KAPASITAS ASSY SESUAI LAYOUT

6 MAN / CONVEYOR
HASIL
NO CT /RATA2 PCS/JAM KEB LINE KEB MAN POWER DANDORI
PROD/SHIFT/CONV
1 72 50 350 2 12 1

KETERANGAN
CYCLE
1. TIME = 3600/50 = 72 DETIK
2. PCS/JAM/CONVEYOR = 3600/72 = 50 PCS
3. HASIL PRODUKSI = 50 * 7 JAM = 350 PCS
4. LINE = 2 LINE
5. MAN POWER + DANDORI = 13 ORANG/SHIFT
6. TOTAL PRODUKSI 1 SHIFT = 350 * 2 = 700 PCS
7. KAPASITAS MAX 3 SHIFT = 700 * 3 = 2100 PCS
8. JUMLAH MAN POWER 3 SHIFT = 13 MP * 3 = 39 MP
TOTAL MP TOTAL PROD / SHIFT

13 700
KAPASITAS ASSY SESUAI LAYOUT
1 MAN / TABLE
PCS/JAM/1 HASIL PROD/SHIFT/1
NO CT /RATA2 LINE KEB MAN POWER DANDORI
MP MP
1 300 12 84 10 10 2

KETERANGAN
CYCLE
1. TIME = 3600/12 = 300 DETIK
2. PCS/JAM/1 MP = 3600/300 = 12 PCS
3. HASIL PRODUKSI = 12 * 7 JAM = 84 PCS
4. LINE = 10 LINE
5. MAN POWER + DANDORI = 12 ORANG/SHIFT
6. TOTAL PRODUKSI 1 SHIFT = 84 * 10 = 840 PCS
7. KAPASITAS MAX 3 SHIFT = 840 * 3 = 2520 PCS
8. JUMLAH MAN POWER 3 SHIFT = 12 MP * 3 = 36 MP
TOTAL MP TOTAL PROD/SHIFT

12 840