Start-up time (upto full load), and loading capabilities for the complete unit
(boiler, turbine and generator together) for cold start, warm start and hot start
conditions as agreed shall be demonstrated, ensuring that the various turbine
operational parameters like vibration, absolute and differential expansion,
eccentricity and steam metal temperature mismatch etc. are within design
limits.
5.4.3 Rate of change of load and sudden load change withstand capability
i) Coal fineness Not less than 70% through 200 mesh and not less than
98% through 50 mesh screen.
ii) Test coal Any available coal from the specified range with coal
sampling done as per ISO 9931.
Life of mill wear parts, in hours of operation, for the entire range of coal
characteristics specified shall be demonstrated.
15