Professional Documents
Culture Documents
Test Procedure Batching Plant Certification R1
Test Procedure Batching Plant Certification R1
Owner :
PT. Energi Bayu Jeneponto
Contractor :
Project Title :
TOLO I WIND FARM PROJECT
Document No. :
Manufacture No. :
Purpose :
ISSUED FOR APPROVAL
1 General Description
This document describes each of the factors involved in the preparation of readymixed concrete for
Wind Farm Project the Tolo 1 field in Jeneponto, South Sulawesi, Indonesia. The present procedure
is to define chronologically the steps which must be followed in order to start up the batch plant
and to certify the concretes may be used. Batching plant using dry mix. A Dry mix Concrete Plants,
also known as Transit Mix Plants, weighs sand, gravel and cement in weigh batchers via digital or
manual scales . All the ingredients then are discharged into a chute which discharges into a truck.
Meanwhile, water is either being weighed or volumetrically metered and discharged through the
same charging chute into the mixer truck.
The pouring of the concrete is carried out directly from the mixing truck to A telescopic pump, to be
later placed and consolidated by the use of air vibrators. The ambient temperature range within
which the element is estimated between 24 C and 35 C, while ambient humidity exceeds 80% during
conditions that are given of constant form throughout the year. In consequently, there are no abrupt
changes that warranty special respect, except as indicated for the preparation and placement of
concrete in weather warm, according to ACI 305-99.
Tittle Person
Head of Batching Plant 1
Operator Batching Plant 2
Crew Batching Plant And Laboratory 5
Operator Loader 1
Operator Water Truck 1
Operator Truck Mixer 5
Mechanical 2
Electrical 1
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 4 of 20
3.3 Material
The material source is from local cement producent and local quaries that used for readymix for all
structures and should be inspected and tested with the following standards.
3.3.3 Cement
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 5 of 20
3.3.4 Water
Element Type Resources
Clean water for Drilling on Batch plant
Water
readymix location
3.3.5 Additives
The additive thats used is Sika Indonesia Plastiment - VZ
Material Control
Mix Design
1. Performed by independent laboratory
2. Approved by Engineering
Concrete Testing
1. Slump Test Evaluation of Test Results
2. Concrete temperature 1. Quality Control Charts
3. Unitary Weight 2. Distribution of test report
4. Molding, Sampling, curing and testing
cylinder
Adjustment of Variable
1. Materials
2. Mix Design
If the current on site batching plan is not capable of doing the mass concrete especially for the wind
turbine foundation, we will combine by using the backup bathcing plan located in Bantaeng, 35 KM
from the site location. Additional truck mixers will be added due this acceleration of concreting to not
over than 16 hours. The back up batching plan will use the same materials as mentioned above and
the material will be tested for mix design and trial mix sample compressive strength tests as the
current on site batching plan procedure.
result in inadequate or poor quality concrete if it is not executed correctly, a bad mix design
will of course always give poor results. Who is responsible for designing the mix depends on
the type of project. For large, publicly funded projects the responsibility for the final design
falls to a licensed civil engineer. For residential projects such as foundations and driveways it
is the private contractor, whose professional reputation is generally his only credential. For
do-it-yourself projects it is of course the homeowner who must design his own mix.
Mixing of concrete is a very important step for achieving good final properties, and one
that can be quite difficult without the right equipment. This is one of the best reasons for
using ready-mixed concrete. Mixing distributes the aggregate evenly throughout the cement
paste, ensures that all of the cement has been fully saturated in water, and removes large air
voids. In addition, mixing breaks up agglomerated clusters of cement particles and allows air
entraining admixtures to generate the correct air void system. Undermixing leaves large flaws
and thus results in inferior strength, while overmixing wastes time and energy and can
destroy entrained air voids. The lower the workability, the more mixing energy and mixing
time is required.
