Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 25

No Agenda 9-11-2016

1 Cement Indonesia -
-

2 Jembatan BG-30 -
3 Jembatan BG-60 -
4 Jembatan BG-25 -
5 Jembatan CG-25 -
6 Jembatan Sei Wampu -
7 Sky Walk da Antapani -

8 Ducting Hanazono -

9 Elnusa -

10 Steel Pole Pama -

11 Steel Pole Solo -


12 Hanggar Semarang -

13 Karlita -

14 Cilengsi -

15 Trunajoyo -

16 Office lt-2 -
Keterangan Date-1 Date-2
End Date
Joint Survey hari 11/11/2016
Routine meeting Jam 10.00
Gambar

Material

Fabrikasi

Pontianak 11/11/2016
Cipta Konstruksi 11/25/2016
TPJ 11/7/2016 11/18/2016
TPJ 11/7/2016 11/25/2016
Bikin Surat ke TPJ perihal surat Crane 22-11-2016 11/30/2016
Cihampelas
PJU
FGB
Box 225 X 250
Stair
Handril Platform 11/10/2016
Handrail Stair 11/11/2016 11/12/2016
Angkur dan template
Antapani
PJU
Struktur Trafic Light
Angkur dan template
Line-1, Lain-3 dan line 2 belum jalan 12/1/2016
Cutting line-1
Cutting line-3
Roll Line-1
welding Line-1
Assembly line-1 12/10/2016
Akan dilakukan meeting dengan Hanazono mengenai permasalahan DHJ
Grating tebal 3 mm menjadi 5 mm ada tambahan Kerja
Material datang Checker Plate 6 mm 11/9/2016
Rajanto untuk koordinasi pengiriman tgl 10/11/2016 malam
Erection Drawing
Packing
Mill sheet
Curva S 11/9/2018
karena over weight 80%
Design memasuki defleksi, material upgrade tebal dan lebar
Speck 6 mm dan 8 mm sudah ready 100 ton
Design belum approved
Schedule 60 hari setelah gambar di approved
Kontrak tanggal 1/11/2016 dikirim diwaskita 4/11/2016
Dokumen kirim ke eng
Scope of work
sondir
Engineering
Kerjaan Sipil
Struktur steel plate TSP 15 dan TSP 6, TSP 9 untuk 2 unit
Schedulle 4 bulan + 1 bulan = total 5 bulan
3 bangunan, 2 bangunan , 1 lagi dicalculation
Joint Survey dengan Hanggar semarang 11/10/2016
Rencana Pabrikasi 12/1/2016
Rencana erection 1/1/2012
Total 900 ton
Produksi
erection
Outstanding anchor 11/9/2016
Hoist capasitas 20 ton ; gambar turun 9/11/2016 ; untuk 2 unit
Cutting mulai hari ini 11/9/2016
Roda ada 4 stock, tetapi tetap diorder 8
Pabrikasi hoist 11/24/2016
Diputuskan hari ini untuk subcontractor
Selesai 11/30/2016
258 Tower Sutet, 150 KV; 270 KV ; 500 KV
Schedulenya 1 tahun
Estimasi PO 1/1/2017
Trial 1 tower Type 150 kv AA+0 11/28/2016
Engineering 11/14/2016
Fabrikasi 11/21/2016
Material tidak diorder lagi, sudah ready stock 3 bulan lalu
Rencana 2 minggu
Progress 28%, Karena crane kato
Lokasi Kerja
Meeting dengan Pak Jaka 11/9/2016
Wire mesh ada
Keterangan

RFD
RFD
RFD
4 Type Star

10 module
RFD

ok
ok
RFD
eng 100%
66%
0%
30%
24%
7%

ok
ok
0%

blm ada feed back


SPH Insulator
SPH Konduktor
SPH Civil

100%
belum

28%
Project Cement Indonesia

No Engineering
Drawing Mto Spb
1
2
3
4
5
6
7
8
9
10
Fabrikasi
Material Cutting Bending Welding
Pembayaran
Pengiriman
Assembly Dp Termin-1
Termin-2
Agenda 17-11-2016

No Project SPK

1 Cement Indonesia

2 Jembatan BG-30 0317


Terima SPK 10/10/2016
Tonase (ton) 43

3 Jembatan BG-60 0349


Terima SPK 4/11/2016
Tonase (KG) 12,075.53
Ext : Anchor, Bolt

4 Jembatan BG-25 0344


Terima SPK 1/11/2016
Tonase (KG) 27,475
5 Jembatan CG-25 0350
Terima SPK 8/11/2016
Tonase (KG) 21,879.16
akan revisi berat spk (ariyanto)

6 Jembatan Sei Wampu


7 Sky Walk da Antapani

8 Ducting Hanazono 1980

9 Elnusa

10 Steel Pole Pama


11 Steel Pole Solo

12 Hanggar Semarang

13 Karlita

14 Cilengsi

15 Trunajoyo

16 Office lt-2 1928


Terima SPK 29/09/2016
Tahap 1

1928
29/09/2016
Tahap 2
17 Jembatan B 45 0355
Terima SPK 10/11/2016
Tonase (KG) 80,971.89
Keterangan Start End
Target
Joint Survey hari 11/11/2016
Routine meeting Jam 10.00
Gambar

