Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

2304 INDUSTRIAL AND ENGINEERING CHEMISTRY Vol. 43, No.

10

to the 51,800,000 material figuie and both the material and the failure to investigate the accuracy of available unit cost data.
labor estimate should be rechecked. Poorly defined unit costs are hazardous. The fact that a cost
Partially Detailed Estimates. Many times the complete engi- has been recorded sometimes lends i t a validity that is not war-
neering information, essential to a. detailed estimate, is available ranted. I n applying a known cost such as that of placing con-
for large portions of a job, but lacking for other portions-for crete in a structure, the subsidiary factors (hauling and elevat-
example, the size and details of the units of equipment are known, ing the concrete and the time of year and general conditions
but the piping is in the form of preliminam sketches, nith some under which it will be poured) must be accounted for if the cost
of the lines not even sized. In this casc, the piping portion of used is to mean anything.
the job can be forecast more accurately by considering its cost
Summary and Conclusion
relationship to the major units of equipment than by an attempt
a t a detailed piping estimate. The important points to be stressed in preparing cost estimates
The authors experience indicates that the most difficult i t e m for the process industries are:
to estimate accurately on any industrial or process projects are: 1. Carbon copy jobs are rare; even a hurriedly prepared esti-
Piping, electrical work, and supporting structures. It is dif- mate requires thoughtful analysis.
2. -4n estimate is onlv as good as the information upon which
ficult to foresee all the small piping that is required on a job no it is based; all informa6on should be verified; and cost figures
matter how well established the main lines may be. Steam trac- should be accompanied by clear-cut definitions of the scope of
ing of viscous lines can easily be underestimated. Electrical thi work operations they cover.
conduit work involving many changes in direction can easily be 3. Past experience is the best guide; after an estimate is
assembled, it should be checked with similar jobs for reasonable-
underestimated, particularly when the estimator is accustomed ness.
to working with long runs of straight conduit. Small steel mem- 4. hfost estimates represent the rvork of more than one per-
bers for equipment supports, pipe supports, and walkway con- son: the efforts of the designers in furnishing good engineering
nections are frequently underfigured. information; the men in the field in furnishing good cost data,
and the estimators in evaluating it, all affect the quality of the
Some of the pitfalls an estimator must avoid are: Failure to job. Teamwork is just as essential to good estimating as t o a n y
visit the job site; failure to study and coordinate material dr- engineering problem.
liveries so that the time allon-ed for construction is realistic: and R F F F I X ~4priI
D 16, 1951

