm > Mmax = 36.075 kgm (.. OK)

55 mm

312.00 kg/m
b a

kgm > Mmax = 94.16 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
D10 - 600 mm

M6 - 150 mm + D10 - 450 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS4D Area residential

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.93 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1340.056 kgm

Mu 1340.06
Mn = = 1675.07 kgm
0.8
Koefisien Ketahanan Rn;
Mn 167507
Rn = = 15.19 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.519 = 0 , didapat = 0.003157

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.31 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.31
= = 11.71 atau 12.0
Ab 0.2827
Required U6 - 90.91 mm
use : M6 - 150 + D10 - 450 ; 3.38 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.38
aktual = = 0.00322
100 x 10.5
As x fy = 0.8 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1706.9 kgm
Jadi, Mn aktual > Mn perlu (1675.07 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai M6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3930
fr saat stripping : 2.71 Mpa B= 1150
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.93 m
q1x = 220.8 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 110.40 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -13.80 kgm
Output model SAP a b
MAB = MBA = 104.67 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 157.005 kgm
Ig = 0.5*1/12*B*t = 24533333.33 mm4
3

Mcrack = fr*Ig/y = 1662133.333 Nmm = 1.662 kNm = 166.2 kgm > Mmax = 157.005 kgm

Check terhadap momen yang terjadi :


Mn = Mmax 157.005
= = 196.25625 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2/m
a = As*fy/ 0.85*fc'*b = 1.33 cm
Mn = As*fy*(d-a/2) = 310.115 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.55 m
q1x = 754.56 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 377.28 kg/m
y = 0.5t = 40 mm q=

MA = MB = -16.98 kgm Output model SAP


MAB= 24.05 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 36.075 kgm
Ig = 0.5*1/12*L*t = 3
83840000 mm4
Mcrack = fr*Ig/y = 5680160 Nmm = 5.68 kNm = 568 kgm > Mmax = 36.075 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 36.075
= = 45.09375 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 252.44124 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.786 m
b = (L-2a) = 2.358 m
q1x =t*B*2400 = 220.8 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -68.20 kgm Output model SAP


MAB = 94.16 kgm 94.16
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 49066666.67 mm4
Mcrack = fr.Ig/y = 3324266.667 Nmm = 3.324 kNm = 332.4 kgm > Mmax = 94.16 kgm ( O
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 94.16
= = 117.7 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.965 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 373.76658 kgm
Mmax 373.7666
Mn = = = 467.21 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 3.93^2 = 1637.8458 kgm
9 9
Mu 1637.846
Mn = = 2047.31 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 204730.73
= 18.57 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.857 = 0 , didapat = 0.003894
Dengan memperhitungkan min dan max, diambil nilai = 0.003894
Luas tulangan yang dibutuhkan, As = x b x d = 4.09 cm2
Digunakan baja tulangan M6 - 150 + D10 - 300 ;
As = 4.356 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2156.705 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 90.91 mm

mm
mm
mm
110.40 kg/m

b a
B
kgm > Mmax = 157.005 kgm ( OK)

25 mm

377.28 kg/m

b a

kgm > Mmax = 36.075 kgm (.. OK)

55 mm

220.80 kg/m
b a

kgm > Mmax = 94.16 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
D10 - 450 mm

M6 - 150 mm + D10 - 300 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS1H Area residential

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.725 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1203.900 kgm

Mu 1203.90
Mn = = 1504.87 kgm
0.8
Koefisien Ketahanan Rn;
Mn 150487
Rn = = 13.65 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.365 = 0 , didapat = 0.002824

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.97 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.97
= = 10.51 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + D10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (1504.87 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai M6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3725
fr saat stripping : 2.71 Mpa B= 1800
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.725 m
q1x = 345.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 172.80 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -21.60 kgm
Output model SAP a b
MAB = MBA = 138.79 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 208.185 kgm
Ig = 0.5*1/12*B*t = 3
38400000 mm4
Mcrack = fr*Ig/y = 2601600 Nmm = 2.602 kNm = 260.2 kgm > Mmax = 208.185 kgm

Check terhadap momen yang terjadi :


Mn = Mmax 208.185
= = 260.23125 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 1.2 m
q1x = 715.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 357.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -16.09 kgm Output model SAP


MAB= 41.12 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 61.68 kgm
Ig = 0.5*1/12*L*t = 3
79466666.67 mm4
Mcrack = fr*Ig/y = 5383866.667 Nmm = 5.384 kNm = 538.4 kgm > Mmax = 61.68 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 61.68
= = 77.1 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 252.44124 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.745 m
b = (L-2a) = 2.235 m
q1x =t*B*2400 = 345.6 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -95.91 kgm Output model SAP


MAB = 128.27 kgm 128.27
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 76800000 mm4
Mcrack = fr.Ig/y = 5203200 Nmm = 5.203 kNm = 520.3 kgm > Mmax = 128.27 kgm (
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 128.27
= = 160.3375 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.8625 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 335.790125 kgm
Mmax 335.7901
Mn = = = 419.74 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =954.4 x 3.725^2 = 1471.4329 kgm
9 9
Mu 1471.433
Mn = = 1839.29 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 183929.12
= 16.68 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.668 = 0 , didapat = 0.003480
Dengan memperhitungkan min dan max, diambil nilai = 0.00348
Luas tulangan yang dibutuhkan, As = x b x d = 3.65 cm2
Digunakan baja tulangan M6 - 150 + D10 - 450 ;
As = 3.66 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2044.206 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
172.80 kg/m

b a
B
kgm > Mmax = 208.185 kgm ( OK)

25 mm

357.60 kg/m

b a

kgm > Mmax = 61.68 kgm (.. OK)

55 mm

345.60 kg/m
b a

kgm > Mmax = 128.27 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
D10 - 600 mm

M6 - 150 mm + D10 - 450 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE HS1H Area residential

I. Data Half Slab


- Mutu beton half slab K-300 fc = 29 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.725 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban finishing = 120 kg/m2
- Beban M&E = 50 kg/m2 +
Total = 170 kg/m2

- Beban Konstruksi (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+170) + 1.6 (250)
= 978.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1234.174 kgm

Mu 1234.17
Mn = = 1542.72 kgm
0.8
Koefisien Ketahanan Rn;
Mn 154272
Rn = = 13.99 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5086.207 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

5086.207 2 - 500 + 1.399 = 0 , didapat = 0.002883

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0228573
fy 600 + fy 500

max = 0.5b = 0.011428636


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.94 cm2
Digunakan wiremesh M5, Ab = 0.1963 cm2
n= As perlu 2.94
= = 14.98 atau 15.0
Ab 0.1963
Required U5 - 71.43 mm
use : M5 - 150 + D0 - 300 ; 12.356 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

12.356
aktual = = 0.01177
100 x 10.5
As x fy = 2.51 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 5711.561 kgm
Jadi, Mn aktual > Mn perlu (1542.72 kgm) OK

- Tulangan arah pendek


M5 - 150 mm As = 1.374 cm2
aktual = 0.00141
aktual < izin (0.0018) Not OK
dipakai M5 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 17.4 Mpa Ukuran precast Half Slab, L= 3725
fr saat stripping : 2.92 Mpa B= 1800
t= 80
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.725 m
q1x = 345.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 172.80 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -21.60 kgm
Output model SAP a b
MAB = MBA = 138.79 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 208.185 kgm
Ig = 0.5*1/12*B*t = 3
38400000 mm4
Mcrack = fr*Ig/y = 2803200 Nmm = 2.803 kNm = 280.3 kgm > Mmax = 208.185 kg

Check terhadap momen yang terjadi :


Mn = Mmax 208.185
= = 260.23125 kgm
0.8
digunakan besi tulangan M5 - 150 mm, As = 12.356 cm2/m
a = As*fy/ 0.85*fc'*b = 4.18 cm
Mn = As*fy*(d-a/2) = 253.298 kgm < Mn perlu ( Not OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 1.2 m
q1x = 715.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 357.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -16.09 kgm Output model SAP


MAB= 41.12 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 61.68 kgm
Ig = 0.5*1/12*L*t = 3
79466666.67 mm4
Mcrack = fr*Ig/y = 5801066.667 Nmm = 5.801 kNm = 580.1 kgm > Mmax = 61.68 kgm (..

