Professional Documents
Culture Documents
Alb Ornamentacion
Alb Ornamentacion
in Landscape
While the contents of this publication are
believed to be accurate and complete, the
information given is intended for general
guidance and does not replace the
services of professional advisers on
specific projects. Local or state
regulations may require variation from
thepractices and recommendations
contained in this publication. Think
Brick Australia disclaims any liability
whatsoever regarding the contents of
this publication.
5 Brickwork basics
12 Paving
20 Architectural furniture
4 / Brickwork in Landscape
2. Brickwork Basics
2.1 Preparation and 2.2 Setting out footings 2.3 Mortar and bricklaying
planning and brickwork Care should be taken when mixing
Time spent on preparation and Unless a very imperfect finish is mortar to ensure that the correct
planning is an investment that will acceptable, the footings and proportions are achieved and that
pay dividends during the brickwork should not be foreign matter does not
construction stage and in the constructed without careful contaminate the mix. The cement
outcome of the project. Particular preparation. The use of profile and lime should be kept in good
attention should be given to the boards and string lines is a simple condition under cover and not in
characteristics of the foundation method of controlling the accuracy contact with the ground.
soil, the degree of exposure to of the structure and is well suited
wind, sun and rain, and the to those with a limited experience The sand should be carefully
natural drainage of the site. Many in bricklaying. selected to be free from excessive
otherwise good brick structures clay (maximum 10% -75 micron)
have been spoiled by a lack of Profile boards consist of stakes and earthy matter and the
attention to such considerations, driven into the ground with presence of soluble salts. The
particularly the adequacy of the crossbars fixed to them at a known mortar ingredients should be
footings. (If a qualified tradesman height. Nails are driven into the measured by volume in a
is not carrying out the top surface of the crossbars convenient container like a
construction of footings and representing the faces of the bucket and if mixing is to be done
brickwork it is advisable to seek brickwork and footings. String is manually, they should be
advice from a qualified person stretched between the nails and a thoroughly mixed prior to the
regarding the design of the spirit level is then employed to addition of water. The mortar
footing.) locate the position and height of should be used in a condition as
the structural elements. The base plastic as is practicable.
The problems associated with of footings should be set at a depth
footings usually result from heave removed from seasonal moisture Most modern bricks are low in
or shrinkage caused by moisture changes, generally not less than suction and need not be wetted
reactive soils or the activity of tree 450 mm below natural grade level. before laying. Where brick suction
roots. Soils that produce cracking is unusually high, as will be
in brickwork are the dry clay Once the required finished height indicated by the mortar stiffening
types which exist in nature in a of the brickwork has been decided, too quickly for easy bricklaying,
condition of moisture deficiency. the height of the top surface of the pre-wetting of the bricks can be
When they gain or lose water they footing can be calculated allowing helpful. As the bricks are laid the
change their volume and fairly for full courses of brickwork. If the excess mortar should be struck
predictable seasonal changes can foundation slopes, the footing can from both sides of the brickwork
be observed. Trees that draw large be stepped. Each step should be throughout the bricklaying
quantities of moisture can cause equal to a full number of brick process.
localised downward foundation courses. All excavations should be
movement and it is therefore clean and contain no loose earth or Never move a brick after it has
advisable to determine the free water and steel reinforcement been in position for more than a
relevant characteristics of their should be securely fixed prior to few seconds as this will destroy the
root activity if trees are to be in pouring of concrete and have a bond. New brickwork should be
the proximity of brickwork. minimum cover of 65 mm. protected from the rain and sun
until it is 24 hours old.
Brickwork in Landscape / 5
2.4 Basic footing Figure 1. Set out
String lines
construction and
Outside nails for
bricklaying procedure trenches/footings
First brick
Second brick
6 / Brickwork in Landscape
Step 4 Build up the corners first Figure 4. Building up corner brickwork
by laying five bricks at each wall
end. Level them and check the per-
pends for distance. Build the bricks Rake of brickwork courses
up in courses, each course being
racked back as illustrated.
Corner
Continually check the perpends, brickwork
the rake and the plumb of the built up
brickwork. When the ends are
found to be true, stretch the string
line between the corners using
Corner
corner blocks and complete a full block
course at a time. The string should
not be too long or slack otherwise
it will sag. An intermediate section
can be built up to which can be
attached a plate to support the
String line
line (called a tingle plate). The
operation is repeated until the
required height is reached.
