Equalization Tank:
pH/Flow
Neutralization Tank:
pH Control
Points to note while
selecting
pH Sensor
Solid Reference electrolyte
17th Oct 2008, Chennai
INSTALLATION
CONDITIONS
INSTALLATION CONDITIONS
Analysers For Waste Water
Primary Clarifier :
Sludge Level
Clarifier Overflow:
Turbidity/TOC
Aeration Tank:
DO Control/pH/MLSS
Analysers For Waste Water
Secondary Clarifier :
Sludge Level
Treated Effluent:
pH/Sulphide/TOC/Oil &
Grease/Phenol/Turbidity/
Ammonia/Nitrate/Nitrite/Phosphorous
Sludge Level Control
Controlling a Desludgeing pump with Timer is not as
good as Sludge Level Blanket Control
Heavy sludge loading can overwhelm the timer
controlled desludging pump allowing the sludge to slip
from top while the blanket level controller maintains the
sludge level within high & low set points.
Sludge loading varies widely from
Day /Night
Weekdays
Summer / winter
Control Desludge pumps by sludge blanket Control NOT
BY Timers
SLUDGE BLANKET
LEVEL CONTROL
VERSUS
TIMER BASED
BLANKET LEVEL
DESLUDGING
Possible Instrumentation at
Clarifier Overflow:
Turbidity
Aeration Tank:
DO Control/pH/MLSS
Dissolved Oxygen
Critical parameter for
measurement and control
Should have fast response
time
Less & Quick Maintenance
Measurement independent
of Flow rate.
Unaffected by Co2 &H2S
Membranes to withstand
high pressure
Luminscence DO Sensor
Luminophore in initial state
Absorbing photon
O2 absent O2 present
O2
Colliding with O2
Energy is
transferred to
O2 O2 molecule
Luminophore emits
red light when in (quenching)
excited state
Luminophore returns to
initial state
D.O BASED AUTOMATIC AERATION
1
SYSTEM
2 3
AIR BLOWERS
Cyclic operation
of Blowers
DIGITAL OUTPUTS
PID
Controller D.O Low /
Program High Alarm
4-20 mA, Analog Input
On-line D.O
Meter
Aeration Tank
BENEFITS
High Degree of process control & Efficiency
seen.
6 mg/l
Manual Control
0 mg/l
Automated D.O2
Control
Possible Instrumentation at
Secondary Clarifier :
Sludge Level/Flow
Nitrification/De Nitrification
Ammoinium/DO
Filter Backwash
Turbidity
Possible Instrumentation at
Treated Effluent:
pH/Sulphide/TOC/Oil &
Grease/Phenol/Turbidity/COD
Ammonia/Nitrate/Nitrite/Phosphorous/
Residual Chlorine/Flow
Points to note while
selecting
Special Analysers
Measuring Principle suitable for
On line use in terms of
Availability
Maintenance
Cross Reference
Measuring Principle free from
reagents or with locally available
reagents
Analyser with Auto cleaning/Auto
calibration facility
Complete Automation