Professional Documents
Culture Documents
NHT Unit
NHT Unit
Draft
OPERATING MANUAL FOR
NAPHTHA HYDROTREATER UNIT, Rev. A
VRCFP, HPCL VISAKH Page 1 of 197
OPERATING MANUAL
FOR
PREFACE
This operating manual for Naphtha Hydrotreater Unit of HPCL, Visakh has been prepared by M/s
Engineers India Limited for M/s Hindustan Petroleum Corporation Limited.
This manual contains process description and operating guidelines for the unit and is based on
documents supplied by the process licensor. This manual contains process description and
operating guidelines for the unit and is based on documents supplied by the Process
Licensor (UOP). Hence the manual must be reviewed /approved by the licensor before the
start-up /operation of the unit.
Operating procedures & conditions given in this manual are indicative. These should be treated as
general guide only for routine start-up and operation of the unit. The actual operating parameters and
procedures may require minor modifications/changes from those contained in this manual as more
experience is gained in operation of the Plant.
For detailed specifications and operating procedures of specific equipment, corresponding Vendor's
operating manuals/instructions need to be referred to.
.
Table of Contents
SECTION-1 .................................................................................................................................... 8
INTRODUCTION .......................................................................................................................... 8
1.1 INTRODUCTION ............................................................................................................ 8
SECTION-2 .................................................................................................................................... 9
DESIGN BASIS.............................................................................................................................. 9
2.1 INTRODUCTION ............................................................................................................ 9
2.2 UNIT CAPACITY ........................................................................................................... 9
2.3 TURNDOWN CAPABILITY .......................................................................................... 9
2.4 FEED ................................................................................................................................ 9
2.5 PRODUCTS ................................................................................................................... 13
2.6 BATTERY LIMIT CONDITIONS FOR NHDT ........................................................... 14
2.7 UTILITY CONDITION ................................................................................................. 15
SECTION-3 .................................................................................................................................. 19
CHEMISTRY OF THE PROCESS .............................................................................................. 19
3.1 PROCESS CHEMISTRY .............................................................................................. 19
3.2 SULFUR REMOVAL .................................................................................................... 19
3.3 NITROGEN REMOVAL ............................................................................................... 20
3.4 OXYGEN REMOVAL .................................................................................................. 21
3.5 OLEFIN SATURATION ............................................................................................... 21
3.6 AROMATIC SATURATION ........................................................................................ 22
3.7 METALS REMOVAL ................................................................................................... 22
3.8 HALIDES REMOVAL .................................................................................................. 23
3.9 REACTION RATES ...................................................................................................... 23
3.10 HYDROCARACKING REACTIONS .......................................................................... 24
3.11 CATALYST DEACTIVATION .................................................................................... 24
SECTION-4 .................................................................................................................................. 29
PROCESS DESCRIPTION .......................................................................................................... 29
4.1 PROCESS VARIABLES ............................................................................................... 29
SECTION-1
INTRODUCTION
1.1 INTRODUCTION
The purpose of the "Naphtha Hydrotreater" is to produce clean hydrotreated feedstocks to feed
the isomerization unit and CCR unit. These feedstocks must be sufficiently low in contaminants
such as sulfur, nitrogen, water, halogens, diolefins, olefins, arsenic, mercury and other metals so
as not to affect the downstream unit performance in particular the isomerization unit.
Naphtha hydrotreater feed is a blend of full boiling range straight run naphthas (97.6 wt %) and
visbroken naphtha (2.4 wt% maximum, 166 deg). from CDU-1, CDU-2, CDU-3 and VBU
naphtha. Apart from this FCC heart cut naphtha and naphtha from storage can also be processed.
These feed all contain levels of contaminants which would be detrimental to the isomerization &
CCR catalysts and therefore pretreatment is necessary.
This process involves the treatment of the naphtha in an adiabatic reactor over a fixed bimetallic
catalyst bed within a hydrogen environment. A moderately high temperature in the range of 280-
310C is required to promote the chemical reactions. After the reaction process, the naphtha is
stripped to remove light ends, gaseous products including H2S and water. The naphtha from
stripper bottom is the feed to the naphtha splitter. The naphtha splitter top is fed to the
Isomerization unit and splitter bottom is fed to the Platformer unit.
When diolefins and olefins are present in the feed, then a separate treatment step is required at a
lower temperature with a special catalyst to hydrogenate the unsaturated components prior to the
higher temperature treatment.
The performances of the isomerization unit are very much dependent upon the efficiency of the
naphtha hydrotreater.
SECTION-2
DESIGN BASIS
2.1 INTRODUCTION
The unit is designed for two different cases. Case-I, is the proposal feed case which was based on
feed supplied in HPCL (NIT case) and Case-II is Bombay High (BH Case). The purpose of the
NHDT unit is to produce clean desulfurized light naphtha cut to be processed in the Platformer
unit after removal of all impurities which are poisons for catalysts (sulfur, nitrogen, water,
halogens, diolefins, olefins, arsenic, mercury and other metals).
Important content of design basis is given below.
2.4 FEED
Naphtha hydrotreater feed is a blend of full boiling range straight run naphthas (97.6 wt %) and
visbroken naphtha (2.4 wt% maximum, 166 deg). The straight run naphthas are from CDU-1,
CDU-2, and CDU-3; visbroken naphtha from VBU. Apart from this FCC heart cut naphtha and
naphtha from storage can also be processed. These feed all contain levels of contaminants which
would be detrimental to the CCR catalysts and therefore pretreatment is necessary.
Impurities:
FBR Naphtha contaminants:
Value
Total sulfur wt ppm 670 max
Total Nitrogen wt ppm 2.2 max
2.4.2. Hydrogen
Hydrogen make-up to this unit is needed for naphtha hydro treatment. Hydrogen is supplied from
Net Gas Chloride Treater at Platforming unit through a 2 header to upstream of product
condenser 73-A-01.
2.5 PRODUCTS
The NHT unit shall produce hydrotreated and stripped light naphtha and heavy naphtha suitable
fro downstream processing. The light hydrotreated naphtha will be used as feed to isomerization
unit and heavy naphtha will act as feed to Platformer. The hydrotreated light naphtha from the
NHT unit shall have the following specs:-
Product Value
Sulfur wt ppm 0.5 max
Nitrogen wt ppm 0.1 max
Metals wt ppb Nil
Chlorides wt ppb Nil
The hydrotreated heavy naphtha from the NHT unit shall be designed to meet the following
required product properties and conditions:
Product Value
Sulfur wt ppm 0.5 max
Nitrogen wt ppm 0.5 max
Stripper column off gases are routed to amine treating (by others) and then to the refinery fuel
gas system. Sour water from the separator and stripper column is sent to sour water stripping and
then to the refinery.
SRU Integration
Stripper off gas 53 5.6
Project
Naphtha Splitter Bottom Platformer 93 9.6
Naphtha Splitter Overhead Isomerization 40 6.1
Sour Water
Sour Water 55 5.0
Stripper
Closed Blow
Stripper Overhead ** 1.7
Down
1 VVHP STEAM
Pressure, Kg/cm2g 43.5 43.5 43.5 50.5
Temperature, oC 264 264 264 395
2 VHP STEAM
Pressure, Kg/cm2g 33 35 38 40.0
Temperature, oC 340 360 380 400
3 MP STEAM
Pressure, Kg/cm2g 9 10 11 12.5
Temperature, oC Satd 250 280 300
4 LP STEAM
Pressure, Kg/cm2g 2.5 3.0 4.0 5.5
Temperature, oC Satd 150 170 190
2.7.8. Nitrogen
Minimum Operating Pressure Kg/cm2 5.0
Normal Operating Pressure Kg/cm2 6.0
Maximum Operating Pressure Kg/cm2 7.0
Mechanical Design Pressure Kg/cm2 10.5
2.7.9. Caustic
Caustic Strength wt% 10
Supply Pressure Kg/cm2 3.0
Supply Temperature oC 40
SECTION-3
CHEMISTRY OF THE PROCESS
The comparison of the relative difficulty of hydrotreating different classes of sulfur containing
compounds is shown in figure1.
B. Cyclic Olefins
C C
C C C C
+ H2
C C C C
C C
may retain as much as 100 wt% metals based on fresh catalyst weight. Such catalysts typically
have a lower activity for desulfurization and denitrogenation.
C C
C C -C-C-C-Cl C C -C-C-C
+ H2 HCl +
C C C C
C C
Desulfurization 1
Olefin Saturation 2
Denitrogenation 1
Aromatics Saturation 1
All of the reactions discussed above are exothermic and result in a temperature rise across the
reactor. Olefin saturation and some desulfurization reactions have similarly rapid reaction rates,
but it is the saturation of olefins, which generates the greatest amount of heat than any other
hydrotreating reactions.
of the catalyst. Coke deposition occurs at a relatively slow rate and the catalyst is able to operate
for periods of one year or more before regeneration becomes necessary. Reactor temperatures
must be increased to compensate for the slow decline in activity caused by the accumulation of
coke on the catalyst. During upsets or when catalyst is subjected to operating conditions beyond
the operating limits of the unit, coke formation accelerates and catalyst life is reduced. Most of
the catalyst activity can usually be recovered by regeneration by oxidizing the coke to carbon
dioxide gas and hence coke deposition can be considered as temporary deactivation of catalyst.
However, when deactivation is caused by extreme conditions, such as very high reactor
temperatures or high end point feed, regeneration may not be successful.
Approximate
factor of difficulty
FIGURE-1
FIGURE-2
FIGURE-3
SECTION-4
PROCESS DESCRIPTION
Figure III-1
Desulfurization and Denitrification vs. Catalyst Temperature
Temperatures above this minimum will only lead to higher rates of coke formation and a reduced
cycle length. Guidelines for temperature adjustments are summarized below.