Check terhadap momen yang terjadi :


Mn = Mmax 61.68
= = 77.1 kgm
0.8
digunakan besi tulangan P5 - 150 mm, As = 1.374 cm2
a= 0.22 cm
Mn = As fy (d-a/2) = 177.74064 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.745 m
b = (L-2a) = 2.235 m
q1x =t*B*2400 = 345.6 kg/m
y = 0.5*t = 40 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -95.91 kgm Output model SAP


MAB = 128.27 kgm 128.27
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 76800000 mm4
Mcrack = fr.Ig/y = 5606400 Nmm = 5.606 kNm = 560.6 kgm > Mmax = 128.27 kgm (
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 128.27
= = 160.3375 kgm
0.8
digunakan besi tulangan M5 - 150 mm, As = 12.356 cm2
a= 4.18 cm
Mn = As fy (d-a/2) = 2106.698 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.8625 m
beban pelaksanaan = 250 kg/m2
beban beton topping 5.5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 335.790125 kgm
Mmax 335.7901
Mn = = = 419.74 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 17.4 Mpa
a= 4.18 cm
Mn = As fy (d-a/2) = 2106.698 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =978.4 x 3.725^2 = 1508.4346 kgm
9 9
Mu 1508.435
Mn = = 1885.54 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 188554.33
= 17.10 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5086.207 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5086.207 2 - 500 + 1.71 = 0 , didapat = 0.003549
Dengan memperhitungkan min dan max, diambil nilai = 0.0035486
Luas tulangan yang dibutuhkan, As = x b x d = 3.73 cm2
Digunakan baja tulangan M6 - 150 + D10 - 450 ;
As = 3.66 cm2
(*)
< As perlu ( Not OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2095.611 kg
2
Vc = 1/6fc'bwd = 9424.038 kg
Vc = 7068.029 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U5 - 71.43 mm

mm
mm
mm
172.80 kg/m

b a
B
kgm > Mmax = 208.185 kgm ( OK)

25 mm

357.60 kg/m

b a

kgm > Mmax = 61.68 kgm (.. OK)

55 mm

345.60 kg/m
b a

kgm > Mmax = 128.27 kgm ( OK)


55 mm

55 mm

105 mm

( Not OK)
M5 - 150 mm
D10 - 300 mm

M6 - 150 mm + D10 - 450 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE B2

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 75 mm
- Tebal topping t top = 55 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.9 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1319.675 kgm

Mu 1319.67
Mn = = 1649.59 kgm
0.8
Koefisien Ketahanan Rn;
Mn 164959
Rn = = 14.96 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.496 = 0 , didapat = 0.003107

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.26 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.26
= = 11.53 atau 12.0
Ab 0.2827
Required U6 - 90.91 mm
use : M6 - 150 + U10 - 600 ; 3.308 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.308
aktual = = 0.00315
100 x 10.5
As x fy = 0.78 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1672.194 kgm
Jadi, Mn aktual > Mn perlu (1649.59 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3900
fr saat stripping : 2.71 Mpa B= 1018
t= 75
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 1.3 m
b= 1.3 m
q1x = 183.24 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 91.62 kg/m
y = 0.5*t = 37.5 mm q=

MA = MB = -77.42 kgm
Output model SAP a b
MAB = MBA = 77.42 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 116.1284 kgm
Ig = 0.5*1/12*B*t = 17894531.25 mm4
3

Mcrack = fr*Ig/y = 1293178.125 Nmm = 1.293 kNm = 129.3 kgm > Mmax = 116.12835 k

Check terhadap momen yang terjadi :


Mn = Mmax 116.1284
= = 145.160438 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.308 cm2/m
a = As*fy/ 0.85*fc'*b = 1.3 cm
Mn = As*fy*(d-a/2) = 305.99 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.4 m
b= 0.7 m
q1x = 702 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 351.00 kg/m
y = 0.5t = 37.5 mm q=

MA = MB = -28.08 kgm Output model SAP


MAB= 86.00 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 128.9925 kgm
Ig = 0.5*1/12*L*t = 3
68554687.5 mm4
Mcrack = fr*Ig/y = 4954218.75 Nmm = 4.954 kNm = 495.4 kgm > Mmax = 128.9925 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 128.9925
= = 161.240625 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 228.69324 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.78 m
b = (L-2a) = 2.34 m
q1x =t*B*2400 = 183.24 kg/m
y = 0.5*t = 37.5 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -55.74 kgm Output model SAP


MAB = 501.67 kgm 501.67447
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 35789062.5 mm4
Mcrack = fr.Ig/y = 2586356.25 Nmm = 2.586 kNm = 258.6 kgm < Mmax = 501.674472 kgm
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 501.6745
= = 627.09309 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.308 cm2
a= 1.3 cm
Mn = As fy (d-a/2) = 719.49 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.95 m
beban orang bekerja = 250 kg/m2
beban beton topping 5.5 cm = 132 kg/m2
berat sendiri Half Slab = 180 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 368.082 kgm
Mmax 368.082
Mn = = = 460.10 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.3 cm
Mn = As fy (d-a/2) = 719.49 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 3.9^2 = 1612.936 kgm
9 9
Mu 1612.936
Mn = = 2016.17 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 201617.00
= 18.29 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.829 = 0 , didapat = 0.003831
Dengan memperhitungkan min dan max, diambil nilai = 0.003831
Luas tulangan yang dibutuhkan, As = x b x d = 4.02 cm2
Digunakan baja tulangan M6 - 150 + U10 - 300 ;
As = 4.356 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2140.242 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 90.91 mm

mm
mm
mm
91.62 kg/m

b a
B
kgm > Mmax = 116.12835 kgm ( OK)

25 mm

351.00 kg/m

b a

kgm > Mmax = 128.9925 kgm (.. OK)

50 mm

183.24 kg/m
b a

kgm < Mmax = 501.674472 kgm ( Not OK)


50 mm

50 mm

105 mm
M6 - 150 mm
U10 - 600 mm

M6 - 150 mm + U10 - 300 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.45 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m2

- Beban Hidup (LL) = 400 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 150) + 1.6 (400)
= 1194.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1292.395 kgm

Mu 1292.40
Mn = = 1615.49 kgm
0.8
Koefisien Ketahanan Rn;
Mn 161549
Rn = = 14.65 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.465 = 0 , didapat = 0.003040

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.19 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.19
= = 11.28 atau 12.0
Ab 0.2827
Required U6 - 90.91 mm
use : M6 - 150 + U10 - 450 ; 3.38 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.38
aktual = = 0.00322
100 x 10.5
As x fy = 0.8 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1706.9 kgm
Jadi, Mn aktual > Mn perlu (1615.49 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3450
fr saat stripping : 2.71 Mpa B= 900
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.45 m
q1x = 172.8 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 86.40 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -10.80 kgm
Output model SAP a b
MAB = MBA = -10.80 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 16.2 kgm
Ig = 0.5*1/12*B*t = 3
19200000 mm4
Mcrack = fr*Ig/y = 1300800 Nmm = 1.301 kNm = 130.1 kgm > Mmax = 16.2 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 16.2
= = 20.25 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2/m
a = As*fy/ 0.85*fc'*b = 1.33 cm
Mn = As*fy*(d-a/2) = 310.115 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.3 m
q1x = 662.4 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 331.20 kg/m
y = 0.5t = 40 mm q=

MA = MB = -14.90 kgm Output model SAP


MAB= -14.90 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 22.356 kgm
Ig = 0.5*1/12*L*t = 3
73600000 mm4
Mcrack = fr*Ig/y = 4986400 Nmm = 4.986 kNm = 498.6 kgm > Mmax = 22.356 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 22.356
= = 27.945 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.69 m
b = (L-2a) = 2.07 m
q1x =t*B*2400 = 172.8 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -41.14 kgm Output model SAP


