Professional Documents
Culture Documents
110 Report Ot World Bank After Janaury 2017 Missionwithout Cost
110 Report Ot World Bank After Janaury 2017 Missionwithout Cost
110 Report Ot World Bank After Janaury 2017 Missionwithout Cost
Date: 19-Feb-2017
The support of the world bank to MoE is multidimensional and one to the
important part is its support to the infrastructure part, construction of building
for educational facilities i.e. schools, teacher training centers, administration
building, hostels and etc.
Under EQUIP Phase I,II from 2004 to 2012, a total of 1347 community
contracts were planned out of which for 110 community contracts Buildings and
some of their related contracted components ( water well, latrines, and
furnitures) remains incomplete and currently stopped.
a. Design Problem:
The committee has identified that the civil works quantities were under
estimated and there has been discrepancies in bill of quantities and drawing.
Moreover the site specific Designs were not adopted and the terrain conditions
were not assessed properly resulting in more excavation and extra work in
construction activities. Since it was lump sum contract with fix celling, the
community were not paid for the additional work performed. Hence the
community could only complete the building with the available money and the
contracted components remained incomplete.
The committee assessed the variation in terms of extra work by re-calculating
the quantities from the drawings to figure out the difference between
Contracted BoQ and Drawings and physically surveying the site and reported
the actual work performed versus contracted quantities.
The unit cost were not derived from Site Specific Construction Material Rates,
No rate analysis has been performed and the transportation cost to the site were
not considered. In fact the same contract amount were paid to the communities
across Afghanistan irrespective of considering geographical and climatic
conditions. In EQUIP I (2004-2008), a lump sum amount of 32000 USD has
been paid to the communities across Afghanistan and in EQUIP II (2008-2012) ,
a lump sum amount of 64000 USD has been paid to communities.
e. Missing items:
The boundary walls and electricity system was not part of the contract with
community and they were missed from the original contract, however the
provision of these components are important for the schools hence it is
There are Money in shura Account (220,717 USD) for some schools which has
not been spent so far.
There are 27 projects which will be write- off due to different reasons:
A. Balkh Province: there are 2 projects in balkh province which was write-off and the relevant information is presented in bellow
table:
S# Project name District Physical progress Financial Reasons for MoE Actions
progress write-off
1 Surkh Koch charkint 60% 100% Due to security Will be
school challenges , it is completed once
not possible to the security
complete the condition gets
remaining works better
2 Sayed Qasim Zari 45% 100% Due to security Will be
Mohamadi challenges , it is completed once
School not possible to the security
complete the condition gets
remaining works better
B. Daikundi Province: there are 1 project in Daikundi province which was write-off and the relevant information is presented in
bellow table:
S# Project name District Physical progress Financial Reasons for MoE Actions
progress write-off
1 Sardara Khodi khadeer 10% 50% Located in flood Will be
High school plain area, completed once
security issues the security
and community condition gets
problems better
C. Ghazni Province: there are 1 project in Ghazni province which was write-off and the relevant information is presented in bellow
table:
S# Project name District Physical progress Financial Reasons for MoE Actions
progress write-off
1 Deh Yak Primary Dehyek 0% 25% Security issue, Will be
School construction completed once
material the security
purchased but condition gets
insurgents not better
allowing shura to
work
D. Helmand Province: there are 1 project in Helmand province which was write-off and the relevant information is presented in
bellow table:
S# Project name District Physical progress Financial Reasons for MoE Actions
progress write-off
1 Nawmish Baghran 50% 50% Security issue Will be
Baghran School completed once
the security
condition gets
better
D. Nuristan Province: there are 11 project in Nuristan province which was write-off and the relevant information is presented in
bellow table:
S# Project name District Physical progress Financial Reasons for MoE Actions
progress write-off
1 Nilab Primary Dooab 51.65% 75% Security issue, in Shura has ()
School addition to this AFS in there
the existing account, MoE
construction is working on
poor quality , not collecting the
recommended to money back
complete the from these
remaining works shura, Will be
but to build a completed once
new school for the security
which the condition gets
security does not better
permit
Piyar Girls
School
Palagal School
Jonia School
Shokoor Zada
School
Karach School
Mandool School
Linar School
Pashagar Girls
School
Mandeel / Malil
School
Masawi School
II. Strategy for completion:
The MoE-ISD Engineers conducted survey of each school and identified the incomplete items and prepare the site plan on the basis of
which the design drawing and price estimates were prepared for completion of these items. Outmost care were taken to consider site specific
design and construction material rates. The committee has reviewed and approved the technical documents which were again cross checked
by World Bank civil work consultant.
b. Required Budget:
The total estimated budget for completion of 110 incomplete schools excluding write-off projects is 2,704,572USD.
c. Completion period:
The schools will require 12 months for completion including procurement process.
The incomplete items will be provided by contractors, The projects has been arranged into Lots and packages considering the
geographical location of the schools and the centralized National competitive bidding method will be used for selecting the contractor. The
technical designs for these projects are completed and submitted to procurement department on 25-march-2017
report analyzed by
Regional Managers/
instructions provided to Technical committee
Contractor and Senior
Engineers
report submitted to
database and relevant
departments