PART C: PLACE
The edges of strategic routes and existing roads are colour coded
according to the type of access or movement permitted along that
edge. The purpose of this section is to clarify where vehicular access
to plots will be restricted.
There are very few locations where this restriction applies. The key
reason for restricting vehicular access is to create pedestrian routes
along shopping frontage in the district and local centres. Lenghts of
street with special avenue tree planting and swales are other
locations where restricted access will apply. The locations of
restricted access are shown on the regulatory plan and are
mandatory.
Site Boundary
A28 Edge
Discovery Park
Rural Edge
Green Corridors
Green Arc
12.6
12.1
12.2
12.3
12.7
12.4
12.19
12.5 12.14
12.18 12.8
12.17
12.13
12.20 12.10
12.16
12.12
12.9
12.12
12.15
12.11
A28
12.1 A28 edge north of northern access to 12.2 A28 edge to northern roundabout
Chilmington Green
A significant landscape buffer separates the The landscape edge to the northern
A28 from proposed residential frontages roundabout performs a similar function in
north of the northern access to the site, reducing noise through separation distance,
and to the north of the roundabout. This landscaping and planting. However the
helps to reduce the visual presence of gateway landscaping will provide views of
Chilmington Green from sensitive locations housing.
along the road. The separation distance will
also mitigate traffic noise from the A28. Mounding in this location will also play an
Shared-surface edge streets will provide important role in visually framing the
access to a limited number of dwellings. gateway to the development.
Key plan
A28
12.3 A28 edge south of northern 12.4 A28 edge to secondary school
roundabout
The treatment of the edge north of the Secondary school playing fields will have a
roundabout is repeated immediately to the landscaped edge as well as an acoustic
south, with a tapering landscape buffer barrier to mitigate noise impact from the
providing visual screening and noise road.
mitigation from the A28. Access to
dwellings is also via a shared-surface edge
street
Key plan
A28
Key plan
Set back
Edge Street
Landscape buffer
12.6 Great Chart Ridge edge to Singleton 12.7 Great Chart Ridge edge to ridge-top
tree belt
The proposed landscape buffer to the east Development will be set back from Great
of Chilmington Green where the land rises Chart Ridge and, in this case, its associated
to the Great Chart Ridge and Singleton ridge-top tree belt. This buffer will help to
includes significant native woodland planting screen views of the development from the
in order to screen long distance views of east.
Singleton and create tree lined ridge.
Key plan
Discovery Park
12.8 Discovery Park edge to Colemans 12.9 Discovery Park edge to main park
Kitchen Wood area
At the residential edge of the Discovery Where a residential parcel sits adjacent to
Park and Colemans Kitchen Wood, a minor the main Discovery Park, a landscape buffer,
access road with street trees and planting including a swale, will separate development
will mark the interface of the development from the Park. Edge Streets will provide
with the park. access to relatively small numbers of
dwellings along the edge.
Key plan
Discovery Park
Green axis
Key plan
Rural Edge
10m
Landscape Edge street Set back &
Farmland buffer (see 10.4.1) boundary
At the eastern rural edge, residential At the western rural edge, properties will
dwellings will back onto farmland. Gardens front onto farmland. Farmland will be
and appropriate rear property boundary separated from residential parcels by a
treatments will provide a soft edge at this landscape buffer. Edge streets should
location. provide street trees and a footpath in this
location.
Key plan
Rural Edge
3m
Landscape
Minor Access street Set back &
buffer
Open countryside boundary
Key plan
Existing
B5 - refer to Front boundary byway
typologies in Appendix
B02/B03 (B04 where boundary to allotments) - refer to
Open Space boundary typologies in Appendix
12.14 Green Corridor edge to byway 12.15 Green corridor edge general
Key plan
B6 - refer to Front boundary B07 - refer to Play space & school Existing hedge
typologies in Appendix boundary typologies in Appendix
12.16 Green Arc edge to play area 12.17 Green Arc edge to attenuation
basins
Where the Green Arc meets a play area, an An appropriate area of open landscape will
appropriate boundary treatment will be separate the edge streets, and associated
adopted, as per Play space & school residential development, from the
boundary typologies in the Appendix. attenuation basins within the Green Arc.
Minor access streets and edge streets
adjacent to this boundary will provide
access to dwellings.