Figure III-2
Weight Average Bed Temperature
The rate of increase in WABT is referred to as the deactivation rate expressed as C per m3 of
feed per kilogram of catalyst (F per barrel of feed per pound of catalyst), or more simply as C
per day (F per day). During the course of an operating cycle, the temperature required to obtain
the desired product quality will increase as a result of catalyst deactivation (See Figure III-3).
The gradual loss in catalyst activity can be compensated for by increasing reactor temperatures.
In general, above a certain level, cracking and coke formation become very rapid and little
improvement in performance is obtained.
Catalyst bed thermocouples are extremely useful for judging the effective utilization of the
catalyst. However, it must be remembered that the bed couple is measuring the temperature at
one point in a large cross sectional area. If temperature maldistribution is occurring, then the bed
couple may not necessarily be representative of the average catalyst temperature. Causes of
temperature maldistribution include poor catalyst loading, mechanical problems with internals or
coke formation resulting from unit upsets or a temperature excursion.
Figure III-3
WABT Vs/ Cycle Life
420
410
400
390
380
370
0 1 2 3 4 5 6
Life, M3/kg
A reactor temperature profile plot is a useful tool for evaluating catalyst performance,
effectiveness of quench, and reactor flow patterns. A temperature profile can be constructed by
plotting the catalyst temperature versus distance into the catalyst bed (or more accurately versus
weight percent of catalyst). In addition to monitoring the temperature profile, the radial
temperature spread needs to be monitored.
The reactor temperature profile should be adjusted to maintain equal peak temperatures across
each catalyst bed. This ensures equal utilization of the catalyst inventory. The design
temperatures of the reactor and charge heater will also determine the maximum allowable
operating values. The temperature rise across the reactors must be monitored continuously in
order to assure that the design limitation of the unit is not exceeded. This can be especially
important when increasing the ratio of cracked stock to straight run material in the feed since
olefin saturation results in considerably higher heats of reaction. Units are typically designed for
a maximum reactor bed temperature rise of <42C (75F).
c) UOP K
Higher UOP K of the feed stock is an indication of higher paraffinicity of the feed stock. The
feed with lower UOP K will result in increased hydrogen consumption and higher temperature
rise across the reactor bed.
d) Bromine number
Higher bromine number of the feed stock is an indication of higher unsaturates content. The feed
with higher bromine number will result in increased hydrogen consumption and higher
temperature rise across the reactor bed. This will also enhance the condensation reaction to form
more coke in the reactor. This will reduce the cycle length.
e) Sulfur content
Higher sulfur content increases operating severity and increases hydrogen consumption. Also
reactor temperatures should be increased, which will lead to coke formation, to achieve the
required product sulfur.
f) Nitrogen content
Higher nitrogen content demands high reactor temperatures which will lead to coke formation.
Also hydrogen consumption increases if feed is having higher nitrogen content.
g) Conradson carbon
Conradson carbon is a measure of residue after destructive distillation. The feed with higher
Conradson carbon is an indication of higher coking tendency and this will reduce the cycle
length.
h) ASTM colour
ASTM colour is a measure of residue entrainment. Higher value will reduce the cycle length and
vice-versa.
i) Metal content
Organo-metallic compounds contained in the feed will decompose and the metals will be
retained on the catalyst, thus decreasing catalyst activity. Since metals are normally not
removable by oxidative regeneration, once a catalyst has been poisoned by metals, its activity
can not be restored.
An increase in the charge rate will require higher reactor temperature to achieve a constant
desulfurization, as well as higher recycle gas rate to maintain a constant ratio of H2 to
hydrocarbon. The increased reactor temperatures will also lead to a faster rate of coke formation
which will reduce the period between regenerations. The reduced feed rate may lead to bad flow
distribution through the catalyst, such that higher temperatures will be required to obtain good
product quality. In order to minimize the effect of variations in charge rate, it should be made
common practice to reduce the reactor temperature before lowering the feed rate, and conversely,
to increase the feed rate before raising the reactor temperature. The type of feed being processed
is best indicated by its distillation range and API gravity. An increase in the end point of the feed
will make sulfur and nitrogen removal more difficult, thus requiring higher reactor temperatures
which then accelerates coke formation (See Figure III-4).
Figure III-4
Catalyst Deactivation
Good Bad
Feed Quality
Coke deposition is also accelerated by the fact that heavier feed contains more of the precursors
that favor coke formation. In addition to the above, high boiling fractions also contain increased
quantities of metals which lead not only to higher reactor pressure drop, but to rapid catalyst
deactivation as well. It must be remembered that regeneration will not restore the activity of a
catalyst that has been poisoned by excessive quantities of metals.
Thus, it is seen that processing higher than design end point feeds will, at best, reduce the length
of the operating cycle, and under extreme conditions, may lead to an irrecoverable loss of
catalyst activity. Therefore, every effort must be made to maintain the end point of the feed
within the design limits by operating the crude and other units such that an acceptable feed stock
is obtained. A reduction in the API gravity of the feed for the same boiling range is an indication
of higher unsaturated content. This type of feed will result in increased hydrogen consumption
and higher temperature rise across the catalyst bed. It also contains more of the materials that
easily condense to form coke in the reactor and associated equipment.
Organo-metallic compounds contained in the feed will decompose and the metals will be
retained on the catalyst, thus decreasing its activity. Since metals are normally not removable by
oxidative regeneration, once a catalyst has been poisoned by metals, its activity cannot be
restored. Therefore, metals content of the feedstock is a variable that should be monitored.
Naphtha feedstock metals contamination is rare might be some metals which are introduced by
upstream processing or contamination such as lead, sodium, silicon and phosphorous. Iron
sulfide is usually present as a corrosion product and is normally not considered a poison to the
catalyst. Thus it is usually omitted when referring to total metals.
Hydrotreating catalysts exhibit a moderate tolerance for metals such as arsenic and lead. Total
metal content of 2-3 wt% of the Hydrotreating catalyst have been observed. However, product
analysis frequency should be increased to monitor breakthrough when calculations show the
metals level on the Hydrotreating catalyst exceeds 0.5 wt%. Catalyst replacement should be
considered when metal loadings of 1-2 wt% are exceeded on the Hydrotreating catalyst.
The graded catalyst bed, if used, may contain demetallization catalysts that have a high metals
retention capacity. Some of these catalysts may retain as much as 100 wt% of the fresh catalyst
weight as metals from the feed. These demetallization catalysts typically have a lower activity
for desulfurization and denitrogenation.
Apparent catalyst deactivation may be caused by the accumulation of deposits on top of the
catalyst bed. Solid material, such as corrosion products and coke, will lead to rapid fouling of the
catalyst bed if allowed to enter the reactor. This problem is remedied by skimming a portion of
the catalyst, screening and reloading. Feed filtering is quite effective in removing solid material,
and as such results in longer operating cycles due to the lower rate of reactor pressure drop build-
up. The use of feed filtering will depend on the type of feed processed and its source.
ratio of volumetric feed rate per hour to the catalyst volume and is defined as:
A simplified kinetic expression based on sulfur and/or nitrogen removal determines the initial
liquid hourly space velocity for most feedstocks and processing objectives. This initial value may
be modified due to other considerations such as unit size, extended catalyst cycle life, abnormal
levels of feed metals and requirements of other processing units in the refinery flow scheme.
An increase in the LHSV will require higher reactor temperature to achieve a constant level of
desulfurization, as well as higher recycle gas rate to maintain a constant ratio of H2 to
hydrocarbon. The increased reactor temperatures will also lead to a faster rate of coke formation
that will reduce the period between regenerations. A reduction in LHSV may lead to bad flow
distribution through the catalyst, such that higher temperatures will be required to obtain good
product quality. In order to minimize the effect of variations in LHSV, it should be made
common practice to reduce the reactor temperature before lowering the feed rate, and conversely,
to increase the feed rate before raising the reactor temperature.
Unit designs are based on operational criteria to achieve optimal performance. One criterion for
hydrotreating is liquid mass flux across the catalyst bed. A mass flux of 2000 lb/hr/ft2 is
considered a reasonable minimum for adequate flow distribution. At reduced throughput, unit
operation may become difficult due to hydraulic considerations (i.e. control valves operating
closed, etc.). Also, reactant distribution in the reactor may become unequal as preferential flow
paths are established. For these reasons, the unit should not be operated below the minimum
turndown capacity for extended periods. Unit turndown will vary for each design and is typically
50-70% of design capacity.
Figure III-5
Desulfurization vs. H2 Partial Pressure
H2 Partial Pressure
H2 Circulation
A reduction in operating pressure below its design will have a negative effect on the activity of
the catalyst and will accelerate catalyst deactivation due to increased coke formation. Figure III-6
shows the general trend in the effects of lower hydrogen partial pressure on catalyst deactivation.
Operating at higher than design pressure may not be possible. There will be a practical
equipment limitation on most units that will not allow significantly higher pressure than design,
such as the pressure rating of the heaters, exchangers, and vessels. Also, the recycle gas
compressor usually will not be able to put up the required head on a significantly lighter, higher
purity recycle gas. The major control variable for hydrogen partial pressure is the recycle gas
purity that should be monitored closely to assure it is always maintained above the minimum
value. The hydrogen purity can be improved by increasing the hydrogen purity of the makeup
hydrogen, venting gas off the product separator, or reducing the temperature at the product
separator.
Figure III-6
Catalyst Deactivation
Low High
H 2 Partial Pressure
hydrocarbon so that the hydrogen is available at the sites where the reaction is taking place. This
is accomplished by circulating the recycle gas throughout the reactor circuit continuously with
the recycle gas compressor. The amount of gas that must be recycled is a design variable again
set by the design severity of the operation. The standard measure of the amount of gas required is
the ratio of the gas being recycled to the rate that fresh feed is being charged to the catalyst.