Brickwork in Landscape / 7
3. Walls and Fences
8 / Brickwork in Landscape
1. The coping unit should shed Figure 7. Design and construction considerations
rainwater clear of the wall by at for staggered brick fence
least 12 mm.
1 2 3
2. A damp-proof course should be
provided beneath the coping unit
or last course of brickwork.
Brickwork in Landscape / 9
Table 2. Specification of staggered walls
Spacing of
returns (mm) 2200 2700 4700 5700
Thickness of
wall (mm) 90 110 190 230
590 290
Wall height 470
900 mm
230
350
390
Wall height N.A. 710
1500 mm
470
490
Wall height N.A. N.A.
1800 mm
470
Wall height N.A. N.A. N.A.
2100 mm
10 / Brickwork in Landscape
3.2 Low earth retaining 3.2.3 Construction
walls The base of the footing must be at a
depth free from seasonal moisture
3.2.1 Introduction changes and must provide a firm
Low earth retaining walls are a foundation with a minimum
common requirement in landscape bearing capacity of 75 kPa. All
architecture. They are used to form excavations should be clean and
the edges to paved areas, retain contain no loose earth or free
earth at driveways, to form terraces water.
and maintain cuttings. All retaining
walls over 600 mm in height should Unless otherwise specified by the
be designed by a qualified engineer. designer, the reinforcing mesh
should have a minimum cover of
3.2.2 General guidelines 65 mm in the footings and 20 mm
In general, small retaining walls from the internal face of the
should be designed and constructed brickwork. It should be accurately
on the following basis. positioned, straight and be free of
rust or other contamination that
i. The surface of the back fill is may reduce the bond of the
horizontal. concrete or grout.
ii. The soils retained are non- The brickwork must be accurately
cohesive and not of the laid using a string line and be
moisture reactive type. plumbed level with all mortar joints
completely filled. Joints should not
iii. Brickwork and reinforcement
be greater than 13 mm in thickness.
complies with AS3700-2001,
The Masonry Code. The cavity must be kept clear of
mortar droppings and mortar
iv. The back of the wall must be
squeezed out into the inside should
rendered or covered with
be cut off flush and removed as the
moisture penetration barrier,
brickwork proceeds.
weep holes should be provided
at approximately 1200 mm The wall should be provided with a
centres at the base of the wall. coping unit beneath which a damp
proof course is placed. The coping
v. The back of the wall must be
unit (or the damp proof course)
lined with a minimum
should shed rainwater clear of the
thickness of 300 mm of porous
wall face by not less than 12 mm.
backfill.
The earth in front of the base of the
vi. Only bricks classified Exposure
wall should be protected to prevent
Grade that are resistant to salt
water accumulating there and
attack should be used,
softening the foundations
together with an M4 mortar.
Brickwork in Landscape / 11
4. Paving
Height
Base Base
The area of a triangle = half the
width of the base x height. For
example: a triangle with a base 10
metres wide and a height of 8
metres = 5 x 8 metres = 40 m2.
12 / Brickwork in Landscape
Example 2: As example 1 but with Example 3: An irregular area, Example 4: Another irregular area,
an irregular pool treated as two triangles treated as arectangle and two
triangles
11 m
m
3.8 Triangle 1
Height
ht
1.7 m
g
ei Base 6.5 m
H
Height
4m Triangle 1 1.5 m
m
Ba
6m 8
9m 4.
se
Base 5.9 m
t
7.5
gh
ei
Height 5.9 m
H Triangle 2
Triangle 2 Rectangular
Measure the length and width of the Area of triangle 1 = (half width of the
base) x height = (7.5 divided by 2) x 3.8 Length 5.0 m
area to be paved. Measure the
length of the pool and the two = 3.75 x 3.8 = 14.3 m2
widths shown.
Area of triangle 2 = (7.5 divided by 2) Area of rectangle = length x width
x 4.8 = 3.75 x 4.8 = 18.0 m2 = 5.0 x 5.9 = 29.5 m2
Average width of pool = (widest +
narrowest) divided by 2 = (6 + 4)
Area to be paved = 14.3 + 18.0 Area of triangle 1 = (half width of the
divided by 2 = 10 divided by 2 = 5
= 32.3 m2 base) x height = (6.5 divided by 2) x 1.7
metres.