Key plan
12.18 Green Arc edge to cricket green 12.19 Green Arc edge to watercourse &
Greensands Way
A green verge and footpath will separate Greensands Way and the existing
the Green Arc at the cricket green from the watercourse will be separated from houses
residential development. Edge streets will by a verge and proposed planting. Edge
provide access to properties. streets will also provide access to dwellings.
Key plan
Pedestrian/
cycleway
B4 - refer to Front boundary
typologies in Appendix
Key plan
Staggered frontage
Consists of predominantly detached and some
semi-detached dwellings of varying size
2 Frontage may include garages and garden walls
but garages must be set behind main frontage
Distance between street edge and frontage
may vary
Consistent frontage
Consists of dwellings of a similar typology and
size, plotted the same distance apart to create
3 rhythm and order
Distance from street edge to frontage
consistent along row
Mixed use
6 Continuous, formal frontage facing square
Consists of mixed use blocks with gaps only for
pedestrian access to parking at rear
14 Residential layout
14.1 Residential plot components
Dwelling typologies
D - Detached
SD - Semi-detached
T - Terraced
F - Flats
Parking typologies
P1 - On-plot frontage
P2 - On-plot corner
P3 - On-plot between dwellings
P4 - Courtyard
P5 - Mews
P6 - Front access drive through
P7 - Rear parking courts
P8 - Forecourt
P9 - Detached car barns
P10 - On-street visitor parking*
P11 - Forecourt attached
*P10 can be used where required on any street subject to detailed design of junctions etc.
Set back
Dwelling height
MATRIX A
MATRIX B
MATRIX C
MATRIX C
MATRIX D
MATRIX D
MATRIX E
MATRIX E
MATRIX F
MATRIX F
MATRIX G
PALETTE a
(General Palette)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Grey slates natural Standing seam Flat roof behind Green roof
clay tiles tiles orange/dark red or good quality metal parapet
reconstitution
Walls
Stone Ragstone Red stock brick Red/orange brick Red multi mix brick Brown multi mix Yellow brick
brick
Grey/ blue brick* White painted Hand made clay Hand made clay Self coloured White stained Natural stained
brick tiles red/ orange tiles various colours render or painted weather boarding
weatherboarding
Stained or painted Black stained Fibre board Oak frame Glazed or solid
weatherboarding weatherboarding cladding cladding panels
Windows
Timber natural Timber white Metal White UPVC Grey UPVC Shop windows
stain
Balconies
PALETTE b
(Chilmington Rise)
Roofs
Orange / red plain Dark red plain clay Standing seam Grey slates natural Flat roof behind Green roof
clay tiles tiles metal or good quality parapet
reconstitution
Walls
Predominant
Stone Red stock brick Red multi mix brick Red/orange brick
Limited
Brown multi mix Yellow brick Grey/ blue brick* White painted Self coloured White stained Hand made clay
brick brick render or painted tiles red/ orange
weatherboarding
Windows
Balconies
Key plan
PALETTE c
(Market Square and High Street)
Roofs
Orange / red plain Dark red plain clay Standing seam Flat roof behind Green roof
clay tiles tiles metal parapet
Walls
Predominant
Limited
Grey/ blue brick* Yellow brick White painted White stained Hand made clay Fibre board Glazed or solid
brick or painted tiles red/ orange cladding cladding panels
weatherboarding
Windows
Balconies
Key plan
PALETTE d
(Chilmington Gardens)
Roofs
Orange / red plain Dark red plain clay Standing seam Flat roof behind Green roof
clay tiles tiles metal parapet
Walls
Predominant
Limited
Grey/ blue brick* Red multi mix brick White painted White stained Hand made clay Glazed or solid
brick or painted tiles red/ orange cladding panels
weatherboarding
Windows
Balconies
Key plan
PALETTE e
(Chilmington Square)
Roofs
Orange / red plain Dark red plain clay Standing seam Flat roof behind Green roof
clay tiles tiles metal parapet
Walls
Predominant
Limited
Grey/ blue brick* Red multi mix brick White painted White stained Hand made clay
brick or painted tiles red/ orange
weatherboarding
Windows
Balconies
Key plan
PALETTE f
(Northern Gateway)
Roofs
Walls
Predominant
Stone Red stock brick Red multi mix brick Red/orange brick
Limited
Windows
Balconies
Key plan
PALETTE g
(Orchard Village Neighbourhood)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Standing seam
clay tiles tiles orange/dark red metal
Walls
Predominant
Limited
Stone Red stock brick Red multi mix brick Self coloured White painted
render brick
Windows
Balconies
Key plan
PALETTE h
(Orchard Village Local Centre)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Standing seam Flat roof behind Green roof
clay tiles tiles orange/dark red metal parapet
Walls
Predominant
White stained or painted Stained or painted Black stained weatherboarding Self coloured