As with hydrogen partial pressure, the recycle gas to feed ratio should be maintained at the
design ratio. The definition for the gas-to-oil ratio is:
As with hydrogen partial pressure, any reduction of the gas-to-oil ratio below the design
minimum will have adverse effects on the catalyst life Figure III-7 gives a general observation of
this effect. The gas-to-oil ratio can be affected by several ways in the Hydrotreating Unit.
Figure III-7
Effect of Reactor Recycle Gas Rate on Catalyst Stability
Catalyst Life
The quantity of gas circulated from the product separator to the reactor is relatively large. The
gas flow is required for the following purposes:
Provides the excess hydrogen needed to assure that the reactions are carried to
completion.
Absorbs some of the heat of reaction minimizing the catalyst bed temperatures.
Minimizes charge heater and combined feed exchanger tube wall temperatures by
increasing the flow through the equipment. The excess hydrogen also prevents formation
of coke as the charge is heated to reaction temperature.
A gradual reduction in recycle gas rate may be observed during the course of an operating period
as a result of higher reactor system pressure drop. This effect is especially pronounced on units
that use a centrifugal recycle gas compressor. Such a reduction in the recycle gas rate is
acceptable as long as the calculated gas-to-oil ratio does not fall below the design value. When it
is no longer possible to maintain the minimum gas-to-oil ratio, the catalyst must be regenerated
and screened in order to reduce the reactor pressure drop. In all cases that result in less than
design gas-to-oil ratio due to pressure drop or mechanical difficulties, the raw oil charge rate
must be lowered in order to obtain the required gas-to-oil ratio. In the event of a complete loss of
recycle gas, immediate remedial action must be taken to protect the catalyst and equipment.
In most instances, the makeup gas H2 purity cannot be easily manipulated since it is fixed by the
hydrogen source, typically naphtha reforming unit or a hydrogen manufacturing plant. The light
hydrocarbons present in the recycle gas enter the system with the makeup gas in addition to those
being formed in the reactor, and must be vented from the product separator to prevent their
accumulation in the recycle gas. The amount of hydrogen required is determined by:
Chemical Hydrogen Consumption The hydrogen consumed during the hydrotreating
reactions.
Solution Losses The hydrogen that is removed from the reactor circuit dissolved in the
liquid hydrocarbon leaving the product separator.
Mechanical Losses The hydrogen lost through the makeup and recycle gas
compressors' packing vents and seals. This value may be roughly estimated at 3-5% of
the combined chemical consumption plus solution losses.
Venting Losses The hydrogen lost in the purge stream from the product separator to
maintain recycle gas purity.
The H2S formed in the reactors can reach equilibrium values as high as 5 mol% in the recycle
gas. This concentration of H2S has a depressing effect on the activity of the catalyst. Therefore,
in many cases it is desirable to remove the H2S from the recycle gas by venting it from the
product separator.
The sulfur and nitrogen found in the feed can be considered contaminants to the extent that they
produce hydrogen sulfide and ammonia which can react to form ammonium bisulfide. The water
injected into the reactor effluent dissolves the ammonium bisulfide and prevents exchanger
fouling. Organic nitrogen in the feed, if present in amounts higher than expected, will require
higher reactor temperatures for processing, and will lead to a reduction in catalyst life.
If the water injection should be stopped for any period of time, the H2S and NH3 may accumulate
in the recycle gas and result in a sudden loss in catalyst activity. The activity will return to
normal once wash water is reestablished. Catalyst bed temperatures should not be increased to
compensate for the temporary activity loss.
Small amounts of molecular nitrogen, CO and CO2 that enter the system with the makeup gas are
not harmful to the catalyst, but must be vented to prevent accumulation in the recycle gas.
Excessive amounts of CO and CO2 may have an adverse effect on catalyst performance as they
may be methanated by the catalyst taking up active sites and liberating heat. This will raise the
outlet temperature and reduce the apparent catalyst activity. The unit should never be pressured
up with high CO + CO2 containing makeup gas as a temperature runaway may result. The
presence of O2 could increase equipment fouling (especially the feed/effluent exchangers).
Feed section: Cold/hot feed lines at battery limit feed surge drum (73-V-01) charge
pumps suction.
High pressure reactor section: Charge Pump (72-P-01 A/B) Feed Filter (73-X-01)
Combined Feed Exchanger (72-E-01) Charge Heater (72-F-01) Reactor (72-R-01)
Separator (72-V-04) recycle gas compressor knockout drum (72-V-05) recycle gas
compressors (72-K-01 A/B).
MP Stripper Section Stripper Feed Naphtha Splitter Bottom Exchanger (72-E-02)
Stripper Feed Bottom Exchange (72-E-03) Stripper (72-C-01) Stripper Reboiler (72-E-
04) Stripper condenser (72-A-02) Stripper Receiver (72-V-06) Stripper Reflux
Pumps (72-P-04 A/B).
Naphtha Splitter Bottom pumps (72-P-05 A/B) Stripper Feed Naphtha Splitter Bottom
Exchanger tube side (72-E-02) battery limit.
Naphtha Splitter Overhead pumps 72-P-06 A/B Naphtha Splitter Overhead Cooler (72-E-
05 A/B) battery limit.
Low pressure product fractionation section: Naphtha Splitter (72-C-02) Naphtha
Splitter Reboiler Heater (72-F-02) Naphtha Splitter Condenser (72-A-03) Naphtha
Splitter Receiver (72-V-07).
A. FEED
The feed to the Naphtha Hydrotreater unit is a blend of full boiling range straight run naphthas
from CDU-1, CDU-2, CDU-3 and visbroken naphtha from visbreaking unit.
Hot feed
In order to maximize energy efficiency, Naphtha Hydrotreater unit will be normally processing
hot straight run naphtha at 75 oC and pressure of 4.5 Kg/cm2 exiting CDU-1, CDU-2 and CDU-3.
VB naphtha from visbreaking unit will also come along with SRN from CDU. Hot feed is taken
into the unit through an 8 header. FCC heart cut naphtha and Naphtha with contaminated DSO
from CFC can also be processed in the NHT when required.
Cold feed
Naphtha hydrotreater unit will be processing cold feed from storage during unit start up, and
during normal operation if necessary.
C. FEED FILTRATION
Straight run naphtha is clean products and doesnt contain much of contaminants viz., pipe scale,
dirt, and degradation products. However, small quantities of contaminants are always present.
These contaminants, if enter the reactor along with naphtha, accumulate in the reactor catalyst
beds. This accumulation of particulate matter in the catalyst beds builds up the pressure drop
across the reactor. Naphtha Hydrotreater unit has (72-X-01) continuous magnetic feed filters.
Charge pump discharge is filtered through this filter to a filtering degree of 50 micron before
going to reactor. Maximum clean pressure drop across these filters is 0.2 kg/cm2 (g) and
maximum dirty pressure drop across these filters is 1.8 kg/cm2 (g). The pressure drop across the
filters is indicated by PDT0703 in the field and by PDI0703 on DCS panel. A nitrogen supply
line connection is given to the inlet line of each filter for purging purpose, and also to drain the
filter in a short period of time under nitrogen pressure.
E. CHARGE HEATER
Charge Heater (72-F-01) is a vertical cylinder fuel oil / fuel gas fired heater with 2 pass entering
convection section. It is vertical cylindrical type having two pass vertical tubes in the radiant
section. Flue gas leaving the convection section of charge heater shall be ducted beneath the
common convection section of stripper reboiler heater (72-F-02). It has 6 nos. of low NOX
combination of oil and gas burners. Preheated combined feed is further heated from 278 oC to
332 oC. The combined feed enters the heater at a pressure of 30.0 kg/cm2 (g) and exits at a
pressure of 24.9 Kg/cm2 (g). A 3 multipurpose point is provided at inlet and outlet of both the
passes for neutralization purposes. Charge heater outlet temperature i.e. reactor inlet temperature
is an important control parameter for the reactor performance and is controlled by TIC0809. This
temperature control is being achieved by controlling the fuel oil / fuel gas and combustion air
flow rates to the charge heater cascaded through fuel oil / fuel gas flow controller and
combustion air flow controller.
F. REACTOR
The two phase combined feed exiting heater enters the top of the reactor at a temperature of
332 oC and at a pressure of 24.9 Kg/cm2 (g). As the reaction mixture flows downward through
the catalyst beds, the hydrotreating reactions occur which are exothermic in nature. The heat
liberated is absorbed by the liquid and gas streams and hence the reactor effluent outlet
temperature increases to 343 oC. The reactor inlet temperature is controlled by TIC0809. The
pressure at reactor outlet is 24.4 Kg/cm2 (g) and it decreases towards EOR. The pressure drop
across the reactor is monitored by PDI0903 which gets the input from PI-0901 and PI-0902.
