Actual Work Critical Remaining Work Summary Page 1 of 3 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Classic Schedule Layout 22-Aug-17 20:18
D'NEST PASIR RIS
Activity ID Activity Name Original Remaining Schedule % Start Finish 2013 2014 2015 2016 2017
Duration Duration Complete J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
A2550 Block 8 (BLK 141) 420 420 100% 22-Sep-14 29-Apr-16 Block 8 (BLK 141)
A2570 Mechanical and Electrical (Block 8) 420 420 100% 22-Sep-14 29-Apr-16 Mechanical and Electrical (Block 8)
A2580 ACMV, Sanitary, Plumbing & Gas 410 410 100% 22-Sep-14 15-Apr-16 ACMV, Sanitary, Plumbing & Gas
A2590 Electrical & Security 420 420 100% 22-Sep-14 29-Apr-16 Electrical & Security
A1450 Block 6 (BLK 137) 43 43 100% 08-Oct-14 05-Dec-14 Block 6 (BLK 137)
A2440 Soft Landscape Works 294 294 100% 17-Oct-14 02-Dec-15 Soft Landscape Works
A1810 Mechanical and Electrical (Block 7) 405 405 100% 20-Oct-14 06-May-16 Mechanical and Electrical (Block 7)
A1820 ACMV, Sanitary, Plumbing & Gas 403 403 100% 20-Oct-14 04-May-16 ACMV, Sanitary, Plumbing & Gas
A1830 Electrical & Security 405 405 100% 20-Oct-14 06-May-16 Electrical & Security
A1850 Block 12 (BLK 149) 405 405 100% 20-Oct-14 06-May-16 Block 12 (BLK 149)
A1890 Mechanical and Electrical (Block 12) 405 405 100% 20-Oct-14 06-May-16 Mechanical and Electrical (Block 12)
A1900 ACMV, Sanitary, Plumbing & Gas 403 403 100% 20-Oct-14 04-May-16 ACMV, Sanitary, Plumbing & Gas
A1910 Electrical & Security 405 405 100% 20-Oct-14 06-May-16 Electrical & Security
A1950 Mechanical and Electrical (Block 6) 405 405 100% 20-Oct-14 06-May-16 Mechanical and Electrical (Block 6)
A1960 ACMV, Sanitary, Plumbing & Gas 403 403 100% 20-Oct-14 04-May-16 ACMV, Sanitary, Plumbing & Gas
A1970 Electrical & Security 405 405 100% 20-Oct-14 06-May-16 Electrical & Security
A2610 Block 7 (BLK 139) 405 405 100% 20-Oct-14 06-May-16 Block 7 (BLK 139)
A1620 Structure RC Works (Block11) 199 199 100% 21-Oct-14 24-Jul-15 Structure RC Works (Block11)
A1680 Fire Protection 398 398 100% 21-Oct-14 28-Apr-16 Fire Protection
A1700 Structure RC Works (Block 9) 199 199 100% 21-Oct-14 24-Jul-15 Structure RC Works (Block 9)
A1760 Fire Protection 398 398 100% 21-Oct-14 28-Apr-16 Fire Protection
A1780 Structure RC Works (Block 8) 199 199 100% 21-Oct-14 24-Jul-15 Structure RC Works (Block 8)
A2540 Fire Protection 398 398 100% 21-Oct-14 28-Apr-16 Fire Protection
A2600 Fire Protection 398 398 100% 21-Oct-14 28-Apr-16 Fire Protection
A1460 Substructure PHASE 2 64 64 100% 27-Oct-14 22-Jan-15 Substructure PHASE 2
A1470 Block 5 (BLK 135) 30 30 100% 27-Oct-14 05-Dec-14 Block 5 (BLK 135)
A1480 Block 4 (BLK 133) 34 34 100% 27-Oct-14 11-Dec-14 Block 4 (BLK 133)