weatherboarding weatherboarding various colours render
Limited
Red stock brick Red multi mix brick Grey/ blue brick* Fibre board Glazed or solid
cladding cladding panels
Windows
Balconies
Key plan
PALETTE i
(Chilmington Brook Neighbourhood)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Grey slates natural Standing seam
clay tiles tiles orange/dark red or good quality metal
reconstitution
Walls
Predominant
Limited
Stone Red stock brick Red multi mix brick Brown multi mix Self coloured
brick render
Windows
Balconies
Key plan
PALETTE j
(Chilmington Brook Local Centre)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Grey slates natural Standing seam Flat roof behind Green roof
clay tiles tiles orange/dark red or good quality metal parapet
reconstitution
Walls
Predominant
White stained or painted Stained or painted Natural stained weather Self coloured
weatherboarding weatherboarding various colours boarding render
Limited
Red stock brick Red multi mix brick Grey/ blue brick* Fibre board Glazed or solid
cladding cladding panels
Windows
Balconies
Key plan
PALETTE k
(The Hamlet)
Roofs
Orange / red plain Dark red plain clay Grey slates natural Standing seam Green roof
clay tiles tiles or good quality metal
reconstitution
Walls
Predominant
Stone Red multi mix brick Red/orange brick Black stained weatherboarding
Limited
Brown multi mix Hand made clay Hand made clay White stained Natural stained Stained or painted Oak frame
brick tiles red/ orange tiles various colours or painted weather boarding weatherboarding
weatherboarding various colours
Windows
Balconies
Key plan
PALETTE l
(Cricket Green)
Roofs
Orange / red plain Dark red plain clay Grey slates natural Standing seam
clay tiles tiles or good quality metal
reconstitution
Walls
Predominant
Stone Red multi mix brick Brown multi mix White stained or painted
brick weatherboarding
Limited
Hand made clay Hand made clay Natural stained Stained or painted Black stained Oak frame
tiles red/ orange tiles various colours weather boarding weatherboarding weatherboarding
various colours
Windows
Balconies
Key plan
PALETTE m
(Brisley Farm extension)
Roofs
Orange / red plain Dark red plain clay Profiled tiles red/ Standing seam
clay tiles tiles orange/dark red metal
Walls
Predominant
Stone Red stock brick Red multi mix brick Self coloured
render
Limited
Windows
Balconies
Key plan
Dwelling typologies
Parking typologies
Public realm
Hard landscaping
Architectural principles
Technical information
Street junction design
SuDS & drainage strategy
Sustainability strategy
Waste & recycling strategy
Utilities strategy
Secure by Design
Inclusive Design
Dos & Donts
DWELLING TYPOLOGIES
DETACHED ILLUSTRATION
DESCRIPTION
TYPOLOGIES (illustrative purposes only)
The principal frontage width is greater than the depth of the primary building
D1 form
Wide frontage The principal frontage more than 7m wide
The ridge line is parallel to the principal frontage
The principal frontage width is less than the depth of the primary building form
D2 The principal frontage is less than 7m wide
Narrow frontage The ridge line is perpendicular to the principal frontage
The principal frontage width is between 90-110% of the depth of the dwelling
D3
The principal frontage is more than 8m
Villa
D4
The dwelling has two principal frontages at 90 degrees to one another
L-shaped/corner
house
The mass of the secondary building form is less than 50% of the mass of the
primary built form
D5
When the secondary building form includes a garage, the width of the primary
Linked detached
building should be more than 7m wide
DWELLING TYPOLOGIES
SD1 The combined principal frontage width is less than 15m wide
Narrow frontage The ridge line is perpendicular to the principle frontages
The combined principal frontage width is greater than the depth of the primary
SD2 building form
Wide frontage The combined principal frontage width is more than 15m wide
The ridge lines are parallel to the principal frontages
SD4 The dwellings have two principal frontages at 90 degrees to one another
Inverted L-shaped Two dwellings are attached to form a symmetrical form
The T consists of a wide frontage (D1) and an adjoining narrow frontage (D2)
The wide frontage units principal frontage is more than 7m wide
SD5
The ridge lines are perpendicular to each other and are adjoining
T-shaped
The dwellings are set perpendicular to each other
DWELLING TYPOLOGIES
TERRACED ILLUSTRATION
DESCRIPTION
TYPOLOGIES (illustrative purposes only)
The combined principal frontage width of the dwelling is less than the depth of
the primary building form
T1
The individual principal frontage width is less than 7m wide
Narrow frontage
The overall frontage width of the row of terraces must be more than 18m and
consist of at least three dwellings.