If the mixture of the components is realized inside the hopper of the truck mixrs, hoppers
rotational speed must be constant to ensure the mixing and homogeneity of the concrete if
pre-mixer, the concrete will be introduced into the trucks hoppers properly mixed. Once the
homogeneity of the mixture is granted in the truck, a sample will be taken to be analysed :
Elapsed time from mixing
Temperature of concrete mass and ambient
Visual appearance (if there is any segregation or anything to be noted)
Abrams cone. It is recommended to do 2 abrams cone.
Once the fresh concrete is dehydrated, add some retarder to make the slump is enough and
good for concrete pouring flow in the foundation.
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 8 of 20
5 Quality assurance
Flowchart of the quality assurance for batch plan readymix production and quality control
Frequency
Element Test Standard
By Third Party
By Site Laboratory
Laboratory
Humidity ASTM C566-13 Each 15 days Every 2 months
Organic Material ASTM C40-11 Each 15 days Every 2 months
Sanity ASTM C88-05 1 per week Every 2 months
Can Not be
Granulometry ASTM C33-13 Every 2 months
Fine implemented
Aggregate Unitary Weight ASTM C29-09 Each 15 days Every 2 months
Specific gravity
ASTM C128-12 Each 15 days Every 2 months
and absorption
Fine Modulus ASTM C136-06 Each 15 days Every 2 months
Abrasion ASTM C131-06 Every 6 months Every 6 months
Humidity ASTM C566-13 Each 15 days Every 2 months
Can Not be
Organic Impurities ASTM C40-11 Once during project
implemented
Sanity ASTM C88-05 Every 3 months Every 3 Monthly
Can Not be
Granulometry ASTM C33-13 Every 2 months
implemented
Coarse
Can Not be
Aggregate Peso Unitario ASTM C29-09 Every 2 months
implemented
Specific Gravity Can Not be
ASTM C127-12 Every 2 months
and Absorption implemented
Reaction to lcali-
ASTM C289-07 Each 15 days Every 2 months
Aggregates
Abrasion ASTM C131-06 Monthly Every 2 months
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 9 of 20
Chemical
Water ASTM C94-10 Every 3 months Every 3 months
acceptance
Monthly By Monthly By Cement
Blaine ASTM C204-11
Suplayer Suplayer
Cement
Monthly By Monthly By Cement
Strength ASTM C109-12
Suplayer Suplayer
Sampling ASTM C173-12 Each 50 m3 No needed
Slump Test ASTM C143-12 Every 8 m3 No needed
ASTM C1064- No needed
Temperature Every 8 m3
Fresh 12
concrete Unitary weight ASTM C138-12 1 per week No needed
Ratio No needed
ACI-318 Every 8 m3
Water/Cement
Elaboration of No needed
ASTM C31-12 Every 80 m3
samples
Hardened Compression
ASTM C39-12 10 at 7,14,28 days 6 at 28 days
Concrete strength
All these 3rd party testing plan item, contractor will inform to owner to whitness the test 3 days before
the event and the results as per contract request and some monthly on Site lab test to ensure the
quality of the batch plan product.
Discipline Legend
CIVIL AND STRUCTURE H : Hold Point A : Approval Required TPI : Third Party Inspection
Project Title : Tolo I Wind Farm Project W : Witness R : Review EBJ : Owner
Job No : p : Perform M : Monitoring PP : Pembangunan Perumahan
Description : Project Inspection and Test Plan-Site
Equipment Tag No. : - BSB : Supplier Concrete
Location : -
INSPECTION INSPECTION LEVEL
No. DESCRIPTION REFERENCE DOCUMENT ACCEPTANCE CRITERIA VERIFIED DOCUMENT
METHOD BSB PP EBJ TPI
1 CONCRETE
1.1 Project Document
a. Inspection and Test Plan Review Comply with Approved ITP Approved ITP P R R -
1.2 Procedure
Concrete Work Review Comply with spec & proc. Approved Procedure P,R R,A R -
a. Material Inspection
ASTM C204-11 TLO -Q-FM- 0014
1. Cement type as per specification Inspect Comply with spec. & DWG. P,R W,A W -
ASTM C109-12 &Laboratorium Report
2. Water Test Inspect ASTM C94-10 Comply with spec. Laboratorium Report P,R W,A W -
Mix Proportioning and Trial Mix & Equipment TLO -Q-FM- 0014
b. Inspect ASTM C94 Comply with spec. P,R W,A W -
Calibration &Laboratorium Report
d. Concrete Pouring
5. Slump Test Inspect ASTM C143-12 Comply with spec. TLO -Q-FM- 0016 P,R W W -
6. Concrete test (compressive strength test) Inspect ASTM C39-12 Comply with spec. TLO -Q-FM- 0017 P,R W,A W -
FINE AGGREGATE
Total
AGGREGATES VOLUME
Aggregates : Kg
Sand 1 : Kg
Sand 2 : Kg
Gravel - 01 : Kg
Gravel - 02 : Kg
Gravel - 03 : Kg
Total : Ton
Density : T/CuM
Signature
Name
Sign Date
Job Title
Form Code : TLO-Q-FM-0014 Rev.1
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 14 of 20
6 Revision Plan
All equipment of batching plant should be tested including equipment in laboratorium on the batch
plant.