= 3.25 x 1.7 = 5.5 m2
Approximate area of pool = length x
Area of triangle 2 = (half width of the
average width = 9 x 5 = 45 m2
base) x height = (5.9 divided by 2)
x 1.5 = 2.95 x 1.5 = 4.4 m2
Area to be paved = Total area = Area
pool = 99 45 =54 m2
Area to be paved = rectangle
+ triangle 1 + triangle 2 = 29.5 + 5.5
Note this calculation is only
+ 4.4 =39.4 m2
approximate allow extra pavers.
Brickwork in Landscape / 13
4.2 Laying clay pavers 4.2.3 Drainage is important
Rain water must flow off the
4.2.1 Introduction
finished pavement and away from
The method described here is
buildings. For this reason, the
suitable for clay brick paving
pavement must not be perfectly flat,
around the house, such as paths,
but should slope a little (about 15 mm
patios and driveways on a gentle
per metre). If the pavement is against
slope. However it may not be
the side of the house, the pavers
suitable for driveways on a steep
must be below the damp-proof
slope or for commercial paving.
course. Never bridge damp-proof
courses or air vents.
4.2.2 Tools and equipment
You will need these tools:
Figure 8. Typical drainage details
tape measure
barrow
Existing building
spade
garden rake with metal prongs
Damp proof course
ball of string
line level Run-off channelled to drainage point
14 / Brickwork in Landscape
4.2.4 Base construction The next step is to level the
For vehicular traffic, high rainfall or bedding surface. This is called
poorly drained soil, this is how your screeding. It is advisable to
finished pavement should look in compact the sand using a
cross section. Excavate the soil to a vibrating plate compactor prior
reasonably constant depth. to laying. Set up a stringline along
one edge. Place a line level on the
Completely remove all weeds and stringline to ensure it slopes in the
grasses. For pedestrian traffic on well desired direction. Bed pavers to
drained soil the bedding sand will be the correct finished surface level
about 30 mm thick after being at intervals along the stringline.
compacted. Remove the pavers to reveal the
correct level of the bedding sand.
Compacting is the process of packing
the loose layers of the pavement. This Repeat this process to create
gives a firm base which will 'stepping stones' (or reference
support heavy loads. Failure to levels) over the area.
properly compact the bedding sand
and roadbase (where used) may Use the screeding bar to level
cause the pavement to subside. between the 'stepping stones' and
create parallel tracks. Place screeding
The roadbase may need to be rails in two tracks and screed
compacted in layers as most between the tracks. Repeat this over
compactors are not powerful enough the whole area. If you are using
to compact the full thickness. timber or water pipe for screeding
rails, dont forget to fill in the ruts in
For small areas make a hand the sand left by the screeding rails.
compactor as discussed previously.
Keep the head small to ensure
Figure 9. Typical cross-section
maximum impact and overlap to
for pedestrian pavement on
compact the area thoroughly.
well-drained soil
30 mm Washed
concrete sand
30 mm Washed
concrete sand
100 mm roadbase
Brickwork in Landscape / 15
Figure 11. Use of stringlines Figure 12. Use of reference levels 4.2.5 Laying pavers
Clay pavers, being made from
natural minerals, vary slightly in size.
If you do not allow for this size varia-
tion, the pattern of the pavement
may not stay in line.
The best way to regulate the
pattern is to use a grid of
stringlines spaced at exact
intervals. It sounds complicated, but
it's really very simple and will save
work in the long run.
rs
ve
0 pa
2
of
idth
w
re
easu
M
16 / Brickwork in Landscape
Figure 15. Laying header course
Stringline
2.5 mm joint
Key pavers
The header course is the row of As appropriate, position other Figure 16. Determining
pavers along the edge of the stringlines around the perimeter. squareness
pavement. They give it a strong, neat Use the ratio of 3:4:5 to determine
edge. The first header course may be squareness.