The combined principal frontage width of the dwelling is more than the depth of
the primary building form
T2 The individual principal frontage width is more than 7m wide
Wide frontage The ridge lines are parallel to the principal frontages and are adjoining
The overall frontage width of the row of terraces must be more than 21m and
consist of at least three dwellings
The mass of the secondary building form is less than 60% of the mass of the
primary built form
T3 When the secondary building form includes a garage, the frontage of the
Stepped/L-shaped dwelling is more than 7m wide
The overall frontage width of the row of terraces is more than 200% of the
principal depth of the dwellings
The combined principal frontage width is greater than the depth of the primary
T5 building form
Side terrace The overall frontage width of the row of terraces must be more than 21m and
consist of at least three dwellings
The combined principal frontage width is less than the depth of the primary
T6 building form
Rear terrace The overall frontage width of the row of terraces must be more than 18m and
consist of at least three dwellings
DWELLING TYPOLOGIES
FLATS
DESCRIPTION
TYPOLOGIES
NB: Innovative typologies can be submitted for approval, the four typologies above give an example of what could be used
PARKING TYPOLOGIES
P3
On-plot between
dwellings
PARKING TYPOLOGIES
P5
Mews
PARKING TYPOLOGIES
PARKING TYPOLOGIES
FRONT BOUNDARIES
The table on the pages 203-204 set out the appropriate front
boundary typologies for residential development addressing
the public realm. The table explain the appropriate front
demarcation treatment. This is mandatory and must be adhered
to link the front boundary treatment type(1a) and property
demarcation treatment type(1b). Boundary typology definition
Rain Gardens
Where specified as part of the SuDS system permeable areas
acting as rain gardens to are to included.
SIDE BOUNDARIES
REAR BOUNDARIES
3c
Property
demarcation (1b)
Height 0.9 / 1.2 m max*
to be created
Set back minimum 2m
B6 through
Post and wire fence integral to
Hedge ornamental
the hedge while it establishes
hedge of similar
species and
height
Property
demarcation (1b)
Height maximum 600mm
to be created
Set back minimum 2m
B7 through
Low clipped hedge with shrub
Planted zone ornamental
planting
hedge of similar
species and
height
Plan
Property
Height 1.2m max demarcation (1b)
Set back greater than 2m to be created
B8
Gates to match through same
Cleft fencing
Stepped cleft fencing or
ornamental
hedge
Property
Height 1.2m-1.5m max demarcation (1b)
B9 Set back greater than 2m to be created
Cleft fencing with Applicable to the rural edge through same
hedge Gates to match cleft fencing or
ornamental
hedge
PUBLIC REALM
Key design
principles:
Seating
Simple
Functional
Declutter
Integrated
Contemporary timber
Timber bollard to hard landscape Timber bollard to soft landscape Timber bins to be Hardwood timber bollard
bollard in timber
(with integral way marking) - limited and park edges (with integral way co-ordinated with dog
locations marking) - limited locations litter bins or similar and
approved
PUBLIC REALM
Key design
principles:
Seating
Simple
Functional
Declutter
Integrated
PUBLIC REALM
Lighting
Column type
Low level, timber lighting bollard (if required to non- Low level, timber/metal lighting bollard (if required to Low level, metal lighting bollard (if required to non-
adoptable pedestrian paths only) non-adoptable pedestrian paths only) adoptable pedestrian paths only)
Feature lighting
PUBLIC REALM
Public art
Tree details
HARD LANDSCAPING
Permeable keyblock paving Red block paving Brick paving - Wienerberger Foru Brick paving - Vandemoortel
HARD LANDSCAPING
Permeable
Exposed blocks and
aggregate blocks, roman format
Stone mastic SMA SMA SMA SMA
permeable sett SMA brick detailing
CARRIAGEWAY asphalt (SMA)
blocks and fine (i.e. 200x100x
surface asphalt 48/50mm
(60/40%) brick on
edge)
Fine surface Fine surface Fine surface Fine surface Brick paving with Roman format Fine surface
asphalt with asphalt with asphalt with asphalt with Conservation Brick feature asphalt with
Conservation Conservation Conservation Conservation trims paving, Conservation
trims trims trims trims Conservation trims
Linear tree edging
Permeable
Linear tree Linear tree Linear tree Linear tree trenches Tree pits and Linear tree
blocks and
FOOTWAY trenches trenches trenches trenches surfaced with trenches with trenches
roman format
surfaced with surfaced with surfaced with surfaced with permeable permeable self surfaced with
brick detailing