Material

Fabrikasi

Pontianak 10/10/2016 14/11/2016

Drawing
SPB
PO - Kirim
Fabrikasi =) Cut and Dril

=) Asembly
=) Welding

=) Painting 20/11/16
=) Kirim 21/11/16

PT. Cipta Konstruksi 5/11/2016 25/11/2016

Drawing
MTO 11/11/2016
Material

Fabrikasi =) Cut and Dril

Tripanajaya
11/7/2016 11/20/2016
Drawing
Material

18-11-2016

Fabrikasi =) Cut and Dril


=) Asembly
=) Welding

Tripanajaya 11/7/2016 11/25/2016

Drawing
MTO 16/11/2016
List 16/11/2016
Material
Fabrikasi =) Cut and Dril

=) Asembly
=) Welding

Bikin Surat ke TPJ perihal surat Crane 22-11-2016 11/30/2016


Cihampelas
PJU
FGB
Box 225 X 250
Stair
Handril Platform 11/10/2016
Handrail Stair 11/11/2016 11/12/2016
Angkur dan template
Antapani
PJU
Struktur Trafic Light
Angkur dan template
PO From customer 12/1/2016
=) Kirim
Drawing
Fabrikasi =) Cut and Dril
=) Welding
=) Kirim

11/9/2016
Rajanto untuk koordinasi pengiriman tgl 10/11/2016 malam
Erection Drawing
Packing
Mill sheet
Curva S 11/9/2018
karena over weight 80%
Design memasuki defleksi, material upgrade tebal dan lebar
Speck 6 mm dan 8 mm sudah ready 100 ton
Design belum approved
Schedule 60 hari setelah gambar di approved
Kontrak tanggal 1/11/2016 dikirim diwaskita 4/11/2016
Dokumen kirim ke eng
Scope of work
sondir
Engineering
Kerjaan Sipil
Struktur steel plate TSP 15 dan TSP 6, TSP 9 untuk 2 unit
Schedulle 4 bulan + 1 bulan = total 5 bulan
3 bangunan, 2 bangunan , 1 lagi dicalculation
Joint Survey dengan Hanggar semarang 11/10/2016
Rencana Pabrikasi 12/1/2016
Rencana erection 1/1/2012
Total 900 ton
Produksi
erection
Outstanding anchor 11/9/2016
Hoist capasitas 20 ton ; gambar turun 9/11/2016 ; untuk 2 unit
Cutting mulai hari ini 11/9/2016
Roda ada 4 stock, tetapi tetap diorder 8
Pabrikasi hoist 11/24/2016
Diputuskan hari ini untuk subcontractor
Selesai 11/30/2016
258 Tower Sutet, 150 KV; 270 KV ; 500 KV
Schedulenya 1 tahun
Estimasi PO 1/1/2017
Trial 1 tower Type 150 kv AA+0 11/28/2016
Engineering 11/14/2016
Fabrikasi 11/21/2016
Material tidak diorder lagi, sudah ready stock 3 bulan lalu
Rencana 2 minggu 29/09/2016
Drawing 24/10/2016
SPB
Fabrikasi =) Welding, painting 14/10/2016
=) Kirim 10/10/2016
Surat Jalan 10/10/2016
Install 18/10/2016
Progress 26/11/2016

Drawing 07/11/2016
SPB 28/10/2016
Fabrikasi =) Assembly 28/10/2016
=) Welding, painting 05/11/2016
=) Kirim 08/11/2016
Surat Jalan 08/11/2016
Install
Progress
PT. Cipta Konstruksi 11/11/2016 27/11/2016

Drawing

MTO 16/11/16
Material

Fabrikasi =) Cut and Dril


Keterangan

Closed
Closed
Closed

Closed

Galvanise finish

by customer release to Ws Setu 10/11/16


Finish
By Stock
PL 21 & 38 SM490YB (O/S)
Memo 141 Single part WS Tambun Deadline 15/11/16
Material belum di kirim ke WS Setu DELAY 2 Hari

By customer release to Ws Setu


By Stock
Deform D16
Bolt M 20x60
Anchor
U Bolt
Memo 135 Deadline :7/11/16
Progress 63,3% (4521,22) DELAY !
Progress 13.54%
Progress 13.54%

By Customer 09/11/16 Release to produksi WS Setu 14/11/16

Belum di alokasi by stock, by spb


Memo 146 End 19/11/16
Cutting welded beam WS Tambun
Memo 147 End 19/11/16
Single Part (3.768.8 kg)
DELAY !!!
SPEED UP MATERIAL, PRODUKSI, SINGLE PART

RFD
RFD
RFD
4 Type Star

10 module
RFD

ok
ok
RFD
141122-AYFE001
Pipe 87.7% , Flange 100%
Finish with note delay plus minus 25 days
assembly list Part 20%
62%
Target next week partial delivery

ok
ok
0%
blm ada feed back
SPH Insulator
SPH Konduktor
SPH Civil

100%
belum

Using stock

No SPB 142651

Next
Next
by customer 13/11/16 release to produksi WS Setu 14/11/16 (Assembly)
Loose part (belum release) DELAY 2 Hari
Finish
WF 198x99
RB D36, L=6000
PL 21 SM490YV
PL 38
No SPB 142686 16/11/16
No SPB 142692 belum sign pak arief
BELUM TURUN MEMO PRODUKSI
Column1

- Repair Marking AMG 3 (Rev drawing 15/11 drafting)


- Delay 2 hari untuk repair
- Double (ost (material+repair)
- Repair (bongkar = pasang)
-Closed 16/11/2016

No SPB 142690 belum sign pak arief 15/11/16

O/S
SPEED UP FABRIKASI PROSES WELDED
1/16 (Assembly)

You might also like