Preliminary Estimation of Operating Costs


ROBERT D. N E W T O N
v v v Chas. Pfizer & Co.,Inc., 7 I Bartlett St.,
The evaluation of a new chemical process plant must include not only an Brooklyn 6, N. Y.
estimation of capital expenditure but also a determination of operating
cost with an ultimate expression of profit. All operating expenses may ROBERT S. ARIES
be quantitatively related to raw materials, utilities, labor, or equipmenf.
R. S. Aries & Associafes, 400 Mudison Ave.,
Factors have been derived which may be used for estimating purposes.
New York 77, N. Y.
Consideration must b e given to the type of process and flow of products.
After calculation of the operating costs, further factors are indicated from
which to ascertain profits.
the same material a t identical rates of production. In process 2,
A A A although the profit before taxes is actually greater because of
lower operating expense, the higher investment is unjustified be-
cause the profit, when expressed as the per cent return on the in-
HEMICAL plants are built to earn profits. On the surface
C this seems an absurdly simple observation, yet the economic
evaluation of many proposals is not made on this basis. Evalua-
vestment, is higher in process 1. On the other hand, an analysis
of process 3 in comparison to 2 shows that the additional capital
investment of 2 is entirely warranted since a greater return is
tions that are extended only as far as the estimation of the total realized.
plant cost may be seriously misleading as a basis for decisions.
A good evaluation not only entails the calculation of the capital Variables of Operating Costs
investment, but also requires an estimation of operation costs and
ultimately an expression of profits. To illustrate how an estima- All the expenses incurred in the operation of chemical plants
tor may be mislead by his own failure to carry the evaluation of a can in some way be related to one of three basic factors of cost-
new project t o its fullest extent, consider the three different proc- labor, equipment, and raw materials. A breakdown of the vari-
ess installations illustrated in Table I; all are designed to produce ous components of operating expenditures shows to which each is
primarily associated :
Labor Equipment Materials
Direct labor Depreciation Raw materials
Table I. Variance in Investment and Costs Supervision Maintenance Utilities
Lab,ot overhead Plant supplies
Process 1 Process 2 Process 3 Indirect production cost Local taxes
Insurance
Total plant investment Sl,OOO,OOO $1,500,000 $1,000,000
Net sales, minus sales, research, Obviously, one would think that these operating expenses
and administrative costs 800,000 800,000 800,000
Profit before taxes 400,000 450,000 200,000 should be somewhat proportional to indexes illustrative of each
Manufacturing cost 400,000 350,000 600,000
of the basic factors. Figure 1shows how earnings in the chemical
Return on investment before
taxes, 70 40 30 20 and allied industries (2), costs ( S ) , prices (6),and consumption
( 4 ) varied from 1939 to 1950; all are based on an index value of
October 1951 INDUSTRIAL AND ENGINEERING CHEMISTRY 2305
100 for the year 1939. Thurj, labor rates have more than doubled ating expense is material costs. Raw material costs may be
and equipment costs have increased only slightly less. Chemical computed by applying suppliers quotations or the prices pub-
prices, however, show a much smaller increase than would be lished in Chemical and Engineering News t o a material balance
anticipated by such startling changes in labor and equipment. on the operation. I n many cases, process materials may be used
The items of manufacturing expense, functional of labor and only as an agent of production, and may be to some extent re-
equipment, did not rise t~ the same extent according to the in- coverable.
dexes as is evident in Table 11. The firms represented by the
the data of Table I1 in each of the year classifications are not the
same because of mergers and changes in operations, but the per-
Table 111. Operating Cost Estimate
centage figures are still illustrative of the trend.
Direct production cost Indirect production cost
The effect of wage and equipment increases has been offset pri-
Raw materials Fixed cost
marily by expanded capacity of equipment, and a more oppor- Utilities Depreciation
tune deployment of labor has reduced the ratio of manpower and Direct !+bar Local taxes
Supervlsion Insurance
equipment to production. The chemical industry also has had Payroll overhead
Maintenance
an expanding market for new and existant products (index of Supplies
consumption, Figure 1).

Utilities. IJtility costs are a highly variable item, being de-


pendent not only on consumption but also on the plant location.
Table II. Costs of Manufacturing Services may be supplied through ony one of the following
(Source: R. S. Aries SS Associates) methods:
Per Cent
1941 1947 1950 1. The utility may be purchased a t established rates, and only
70 67 57
the cost for the actual requirements will be charged to manufac-
Raw materials and fuels
Labor 19 21 28 turing.
Fixed costs and other manufacturing expense 11 12 15

Consideration of Process Types


The analysis of chemical manufacturing cost is sometimes
quite difficult and can become quite involved. Until recently
little of a quantitative nature was published on the subject
however, in the past year or two, four publications have been re-
Iemed on this subject (1,W , 6,8).
Since the number of proposals faring the estimator may prove
numerous, methods may be calculated which will allow their pre-
liminary evaluation to proceed with a certain degree of ease
Numerous short cuts have already been devised which may be
used to estimate total plant costs from equipment prices without
detailed designs being required; these have been based on the
relative magnitude of various components of capital costs.
Likewise, it is possible to determine factors that may be em-
ployed to estimate operating rosts from labor, plant, and ma-
terial expenditures on a yearly basis.
First, consideration must be given to the type of operation
involved to determine whether the cost must be apportioned
among several products or borne entirely by one and whether
any by-product value must be credited:

