CONSTRUCTION & COMPLETION OF 500 HOUSES IN OUD MUTEENA

MANPOWER FORECAST FOR THE BALANCE WORK -CONCRETE, BLOCK WORKS & PLASTER WORKS

Villa
Productivity
Sl.No Description rate / Day Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17
Concrete works
Carpentar 650 639 623 564 369
Scaffolder 76 76 76 76 69
Mason 65 58 58 40 27
1 Steel Fixer 553 553 553 324 314
3.3
Coolie 413 400 388 252 162
Total Manpower 1757 1726 1698 1256 941
Gang Leaders 88 86 85 63 47
Charge hands 44 43 42 31 24
Block Works (Including lintels, Sun shades, Window sills etc.)
Mason 317 317 317 317 317 192
Steel Fixer 23 23 23 23 23 14
2 Carpentar 63 63 63 63 63 38
Coolie 3.3 188 188 188 188 188 114
Total Manpower 591 591 591 591 591 358
Gang Leaders 30 30 30 30 30 18
Charge hands 15 15 15 15 15 9
Plaster Works (Internal & External)
Mason 889 889 889 889 889 762 508
3 Coolie 599 599 599 599 599 513 342
Total Manpower 3.5 1488 1488 1488 1488 1488 1275 850
Gang Leaders 74 74 74 74 74 64 43
Charge hands 744 744 744 744 744 638 425