permeable permeable permeable permeable tarmac/ bound gravel permeable
tarmac/ tarmac/ tarmac/ tarmac block and surfacing, block/ self bound
block and block and block and /block and Conservation galvanised steel gravel and
Conservation Conservation Conservation Conservation trims edging Conservation
trims trims trims trims trims
Permeable Permeable
blocks and blocks and
PARKING AREA SMA SMA SMA SMA SMA SMA
roman format roman format
brick detailing. brick detailing
DEMARCATION
Stainless Steel Stainless Steel Stainless Steel Stainless Steel Stainless Steel Stainless Steel
EXTENT OF Brass Studs Brass Studs
studs studs studs studs studs studs
ADOPTION
Buildings must directly address routes and spaces such that their
primary frontage is parallel to the edge of that route or space.
Buildings should not be positioned at an angle to the back-of-
footpath line, or to the defined edge of a shared surface.
For informal arrangements the dwelling must still align to the
immediate edge of the route or space it faces.
Primary entrances to buildings must be visible from the public
realm.
Min 2m Min 2m
ARCHITECTURAL PRINCIPLES
Recognisable form
Silhouette
Landmark
ARCHITECTURAL PRINCIPLES
Celebrate entrances
Balcony over bay Double height Porch & Balcony to Porch cut-out of
projecting entrance porch & loggia with first floor across plan to create interest
gable highlighting habitable rooms & protection and
entrance provide shelter at
entrance
Honesty
Simple Window
Palette; Used to
form other elements
Simple brick form with clip Simple wide fronted units
on elements Bay, porch, with subservient elements
chimney, loggia e.g. garage, bay etc.
Responding to slope
TECHNICAL
1. Consideration of SuDS throughout the design process from 4. Strategic, Innovative, Multifunctional SuDS - Focus should
inception During the masterplan phase of the project an remain on strategic, innovative, multifunctional, high quality,
integrated approach between landscaping and SuDS should centralised SuDS systems. These should be easy to maintain
be completed, ensuring that the visual features of SuDS are and allow developers to feed into when development of land
integrated with the engineering elements of a feasible SuDS parcels occurs. As part of the drive towards a strategic SuDS
design. This integrated approach between SuDS and landscaping solution, cross site (Land Parcel) integration and partnership
should remain at the forefront of the design should focus on working between developers should be encouraged wherever
open SuDS elements whilst seeking innovation to this high possible; this should be encouraged through effective design
quality development. within the SuDS masterplan. Strategic SuDS should be
appropriate to not only ground, but also wider topographic
2. Integrating SuDS throughout the Landscape Design - The conditions, as well as the natural land drainage regime.
SuDS engineering solution should not become an After Enhancements to biodiversity and water quality should also
thought with engineering fundamentals and feasibility be applied to assist in achieving the ambitions of the Water
integrated with in wider landscaping throughout the design Framework Directive.
process, from inception through completion into construction
and beyond. If suitably appropriate design of SuDS is considered 5. Designed with the end in mind - Maintenance provisions for
from the outset this should not make the inclusion of SuDS all SuDS should be considered from the inception stage of the
an additional hurdle, or burden unnecessary expenditure on design and throughout the design process, this includes (but
developers, or future owners. Well designed, innovative SuDS is not limited to) consideration of the access for maintenance,
provides opportunity to reduce the installation of below ground being suitable to the capability of plant and providing suitable,
infrastructure, enhance the wider landscaping design and add safe points of access to undertake maintenance throughout
value by improving the overall quality of the development. the scheme. Practicality, buildability (including construction
CIRIA C697 The SuDS Manual should be used as a catalyst H&S) and future public Health & Safety should be considered
for ideas and methodologies for uses of best practices throughout the design of the scheme; this will ensure that SuDS
in integrating SuDS from masterplanning phase through features remain safe, but not unsightly; for example uses of
installation, future operation and maintenance. hard barrier protection should not be used to protect SuDS
anywhere within the development.