Reactor effluent from combined feed exchanger is routed to the product condenser (72-A-01)
before entering the separator (72-V-04). It is recognized that the inherent corrosivity of the
reactor effluent stream is a function of the ammonia and hydrogen sulfide content. The primary
corrosive component in the system is aqueous ammonium bisulfide formed when the process
stream is condensed. Presence of oxygen in the system may aggravate the corrosion problem. It
is also noted that the corrosive medium acts in conjunction with high tube velocities, generally in
excess of 4-6 m/sec. This subjects the tube to corrosion-erosion type of attack. Areas of high
velocity and high turbulence, such as tube ends, return bends and downstream pipe bends are
most prone to attack with the corrosion occurring in a highly localized, random manner. Thus the
specific design of the air cooler restricts the velocities to 6 m/sec max and 3 m/sec min from
common junction at inlet to the common junction at the outlet. Uneven distribution of flow to the
condenser may result in tube velocities in excess of the recommended maximum limit of 4-6
m/sec. The importance of the good distribution has been recognized and symmetrical
manifolding at the condenser inlet and outlet is provided. A constant supply of wash water is
necessary to dissolve ammonium bisulfide and ammonium chloride salts from the reaction
products. Both ammonium bisulfide and ammonium chloride can solidify and precipitate on cold
surfaces in the combined feed exchangers if the ammonium concentration is allowed to build up
in the recycle gas. Low condenser temperatures may result in tube plugging due to the
precipitation of solid ammonium bisulfide, ammonium chloride that can corrode/foul the product
condenser tubes. If the temperature in any of the bundles drop below the salt deposition
temperature, tube plugging can occur which in turn increases the velocity through the tubes
exposing them to attack by corrosion-erosion. It is not sufficient to measure and control the
temperature of the combined stream leaving the condenser, since the outlet temperature from
some of the bundles may be considerably lower as a result of uneven flow distribution or
excessive air flow to some areas.
Ammonium Chloride may be formed if there is any chloride in the system. The purpose of the
wash water injection is to dissolve these salts before they precipitate on tube surfaces in
exchangers and piping surfaces. To avoid the precipitation of these salts that can corrode and a
foul cooler tubes, wash water is injected into the reactor effluent stream before it enters product
condenser. There are two injection points. One injection point, usually in line, is at the inlet of
product condenser (72-A-01) and the other one is at the inlet of combined feed exchanger (72-E-
01 A-G). Wash water injection upstream of 72-E-01 is intermittent and is carried out if fouling is
suspected due to ammonia salts. Wash water is injected in a vertical run of pipe through an
injection quill that facilitates mixing. Following are the guidelines to determine wash water rate
and quality:
Sufficient water should be injected to ensure at least 20% of water remains liquid after
injection. This is to avoid flashing of the water and creating an acidic environment when the
first drop of water begins to condense or a localized high concentration of salts.
Sufficient water should be injected to maintain the concentration of ammonium bisulfide in
the sour water below 8 wt%. This will minimize the potential corrosivity of the sour water in
the air cooler tubes and outlet piping.
The minimum wash water injection rate is 5 vol% of the fresh feed.
Wash water should be clean condensate. Stripper sour water can be used up to maximum 50
% of the total rate depending on its quality. However, stripper sour water should come from a
sour water stripper that does not process sour from other units particularly FCCU.
The product condenser inlet and outlet piping should be symmetrical to ensure even
distribution of flow through each tube bundle. The velocity through the tubes should be in the
range of 3-6 m/sec.
Wash water used in the unit is clean cold condensate. Wash water break tank level is controlled
by LIC1101 with cold condensate make up. Cold condensate is received via 3 line. Wash water
pumps (72-P-02 A/B) take suction from wash water break tank and the pump discharge is going
to product condenser inlet line and combined feed exchangers tube side inlet line by separate 2
lines. Wash water injection rate to the inlet of the product condenser (72-A-01) is controlled by
FIC1101. Alternative wash water injection point has been provided in the upstream of 72-E-01
via 2 pipe. If fouling due to ammonium salts is suspected in the combined feed exchangers,
washing of these exchangers can be performed by changing wash water injection point location
from the upstream of product condenser to the upstream of these exchangers. Tube side pressure
drop across 72-E-01 indicates fouling of tubes.
I. SEPARATOR
Reactor effluent finally enters the separator (72-V-04) via inlet distributor at a temperature of
55 oC. Separator is a horizontal KCS vessel having a water boot welded to the underside. The
purpose of the separator is to separate the recycle gas, water phase and hydrocarbon phase in the
reactor effluent. A mesh blanket is provided to coalesce water droplets from the hydrocarbon
phase. The bottom half of the separator is lined with a 3mm layer of SS for corrosion protection.
The reactor effluent enters the separator through a slotted inlet distributor at one end. The sour
water coming out from separator water boot is sent to the sour water treating unit on interphase
level control LIC1301. This sour water contains a large concentration of highly toxic H2S and
NH3. The hydrocarbon level in the separator is controlled by LIC1302, which actuates level
control valve LV1302 going to the stripper feed naphtha splitter bottom exchanger (72-E-02).
This stream then passes through stripper feed bottom exchanger 72-E-03 A/B for preheating
before entering stripper (72-C-01) on feed distributor tray between 20th and 21st trays. Separator
pressure i.e. system pressure is controlled by pressure controller PIC1301. Low pressure in the
separator will open PV1301 and introduce more make up hydrogen upstream of the product
condenser. High pressure in the separator will be lowered by opening HIC1301 and venting
hydrogen rich gas to flare.
separator hydrocarbon to stripper line via 1.5 line from the bottom of the drum periodically.
Level indicator LI1401 provides high/low level alarm in the DCS control room.
M. STRIPPER
Stripper (72-C-01) is a vertical vessel constructed of killed carbon steel. It has 25 nos. of valve
trays. Feed is introduced on the 20th tray via distributor. A reboiler is provided to strip off H2S
and lighter components from the hydrotreated naphtha by providing necessary heat of
vaporization. Reboiler vapor stream is admitted below the bottom tray i.e. 1st tray. Unstabilized
naphtha from stripper reflux pumps is introduced on the top tray i.e. 25th tray as cold reflux to
control stripper overhead temperature and to achieve product specifications. Two nos. of
pressure safety valves (PSV05A/B) are provided on the stripper to relieve the pressure build up
by loss of reflux due to partial power failure/cooling water failure. Preheated separator
hydrocarbon enters the stripper at 166 oC.
Stripper runs on total reflux. Stripper overhead vapors leaving the top of the stripper are cooled
in stripper overhead condenser (72-A-02) from 122 oC to 55 oC. Stripper overhead condenser
handles stream containing high H2S. Overhead product exiting overhead condenser is routed to
stripper overhead vapor line through a line which expands to 1 before connecting to stripper
overhead line.
cascaded through fuel gas flow controller. Stripper naphtha splitter bottom level is controlled
bottom level is controlled by LIC1901 cascaded with FIC1601 controlling flow to storage.
Naphtha splitter bottom is routed to CCR unit through stripper feed splitter bottom exchanger
tube side (72-E-02).
UTILITY SYSTEM
4.3.1. Sea cooling water system
Sea cooling water to Naphtha hydrotreater is supplied to NHT / CCR ISBL through 26 header.
A 24 cooling water supply header supplies cooling water in Unit 72 to exchangers (72-E-06
A/B/C/D), (72-E-05 A/B/C/D) and compressor (72-K-01 A/B).
SECTION-5
PRECOMMISSIONING
5.1 PRECOMMISSIONING
As the new unit nears completion, there is a large amount of preparatory work, which should be
performed by the operating crew. A planned check of the unit will not only set the foundation of
a smooth start-up, but will also provide a firm basis for acquainting operators with the
equipment. Start-up is a critical period and the operator must know exactly the operation of all
equipments.
Some of the pre-commissioning works can be carried out simultaneously along with
construction. But, care in the organization of this work is necessary so that it will not
interfere with construction work. It is most important to plan schedule and record with
checklists and test schedules all the preliminary operation and to co-ordinate the
construction program.
Once contractor completes work, sections of the unit should be checked out by both refinery and
UOP personnel in those areas. Immediately punch lists that indicate the deviations from the
design specifications, should be written following inspection of those areas, and distributed to
the contractor. In this manner mistakes in construction can be found and corrected early.
Inspection of the plant can be basically divided into the following areas:
Vessels
Piping
Heater
Exchanger
Pumps
Compressors
Instrumentation
Catalyst/Chemicals Inventory
A discussion and lists of the major points that must be examined in the inspection of these areas
follows:
B. Other Vessels
1. Vessel trays: spacing; levelness, orientation and dimensions of weirs, downcomers,
accumulators, drawoff and trap trays, seal pans, distributors, baffles, nozzles, tray contact
devices; metallurgy of trays, contact devices, clips, bolts, nuts and gaskets; freedom of
movement of valve caps or other contact devices; number, size, and distribution of tray
contact devices or perforated plate holes; proper fit of all internals and proper welding of
support rings or other support devices; liquid tightness of drawoff trays, seal pans and
accumulators, all bolting and clips tightened.
2. Mesh blankets and outlet screens: size, location, levelness, suitability of fit (no bypassing
allowed), metallurgy of blanket, support, tie wires, and grids.
3. Vortex breakers: type, size, and orientation.
4. Baffles: type, orientation, levelness.
5. Instrument nozzles: location, orientation, cleanliness, thermowell length and metallurgy,
baffle size and type.
6. Inlet distributors: type, size, orientation, levelness, freedom to expand.
7. Non-fired reboilers: location, orientation, proper supports.
8. Packing: type, size, support, installation.
9. Internal ladders and other devices: location, size, orientation, properly secured.
10. Lining and refractory:-
Hex-steel for concrete lining: clean and properly secured. Lumnite or other specified
cement applied according to the specifications, with no holes or gaps in the
applications.
Metal linings in good condition. Weld overlays have no gaps or holes in the
application.
Lining is of the proper thickness and covers the required portion of the vessel.
Other refractory installed correctly with no gaps or holes in the application.
C. General
The vessel should be clean (free from trash) and should not have excessive mill scale.
Reactor skin thermocouples are located properly and installed so that they have good
contact with the wall.