MAB = -41.14 kgm 41.13504
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 38400000 mm4
Mcrack = fr.Ig/y = 2601600 Nmm = 2.602 kNm = 260.2 kgm > Mmax = 41.13504 kgm (
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 41.13504
= = 51.4188 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.725 m
beban orang bekerja = 400 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 1014.4 kg/m
Mu = 1/8*Qu*a2 = 377.30925 kgm
Mmax 377.3093
Mn = = = 471.64 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =1194.4 x 3.45^2 = 1579.594 kgm
9 9
Mu 1579.594
Mn = = 1974.49 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 197449.25
= 17.91 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.791 = 0 , didapat = 0.003748
Dengan memperhitungkan min dan max, diambil nilai = 0.003748
Luas tulangan yang dibutuhkan, As = x b x d = 3.94 cm2
Digunakan baja tulangan M6 - 150 + U10 - 300 ;
As = 4.356 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2369.391 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 90.91 mm

mm
mm
mm
86.40 kg/m

b a
B
kgm > Mmax = 16.2 kgm ( OK)

25 mm

331.20 kg/m

b a

kgm > Mmax = 22.356 kgm (.. OK)

55 mm

172.80 kg/m
b a

kgm > Mmax = 41.13504 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 450 mm

M6 - 150 mm + U10 - 300 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE B3

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 75 mm
- Tebal topping t top = 55 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.7 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1187.794 kgm

Mu 1187.79
Mn = = 1484.74 kgm
0.8
Koefisien Ketahanan Rn;
Mn 148474
Rn = = 13.47 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.347 = 0 , didapat = 0.002785

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.92 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.92
= = 10.33 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + U10 - 750 ; 3.1 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.1
aktual = = 0.00295
100 x 10.5
As x fy = 0.73 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1570.925 kgm
Jadi, Mn aktual > Mn perlu (1484.74 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3700
fr saat stripping : 2.71 Mpa B= 1018
t= 75
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 1.2 m
b= 1.3 m
q1x = 183.24 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 91.62 kg/m
y = 0.5*t = 37.5 mm q=

MA = MB = -65.97 kgm
Output model SAP a b
MAB = MBA = 77.42 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 116.1284 kgm
Ig = 0.5*1/12*B*t = 17894531.25 mm4
3

Mcrack = fr*Ig/y = 1293178.125 Nmm = 1.293 kNm = 129.3 kgm > Mmax = 116.12835 k

Check terhadap momen yang terjadi :


Mn = Mmax 116.1284
= = 145.160438 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.1 cm2/m
a = As*fy/ 0.85*fc'*b = 1.22 cm
Mn = As*fy*(d-a/2) = 292.95 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.4 m
b= 0.7 m
q1x = 666 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 333.00 kg/m
y = 0.5t = 37.5 mm q=

MA = MB = -26.64 kgm Output model SAP


MAB= 81.59 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 122.3775 kgm
Ig = 0.5*1/12*L*t = 3
65039062.5 mm4
Mcrack = fr*Ig/y = 4700156.25 Nmm = 4.7 kNm = 470 kgm > Mmax = 122.3775 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 122.3775
= = 152.971875 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 228.69324 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.74 m
b = (L-2a) = 2.22 m
q1x =t*B*2400 = 183.24 kg/m
y = 0.5*t = 37.5 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -50.17 kgm Output model SAP


MAB = 451.54 kgm 451.54001
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 35789062.5 mm4
Mcrack = fr.Ig/y = 2586356.25 Nmm = 2.586 kNm = 258.6 kgm < Mmax = 451.540008 kgm
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 451.54
= = 564.42501 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.1 cm2
a= 1.22 cm
Mn = As fy (d-a/2) = 680.45 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.85 m
beban orang bekerja = 250 kg/m2
beban beton topping 5.5 cm = 132 kg/m2
berat sendiri Half Slab = 180 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 331.298 kgm
Mmax 331.298
Mn = = = 414.12 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.22 cm
Mn = As fy (d-a/2) = 680.45 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 3.7^2 = 1451.7484 kgm
9 9
Mu 1451.748
Mn = = 1814.69 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 181468.56
= 16.46 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.646 = 0 , didapat = 0.003431
Dengan memperhitungkan min dan max, diambil nilai = 0.003431
Luas tulangan yang dibutuhkan, As = x b x d = 3.6 cm2
Digunakan baja tulangan M6 - 150 + U10 - 450 ;
As = 3.66 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2030.486 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
91.62 kg/m

b a
B
kgm > Mmax = 116.12835 kgm ( OK)

25 mm

333.00 kg/m

b a

kgm > Mmax = 122.3775 kgm (.. OK)

50 mm

183.24 kg/m
b a

kgm < Mmax = 451.540008 kgm ( Not OK)


50 mm

50 mm

105 mm
M6 - 150 mm
U10 - 750 mm

M6 - 150 mm + U10 - 450 mm


Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE B4

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 75 mm
- Tebal topping t top = 55 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 2.6 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312+150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 586.522 kgm

Mu 586.52
Mn = = 733.15 kgm
0.8
Koefisien Ketahanan Rn;
Mn 73315
Rn = = 6.65 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.665 = 0 , didapat = 0.001352

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 1.42 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 1.42
= = 5.02 atau 6.0
Ab 0.2827
Required U6 - 200 mm
use : M6 - 150 + U10 - 1500 ; 2.676 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

2.676
aktual = = 0.00255
100 x 10.5
As x fy = 0.63 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1362.753 kgm
Jadi, Mn aktual > Mn perlu (733.15 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 1.979 cm2
aktual = 0.00206
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 2600
fr saat stripping : 2.71 Mpa B= 1018
t= 75
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.75 m
b= 1.1 m
q1x = 183.24 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 91.62 kg/m
y = 0.5*t = 37.5 mm q=

MA = MB = -25.77 kgm
Output model SAP a b
MAB = MBA = 55.43 kgm A
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 83.14515 kgm
Ig = 0.5*1/12*B*t = 17894531.25 mm4
3

Mcrack = fr*Ig/y = 1293178.125 Nmm = 1.293 kNm = 129.3 kgm > Mmax = 83.14515 kg

Check terhadap momen yang terjadi :


Mn = Mmax 83.14515
= = 103.931438 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 2.676 cm2/m
a = As*fy/ 0.85*fc'*b = 1.05 cm
Mn = As*fy*(d-a/2) = 264.255 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.9 m
q1x = 468 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 234.00 kg/m
y = 0.5t = 37.5 mm q=

MA = MB = -10.53 kgm Output model SAP


MAB= 94.77 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 142.155 kgm
Ig = 0.5*1/12*L*t = 3
45703125 mm4
Mcrack = fr*Ig/y = 3302812.5 Nmm = 3.303 kNm = 330.3 kgm > Mmax = 142.155 kgm (..