Example
placed along an existing straight
3m:4m:5m
edge such as a concrete path or the Set out key pavers on other
1.5 m : 2 m : 2.5 m
wall of the building. edges at grid spacing intervals as 3 feet : 4 feet : 5 feet
calculated from average paver 5u
nit
If there is no straight edge, set up a dimensions. s
3 units
Brickwork in Landscape / 17
Position the stringline from Figure 17. Stringline grid
opposing key pavers (that is every
eighth paver). Repeat this over
the whole area.
8
6
7
4 12
5 15
2 11
3 14
Half 10
1 13
Half 9 Half
18 / Brickwork in Landscape
4.2.6 Cutting, sanding and edge
restraints
Most paving patterns require some
cutting. Most clay pavers are very
hard and can only be cut cleanly with
a diamond saw.
45
Brickwork in Landscape / 19
5. Architectural furniture
5.1 Introduction
This section provides drawings
of a number of useful brick
constructions for the garden
setting. Specifications,
dimensions and materials
quantities are also included.
B B
20 / Brickwork in Landscape
5.2 Brick barbeque Quantities
Work top
Fuel store
Spark arrestor
The construction may be discontinued at this
point if a chimney is not required, in which
case there will be a saving of 70 bricks
75 x 100 mm arch bar 800 mm
in length. The arch bar should
be oiled before it is installed
and there should be an
Fibre cement sheet allowance at each end for
3 mm thermal expansion.
Grill
Hot plate
Grate
Ash Pit
Brickwork in Landscape / 21
5.3 Fly-proof compost bin
Compost is formed from decayed A 12 mm layer of 1:3 cement:sand mortar should
vegetable matter and is of be placed on the internal ledge and be covered
considerable benefit to the garden. with a plastic film. The fibre cement sheet can
Unfortunately it is in decaying then be pressed into position to form a good seal.
matter that flies breed and therefore
every gardener should have a fly
proof method for the disposing of
biodegradable waste. Lawn cuttings
in particular are a major source
of flies.
Notes:
22 / Brickwork in Landscape
Figure 22. Plan and elevation of
typical brick compost bin
Lid
Recessed course to
provide support to
fibre cement sheet lid
Side elevation
Compost-making procedure
Brickwork in Landscape / 23
5.4 Garden steps Steps that are much steeper than 37 Step 3 Accurately place the first and
degrees are difficult to climb. Long last row of riser bricks in position
5.4.1 Design considerations checking that they are true and level.
straight flights of steps should be
Changes in ground level occur in Use the string level to complete the
avoided and consideration should be
most gardens and steps can be risers of the remaining steps as in
given as to whether or not a handrail
used to answer both functional step 2, repeating the procedure
is required.
needs and also to provide dramatic where there are two bricks to the
emphasis. Steps that are easy to 5.4.2 Construction riser. The spaces behind the risers
use have a mathematical Step 1 Roughly cut the foundations should be filled with screening to
relationship between the riser to the profile of riser and going with support the goings, but the
(tread height) and the going the cut moved along and down by going-bricks should be laid upon a
(tread depth). one complete step. The steps should bed of mortar. Use a mortar not
not be built upon loam or fine weaker than 1:0.5:4.5 cement:lime:
Shallow risers should be sand, and ensure that all of the joints
non- cohesive soils or where water is
accompanied by a deep going and are filled and tooled to a smooth
expected to collect. In these instances
large risers should have a short finish. The going should slope forward
the steps should be built upon a
going. slightly (about 1 mm in 100 mm) to
continuous reinforced concrete base
to eliminate the risk of slippage. prevent rainwater collecting there.
The formula used to determine the
steps in Figure 23 is: twice the riser Note: The method shown in Design 5
Step 2 The lowest step is begun first
(height) + the going (width) = 680 is suitable in many situations where
and should be used as a datum point.
mm. The gradients of Designs 1 to an informal effect is required of only a
Place the first row of bricks on a bed
4 are: minor gradient. This technique is
of mortar and tap it into position
1. 1 in 5.5 (10) suited to curved step arrangements.
ensuring that it is at the required
2. 1 in 3.7 (15 The space behind the riser bricks
height. Position the corresponding
3. 1 in 2.0 (25) should be filled with screenings or
brick of the last step next and stretch
4. 1 in 1.3 (37) river pebbles
a string line between the two to help
in achieving an even gradient.
Complete all of the first courses of Figure 23. Five typical step designs
bricks before proceeding to the next
1 in 1.3 (37)
course.