5.3 PIPING
The unit must be constructed in accordance with Piping and Instrumentation Diagrams (P&ID's),
including all details, elevations, dimensions, arrangements, and other notes on the P&ID's. One
must be able to startup, shutdown and conduct normal operations on the unit as envisioned in the
licensor design. Also, piping for special procedures such as dry-out, special materials
preparation, regeneration and/or alternative flow schemes may have been incorporated into the
unit's design, and the unit should be able to operate in all of these modes with piping as designed
and constructed.
If the unit is connected to other process facilities, adequate means must be provided to receive
feed from or send products to these facilities without contamination of these streams, and
minimize as much as possible the effects of upsets of other process units especially where
contamination of feed or product stream might occur. Check all tankage interconnections to
minimize the possibility of stream contamination outside of the battery limits.
Check that adequate means of measuring flows, pressures, and temperatures, and sampling of all
process streams has been provided.
The following items must be checked to ensure conformity to the design specifications:
1. Flanges: rating, facing, and metallurgy; type (typically, 2" and smaller are socket weld, 2"
and larger are weld neck flanges).
2. Gaskets: type; metallurgy (materials of retainer, jackets, winding, filler, etc.); thickness, ring
size, etc.
3. Fittings, connections and couplings: rating and metallurgy.
4. Valves: rating and metallurgy (body, trim, seats, etc.); packing; seat inserts; bonnet gaskets;
grease seals; socket-weld or flange type, rating and facing; installed in correct direction of
flow; lubricant provisions; gear operators; extended bonnets; stops; ease of operation.
5. Bolting: stud or machine bolts; bolt and nut metallurgy; bolt size.
c. Fuel gas, fuel oil and pilot burner tips are clean and oriented properly. Burners are
properly mounted with clearance for firing and removal. Castable refractory has not
been used for burner blocks. Fuel oil tip sizing is adequate with respect to actual fuel
oil viscosity.
d. Tubeskin thermocouples, if required, are located properly and installed so that they
have good contact with the tubeskin.
e. Refractory is in good condition before and after refractory dry-out. No refractory is
resting on tubes.
f. Heater shell expansion joints are packed with designed insulation material and clean.
g. Adequate space for tube expansion.
h. Heater shell is sealed to prevent escape of hot gases and entrance of atmospheric
moisture during shutdown.
i. Smothering steam and instrumentation connections are not covered by refractory.
j. Heater is clean and free from debris.
k. Heater instrument connections are open - not filled or covered with refractory.
e. Water coolers; inlet at bottom of exchangers; inlet/outlet block valves with a thermal
relief valve inside the outlet block valve; vent and drain connections inside the block
valves.
f. Witness a shell/tube differential pressure test, if possible (especially important in
feed/effluent exchangers). When leak testing piping and equipment, ensure that the
design shell/tube differential pressure is not exceeded.
6. Air-cooled exchangers:
a. "Auto-variable" or "standard-pitch" fans, as specified.
b. Motor switches accessible from grade and located near the exchanger.
c. Fan pitch set correctly as determined by fan amperage draw.
d. Vibration switches on each fan.
e. Proper motor/fan rotation. Motors properly grounded.
f. Proper elevation and distances from connecting equipment.
g. Belt tension on motor drive pulleys is equal and correct.
h. Motor amperage can be easily checked.
i. Exchanger free to expand.
j. Manifold piping arrangements as shown on P&ID.
k. Split header design where specified.
l. Free draining requirements, as shown on P&ID.
m. Tube fin surfaces are in good condition with no construction debris on top of the fins.
7. Adequate space has been provided for pulling tube bundles.
5.6 PUMPS
A. Centrifugal Pumps
5.6.1. Specification Check
The design specifications should be reviewed against the pump curves and data given by the
vendor to confirm agreement on the following:
a. Head and capacity.
b. Pressure and temperature rating.
c. Speed.
d. NPSH requirement.
e. Pump type, materials of construction, flange ratings, seals, bearings, number of
stages, lubrication and cooling systems, etc.
f. Type of driver.
g. Balancing lines for multistage pumps must have flanged joints (not unions).
B. Reciprocating Pumps
The vendor information should be checked against the specifications to verify agreement on the
following:
1. Head and capacity (minimum, normal, maximum).
2. Materials of construction (body/glands, plungers, diaphragms, packing, internal check
valves).
3. Cooling/lubrication systems.
4. Pressure, temperature ratings.
5. Relief valve setting must be bench tested.
6. Pump speed and stroke.
7. Pulsation suppression devices, if required.
Means for calibrating the pump flow rate should be investigated.
C. General
The following items should be checked for all pumps:
1. Piping to be arranged to permit removal or replacement of pump and driver.
2. Piping independently supported from pump; pump will not be pulled out of alignment when
lines get hot; no vapor pockets in piping.
3. Suction strainer easily removed for cleaning; strainers fit well so no bypassing can occur;
strainers have been installed.
4. Discharge pressure gauge readable from discharge block valve.
5. Suction/discharge valves easily accessible and operable, and near to the pump. Accessibility
of auxiliary piping and controls.
6. Check that NPSH requirements have been met.
7. Warm-up lines provided across discharge check valve when pumping hot fluids.
8. Base plate grouting complete.
9. Steam tracing and insulation provided on suction/discharge lines, pump casing, and process
seal flush lines, as required.
10. Minimum flow bypasses (with restriction orifice), if required.
11. All seal oil, warm-up, etc. lines have flanged connections and valves to permit removal of
pump.
12. Lubrication and cooling systems operate correctly.
13. Adequate means for venting and draining the pump casing are available.
14. Vacuum service pumps must have a discharge vent back to the system to allow filling the
pump with liquid.
15. Pumps and drivers are aligned correctly.
16. Check valves are of proper type and installed in the correct direction.
17. All drains from pumps and associated piping and instrumentation should be routed to a safe
location.
5.7 COMPRESSORS
A. Centrifugal Compressors
5.7.1. Specification Check
The design specifications should be reviewed against the vendor information and drawings to
ensure agreement on the following:
a. Design capacity, temperature, pressure and specific gravity.
b. Compression ratio, number of stages.
c. Type of compressor, materials of construction, flange type, rating and facing.
d. Lube and seal oil systems, and estimated seal oil leakage.
e. Instrumentation, as supplied, must be in accordance with the design specifications.
f. Piping furnished with the compressor must conform to the same pipe class as
connecting lines.
B. Reciprocating Compressors
5.7.3. Specification Check
The vendor information and drawings should be compared with the UOP design specifications to
verify conformity on the following items:
a. Type of compressor, materials of construction, flange type, rating and facing.
b. Number of stages, compression ratio for each stage.
c. Design capacity, pressure, temperature and specific gravity for each cylinder.
d. Compressor speed; piston speed.
e. Lubricated or non-lubricated.
f. Single or double acting; balanced and opposed or dummy crosshead; fixed or variable
clearance pockets; auto or manual suction valve unloading.
g. Cooling to cylinder, packing, gearbox, lube oil.
h. Lube oil system operation.
i. Pulsation suppression devices; distance piece design; packing and distance piece vent
piping.
i. Acidizing requirements have been met and acidized piping is not in contact with the
atmosphere (under nitrogen blanket), includes both process and lube oil piping.
j. Provision for suction strainers, if required.
5.8 INSTRUMENTATION
All personnel on site should check to ensure that the instrumentation is provided as specified;
that it is functional; and that a minimum of instrumentation problems will occur when the unit is
commissioned. Some of the basic items which must be checked include the following:
1. Instrument type, range, and size.
2. Materials of construction and rating of instrument, accessories, and connecting
piping, flanges, and valves.
3. Accessibility of instrument for routine checks and maintenance; rigidly mounted.
4. Installation according to correct UOP drawing details.
5. Accessories (pulsation dampeners, filter/regulators, diaphragm seals, excess flow
checks, seal pots).
6. Location of local indicators so they are readable from grade platform or controller
assembly, as required.
7. Process requirements of flow, temperature, pressure, differential pressure, specific
gravity, etc.
8. Controller type, number of modes, chart type, range, cascades.
9. Power requirements of voltage, frequency; emergency power supply and connections.
10. Calibration of controllers, transmitters, analyzers, special instrumentation.
11. Control valve, block and bypass valve sizes for control valve assemblies.
and are properly stored (for example, in drums, indoors, and on pallets to prevent
contact with moisture).
2. It must be verified that all equipment required to load the catalyst is on site and in
good condition.
B. Chemicals
It must be verified that the proper type and quantity of chemicals (such as inhibitors, sulphiding
agent, soda ash, etc.) are on site and stored properly.
1. Vessel Inspection
Inspection of the vessels can be undertaken as soon as the UOP Chief Technical Advisor arrives
on site. Refer to the previous section on Pre-commissioning for a more detailed discussion on
vessel inspection.
2. Flow Check
The actual arrangement of lines, vessels, pumps, etc., must conform to the UOP Piping and
Instrumentation (P&ID) drawing. As soon as construction is completed, and if possible even
before, the unit must be carefully checked against the P&ID and the appropriate UOP
specifications. This has been discussed in the previous section on Pre-commissioning.
2. 50 psi (3.5 kg/cm2) lower than the lowest shop test applied to any item on the circuit.
5. Utility Systems
The various utility lines should be tested and placed into service as soon as the construction
schedule allows. Pressure tests should be carried out on the steam, condensate, air, fuel gas, fuel
oil, flare, and nitrogen lines. The steam lines should be warmed up gradually to prevent damage
by water hammer. At the same time, all steam traps and condensate lines should be placed into
service. Scale and construction debris can be conveniently removed from the steam lines by
blowing them as long as necessary with steam. The other utility lines can be cleaned by blowing
with steam or air, or by water flushing if possible. All utility lines, with the exception of fuel and
flare, can be put into service as soon as the construction schedule allows.