1. If only one material is produced, the entire cost is charged


to the single commodity.
2. Where two or more primary products are jointly manufac-
tured, the cost of o eration may be divided between the products
on the basis of prodPuct value or quantity produced.
3. Where two or more materials are jointly manufactured to
a certain stage, after which they undergo separate operations,
the charges for the joint operation may be apportioned a8 in 2 YEAR,
but with separate tabulations after the separation point. Figure 1. Comparison of Cost Factors for Chemical
Many chemical operations produce by-products, which may . Industries-1 939-50
have sales potential. The value of such products minus the 1939 = 100
expense of additional processing must be credited to the cost of the
primary products.
2. The service may be produced within the company and
utilized for only one product; the cost of the installation may be
Direct Production Costs included in the capital cost of the unit and appropriate operating
costs charged to manufacturing.
The costs incurred in the actual conversion of raw materials 3. The service may be produced within the company and
into products are classified as direct production costs. Such supplied t o several processes a t a rate based on the investmmt in
the utility unit as well as its operational costs.
expenses are shown in Table I11 in typical form.
Raw Materials. The first expenditure incurred in chemical pro- Although it is desirable to employ more accurate service rates,
duction is the purchase of raw materials. About one half of oper- the following averages may be used for preliminary estimates :
2306 INDUSTRIAL AND ENGINEERING CHEMISTRY Vol. 43, No. 10