37
1
Brick 1 in 5.5 (10)
Going on flat 10
480
Riser 86
4 440
1 in 3.7 (15) Screenings
2 206
Brick 15
on edge
440 Brick on edge
Any desired gradient
Brick on flat
Riser 120
1 in 2.0 (25)
Mortar or
3 concrete bed
25
Brick
on flat 5
360
Screenings or
Riser 172 river pebbles
24 / Brickwork in Landscape
5.5 Seat and planter box
Figure 24. Plan view of typical
planter box
25 mm
Equal Equal
710 mm
Brickwork in Landscape / 25
5.6 Changing ground levels
around trees
Tree roots require air, water and
minerals and it is necessary to
maintain their supply when the
depth of soil over these roots
is either increased or decreased.
The two walls shown here rest on
300 x 300 mm concrete footings
reinforced top and bottom
with three R10 bars
or equivalent.
Figure 26.
Raising ground
level around tree
Fill
Agricultural drainpipes
26 / Brickwork in Landscape
In Figure 26, earth is retained by a
circular twin leaf wall. The well is
drained by 100 mm diameter
agricultural pipes (three to six,
depending upon rainfall). Vertical
pipes are provided beneath the edge
of the tree growth for additional air
and water supply.
Brickwork in Landscape / 27
6. Trees, creepers and brickwork
6.1 Effects of tree roots on In clay soils the trees tend to be 6.2 Remedial action
brickwork shallow rooted because moisture
If cracks have developed in
rests at a higher level and because
An important consideration in the brickwork at the end of summer and
root penetration is impeded by the
suitability of trees when they are there are large or fast growing trees
dense nature of the clay. In a drought
planted close to brickwork is the nearby, then it is probable that the
period many trees have the ability to
possibility that their root systems trees are contributing to the damage
rapidly send out lateral roots in
might cause structural damage. and should therefore be removed.
search of moisture, and these can
This problem has been highlighted in The damage should be left
intrude upon the foundations of
recent years as the younger unpatched for 12 months to allow
building structures.
generations moving into the older the soil to stabilize and the cracks to
inner city suburbs have tended to Some of the more common trees close up. Too early action may cause
plant rapid growing native trees too that have caused trouble include cracking to occur elsewhere.
close to walls and buildings. blue gums, mahogany gums,
If the cracking is only minor and the
lemon-scented gums, poplars, elms
Damage occurs in structures built trees are mature or the drought has
and willows. All of these trees are
on clay soil when during times of been unusually severe, then
rapid growers, gross feeders and
drought the rapid growing trees constant watering of the trees
extract a lot of moisture from
extract moisture from the clay on may prevent the damage from
the soil.
which the structures footings rest. worsening. Excessive watering
When the clay dries out it shrinks To prevent damage occurring in the should be avoided as this could
causing localized downward future, any trees that are planted weaken the soil or cause it to swell.
movements, and cracks may appear should be carefully chosen, bearing
in the brickwork and internal linings If the walls are badly cracked and
in mind the nature of the soil, the
(see section 2.1). The phenomenon of have moved out of the vertical,
type and strength of footing and the
trees causing damage to brickwork underpinning may be required.
distance between the relevant trees
is not limited to old buildings or and the structure. In clay areas the
native trees. rapid growing and gross feeding
trees such as the Tasmanian blue
Sandy loam soils hold little moisture gum (Eucalyptus globulus) should be
in their upper levels and hence tree well separated from structures.
roots need to penetrate deeply to Far more suitable would be the
obtain sufficient moisture. Footings smaller species of eucalypts such as
for structures are usually quite close the swamp mallee (Eucalyptus
to the surface and are not often spathulata). This type of tree has a
affected by moisture removed from low transpiration rate due to the
deeper levels. trees smallness and lightness of
foliage. As an approximate rule-of-
thumb, trees planted on clay soil
should be no closer to a building
structure than half of the trees
mature (ultimate) height.
28 / Brickwork in Landscape
6.3 Creepers and brickwork
Climbing plants attach themselves
to supports in a variety of ways.
The types that are most suitable in
conjunction with brickwork are the
self-clinging types that use suckers
or hooked prickles to adhere to a
surface.
Brickwork in Landscape / 29