Check terhadap momen yang terjadi :


Mn = Mmax 142.155
= = 177.69375 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 1.979 cm2
a= 0.37 cm
Mn = As fy (d-a/2) = 228.69324 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.52 m
b = (L-2a) = 1.56 m
q1x =t*B*2400 = 183.24 kg/m
y = 0.5*t = 37.5 mm
q=
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -24.77 kgm Output model SAP


MAB = 222.97 kgm 222.96643
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 35789062.5 mm4
Mcrack = fr.Ig/y = 2586356.25 Nmm = 2.586 kNm = 258.6 kgm > Mmax = 222.966432 kgm
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 222.9664
= = 278.70804 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 2.676 cm2
a= 1.05 cm
Mn = As fy (d-a/2) = 598.755 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.3 m
beban orang bekerja = 250 kg/m2
beban beton topping 5.5 cm = 132 kg/m2
berat sendiri Half Slab = 180 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 163.592 kgm
Mmax 163.592
Mn = = = 204.49 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.05 cm
Mn = As fy (d-a/2) = 598.755 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 2.6^2 = 716.86044 kgm
9 9
Mu 716.860
Mn = = 896.08 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 89607.56
= 8.13 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.813 = 0 , didapat = 0.001658
Dengan memperhitungkan min dan max, diambil nilai = 0.0028
Luas tulangan yang dibutuhkan, As = x b x d = 1.74 cm2
Digunakan baja tulangan M6 - 150 + U10 - 750 ;
As = 3.1 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 1426.828 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 5/2/2013
| LOGO | Project : Hotel Panghegar
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 200 mm

mm
mm
mm
91.62 kg/m

b a
B
kgm > Mmax = 83.14515 kgm ( OK)

25 mm

234.00 kg/m

b a

kgm > Mmax = 142.155 kgm (.. OK)

50 mm

183.24 kg/m
b a

kgm > Mmax = 222.966432 kgm ( OK)


50 mm

50 mm

105 mm
M6 - 150 mm
U10 - 1500 mm

M6 - 150 mm + U10 - 750 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.3 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 250 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 250) + 1.6 (250)
= 1074.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1063.656 kgm

Mu 1063.66
Mn = = 1329.57 kgm
0.8
Koefisien Ketahanan Rn;
Mn 132957
Rn = = 12.06 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.206 = 0 , didapat = 0.002485

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.94 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.94
= = 10.4 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + U10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (1329.57 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3300
fr saat stripping : 2.71 Mpa B= 1100
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.3 m
q1x = 211.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 105.60 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -13.20 kgm
Output model SAP a b
MAB = MBA = -13.20 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 19.8 kgm
Ig = 0.5*1/12*B*t = 23466666.67 mm4
3

Mcrack = fr*Ig/y = 1589866.667 Nmm = 1.59 kNm = 159 kgm > Mmax = 19.8 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 19.8
= = 24.75 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.5 m
q1x = 633.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 316.80 kg/m
y = 0.5t = 40 mm q=

MA = MB = -14.26 kgm Output model SAP


MAB= -14.26 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 21.384 kgm
Ig = 0.5*1/12*L*t = 3
70400000 mm4
Mcrack = fr*Ig/y = 4769600 Nmm = 4.77 kNm = 477 kgm > Mmax = 21.384 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 21.384
= = 26.73 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.66 m
b = (L-2a) = 1.98 m
q1x =t*B*2400 = 211.2 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -46.00 kgm Output model SAP


MAB = -46.00 kgm 45.99936
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 46933333.33 mm4
Mcrack = fr.Ig/y = 3179733.333 Nmm = 3.18 kNm = 318 kgm > Mmax = 45.99936 kgm (
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 45.99936
= = 57.4992 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.65 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 263.538 kgm
Mmax 263.538
Mn = = = 329.42 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 1074.4 x 3.3^2 = 1300.024 kgm
9 9
Mu 1300.024
Mn = = 1625.03 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 162503.00
= 14.74 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.474 = 0 , didapat = 0.003059
Dengan memperhitungkan min dan max, diambil nilai = 0.003059
Luas tulangan yang dibutuhkan, As = x b x d = 3.21 cm2
Digunakan baja tulangan M6 - 150 + U10 - 600 ;
As = 3.308 cm2
(*)
> As perlu ( OK)
(*)
Dikonversi sesuai mutu tulangan utama
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser 2038.674 kg


Vu = 1.15wu.ln =
2 8732.482 kg
Vc = 1/6fc'bwd =
Vc = 6549.362 kg OK
Jadi Vu < Vc, Maka tidak perlu tulangan geser.
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Tambahan (searah pelat 1 arah)


Tul Utama

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
105.60 kg/m

b a
B
kgm > Mmax = 19.8 kgm ( OK)

25 mm

316.80 kg/m

b a

kgm > Mmax = 21.384 kgm (.. OK)

55 mm

211.20 kg/m
b a

kgm > Mmax = 45.99936 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 600 mm

M6 - 150 mm + U10 - 600 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 2.405 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 250 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 250) + 1.6 (250)
= 1074.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 564.941 kgm

Mu 564.94
Mn = = 706.18 kgm
0.8
Koefisien Ketahanan Rn;
Mn 70618
Rn = = 6.41 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.641 = 0 , didapat = 0.001301

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.94 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 2.94
= = 10.4 atau 11.0
Ab 0.2827
Required U6 - 100 mm
use : M6 - 150 + U10 - 600 ; 3.028 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.028
aktual = = 0.00288
100 x 10.5
As x fy = 0.72 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1535.196 kgm
Jadi, Mn aktual > Mn perlu (706.18 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 2405
fr saat stripping : 2.71 Mpa B= 825
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 1.405 m
q1x = 158.4 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 79.20 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -9.90 kgm
Output model SAP a b
MAB = MBA = -9.90 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 14.85 kgm
Ig = 0.5*1/12*B*t = 3
17600000 mm4
Mcrack = fr*Ig/y = 1192400 Nmm = 1.192 kNm = 119.2 kgm > Mmax = 14.85 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 14.85
= = 18.5625 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2/m
a = As*fy/ 0.85*fc'*b = 1.19 cm
Mn = As*fy*(d-a/2) = 288.417 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.225 m
q1x = 461.76 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 230.88 kg/m
y = 0.5t = 40 mm q=

MA = MB = -10.39 kgm Output model SAP


MAB= -10.39 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 15.5844 kgm
Ig = 0.5*1/12*L*t = 3
51306666.67 mm4
Mcrack = fr*Ig/y = 3476026.667 Nmm = 3.476 kNm = 347.6 kgm > Mmax = 15.5844 kgm (..

Check terhadap momen yang terjadi :


Mn = Mmax 15.5844
= = 19.4805 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.481 m
b = (L-2a) = 1.443 m
q1x =t*B*2400 = 158.4 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -18.32 kgm Output model SAP


MAB = -18.32 kgm 18.323791
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 35200000 mm4
Mcrack = fr.Ig/y = 2384800 Nmm = 2.385 kNm = 238.5 kgm > Mmax = 18.3237912 kgm
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 18.32379
= = 22.904739 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.028 cm2
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.2025 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 139.973405 kgm
Mmax 139.9734
Mn = = = 174.97 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.19 cm
Mn = As fy (d-a/2) = 742.617 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =1074.4 x 2.405^2 = 690.48405 kgm
9 9
Mu 690.484
Mn = = 863.11 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 86310.51
= 7.83 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.783 = 0 , didapat = 0.001596
Dengan memperhitungkan min dan max, diambil nilai = 0.0028
Luas tulangan yang dibutuhkan, As = x b x d = 2.94 cm2
Digunakan baja tulangan M6 - 150 + U10 - 600 ;
As = 3.308 cm2
(*)
> As perlu ( OK)
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 1485.761 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 100 mm

mm
mm
mm
79.20 kg/m

b a
B
kgm > Mmax = 14.85 kgm ( OK)

25 mm

230.88 kg/m

b a

kgm > Mmax = 15.5844 kgm (.. OK)

55 mm

158.40 kg/m
b a

kgm > Mmax = 18.3237912 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 600 mm

M6 - 150 mm + U10 - 600 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 4.025 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 250 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 250) + 1.6 (250)
= 1074.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1582.359 kgm

Mu 1582.36
Mn = = 1977.95 kgm
0.8
Koefisien Ketahanan Rn;
Mn 197795
Rn = = 17.94 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.794 = 0 , didapat = 0.003755

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.94 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.94
= = 13.94 atau 14.0
Ab 0.2827
Required U6 - 76.92 mm
use : M6 - 150 + U10 - 300 ; 4.076 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

4.076
aktual = = 0.00388
100 x 10.5
As x fy = 0.96 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 2042.076 kgm
Jadi, Mn aktual > Mn perlu (1977.95 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 4025
fr saat stripping : 2.71 Mpa B= 725
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 3.025 m
q1x = 139.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 69.60 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -8.70 kgm
Output model SAP a b
MAB = MBA = -8.70 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 13.05 kgm
Ig = 0.5*1/12*B*t = 15466666.67 mm4
3