6. Instruments
All instruments should be checked as soon as possible so that any malfunctions or other faults
can be detected early. The instrument checkout should include the following items:
1. Pressure test of instrument air lines
2. Control valve action and calibration
3. Positioner calibration
4. Board calibration and loop check
5. Thermocouple calibration and identification
6. Level instrument calibration
7. Thermometers, pressure gauges, etc.
All orifice plate bores should be measured, recorded and compared with required sizes. The
orifice plates should also be checked to see if they were counter-bored wherever required. After
hydrotesting and water flushing have been completed, the orifice plates can be installed.
9. Dryout
Excessive amounts of water must be driven out of the reactor circuit prior to catalyst loading.
Under most circumstances, free water can be adequately removed by allowing it to drain from
the lines, heaters, reactors, exchangers, etc. while blowing through the lines with air. However, it
might be convenient to perform the dry-out of the refractory in the charge heater with the run-in
of the recycle gas compressor. Evacuate the reactor section with the steam ejector.
1. Hold the vacuum for several hours and repair any leaks.
2. Break the vacuum with nitrogen to slight positive pressure.
3. Pull another vacuum and break it with nitrogen again to 75-100 psig (5.3-7 kg/cm2g),
or the lowest allowable for recycle compressor operation.
4. Check the entire reactor section for leaks by taping all flanges and checking with a
soap solution through a pinhole in the tape.
5. Purge the recycle compressor with nitrogen and open the suction and discharge block
valves, taking suction from the cold separator.
6. Start the recycle gas compressor and gradually bring it up to full speed.
7. Steam out the recycle gas heater fire box and then remove the blinds from the fuel gas
line.
8. Light pilots in charge heater.
9. Light burners and fire the charge heater as required for refractory dryout. Circulate all
of the recycle gas through the charge heater. Start effluent condenser fans.
10. Drain water from the separator and all low point drains as it accumulates.
11. Raise the reactor inlet temperature to 700F (370C) as allowed by the heater dryout
procedure.
12. The reactor circuit will be considered dry when only a small amount of water collects
in the low point drains and separator.
13. Shut down the heater fires and cool the reactor to about 140F (60C) or less by
continuing gas circulation.
14. When the reactor is cool, shutdown and block in the recycle compressor.
15. Depressurize the system to the atmosphere. While depressurization, some of the gas
could be used to blow back through the reactor charge lines to remove any trapped
water.
16. Open the reactor for catalyst loading.
SECTION 6
COMMISSIONING
The startup procedure must be reviewed / approved by the licensor before the start-up /
operation of the unit.
Pre-startup Checklist
Notification to other department.
Leak Test.
Catalyst drying and prewetting
Testing of emergency depressurizing system.
Catalyst sulphiding.
Establishing normal operation.
The start-up procedure outlined below assumes that all rotating equipment has been run in,
heater refractory and unit dry-out have been completed, and hydrogen is available.
Recycle compressor suction drum 72-V-05 >> Recycle gas Compressor Suction C01.
II. Carry out the leak test of the section by pressurizing the circuit and holding the pressure
for two hours.
III. Depressurize the circuit and prepare the circuit for evacuation.
IV. Deblind suction line to the ejector & line up the ejector for vacuum pulling. Keep
Recycle gas compressor isolated by closing both the isolation valves at suction /
discharge side and closing compressor bypass line. Isolate all instruments like PG/PT
before vacuum pulling. Line up MP steam to ejector and evacuate the section to (500-600
mm Hga).
V. Hold this vacuum for 30 mins. If rate of vacuum fall is more than 25-50 mm of Hg per
hour, break the vacuum by introducing nitrogen at Compressor discharge via line and
pressurize this section to 0.30 kg/cm2g. Identify the leakage and rectify. Repeat the
vacuum test until a good vacuum can be held.
VI. On completion of vacuum test purge the circuit by repeating this pressurization to 0.30
kg/cm2g and pulling vacuum until oxygen content, measured at Reactor downstream is
less than 0.5 mole %.
VII. Compressors are purged separately by pressurizing with nitrogen through nitrogen line in
the compressor suction via compressor discharge and finally depressurizing through
compressor bypass line back to atmospheric vents, located outside compressor shelter.
Repeat this pressurization & depressurization for at least three times to ensure oxygen
content from discharge side is less than 0.5 mole%. While vacuum pulling in the
reactor section being done ensure that compressor is not subjected to vacuum. After
purging, pressurize compressor with nitrogen.
VIII. After completion of purging, of the compressor & HP loop line up both the compressor &
start pressurizing with Hydrogen through the startup line at the compressor discharge.
IX. Start one of the compressors and establish hydrogen circulation across the reactor.
X. Pressurize the reactor to a pressure of 14 kg/cm2
XI. Once the hydrogen circulation is established, start lighting the pilots for charge heater
Template No. 5-0000-0001-T2 Rev A Copyrights EIL- All rights reserved
Doc No. Draft
OPERATING MANUAL FOR
NAPHTHA HYDROTREATER UNIT, Rev. A
VRCFP, HPCL VISAKH Page 81 of 197
Battery limit >> Feed Surge drum 72-V-01 >> Charge Pump 72-P-01 A/B >> Feed filter
72-X-01 >> Start up bypass control valve 72-FV-0702 >> Stripper Feed Naphtha Splitter
Bottom Exchanger Insulate 72-E-02 (shell) >> Stripper Feed Bottom Exchanger Insulate
72-E-03 A/B (shell) >> Stripper 72-C-01 >> Stripper Condenser 72-A-02 >> Stripper Receiver
72-V-06 >> Stripper Reflux Pumps 72-P-04 A/B >> Stripper Bottom >> Stripper Feed Bottom
Exchanger Insulate 72-E-03 A/B (tube) >> Splitter 72-C-02 >>Naphtha Splitter
Condenser 72-A-03 >> Naphtha Splitter Receiver 72-V-07 >>Naphtha Splitter Overhead Pump
72-P-06 A/B >> Naphtha Splitter Bottom Pumps 72-P-05 A/B >> Stripper Feed Naphtha Splitter
Bottom Exchanger Insulate 72-E-02 (tube) >> Naphtha Splitter Bottom Coolers 72-E-06
A/B/C/D >> Feed Surge drum 72-V-01
After steam out operation is complete (when oxygen content is less than 0.5 mole %), line up
nitrogen in order to avoid vacuum formation and subsequent air ingress. Ensure draining all the
condensate from all the points.
I. Before starting steam out ensure the following :
1. Battery limit de-blinding to be done as per list.
2. Fans of fin-fan coolers are stopped & push button switches are locked.
3. Crack open high point vents and low point drains on the vessels to be steam purged.
4. During the steam out of each operation, open vents on all dead legs in the system to purge
these lines free of air. Be sure to steam out feed and product lines all the way to the
battery limit.
5. Close all drain valves and vent connected to flare.
6. All Battery limit valves (Feed and Product) are closed. Feed filter banks are taken in line.
II. Provide LP steam connection to feed from tankage line & hot feed line ex Crude/ VB unit.
III. Feed surge drum pressure control valve remains blocked in. Open charge pump suction and
discharge valve. Keep min. circulation control valves blocked in and its bypass isolation
valve closed. While providing steam out connection, utmost care should be taken to ensure
that steam / condensate does not enter the reactor circuit.
IV. Inhibitor dosing system is to be isolated by closing valve to the stripper overhead line.
Ensure steam out is done via PV 1801 upto battery limit block valve.
V. Steam out stripper bottom circuit till battery limit.
VI. Open steam to all steam out points mentioned above & stripper steam. Continue steam out
for 12 hours. Towards end of steam out start closing the open vents and line up fuel gas to
the Feed surge drum. After draining the condensate close the open drains and gradually
raise the pressure of the feed surge drum.
VII. Deblind nitrogen gas supply connection to stripper receiver. Pressurize stripper receiver to
by backing up nitrogen.
VIII. Receive SRN through battery limit line ex tank.
IX. Keep charge pump discharge isolation valves close & line up minimum circulation flow
control valves. Open pump suction isolation valve to fill the lines of this circuit, gradually
open the discharge isolation valve to fill the lines of this circuit. While filling the lines non-
condensable has to be vented through high points vents.
X. Start the feed charge pump. Take level in the stripper through reactor bypass line &
establish 60% level in stripper. Line up stripper bottom to Splitter & establish close
circulation through startup reactor bypass line by lining up back to feed surge drum through
different exchangers.
XI. Once the level in stripper and splitter has been established start the heat input to allow
sufficient heat reflux to remove essentially all water from the bottom products.
XII. Slowly heat up the column bottom at the rate of 20 oC /hr. When the temperature reaches
100 oC reduce the heat up rate to 10 oC /hr to allow any water in naphtha to expand slowly.
XIII. Change over the charge pump after 4 hrs. Clean the suction strainer. Make sure that all
bypass lines across control valves are flushed out with SRN.
XIV. Ensure that level and flow control instruments are taken into service.
NOTE: At this time the internal circulation should be stopped. Depending on the heat exchange
provided, the stripper feed temperature may drop; adjust the steam flow to steam reboiler to
maintain steady tower operation.
VI. After the 4 hours of once through flushing, re-establish internal circulation from Splitter
bottoms back to the front end, and increase the feed rates through the reactor to the
maximum possible.
VII. Raise Stripper column reboiler temperature or adjust stripper feed preheat in order to
increase Stripper temperature to reject H2S during catalyst sulphiding. Stripper bottom
temperature should be increased to about 220 C before catalyst sulphiding.
VIII. Start naphtha splitter reboiler heater and establish the splitter column.
IX. Higher feed rates over the catalyst will shorten the time required to sulfide the catalyst.
Slowly begin to increase the reactor feed rate as much as possible.