Steam: $0.50 t o $1.00 per 1000 pounds over what is regarded as salvage value. Although tables are
Electricity: $0.0075 to $0.25 per kw.-hr. available from the Bureau of Internal Revenue on allowable
Process water: $0.03 t o $0.25 per 1000 gallons
Cooling water: $0.01 to $0.04 per 1000 gallons rates for tax computation purposes, preliminary estimates are
Natural gas: $0.15 t o $0.60 per 1000 cubic feet customarily based on rates of 10% on equipment installations
Fuel oil: $0.06 to $0.15 per gallon and 570 for buildings yearly.
Local Taxes. Local property taxes are dependent on the local-
Direct Labor. The second major expense involved in manufac- ity in which the plant is situated with rates for mid-city locations
turing costs is labor, which accounts for roughly one quarter of obviously running higher than less populated regions. I n estimat-
operating expenditures. Labor rates have risen quite rapidly ing, a figure of 1 t o 2% of the total plant cost may be employed.
during the past 10 years, but more economic use of manpower Insurance. Insurance usually assumed to be equal to 1% of
has to some extent offset the unit cost of labor. Unfortunately the plant value is carried by chemical firms on their assets; this
there is no short cut method for estimating labor costs on opera- figure of course is subject to revision depending on the type opeia-
tions, although attempts have been made to standardize labor tion involved, but for preliminary work such an estimate will
requirements for some types of equipment and products. A prove satisfactory.
true evaluation of labor costs can be obtained by conducting a Interest. Another factor which is sometimes considered as a
survey of the flow of materials and performance of equipment fixed cost, although wrongly so, is capital investment. Interest
with relation to the time cycles of operation. Labor rates are is fixed in that it is invariant with production but it cannot right-
best obtained through the Bureau of Labor Statistics or other fully be classified as an operating expense This is a debatable
governmental agencies, although an hourly rate of $1.60 will point, but the preponderance of evidence is against its inclusion--
evaluate present averages. for example, depreciation is the mechanism by which the cost of
Supervision. Several items of production costs may be esti- equipment on processing expense is registered. Other reasons
mated from total labor expense. The first is that of supervision; against its use include court decisions and allovvablp tar. proce-
in general, such expenditures may be assumed as being equal to dures.
about 10% of direct labor value.
CQlCulQtioIlO f Profit
Payroll Overhead. Payroll overhead-pensions, vacations,
group insurance, social security, and unemployment taxes-is Operating Cost. The sum of all direct, indirect, and fixed costs
generally on the rise, and in all likelihood will continue to in- is known as the operating cost. I t is the first of five important ex-
crease, probably a t a faster rate than wages. Today an amount penses n hich must be deducted from the net sales return on a
equal t o about 20% of the labor and supervision charges may be product in order to calculate the profit.
employed to cover this item. Sales Expense. The second item of cost to be considered is the
Maintenance. A major portion of direct expense is incurred by cost of sales and distribution. The amount to be spent in such a
maintenance, which includes the cost of all materials, labor and category is dependent largely on the type of product and the
supervision employed in routine maintenance, incidental repairs, nature of selling, statistically, an expense equal to 10 to 30% of
and major revisions of equipment and buildings. Although such the manufacturing cost is realized here.
expenditures are difficult to anticipate, equipment maintenance Research Expense. Research costs depend to a large extent
will vary from 2 to 10% of the plant cost. On the average, 6% on company policies and products, but in geneial an amount
may be employed for normal operations; the two extremes equal to 5% of the manufacturing cost may be employed for
apply for light utilization in simple equipment and severe use in estimating.
more complicated operations. Building maintenance averages Administrative Expense. Administrative expenses equal to 1 to
only about 3 to 4% of building costs. 2y0 of the capital investment must be carried against the sales
A word of caution in regard to items that a t times are confused returns in the determination of profits.
with maintenance: changes that enhance the value of the plant Financial Expense. Financial obligations of the company
are regarded as capital investments; expenses incurred in repairs such a2 interest on indebtedness must be accounted for; interest
due to absolescence and normal near ale covered by depreciation may be calculated on a basis of 4 to 5% for estimating purposes.
rates: and supplies such as gaskets, charts, and lubricants are Profits. The amount that i, left after all these expenditures
classified as plant supplies. have been deducted from the sales return is the profit before
Supplies. The aforementioned plant supplies may be charged taxes. Sometimes ventures are compared on the basis of this
at a rate equal to 15y0 of plant maintenance cost. figure. However, Then taxes are taking an increasing portion
of profits, it seems best to calculate the tax involved. On this
Indirect Production Costs basis a truer picture of the return on the investment is realized.
At the present time the basic tax rate is 47%, plus surtaxes on
The second major portion of manufacturing costs is classified excess profits, and an upward revision in tax rates is expected.
as indirect production expenditures. Such expenses involve Therefore, it seems wisest to include taxes in the estimation of
technical and analytical services, hospital facilities, transportation, profits.
safety, maintenance of roads and yards, stockrooms, and a propor-
tionate share in the expense of nonoperating facilities. These Bibliography
charges are somewhat proportional to labor costs; present esti- Aries. R . S., and Newton, R. D., Chemical Engineering Cost
mates are equal to 60 to 70% of direct labor expense, supervision, Estimation, New York, Chemonomics, Inc., 1950-1951.
and maintenance charges. Bureau of Labor Statistics, U. S. Dept. Labor, Washington 25,
D. C., Index for Earnings in Chemical & Allied Industriea,
1939-1949.
Fixed Costs (3) Chem. Eng., 58, No. 2 , 158 (1951), Marshall & Stevens equip-
ment cost index.
The last major item of manufacturing expense is that of fixed (4)Ibid., p. 302, chemical consumption index.
costs-those which are invariant with production. In other (5) I bid., p . 302, chemical price index.
(6) Dybdal, E. C., Chem. Ens. Progress, 46, 57-66 (February 1950).
words, expenditures which must be paid whether or not the (7)Van Noy, C. W., et al., U. S. Bur. Mines, R e p t . Insest. 4534
plant operates. Such costs are based entirely on the magnitude (1949).
of the investment. (8) Zimmerman, 0. T., and Lavine, I., Chemical Engineering
Depreciation. Depreciation is the attempt to write off the Costs, Dover, N.H., Industrial Research Service. 1950.
cost of equipment, buildings, and other material possessions RECEIVED
April 16, 1951.

You might also like