3. SuDS appropriate to Ashford - To ensure the most appropriate
form of SuDS is used for Ashford the Ashford Borough Council Local guidance should be referred to for possible SUDS solutions.
Sustainable Drainage SPD should be used throughout the Including;
design phase to ensure a good level of appropriateness for ABC Sustainable Drainage SPD Oct 2010 and subsequent
Ashford. Furthermore, SuDS should be appropriate to the local future revisions.
and wider ground conditions; low infiltration rates are expected Water. People. Places. A guide for master planning sustainable
to be prevalent throughout the Chilmington development. drainage into developments. Prepared by the LLFA of the SE of
As such, initial design should assume that infiltration is not England.
feasible from the outset and sufficient space provisions made
throughout the development to facilitate the integration of Relevant national guidelines include
open and green SuDS. More appropriate SuDS for Ashford, The SUDS manual (C697)
as defined in the sustainable drainage SPD, will be required Planning for SuDS making it happen (C687)
in comparison to lower quality SuDS system which have low Going with the flow - SuDS infographic
overall value to a development. Four & five star appropriate Demonstrating the multiple benefits of SuDS - A business case
SuDS, as defined within the Ashford Sustainable Drainage SPD, - Literature review
are expected throughout the scheme with due consideration Site handbook for the construction of SUDS (C698)
on future maintenance and strategic integration. Innovative New Ciria build on the existing information and contain
above ground SuDS design, which add wider benefits will be information on mainte-nance costs and commuted sums for
looked upon favourable and should be used to add value to a suds installations.
development. All are currently available at www.susdrain.org .
TECHNICAL
TECHNICAL
TECHNICAL
The potential for external storage and the type of storage that
is appropriate varies with the type of dwelling, and is illustrated
below :
TECHNICAL
UTILITIES STRATEGY
Photovoltaic panels that are visually intrusive to the public realm are not acceptable
TECHNICAL
SECURED BY DESIGN
As part of Reserved Matters applications, discussions would
need to be held with the local crime prevention officer, covering
defensible space, natural surveillance and access open areas.
INCLUSIVE DESIGN
Variation in pitch angle is not acceptable. Bay windows and dormers with poorly designed GRP details will
not be acceptable.
Rainwater goods will not diagonally cross the building elevation on No unnecessary change of materials.
any given street or edge.
Timber close board addressing public realm will Avoid using different types of street lights in No block paving where white lining
not be acceptable. same space is required
Timber fencing with trellis addressing the Street furniture, lighting, signage clutter should be
public realm will not be acceptable, except as a avoided.
temporary measure to phasing boundaries.
STEP 4
8.2 Mixed use
Landscape Architects 8.3 Secondary school
8.4 Primary school
8.5 Open space
PART A: BACKGROUND
8.6 Civic space
Yes No N/A 8.7 Community buildings
Briefing with ABC & Chilmington Green
Consortium Yes No Partial N/A
9. Green infrastructure
Yes No Partial Green infrastructure compliance with Code?
1.6 Compliance Checklist completed?
Compliance with Code? Which green space(s) is applicable to parcel?
STEP 5
If 1.6 is No or Partial, has Statement of
Justification been provided?
Yes No Partial
STEP 9
7.1 Mixed use with residential Which typology matrix is applicable to parcel?
7.2 Formal urban
STEP 3
STEP 4
8.2 Mixed use
Landscape Architects 8.3 Secondary school
8.4 Primary school
8.5 Open space
PART A: BACKGROUND
8.6 Civic space
Yes No N/A 8.7 Community buildings
Briefing with ABC & Chilmington Green
Consortium Yes No Partial N/A
9. Green infrastructure
Yes No Partial Green infrastructure compliance with Code?
1.6 Compliance Checklist completed?
Compliance with Code? Which green space(s) is applicable to parcel?
STEP 5
If 1.6 is No or Partial, has Statement of
Justification been provided?
Yes No Partial
STEP 9
7.1 Mixed use with residential Which typology matrix is applicable to parcel?
7.2 Formal urban
STEP 3