6.1 Equipment Periodically Revision Plan
The equipment of the batching plan, truck miThis form should be signed together and equipment
should be periodically inspected on the batch plan.
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 16 of 20
7 SHE Plan
The primary purpose of this SHE Plan is to manage the project hazards in order to minimize the
risk and to achieve the project Safety, Health and Environmental Objective. This plan is a living
document and will be kept updated as necessary to accommodate any required improvement or
any change of Projects requirements. Regarding the committed application of this SHE Plans, we
will ensure that our SHE goals are delivered.
7.1 Standard and References
All national standard and regulation regarding SHE aspects. Some international codes and standards
are either applied to support project SHE compliance.
These are some standard and references, but not limited to, as previously mentioned.
UU No.1/1970 : KeselamatanKerja
UU No.13/2004 : KeselamatandanKesehatanKerjaKontraktor
UU No.32/2009 : PengelolaanLingkunganHidup
ISO 9000 : Quality Management System
ISO - 14001 : Environmental Management System
OHSAS - 18001 : Occupational Health and Safety
ANSI : (American National Standards Institution) standard on
Personal Protection Equipment and technical design
Compliance.
NFPA : (National Fire Protection Association) standard on Fire
Protection
ASTM : (American Standard Testing & Material) on equipment testing and material
SKK Migas : All SKK Migas Regulations
Any other related and updated standard and references.
The Project activities should comply with all regulation which applied by Owner/Main Contractor.
Once the standard and references have not described in detail, common best practices completed
with approved technical justification by Owner/Main Contractor can be allowed as PT. Bumi
Sarana Beton (Kalla Group) guidelines.
Job No. : 717003
PROCEDURE FOR THE Doc. No. :
CONCRETE PLANT
Rev. No. : 0
CERTIFICATION
Page No. : 17 of 20
Working at elevated height contains the hazard of fall. Any activity that is carried outs at elevation 2
meter or above is include in the category of working at height. Contractor shall provide protection
system to be implemented to control this hazard consists of the following:
a. Provide access and working platform that is sufficient to allow
b. Area below the elevated work shall be cleared from people access except when wire net is
provided.
c. Provide Personnel Protective Equipment for working at height such as full body harness. PT. Bumi
Sarana Beton (Kalla Group) shall provide approved full body harness with double lanyard and shock
absorbent optionally.
d. All workforces who are assigned to work at elevated area shall get induction training prior to be
released to the job. Such training shall include the safe work procedure, the procedure to use the
fall protection equipment and procedure to maintain the equipment.
e. Safety Prevention about falling from heights, shall prepare early before project activities.
Occupational Health Plan
Medical checkup will be the the most requirement to ensure the workers in this batching plan is
healthy and prevented to several contaminate desease. Health preventiveprograms related to the
question consisted in to awareness & communication program for several deseases (Malaria, AIDS,
TBC, Hepatitis and Dengue), promotion program for reproduction health and sanitation program.