A1990 Superstructure - PHASE 2 510 510 100% 07-Nov-14 20-Oct-16 Superstructure - PHASE 2
A2000 Block 5 (BLK 135) 415 415 100% 07-Nov-14 09-Jun-16 Block 5 (BLK 135)
A2650 Mechanical and Electrical (Block 5) 415 415 100% 07-Nov-14 09-Jun-16 Mechanical and Electrical (Block 5)
A2660 ACMV, Sanitary, Plumbing & Gas 411 411 100% 07-Nov-14 03-Jun-16 ACMV, Sanitary, Plumbing & Gas
A2670 Electrical & Security 415 415 100% 07-Nov-14 09-Jun-16 Electrical & Security
A2690 Block 4 (BLK 133) 415 415 100% 07-Nov-14 09-Jun-16 Block 4 (BLK 133)
A2730 Mechanical and Electrical (Block 4) 415 415 100% 07-Nov-14 09-Jun-16 Mechanical and Electrical (Block 4)
A2740 ACMV, Sanitary, Plumbing & Gas 411 411 100% 07-Nov-14 03-Jun-16 ACMV, Sanitary, Plumbing & Gas
A2750 Electrical & Security 415 415 100% 07-Nov-14 09-Jun-16 Electrical & Security
A1550 Architectural (Block 10) 327 327 100% 11-Nov-14 10-Feb-16 Architectural (Block 10)
A1840 Fire Protection 375 375 100% 19-Nov-14 26-Apr-16 Fire Protection
A1860 Structure RC Works (Block 12) 199 199 100% 19-Nov-14 24-Aug-15 Structure RC Works (Block 12)
A1920 Fire Protection 375 375 100% 19-Nov-14 26-Apr-16 Fire Protection
A2620 Structure RC Works (Block 7) 199 199 100% 19-Nov-14 24-Aug-15 Structure RC Works (Block 7)
A1980 Fire Protection 367 367 100% 01-Dec-14 26-Apr-16 Fire Protection
A2010 Structure RC Works (Block 5) 185 185 100% 08-Dec-14 21-Aug-15 Structure RC Works (Block 5)
A2680 Fire Protection 375 375 100% 08-Dec-14 13-May-16 Fire Protection
A2700 Structure RC Works (Block 4) 185 185 100% 08-Dec-14 21-Aug-15 Structure RC Works (Block 4)
A2760 Fire Protection 375 375 100% 08-Dec-14 13-May-16 Fire Protection
A1490 Block 3 (BLK 131) 31 31 100% 11-Dec-14 22-Jan-15 Block 3 (BLK 131)
A1500 Block 2 (BLK 129) 31 31 100% 11-Dec-14 22-Jan-15 Block 2 (BLK 129)
A1510 Block 1 (BLK 127) 31 31 100% 11-Dec-14 22-Jan-15 Block 1 (BLK 127)
A2530 Unit Mock-Up 202 202 100% 18-Dec-14 25-Sep-15 Unit Mock-Up
A2450 Hardscape, External Works & Timber Deck 92 92 100% 19-Dec-14 27-Apr-15 Hardscape, External Works & Timber Deck
A2040 Mechanical and Electrical (Block 3) 383 383 100% 23-Dec-14 09-Jun-16 Mechanical and Electrical (Block 3)
A2050 ACMV, Sanitary, Plumbing & Gas 378 378 100% 23-Dec-14 02-Jun-16 ACMV, Sanitary, Plumbing & Gas
A2060 Electrical & Security 383 383 100% 23-Dec-14 09-Jun-16 Electrical & Security
A2080 Block 2 (BLK 129) 383 383 100% 23-Dec-14 09-Jun-16 Block 2 (BLK 129)
A2110 Mechanical and Electrical (Block 2) 383 383 100% 23-Dec-14 09-Jun-16 Mechanical and Electrical (Block 2)
A2120 ACMV, Sanitary, Plumbing & Gas 378 378 100% 23-Dec-14 02-Jun-16 ACMV, Sanitary, Plumbing & Gas
A2130 Electrical & Security 383 383 100% 23-Dec-14 09-Jun-16 Electrical & Security