X. As the reactor feed rate is increased, monitor the pressure drop across the reactor beds to
prevent reactor damage due to excessive pressure drop. At the same time increase the
amount of recycle gas in the system to maintain the design hydrogen to hydrocarbon ratio.
XI. Begin raising the hydrotreating reactor inlet temperature, by increasing firing at Combined
Feed Heater, to 230 C at about 30 C per hour maximum once the initial temperature wave
has passed through hydrotreating reactor and the SRN flow has been lined out.
XII. After the reactor inlet and outlet temperatures have been stabilized at 230 oC increase the
product separator pressure to the normal operating level or 28 kg/cm2 which ever is lower.
NOTE: When raising the reactor inlet temperature, monitor the reactor feed heater operation
closely to assure the design heater firebox and stack temperatures and design heater tubewall
temperatures are not exceeded.
total amount of sulphur injected should be controlled at 0.08 0.10 wt % of naphtha charge,
depending on the catalyst metal loading. Before sulphiding begins, conditions in the fractionation
section should be established in order to assure the removal of H2S and light ends from the
reactor effluent. The stripper bottoms temperature should be raised by increasing the VHP steam
flow in the stripper reboiler. Increase stripper column reboiler temperature in order to reject H2S
during catalyst sulphiding. It will be necessary to rely on feed preheat to raise the stripper feed
temperature
Throughout the sulphiding procedure, maintain maximum recycle gas flow and normal operating
pressure with hydrogen. Note that the temperature controllers and transmitters may have to be
temporarily rearranged to control during the initial phases of the startup. Maintain the product
separator at normal operating pressure. Do not begin water injection to the reactor effluent until
after the sulphiding has been completed. The minimum time for this phase of the sulphiding will
be 1-2 hours. In practice, this is a reasonable minimum time required to sample feed, stripper
bottoms, and off gas streams while monitoring recycle gas H2S levels and sulfide chemical
injection rates, in order to perform a sulfur balance on the catalyst.
The objective is to conduct the sulphiding in a controlled, orderly fashion. If a lower sulfur
injection rate is required to accomplish this, the injection rate should be reduced accordingly.
Control the sulphiding within the following limits:
a. Do not exceed 450F (230C) maximum temperature in any catalyst bed.
b. Do not exceed 30F (17C) temperature rise across any catalyst bed.
Throughout this phase of the sulphiding, monitor the separator boot for water accumulation.
When water is detected, drain it from the separator water boot. Throughout the catalyst
sulphiding operation, the separator vent should be held at a minimum or zero to allow
establishing a high concentration of H2S in the recycle gas. After stable sulphiding condition is
established, then the hydrotreating catalyst bed peak temperature can be increased slowly at the
rate of 17 oC/hr up to 290 C. Continue sulphiding at these conditions until H2S in the recycle
gas stream increases abruptly to a higher concentration and stabilizes for a period of at least two
hours.
NOTE: Do not proceed to the next step with higher sulphiding temperature level until the
calculated sulfur laid down on the catalyst system at this point is at least 75% of the catalyst
sulfur requirement.
Increase Charge Heater outlet temperature at 17 C per hour maximum and establish 290 C
peak temperature in hydrotreating catalyst bed. When hydrotreating catalyst bed peak
temperatures reach 290 C, begin a 4 hour hold. Adjust bed inlet temperature set points to
control peak catalyst bed temperature. Continue to analyze the recycle gas for H2S content and
product sulfur. Reduce Charge Heater firing to cool hydrotreating catalyst bed inlet temperature
to 230 C. Stop catalyst sulphiding and isolate the sulphiding facility.
IX. Allow the unit to line out for several hours. Sample all products and adjust reactor
temperature as needed to meet desired product quality. Make small adjustments in reactor
temperature and allow the unit to line out after each change. Operate the reactor at the
minimum required temperature necessary to achieve product specifications. Adjust profile
to operate at equal peak temperatures.
X. After stable reactor and fractionating conditions have been established, the fresh feed rate
can be increased to approach design. The reactor feed rate can thus be increased
simultaneously in small increments until the design feed rate is attained.
XI. Continue to monitor the feed heater to ensure that the design duty and maximum allowable
tube wall temperatures are not exceeded.
XII. Adjust the stripper section as needed to remove H2S from the bottoms product and establish
stable operation.
XIII. When cracked feedstock is introduced, the rate should be increased slowly.
IV. Establish a descending temperature profile in each reactor with the catalyst bed inlet
temperatures being controlled at about 3C below the inlet temperature of the preceding
bed.
V. Start SRN to the reactors at 50% of design feed rate.
VI. Monitor any temperature wave in the reactors caused by the heat of adsorption when oil is
first introduced. Exothermic hydrotreating reactions will also begin generating heat.
Maintain a descending temperature profile throughout the catalyst beds. Watch all
temperatures closely.
VII. Start wash water injection.
VIII. Establish VB naphtha feed flow to the reactor at 50% of design feed rate.
IX. After the adsorption heat waves have passed and a level appears in the product separator,
gradually increase the SRN and VB naphtha feed rates to design. At the same time,
increase the reactor temperature at a rate of about 30 C per hour to 315 oC.
X. Once the reactor temperature has reached 260 oC, increase the separator pressure to normal
operating level.
XI. Once the stripper & splitter operation is stable, sample all products and adjust reactor
temperature as needed to meet product specifications.
XII. Increase the feed flows to the desired rates while at the same time increasing the reactor
temperatures to maintain consistent product quality. If proper precautions were followed,
the catalyst activity should be nearly the same as before the shutdown. Adjust the inlet
temperatures to obtain roughly equal bed outlet temperatures.
XIII. Maintain the product separator pressure at the design level. As the hydrogen consumption
Increases, it may be necessary to adjust the loading on the makeup compressors or put
another compressor on line
SECTION 7
NORMAL OPERATING PROCEDURES
7.1 INTRODUCTION
After the unit has been started up and lined out, the focus shifts to reaching and maintaining a
state of optimum operation. This state of optimum operation can be achieved by establishing a
few general operating rules and being aware of potential problems which can occur. First, a
means of judging performance must be defined.
Secondly, a list of operating variables is established. Using these operating variables, an
approach to operating the Isomar unit is outlined with respect to the performance indicators. This
procedure establishes a logical method for operating the plant, increasing yields and ensuring
longer catalyst cycles.
c. Space velocity
Space velocity coupled with reactor inlet temperature defines the severity of the hydrotreatment.
Severity is increased when either the space velocity is decreased or the temperature is increased.
Space velocity can be varied by changing the naphtha feed flow. Space velocity is reduced;
when the naphtha feed flow is reduced.
SECTION-8
NORMAL SHUTDOWN
The shutdown procedure must be reviewed / approved by the licensor before the start-up /
operation of the unit.
condenser at the start of cooling. Remove as much water as possible from the product
separator.
NOTE: Heat exchanger temperatures may be higher at this time than normal operations. Make
sure the exchanger design temperatures are not exceeded. In order to avoid the possibility of
nickel carbonyl formation, all gas streams containing carbon monoxide must be excluded from
the system when cooling below 260 C.
IX. Continue cooling the reactors with recycle gas to as low a temperature as is possible.
Cooling should be continued till the catalyst bed temperatures reach 65 C to allow time for
removal of heat from the reactor walls. Otherwise, after stopping the recycle compressor,
the catalyst beds will heat up again from the heat remaining in the reactor walls. If the
catalyst is to be skimmed or dumped unregenerated, reduce the reactor temperature to
38C.
X. Completely depressurize the unit to flare.
XI. Purge the reactor section with nitrogen until the system contains less than 1 mol percent
hydrogen plus hydrocarbons.
UNDER NO CIRCUMSTANCES SHOULD AIR BE PULLED THROUGH THE
CATALYST BED WHEN THE CATALYST BEDS ARE ABOVE 80 C. (This is to
prevent burning in the catalyst bed that could lead to high localized temperatures inside
the reactor and the formation of nickel carbonyl).
XII. The Splitter and Stabilizer columns should be cooled down by stopping reboiler heat input,
and should be left under positive fuel gas pressure. De-inventory Splitter and Stabilizer
columns if so desired. Divert products to slop as they go off-spec. Lower levels in all
vessels to minimize the amount of liquid to be drained or pumped out of the unit after it is
shut down. If entry into the columns is required, at a minimum, they must be drained,
steamed out, blinded off from other equipment, and air purged for safe entry.
VIII. The Stripper and Splitter columns and feed surge drum must be drained and steamed out
prior to opening any of the equipment. It is also recommended that the towers and receivers
be washed thoroughly with water before admitting air to prevent the ignition of the iron
sulfide scale on the walls.
NOTE: Special care must be taken during shutdown and maintenance to avoid personnel
entering an atmosphere contaminated with hydrogen sulfide or blanketed with nitrogen. All
vessels that are opened must be thoroughly tested to insure the safety of entry.
SECTION-9
TROUBLE SHOOTING
9.1 GENERAL
The main cause of concern for the operator of the hydrotreating unit is sulphur breakthrough into
the hydrotreated naphtha, contaminating platformer and isomerization unit feed. If an upset
occurs, the operator must be knowledgeable and experienced enough to take the proper
corrective actions immediately and to know if he should shut-off feed to the downstream units
before any catalytic activity loss occurs. It is advisable to even shutdown the downstream units.
The seriousness of the upset and the level of contaminant breakthrough will dictate the necessary
course of action to take.
This section offers some guidelines for troubleshooting various problems that may be
encountered over the course of normal operation of a hydrotreating unit. The information is
organized under the following general subject areas of the unit:
Reactor Temperature Increases
Reactor Pressure Drop
Reactor Catalyst Bed Maldistribution
Reactor Section Operation
Reactor Hydrogen Partial Pressure
Reactor Effluent Condensers
Product Separator Level Control
Corrosion Problems
Stabilizer Bottoms Product
9.2 REACTOR TEMPERATURE INCREASES
Symptom: On normal operation, the reactor top catalyst bed differential temperature
increases.
