Professional Documents
Culture Documents
Assignement Report
Assignement Report
Allocation: Task are assigned to resource during the preparation stage of the project. Assignments are
part of process scheduling. But there is no guarantee that resources are available for all the
assignments.
WBS (Work Breakdown Structure) is used to modify large projects down into controllable chunks for
better planning and management.
Tasks, resources, and cost are three core elements to do planning, organizing and executing the project.
Starting the project by clicking on New the dialog box show in figure 1.
Figure 1
New Dialogue box will be opened which is shown in figure 2. And click on Create project to start the
new project.
Figure 2
In new box shown in figure 3, need to specify project name, manger name and forwarded date to start
the projects.
Figure 3
Once all the datas are made, Click ok to start the work plan sheet or task sheet in which we are
entering datas like different Task, Duration, Precedence as shown figure 4.
Figure 4
Once we have entered all the datas, we can have Gantt chart on right side of the task sheet which
shown in figure 5.
Figure 5
We can easily understand project status using Gantt chart due to its visualization.
The holidays which might have affecting the overall project has been specified to accomplish the task
with in the scheduled time frame. I assumed that to carry out this project in New South Wales. So, I
marked holidays Labors days on 2-october-2017, Christmas day on 25-december-2017, Boxing Day on
26-December-2017 and New Year on 1-january -2018. I have been marked those dates as non-working
time in the calendar. So, available resources can be used with the scheduled in time frame.
Figure 6
Figure 7
After entering different task and assigning available resources in individual task using
Figure 8
After assigning resources respective to the tasks, the Gantt chart obtained was given below.
Figure 8
From resource histogram; it is clearly understood that Principal architect is over allocated
and it must be levelled. In Gantt chart, Sketching Mock-ups and prepare documentations were
over allocated, so I have made some adjustment to maintain critical path as well as leveling of over
allocation After levelling, the problem of over allocation is resolved in the Gantt chart is
shown below.
Figure 9
From resource histogram; it is clearly understood that Draftsperson is not being over
allocated. So maximum utilization of draftsperson during the project is shown below.
Figure 10
Figure 11