Mcrack = fr*Ig/y = 1047866.667 Nmm = 1.048 kNm = 104.8 kgm > Mmax = 13.05 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 13.05
= = 16.3125 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 4.076 cm2/m
a = As*fy/ 0.85*fc'*b = 1.6 cm
Mn = As*fy*(d-a/2) = 346.46 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.125 m
q1x = 772.8 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 386.40 kg/m
y = 0.5t = 40 mm q=

MA = MB = -17.39 kgm Output model SAP


MAB= -17.39 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 26.082 kgm
Ig = 0.5*1/12*L*t = 3
85866666.67 mm4
Mcrack = fr*Ig/y = 5817466.667 Nmm = 5.817 kNm = 581.7 kgm > Mmax = 26.082 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 26.082
= = 32.6025 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.805 m
b = (L-2a) = 2.415 m
q1x =t*B*2400 = 139.2 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -45.10 kgm Output model SAP


MAB = -45.10 kgm 45.10254
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 30933333.33 mm4
Mcrack = fr.Ig/y = 2095733.333 Nmm = 2.096 kNm = 209.6 kgm > Mmax = 45.10254 kgm (
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 45.10254
= = 56.378175 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 4.076 cm2
a= 1.6 cm
Mn = As fy (d-a/2) = 957.86 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 2.0125 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 392.055125 kgm
Mmax 392.0551
Mn = = = 490.07 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.6 cm
Mn = As fy (d-a/2) = 957.86 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 =1074.4 x 4.025^2 = 1933.9946 kgm
9 9
Mu 1933.995
Mn = = 2417.49 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 241749.33
= 21.93 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 2.193 = 0 , didapat = 0.004641
Dengan memperhitungkan min dan max, diambil nilai = 0.004641
Luas tulangan yang dibutuhkan, As = x b x d = 4.87 cm2
Digunakan baja tulangan M6 - 150 + U10 - 150 ;
As = 6.452 cm2
(*)
> As perlu ( OK)
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2486.565 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 76.92 mm

mm
mm
mm
69.60 kg/m

b a
B
kgm > Mmax = 13.05 kgm ( OK)

25 mm

386.40 kg/m

b a

kgm > Mmax = 26.082 kgm (.. OK)

55 mm

139.20 kg/m
b a

kgm > Mmax = 45.10254 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 300 mm

M6 - 150 mm + U10 - 150 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.6 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 250 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 250) + 1.6 (250)
= 1074.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1265.839 kgm

Mu 1265.84
Mn = = 1582.30 kgm
0.8
Koefisien Ketahanan Rn;
Mn 158230
Rn = = 14.35 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.435 = 0 , didapat = 0.002975

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.12 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.12
= = 11.04 atau 12.0
Ab 0.2827
Required U6 - 90.91 mm
use : M6 - 150 + U10 - 450 ; 3.38 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.38
aktual = = 0.00322
100 x 10.5
As x fy = 0.8 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1706.9 kgm
Jadi, Mn aktual > Mn perlu (1582.3 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3600
fr saat stripping : 2.71 Mpa B= 825
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.6 m
q1x = 158.4 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 79.20 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -9.90 kgm
Output model SAP a b
MAB = MBA = -9.90 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 14.85 kgm
Ig = 0.5*1/12*B*t = 3
17600000 mm4
Mcrack = fr*Ig/y = 1192400 Nmm = 1.192 kNm = 119.2 kgm > Mmax = 14.85 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 14.85
= = 18.5625 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2/m
a = As*fy/ 0.85*fc'*b = 1.33 cm
Mn = As*fy*(d-a/2) = 310.115 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.225 m
q1x = 691.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 345.60 kg/m
y = 0.5t = 40 mm q=

MA = MB = -15.55 kgm Output model SAP


MAB= -15.55 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 23.328 kgm
Ig = 0.5*1/12*L*t = 3
76800000 mm4
Mcrack = fr*Ig/y = 5203200 Nmm = 5.203 kNm = 520.3 kgm > Mmax = 23.328 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 23.328
= = 29.16 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.72 m
b = (L-2a) = 2.16 m
q1x =t*B*2400 = 158.4 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -41.06 kgm Output model SAP


MAB = -41.06 kgm 41.05728
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 35200000 mm4
Mcrack = fr.Ig/y = 2384800 Nmm = 2.385 kNm = 238.5 kgm > Mmax = 41.05728 kgm (
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 41.05728
= = 51.3216 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.8 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 313.632 kgm
Mmax 313.632
Mn = = = 392.04 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 1074.4 x 3.6^2 = 1547.136 kgm
9 9
Mu 1547.136
Mn = = 1933.92 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 193392.00
= 17.54 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.754 = 0 , didapat = 0.003668
Dengan memperhitungkan min dan max, diambil nilai = 0.003668
Luas tulangan yang dibutuhkan, As = x b x d = 3.85 cm2
Digunakan baja tulangan M6 - 150 + U10 - 300 ;
As = 4.356 cm2
(*)
> As perlu ( OK)
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2224.008 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 90.91 mm

mm
mm
mm
79.20 kg/m

b a
B
kgm > Mmax = 14.85 kgm ( OK)

25 mm

345.60 kg/m

b a

kgm > Mmax = 23.328 kgm (.. OK)

55 mm

158.40 kg/m
b a

kgm > Mmax = 41.05728 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 450 mm

M6 - 150 mm + U10 - 300 mm


Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE 1

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.7 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 250 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 250) + 1.6 (250)
= 1074.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1337.140 kgm

Mu 1337.14
Mn = = 1671.42 kgm
0.8
Koefisien Ketahanan Rn;
Mn 167142
Rn = = 15.16 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.516 = 0 , didapat = 0.003150

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 3.31 cm2
Digunakan wiremesh M6, Ab = 0.2827 cm2
n= As perlu 3.31
= = 11.71 atau 12.0
Ab 0.2827
Required U6 - 90.91 mm
use : M6 - 150 + U10 - 450 ; 3.38 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.38
aktual = = 0.00322
100 x 10.5
As x fy = 0.8 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1706.9 kgm
Jadi, Mn aktual > Mn perlu (1671.42 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3700
fr saat stripping : 2.71 Mpa B= 1000
t= 80
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.7 m
q1x = 192 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 96.00 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -12.00 kgm
Output model SAP a b
MAB = MBA = -12.00 kgm A
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 18 kgm
Ig = 0.5*1/12*B*t = 21333333.33 mm4
3

Mcrack = fr*Ig/y = 1445333.333 Nmm = 1.445 kNm = 144.5 kgm > Mmax = 18 kgm ( O

Check terhadap momen yang terjadi :


Mn = Mmax 18
= = 22.5 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2/m
a = As*fy/ 0.85*fc'*b = 1.33 cm
Mn = As*fy*(d-a/2) = 310.115 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.4 m
q1x = 710.4 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 355.20 kg/m
y = 0.5t = 40 mm q=

MA = MB = -15.98 kgm Output model SAP


MAB= -15.98 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 23.976 kgm
Ig = 0.5*1/12*L*t = 3
78933333.33 mm4
Mcrack = fr*Ig/y = 5347733.333 Nmm = 5.348 kNm = 534.8 kgm > Mmax = 23.976 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 23.976
= = 29.97 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.74 m
b = (L-2a) = 2.22 m
q1x =t*B*2400 = 192 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -52.57 kgm Output model SAP


MAB = -52.57 kgm 52.5696
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 42666666.67 mm4
Mcrack = fr.Ig/y = 2890666.667 Nmm = 2.891 kNm = 289.1 kgm > Mmax = 52.5696 kgm (
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 52.5696
= = 65.712 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.85 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 331.298 kgm
Mmax 331.298
Mn = = = 414.12 kgm
0.8
asumsi precast Half Slab dipasang pada nilai fc' = 14.94 Mpa
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 1074.4 x 3.7^2 = 1634.2818 kgm
9 9
Mu 1634.282
Mn = = 2042.85 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 204285.22
= 18.53 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.853 = 0 , didapat = 0.003885
Dengan memperhitungkan min dan max, diambil nilai = 0.003885
Luas tulangan yang dibutuhkan, As = x b x d = 4.08 cm2
Digunakan baja tulangan M6 - 150 + U10 - 300 ;
As = 4.356 cm2
(*)
> As perlu ( OK)
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2285.786 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Hotel Patra Jasa
HERE Engineer : MR
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 90.91 mm

mm
mm
mm
96.00 kg/m

b a
B
kgm > Mmax = 18 kgm ( OK)