A2150 Block 1 (BLK 127) 478 478 100% 23-Dec-14 20-Oct-16 Block 1 (BLK 127)
A2180 Mechanical and Electrical (Block 1) 383 383 100% 23-Dec-14 09-Jun-16 Mechanical and Electrical (Block 1)
A2190 ACMV, Sanitary, Plumbing & Gas 378 378 100% 23-Dec-14 02-Jun-16 ACMV, Sanitary, Plumbing & Gas
A2200 Electrical & Security 383 383 100% 23-Dec-14 09-Jun-16 Electrical & Security
A2770 Block 3 (BLK 131) 383 383 100% 23-Dec-14 09-Jun-16 Block 3 (BLK 131)
A1630 Architectural (Block 11) 326 326 100% 29-Dec-14 28-Mar-16 Architectural (Block 11)
Actual Work Critical Remaining Work Summary Page 2 of 3 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Classic Schedule Layout 22-Aug-17 20:18
D'NEST PASIR RIS
Activity ID Activity Name Original Remaining Schedule % Start Finish 2013 2014 2015 2016 2017
Duration Duration Complete J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
A1710 Architectural (Block 9) 326 326 100% 29-Dec-14 28-Mar-16 Architectural (Block 9)
A1790 Architectural (Block 8) 326 326 100% 29-Dec-14 28-Mar-16 Architectural (Block 8)
A2070 Fire Protection 341 341 100% 23-Jan-15 13-May-16 Fire Protection
A2090 Structure RC Works (Block 2) 185 185 100% 23-Jan-15 08-Oct-15 Structure RC Works (Block 2)
A2140 Fire Protection 341 341 100% 23-Jan-15 13-May-16 Fire Protection
A2160 Structure RC Works (Block 1) 185 185 100% 23-Jan-15 08-Oct-15 Structure RC Works (Block 1)
A2210 Fire Protection 341 341 100% 23-Jan-15 13-May-16 Fire Protection
A2220 Other M&E Services & Utility Room 366 366 100% 23-Jan-15 17-Jun-16 Other M&E Services & Utility Room
A2240 ESS 182 182 100% 23-Jan-15 05-Oct-15 ESS
A2780 Structure RC Works (Block 3) 185 185 100% 23-Jan-15 08-Oct-15 Structure RC Works (Block 3)
A1870 Architectural (Block 12) 315 315 100% 26-Jan-15 08-Apr-16 Architectural (Block 12)
A2630 Architectural (Block 7) 315 315 100% 26-Jan-15 08-Apr-16 Architectural (Block 7)
A1930 Architectural (Block 6) 303 303 100% 12-Feb-15 11-Apr-16 Architectural (Block 6)
A2020 Architectural (Block 5) 327 327 100% 12-Feb-15 13-May-16 Architectural (Block 5)
A2710 Architectural (Block 4) 327 327 100% 12-Feb-15 13-May-16 Architectural (Block 4)
A2460 Gondola (BMU) 95 95 100% 09-Mar-15 17-Jul-15 Gondola (BMU)
A2100 Architectural (Block 2) 293 293 100% 01-Apr-15 13-May-16 Architectural (Block 2)
A2790 Architectural (Block 3) 293 293 100% 01-Apr-15 13-May-16 Architectural (Block 3)
A2170 Architectural (Block 1) 393 393 100% 21-Apr-15 20-Oct-16 Architectural (Block 1)
A2250 Fire Hydrant 164 164 100% 27-Apr-15 10-Dec-15 Fire Hydrant
A2280 E-Deck and External Works 350 350 100% 27-Apr-15 26-Aug-16 E-Deck and External Works
A2290 Swimming Pool Works 295 295 100% 27-Apr-15 10-Jun-16 Swimming Pool Works
A2470 Aqua Gym 70 70 100% 27-Apr-15 31-Jul-15 Aqua Gym
