Bored Piling
Bored Piling
WORK PROCEDURE
PROJECT: Ref No. FOUN/04
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS Dec 2012
SUBJECT: BY:
QA/QC ENGINEER
BORED PILING APPROVED BY:
QEHS MANAGER
ACTION VERIFY
1. SCOPE
2. PROCEDURE
.1 Method Statement:
A method statement shall be submitted by the piling Sub- Project Method
contractor for approval which shall include: Manager Statement
i) Construction procedure.
ii) Pile design with calculations.
iii) Testing procedure.
iv) Documentation to be maintained during the execution
of work.
v) Mix design for concrete.
vi) Specification for reinforcement steel and bentonite
clay.
vii) Any other information required by the specification.
.2 Construction Programme:
The sub-contractor shall submit a programme for approval Sub- Approved
based on the Contract Programme. The subcontractor shall contractor Construction
also indicate the mobilisation time of plant, equipment, Programme
materials and work force.
Project Approval
.3 Piling Sequence: Manager
Approval of piling sequence will be given prior to
commencement of piling by the Subcontractor.
.4 Setting-Out: Subcon/
FCC Field Book
HEE will execute pre-piling setting out and offer for cross- Surveyor
checking by Subcontractors Surveyor and Consultants
Representative.
WORK PROCEDURE
.5 Source Certificates:
.7 Testing of Piles:
Pile testing
The Subcontractor shall carry out a load test and integrity test Subcon. record
as specified in the Contract.
.8 Inspection of Work/Checksheet:
.9 Non-Conformity:
Non-
Non-conforming workmanship shall be notified to the Conformity
Subcontractor as Appendix 7/3/6/A and corrective action QA/QC Report
taken in accordance with good working practice and
Consultants approval.
PROJECT: SITE NO.:
SUBCONTRACTOR: FATAYERJI
Checke
STAGE ITEM d DATE
by