25 mm

355.20 kg/m

b a

kgm > Mmax = 23.976 kgm (.. OK)

55 mm

192.00 kg/m
b a

kgm > Mmax = 52.5696 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
U10 - 450 mm

M6 - 150 mm + U10 - 300 mm


Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE S1**

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan fy = 500 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 2.05 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m 2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 364.624 kgm

Mu 364.62
Mn = = 455.78 kgm
0.8
Koefisien Ketahanan Rn;
Mn 45578
Rn = = 4.13 kg/cm2
bd2 100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.413 = 0 , didapat = 0.000835

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.01962573
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 0.88 cm2
Digunakan baja tulangan U6, Ab = 0.2827 cm2
n= As perlu 0.88
= = 3.11 atau 4.0
Ab 0.2827
Required U6 - 333.33 mm
use : M6 - 150 mm ; 1.98 cm2
1.98
aktual = = 0.00189
100 x 10.5
As x fy = 0.47 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1016.235 kgm
Jadi, Mn aktual > Mn perlu (455.78 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 2050
fr saat stripping : 2.71 Mpa B= 1013
t= 80
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 1.05 m
q1x = 194.496 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 97.25 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -12.16 kgm
Output model SAP a b
MAB = MBA = -12.16 kgm A
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 18.234 kgm
Ig = 0.5*1/12*B*t = 21610666.67 mm4
3

Mcrack = fr*Ig/y = 1464122.667 Nmm = 1.464 kNm = 146.4 kgm > Mmax = 18.234 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 18.234
= = 22.7925 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 1.98 cm2/m
a = As*fy/ 0.85*fc'*b = 0.78 cm
Mn = As*fy*(d-a/2) = 208.89 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.413 m
q1x = 393.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 196.80 kg/m
y = 0.5t = 40 mm q=

MA = MB = -8.86 kgm Output model SAP


MAB= -8.86 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 13.284 kgm
Ig = 0.5*1/12*L*t = 3
43733333.33 mm4
Mcrack = fr*Ig/y = 2962933.333 Nmm = 2.963 kNm = 296.3 kgm > Mmax = 13.284 kgm (.. OK

Check terhadap momen yang terjadi :


Mn = Mmax 13.284
= = 16.605 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.41 m
b = (L-2a) = 1.23 m
q1x =t*B*2400 = 194.496 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -16.35 kgm Output model SAP


MAB = -16.35 kgm 16.347389
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 43221333.33 mm4
Mcrack = fr.Ig/y = 2928245.333 Nmm = 2.928 kNm = 292.8 kgm > Mmax = 16.3473888 kgm
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 16.34739
= = 20.434236 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 1.98 cm2
a= 0.78 cm
Mn = As fy (d-a/2) = 505.89 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.025 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 101.7005 kgm
Mmax 101.7005
Mn = = = 127.13 kgm
0.8
asumsi precast Half Slab dipasang pada umur 1 hari sehingga fc' = 14.94 Mpa
a= 0.78 cm
Mn = As fy (d-a/2) = 505.89 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 2.05^2 = 445.65178 kgm
9 9
Mu 445.652
Mn = = 557.06 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 55706.47
= 5.05 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 0.505 = 0 , didapat = 0.001023

Luas tulangan yang dibutuhkan, As = x b x d = 1.07 cm2


Digunakan baja tulangan U10 - 400
As = 3.14 cm2 > As perlu ( OK)
- Gaya geser
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Vu = 1.15wu.ln = 1124.999 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 333.33 mm

mm
mm
mm
97.25 kg/m

b a
B
gm > Mmax = 18.234 kgm ( OK)

25 mm

196.80 kg/m

b a

gm > Mmax = 13.284 kgm (.. OK)

55 mm

194.50 kg/m
b a

gm > Mmax = 16.3473888 kgm ( OK)


55 mm

55 mm

105 mm
M6 - 150 mm
-

U10 - 400 mm
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE S1**

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan utama fy = 500 Mpa
- Mutu tulangan tambahan fy = 400 Mpa
- Tebal Half Slab t slb = 80 mm
- Tebal topping t top = 50 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.55 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 0 kg/m2
- Beban finishing = 110 kg/m2
- Beban M&E = 40 kg/m2 +
Total = 150 kg/m2

- Beban Hidup (LL) = 250 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 150) + 1.6 (250)
= 954.4 kg/m2

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 1093.439 kgm

Mu 1093.44
Mn = = 1366.80 kgm
0.8
Koefisien Ketahanan Rn;
Mn 136680
Rn = = 12.40 kg/cm2
bd2
100 x 10.5^2
fy 500
Rn = fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.24 = 0 , didapat = 0.002557

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.0196257
fy 600 + fy 500

max = 0.5b = 0.009812864


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.68 cm2
Digunakan baja tulangan M6, Ab = 0.2827 cm2
n= As perlu 2.68
= = 9.48 atau 10.0
Ab 0.2827
Required U6 - 111.11 mm
use : M6 - 150 + U10 - 450 ; 3.38 (*)cm2
Dikonversi sesuai mutu tulangan utama
(*)

3.38
aktual = = 0.00322
100 x 10.5
As x fy = 0.8 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1706.9 kgm
Jadi, Mn aktual > Mn perlu (1366.8 kgm) OK

- Tulangan arah pendek


M6 - 150 mm As = 2.262 cm2
aktual = 0.00236
aktual > izin (0.0018) OK
dipakai D6 - 150 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 14.94 Mpa Ukuran precast Half Slab, L= 3550
fr saat stripping : 2.71 Mpa B= 1013
t= 80
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 2.55 m
q1x = 194.496 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 97.25 kg/m
y = 0.5*t = 40 mm q=

MA = MB = -12.16 kgm
Output model SAP a b
MAB = MBA = -12.16 kgm A
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 18.234 kgm
Ig = 0.5*1/12*B*t = 21610666.67 mm4
3

Mcrack = fr*Ig/y = 1464122.667 Nmm = 1.464 kNm = 146.4 kgm > Mmax = 18.234 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 18.234
= = 22.7925 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2/m
a = As*fy/ 0.85*fc'*b = 1.33 cm
Mn = As*fy*(d-a/2) = 310.115 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.3 m
b= 0.413 m
q1x = 681.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 340.80 kg/m
y = 0.5t = 40 mm q=

MA = MB = -15.34 kgm Output model SAP


MAB= -15.34 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 23.004 kgm
Ig = 0.5*1/12*L*t = 3
75733333.33 mm4
Mcrack = fr*Ig/y = 5130933.333 Nmm = 5.131 kNm = 513.1 kgm > Mmax = 23.004 kgm (.. O

Check terhadap momen yang terjadi :


Mn = Mmax 23.004
= = 28.755 kgm
0.8
digunakan besi tulangan P6 - 150 mm, As = 2.262 cm2
a= 0.43 cm
Mn = As fy (d-a/2) = 286.91208 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.71 m
b = (L-2a) = 2.13 m
q1x =t*B*2400 = 194.496 kg/m
y = 0.5*t = 40 mm
q=
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -49.02 kgm Output model SAP