A2490 Clubhouse 156 156 100% 09-Jun-15 12-Jan-16 Clubhouse
A2480 Boundary Wall 129 129 100% 23-Jun-15 18-Dec-15 Boundary Wall
A2500 Audio/Video & Fitness Equipment (Clubhouse) 95 95 100% 30-Jun-15 09-Nov-15 Audio/Video & Fitness Equipment (Clubhouse)
A2230 Lift Installation 235 235 100% 27-Jul-15 17-Jun-16 Lift Installation
A1140 Sculptures 87 87 100% 03-Aug-15 01-Dec-15 Sculptures
A2300 Water Features 241 241 100% 03-Aug-15 04-Jul-16 Water Features
A2310 Irrigation, Planterboxes & Stone Finishes 233 233 100% 10-Aug-15 29-Jun-16 Irrigation, Planterboxes & Stone Finishes
A1560 Common Area & Roof (Block 10) 113 113 100% 07-Sep-15 10-Feb-16 Common Area & Roof (Block 10)
A1150 New Activity 68 68 100% 18-Sep-15 22-Dec-15 New Activity
A1640 Common Area & Roof (Block 11) 113 113 100% 22-Oct-15 28-Mar-16 Common Area & Roof (Block 11)
A1720 Common Area & Roof (Block 9) 113 113 100% 22-Oct-15 28-Mar-16 Common Area & Roof (Block 9)
A2560 Common Area & Roof (Block 8) 113 113 100% 22-Oct-15 28-Mar-16 Common Area & Roof (Block 8)
A2260 MDF Room 105 105 100% 26-Oct-15 18-Mar-16 MDF Room
A2270 Genset Room 114 114 100% 26-Oct-15 31-Mar-16 Genset Room
A1800 Common Area & Roof (Block 7) 113 113 100% 04-Nov-15 08-Apr-16 Common Area & Roof (Block 7)
A1880 Common Area & Roof (Block 12) 113 113 100% 04-Nov-15 08-Apr-16 Common Area & Roof (Block 12)
A1940 Common Area & Roof (Block 6) 113 113 100% 09-Nov-15 13-Apr-16 Common Area & Roof (Block 6)
A1160 Outdoor and Pool Deck Furniture 105 105 100% 11-Nov-15 05-Apr-16 Outdoor and Pool Deck Furniture
A2030 Common Area & Roof (Block 3) 109 109 100% 08-Dec-15 06-May-16 Common Area & Roof (Block 3)
A2640 Common Area & Roof (Block 5) 109 109 100% 08-Dec-15 06-May-16 Common Area & Roof (Block 5)
A2720 Common Area & Roof (Block 4) 109 109 100% 08-Dec-15 06-May-16 Common Area & Roof (Block 4)
A2340 Planting 149 149 100% 04-Jan-16 28-Jul-16 Planting
A2320 Club House 2 ? Gathering Nest 153 153 100% 12-Jan-16 11-Aug-16 Club House 2 ? Gathering Nest
A2390 Drainage Upgrading Works 182 182 100% 05-Feb-16 17-Oct-16 Drainage Upgrading Works
A2370 Quality Mark 122 122 100% 11-Feb-16 29-Jul-16 Quality Mark
A2400 Final Test-Commissioning & Hand Over 249 249 100% 21-Mar-16 02-Mar-17 Final Test-
A2410 Phase 1 (Block 6-12) 151 151 100% 21-Mar-16 17-Oct-16 Phase 1 (Block 6-12)
A2330 Club House 1 ? Recreation Nest 95 95 100% 18-Apr-16 26-Aug-16 Club House 1 ? Recreation Nest
A2420 Phase 2 (Block 1-5) 160 160 100% 22-Jul-16 02-Mar-17 Phase 2 (
A2800 Final Clean-Up 49 49 100% 26-Dec-16 02-Mar-17 Final Clea
A2810 Project Completion 41 41 100% 05-Jan-17 02-Mar-17 Project Co
Actual Work Critical Remaining Work Summary Page 3 of 3 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation