Construction of (500) Houses

In Oud Muteena \ Dubai


Weekly Progress Update as on 21 Jul 16
Based on Baseline Programme Rev. 03, Dt. 29.06.16 (Early Start/Early Finish)

21-Jul-16

Sl. No. (Balance Villas) Activity Description Planned No. of Actual No. of Status
Planned % Actual %
Villas Villas Remarks
Complete Complete
Complete Complete 14/Jul/16 21/Jul/16

1 EARTHWORK 0.08% 0.03%

1.01 Excavation 41 0.07% 16 0.03% (20) (25)

1.02 Excavation for Service Block 25 0.01% 3 0.00% (10) (22)

2 FOUNDATION 0.06% 0.00%

2.01 Blinding 15 0.04% 1 0.00% (6) (14)

2.02 Blinding for Service Block 3 0.00% 0 0.00% 0 (3)

2.03 Footing 3 0.01% 0 0.00% 0 (3)

0.143% 0.0324%

Page 1 of 1 Balance Viilas