MAB = -49.02 kgm 49.022717
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 43221333.33 mm4
Mcrack = fr.Ig/y = 2928245.333 Nmm = 2.928 kNm = 292.8 kgm > Mmax = 49.0227168 kgm
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 49.02272
= = 61.278396 kgm
0.8
digunakan besi tulangan M6 - 150 mm, As = 3.38 cm2
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.775 m
beban orang bekerja = 250 kg/m2
beban beton topping 5 cm = 120 kg/m2
berat sendiri Half Slab = 192 kg/m2
Qu = 774.4 kg/m
Mu = 1/8*Qu*a2 = 304.9805 kgm
Mmax 304.9805
Mn = = = 381.23 kgm
0.8
asumsi precast Half Slab dipasang pada umur 1 hari sehingga fc' = 14.94 Mpa
a= 1.33 cm
Mn = As fy (d-a/2) = 817.115 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 954.4 x 3.55^2 = 1336.4251 kgm
9 9
Mu 1336.425
Mn = = 1670.53 kgm
0.8
Koefisien Ketahanan Rn;
Rn =
Mn 167053.14
= 15.15 kg/cm2
d=

bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.515 = 0 , didapat = 0.003148

Luas tulangan yang dibutuhkan, As = x b x d = 3.31 cm2


Digunakan baja tulangan U10 - 400
As = 3.14 cm2 < As perlu ( Not OK)
- Gaya geser
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Vu = 1.15wu.ln = 1948.169 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Tul Utama Tul Tambahan (searah pelat 1 arah)

Half Slab
Utama
Tambahan

Topping
U6 - 111.11 mm

mm
mm
mm
97.25 kg/m

b a
B
kgm > Mmax = 18.234 kgm ( OK)

25 mm

340.80 kg/m

b a

kgm > Mmax = 23.004 kgm (.. OK)

55 mm

194.50 kg/m
b a

kgm > Mmax = 49.0227168 kgm ( OK)


55 mm

55 mm

105 mm

u ( Not OK)
M6 - 150 mm
U10 - 450 mm

U10 - 400 mm
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE S2

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan fy = 500 Mpa
- Tebal Half Slab t slb = 75 mm
- Tebal topping t top = 55 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 5.14 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 120 kg/m2
- Beban M&E = 20 kg/m2 +
Total = 240 kg/m 2

- Beban Hidup (LL) = 200 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 270) + 1.6 (200)
= 982.4 kg/m

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 2359.510 kgm

Mu 2359.51
Mn = = 2949.39 kgm
0.8

Koefisien Ketahanan Rn;
Mn 294939
Rn = = 26.75 kg/cm2
100 x 10.5^2
bd2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 2.675 = 0 , didapat = 0.005741

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.019626
fy 600 + fy 500

max = 0.5b = 0.0098128636


1,4
min = 0.0028 , jadi min < < max
fy
Luas tulangan yang dibutuhkan, As = x b x d = 6.03 cm2
Digunakan baja tulangan U10, Ab = 0.7854 cm2
n= As perlu 6.03
= = 7.68 atau 8.0
Ab 0.7854
Required U10 - 142.86 mm
use : U10 - 140 mm ; 6.28 cm2
6.28
aktual = = 0.00598
100 x 10.5
As x fy = 1.48 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 3064.64 kgm
Jadi, Mn aktual > Mn perlu (2949.39 kgm) OK

- Tulangan susut dipasang pada arah tegak lurus tulangan utama


Dicoba P8 - 200 mm As = 3.016 cm2
aktual = 0.00331
aktual > izin (0.0018) OK
dipakai P8 - 200 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 6 Mpa Ukuran precast Half Slab, L= 5140
fr saat stripping : 1.71 Mpa B= 2675
t= 75
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.5 m
b= 1.2 m
c= 1.67
q1x = 481.5 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 240.75 kg/m q=
y = 0.5*t = 37.5 mm

MA = MD = -30.09 kgm a b
MB=MC -46.04 kgm Output model SAP A B
MAB = MCD = 3.11 kgm
MBC= 37.89 kgm

Check terhadap retak:


M max stripping = *Mmax = 69.06 kgm
Ig = 0.5*1/12*B*t = 3
47021484.375 mm4
Mcrack = fr*Ig/y = 2144179.6875 Nmm = 2.144 kNm = 214.4 kgm > Mmax = 69.06 kgm

Check terhadap momen yang terjadi :


Mn = Mmax 69.06
= = 86.325 kgm
0.8
digunakan besi tulangan M10 - 140 mm, As = 6.28 cm2/m
a = As*fy/ 0.85*fc'*b = 6.16 cm
Mn = As*fy*(d-a/2) = -182.12 kgm < Mn perlu ( Not OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.5 m
b= 1.675 m
q1x = 925.2 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 462.60 kg/m
y = 0.5t = 37.5 mm q=
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -57.04 kgm Output model SAP


MAB= 102.99 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 154.485 kgm
Ig = 0.5*1/12*L*t3 = 90351562.5 mm4
Mcrack = fr*Ig/y = 4120031.25 Nmm = 4.12 kNm = 412 kgm > Mmax = 154.485 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 154.485
= = 193.10625 kgm
0.8
digunakan besi tulangan P8 - 200 mm, As = 3.016 cm2
a= 1.42 cm
Mn = As fy (d-a/2) = 310.52736 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a= 0.5 m
b= 1.2 m
c= 1.67 m
q1x =t*B*2400 = 481.5 kg/m
y = 0.5*t = 37.5 mm
q=
MA = MD = -60.19 kgm Output model SAP
MB=MC -92.08 kgm 92.08
MAB = MCD = 6.22 kgm
MBC= 75.77 kgm a b c
A B
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


Ig = 1/12*B*t3 = 94042968.75 mm4
Mcrack = fr.Ig/y = 4288359.375 Nmm = 4.288 kNm = 428.8 kgm > Mmax = 92.08 kgm ( O

Check terhadap momen yang terjadi :


Mn = Mmax 92.08
= = 115.1 kgm
0.8
digunakan besi tulangan M10 - 140 mm, As = 6.28 cm2
a= 6.16 cm
Mn = As fy (d-a/2) = 602.88 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1.635 m
b= 1.8 m
beban orang bekerja = 200 kg/m2
beban beton topping 5.5 cm = 132 kg/m2
berat sendiri Half Slab = 180 kg/m2
Qu = 694.4 kg/m
MA=MD= 0 kgm
MB=MC= -196.93 kgm
MAB=MCD= 133.57 kgm
MBC= 84.3 kgm

Mu = 196.93 kgm
Mmax 196.93
Mn = = = 246.16 kgm
0.8
asumsi precast Half Slab dipasang pada umur 1 hari sehingga fc' = 6 Mpa
a= 6.16 cm
Mn = As fy (d-a/2) = 602.88 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 982.4 x 5.14^2 = 2883.8461 kgm
9 9
Mu 2883.846
Mn = = 3604.81 kgm
0.8
Rn;
Koefisien Ketahanan
Mn 360480.76 d=
Rn = = 32.70 kg/cm2
2
100 x 10.5^2
bd
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 2 24.9
Rn = 500 - 5923.695

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 3.27 = 0 , didapat = 0.007144

Luas tulangan yang dibutuhkan, As = x b x d = 7.5 cm2


Digunakan baja tulangan U10 - 100
As = 8.64 cm2 > As perlu ( OK)
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

- Gaya geser
Vu = 1.15wu.ln = 2903.483 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK

Grid 1 Grid 2

Half Slab
Grid 1
Grid 2

Topping
U10 - 142.86 mm

mm
mm
mm
240.75 kg/m

b a
C D

kgm > Mmax = 69.06 kgm ( OK)

25 mm

462.60 kg/m
b a

kgm > Mmax = 154.485 kgm (.. OK)

50 mm

481.50 kg/m

b a
C D
kgm > Mmax = 92.08 kgm ( OK)

50 mm

50 mm

105 mm
U10 - 140 mm
P8 - 200 mm

U10 - 100 mm
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Title : PERHITUNGAN HALF SLAB


ID : TYPE S3

I. Data Half Slab


- Mutu beton half slab K-300 fc = 24.9 Mpa
- Mutu beton topping K-300 fc = 24.9 Mpa
- Mutu tulangan fy = 500 Mpa
- Tebal Half Slab t slb = 75 mm
- Tebal topping t top = 55 mm
- Tebal total Plat t tot = 130 mm
- Panjang Bentang bersih Ln = 3.32 m
- Selimut beton c = 25 mm
d = t tot-c = 105 mm
II. Data Pembebanan
- Beban Mati (DL)
a. Berat sendiri = 0.13 x 2400 = 312 kg/m2
b. Beban mati tambahan
- Beban partisi = 100 kg/m2
- Beban finishing = 120 kg/m2
- Beban M&E = 20 kg/m2 +
Total = 240 kg/m 2

- Beban Hidup (LL) = 200 kg/m2

III. Analisa Perhitungan


Pelat dianggap penuh pada saat menahan beban (t) =130 mm
U = 1.2DL + 1.6LL
= 1.2 (312 + 270) + 1.6 (200)
= 982.4 kg/m

A. Untuk Tulangan Bawah (Half Slab)


- Mu=1/11 q l2 = 984.401 kgm

Mu 984.40
Mn = = 1230.50 kgm
0.8
Koefisien Ketahanan Rn;
Mn 123050
Rn = = 11.16 kg/cm2
bd 2 100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9

Rn = 500 - 5923.695 2
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.116 = 0 , didapat = 0.002295

Pembatasan nilai ;
0,85 fc ' b1 600 0,85 x 24,9 x 0,85
b x 0,545 = 0.019626
fy 600 + fy 500

max = 0.5b = 0.0098128636


1,4
min = 0.0028 , jadi < min
fy
Luas tulangan yang dibutuhkan, As = x b x d = 2.41 cm2
Digunakan baja tulangan U8, Ab = 0.5027 cm2
n= As perlu 2.41
= = 4.79 atau 5.0
Ab 0.5027
Required U8 - 250 mm
use : U8 - 200 mm ; 2.51 cm2
2.51
aktual = = 0.00239
100 x 10.5
As x fy = 0.59 cm
lengan momen dalam = a =
0.85 x fc' x b
Momen nominal
Mn = As fy (d-a/2) = 1280.7275 kgm
Jadi, Mn aktual > Mn perlu (1230.5 kgm) OK

- Tulangan susut dipasang pada arah tegak lurus tulangan utama


Dicoba P8 - 250 mm As = 2.513 cm2
aktual = 0.00270
aktual > izin (0.0018) OK
dipakai P8 - 250 mm

- Tinjauan kondisi demoulding (stripping) dan penumpukan


fc' saat stripping : 6 Mpa Ukuran precast Half Slab, L= 3320
fr saat stripping : 1.71 Mpa B= 2092
t= 75
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Kondisi Stripping
- Tinjauan arah X (arah panjang)
a= 0.664 m
b= 1.992 m
q1x = 376.56 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 188.28 kg/m
y = 0.5*t = 37.5 mm q=

MA = MC = -41.51 kgm
MB= 70.00 kgm Output model SAP a
A
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap retak:


M max stripping = *Mmax = 105 kgm
Ig = 0.5*1/12*B*t = 3
36773437.5 mm4
Mcrack = fr*Ig/y = 1676868.75 Nmm = 1.677 kNm = 167.7 kgm > Mmax = 105 kgm (

Check terhadap momen yang terjadi :


Mn = Mmax 105
= = 131.25 kgm
0.8
digunakan besi tulangan M8 - 200 mm, As = 2.51 cm2/m
a = As*fy/ 0.85*fc'*b = 2.46 cm
Mn = As*fy*(d-a/2) = 159.385 kgm > Mn perlu ( OK) d=

- Tinjauan arah Y (arah lebar)


a= 0.4 m
b= 1.292 m
q1x = 597.6 kg/m
= 1.5

Beban merata b.s. yg terjadi pada satu line titik angkat :


q'x = 0.5*q1x = 298.80 kg/m
y = 0.5t = 37.5 mm q=

MA = MB = -23.90 kgm Output model SAP


MAB= 38.21 kgm a b

Check terhadap retak:


Mmax stripping = *Mmax = 57.315 kgm
Ig = 0.5*1/12*L*t = 3
58359375 mm4
Mcrack = fr*Ig/y = 2661187.5 Nmm = 2.661 kNm = 266.1 kgm > Mmax = 57.315 kgm (..

Check terhadap momen yang terjadi :


Mn = Mmax 57.315
= = 71.64375 kgm
0.8
digunakan besi tulangan P8 - 250 mm, As = 2.513 cm2
a= 1.18 cm
Mn = As fy (d-a/2) = 265.97592 kgm > Mn perlu (OK) d=

Kondisi Penumpukan
a = 1/5*L = 0.664 m
b = (L-2a) = 1.992 m
q1x =t*B*2400 = 376.56 kg/m
y = 0.5*t = 37.5 mm
q=
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

MA = MB = -83.01 kgm Output model SAP


MAB = 142.19 kgm 142.19
a b

Check terhadap retak:


Ig = 1/12*B*t3 = 73546875 mm4
Mcrack = fr.Ig/y = 3353737.5 Nmm = 3.354 kNm = 335.4 kgm > Mmax = 142.19 kgm (
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Check terhadap momen yang terjadi :


Mn = Mmax 142.19
= = 177.7375 kgm
0.8
digunakan besi tulangan M8 - 200 mm, As = 2.51 cm2
a= 2.46 cm
Mn = As fy (d-a/2) = 473.135 kgm > Mn perlu ( OK) d=

Kondisi Pemasangan

digunakan proofing pipa support di tengah bentang half slab


a= 1/2*L = 1.66 m
beban orang bekerja = 200 kg/m2
beban beton topping 5.5 cm = 132 kg/m2
berat sendiri Half Slab = 180 kg/m2
Qu = 694.4 kg/m
Mu = 1/8*Qu*a2 = 239.18608 kgm
Mmax 239.1861
Mn = = = 298.98 kgm
0.8
asumsi precast Half Slab dipasang pada umur 1 hari sehingga fc' = 6 Mpa
a= 2.46 cm
Mn = As fy (d-a/2) = 473.135 kgm > Mn perlu ( OK) d=

B. Untuk Tulangan Atas


- Momen negatif pada daerah tumpuan
Mu= wu ln^2 = 982.4 x 3.32^2 = 1203.1562 kgm
9 9
Mu 1203.156
Mn = = 1503.95 kgm
0.8
Koefisien Ketahanan Rn;
Mn 150394.52 d=
Rn = = 13.64 kg/cm2
bd2
100 x 10.5^2
Rn = fy 500
fy 1 0.59 500 1 0.59
fc ' 24.9
Rn = 500 - 5923.695 2

dengan menyamakan kedua nilai Rn , serta memperhatikan satuannya, diperoleh :


5923.695 2 - 500 + 1.364 = 0 , didapat = 0.002823

Luas tulangan yang dibutuhkan, As = x b x d = 2.96 cm2


Digunakan baja tulangan U10 - 150
As = 5.5 cm2 > As perlu ( OK)
- Gaya geser
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Vu = 1.15wu.ln = 1875.402 kg
2
Vc = 1/6fc'bwd = 8732.482 kg
Vc = 6549.362 kg
Jadi Vu < Vc, Maka tidak perlu tulangan geser. OK
Date : 19/8-10
| LOGO | Project : Rusunami Sanggar Hurip, Bandung
HERE Engineer : YS
YL Engineers Indonesia Doc. Type : Calculation Sheet

Grid 1 Grid 2

Half Slab
Grid 1
Grid 2

Topping
U8 - 250 mm

mm
mm
mm
188.28 kg/m

b a
B
kgm > Mmax = 105 kgm ( OK)

25 mm

298.80 kg/m

b a

kgm > Mmax = 57.315 kgm (.. OK)

50 mm

376.56 kg/m
b a

kgm > Mmax = 142.19 kgm ( OK)


50 mm

50 mm

105 mm
U8 - 200 mm
P8 - 250 mm

U10 - 150 mm
50417.01 13444.54
312
954.4
1908.8
255
875
D10 - 200
392.6991 mm2
9424.778

1.728583
4868843
4.868843