Possible Cause Remedies
A. Feed composition a. Check the operation of the upstream units.
changes from hot feed b. Check relative feed rates from upstream units to determine if
C. Hydrogen makeup compressor a. Check spillback control valves for correct operation.
spillback system has b. Check Product Separator pressure control system
D. Hydrogen makeup compressor a. Check the PSV's on each compressor suction drum, if
suction drums pressure safety passing.
valves passing. b. Check the PSV pressure setting in relation to the
actual operating pressure of the suction drums.
E. Hydrogen supply from a. Check and correct, if possible, the upstream supply
upstream hydrogen plant has problem.
decreased. b. If Hydrogen Plant is equipped with PSA unit, check
operation of PSA absorption cycles.
c. Check the Hydrogen Plant tail end pressure control
system.
d. Check the hydrogen supply pressure from the
Hydrogen Plant. Adjust if, possible, to correct
delivery pressure.
F. Product Separator control a. Check the HIC control valve to flare, if equipped.
valves to flare passing, or b. Check the pressure safety valves on the HPS for
leaking pressure relief valves. leakage.
Symptom: Failure of the Product Separator sour water level control valve.
Possible Cause Remedies
A. Possibly wrong type of valve a. Change valve internals metallurgy to 316SS.
metallurgy or wrong type of
valve.
B. Leak in stripper feed naphtha a. Introduce a chemical species into the feed which may
splitter bottom exchangers that be traced in order to determine if there is a leak.
may allow contamination of
product.
C. Change in Feedstock a. Check that the new feedstock does not have above
design values of nitrogen or sulfur.
b. Increase the reactor inlet temperatures as necessary to
remove all of the sulfur and nitrogen (if there is room
to do so within temperature limitations of
equipment).
c. If the above is not successful, reduce feed rates of
feed stream with higher nitrogen and/or sulfur levels
until blended stream falls within design values.
d. Consider revamping the unit if feedstock change will
be permanent.
SECTION-10
SPECIAL PROCEDURES
This section contains information on various special procedures that may be required in the
operation or maintenance of a hydrotreating unit. This information is organized under the
following subjects:
this time. After completion of unit air-freeing, a low pressure leak test should be performed using
nitrogen. As mentioned in the Pre-startup Checklist, all flanges in the high pressure section
(reactor and make-up gas sections) should have been taped. This allows for easy flange checking
with the use of soapy water solution. In addition to all flanges, all instrumentation fittings and
valve packing need to be thoroughly checked.
Upon completion of a successful pressure test at low pressure with nitrogen, the system pressure
should be raised using nitrogen. A second pressure test and leak testing effort should be
conducted at typical nitrogen supply header pressure.
The next step would typically be to start using hydrogen from the makeup gas compressors to
boost system pressure. Reactor pressure should be increased in increments with sufficient hold
time at each pressure level to allow a detailed leak check on all flanges, fittings and valves to be
performed. Suggested pressure increments are between 200-400 psi (15-25 kg/cm2). The
pressure can be held at each level by placing the make-up compressor into full spillback mode.
Further into the startup, reactor temperatures will be increased as part of the Catalyst Activation
and Establish Normal Feed procedures. At this time hot bolting may be required. Further leak
testing of flanges should be included as part of this work. Several methods can be utilized to
check for leaks. Any of these can be effective, if used properly.
As described above, a soapy water solution can be applied to taped flanges. This is the most
common method used by refiners. However, it will not be effective if the tape will not adhere
to the flange. Tape may not adhere to hot flanges or to flanges in some environments such as
high humidity conditions.
An ultrasonic listening device can be employed. This can be useful for identifying most
leaks. However, it might not be applicable for steam leaks due to low sensitivity.
A hydrogen analyzer or combustibles meter can be used to test all flanges. Using this in
conjunction with taped flanges can increase the ability to detect leaks. This method will not
work if combustibles are not in the unit. For example, during initial pressurization with
nitrogen, a hydrogen analyzer or combustibles meter will not detect a leak. If a leak is
detected, reduce pressure until the leaking stops and then tighten the flange.
a. Non-sparking tools should be used to prevent the possible ignition of hydrogen.
b. A steam hose should be ready and available near the flange to smother any potential fire
that might occur.
c. If a major leak is detected, it will be necessary to completely depressurize the system,
isolate the leaking flange and purge the piping with nitrogen to remove any hydrogen.
d. After a section of piping is hydrogen-free (as shown on combustibles meter), open the
flange and replace the gasket.
e. Re-purge section with nitrogen after performing work and ensure that the affected section
is oxygen-free (<0.5 mol %).
P = P0 emt
where:
P = pressure at any time
Po = pressure at time zero
m = constant = slope of natural logarithm P versus time
t = time
Determine the slope of this line by graphical means or by linear regression of the pressure and
time data. For any two points, 1 and 2, on the plotted line, the slope is:
(ln P2 - ln P1)
m=
(t2 - t1)
The target depressurizing rate is the rate that will decrease the pressure to 20% of normal
operating pressure in 15 minutes. Use the following equation to determine that drop in pressure:
dp
= Po (1 - em)
min
where:
dP/min = decrease in pressure in first minute
Correct the test depressurizing rate to middle-of-run (MOR) operating conditions and gas
properties:
V ZTsMN
0.5
ZT k
dp dp
Test
Test
=
minMOR minTest V ZTsMN
ZT MOR k MOR
where:
(k + 1)
k + 1 (k - 1)
N =
2
If the results of the depressurizing test indicate that the orifice size is incorrect, a new diameter is
calculated with the following expression:
dp 0.5
min
D2 = D1 2
dp
min1
where:
D1 = existing orifice diameter.
Catalyst is typically received in sealed steel drums and/or flow bins. For destinations in North
America, the catalyst can also be transported in DOT approved supersacks. The reactors and the
loading equipment should be free of water and purged with nitrogen prior to and during loading
operations.
10.6.1. Discussion
It must first be decided how the catalyst is to be lifted to the top of the reactors. It could be lifted
in its original drums by a monorail or pulley system, but the quickest and probably best way is to
lift the catalyst by a crane. If a crane is used, the loading time can be greatly reduced by
constructing two large transfer hoppers to move the catalyst from the ground level to the top of
the reactors. In this case, a transfer-hopper loading platform must be constructed in a convenient
place close to the reactors. The loading platform can be constructed of scaffolding and wooden
planks or of any other convenient material. The platform area should be at least large enough to
accommodate enough drums to load one hopper and to allow working room for the personnel
who will do the loading.
Regardless of the way the catalyst will be lifted, a convenient, temporary storage place near the
reactor must be found for the catalyst. The catalyst should be stored on pallets and completely
covered by canvas to give a certain measure of protection against the elements. A forklift or
some other means of moving the catalyst from this site to the loading platform (or to any other
place) should be available.
The catalyst loading path, both on the ground and through the air, must be checked so that it is
entirely free from obstruction. To assure this, it may be necessary to remove or modify the
reactor superstructure, the piping support, or the piping itself. Failure to obtain a clear loading
path could result in a slow and hazardous loading procedure. A typical lay-out for the catalyst
loading is shown in Figure XIII-1.
Figure XIII-1
Typical Lay-out for Catalyst Loading
A list must be made of all the accessory equipment that will be needed to do the loading. A
partial list of some of the items that will be needed follows:
c. One crane (not necessary, but very helpful if available) and safety hitch for the crane hook.
d. One forklift.
e. Two large transfer hoppers (also not necessary, but desirable) and separate lifting cables for
each hopper.
f. One transfer hopper loading platform if transfer hoppers are to be used. One loading hopper
to rest above the reactor.
g. Explosion-proof lights inside the reactor (and also flashlights).
h. Ceramic rope to protect the manway ring joint and to fill crevices created between reactor
internals.
i. Ceramic gasket or wooden cover to protect the reactor manway and elbow flange gasket
surfaces.
j. Canvas for covering the catalyst drums and for covering the reactor inlets between loading
intervals as protection against rain, snow, etc.
k. A safe ladder to enter and leave the reactor.
l. Loading socks of correct diameter and sufficient length to do the loading in the manner
planned.
m. Wooden boards to stand on while inside the reactor and to level the catalyst and catalyst
support material.
n. A vacuum eductor to remove catalyst dust.
o. Dust masks for the personnel who will be working with the catalyst. Fresh air masks may be
desirable for the personnel who will be doing the actual loading inside the reactors.
p. Measuring tapes for both small and large measurements (such as catalyst loading outages).
q. Chalk, crayons, or other types of markers to mark the reactor walls.
r. Miscellaneous hand tools such as pliers, screwdriver, etc.
s. Air hose to supply air to the dense loading machine (for dense loaded catalysts).
t. A planned loading diagram is prepared and supplied to the loading supervisor.
10.6.2. Procedure
The bottom reactor internals consist of the catalyst support outlet cover stool and the catalyst
unloading support plate. The catalyst support stool is typically constructed of profile wire screen.
The entire support grid should be inspected for deviations from the project specification (slot
widths, metallurgy, fit-up, etc.) and for structural weaknesses. Near the base of the catalyst
unloading nozzle the catalyst support plate is installed. A ceramic rope must be placed on top of
the plate to plug the unloading nozzle. The removable support plate rests on three equally spaced
lugs. This support plate allows the removal of the nozzle blank flange and the installation of an
external unloading spout prior to the actual removal of any catalyst.
Once the bottom internals are in place, the loading may be started, beginning with the catalyst
support material as follows:
a. A level layer of 3/4" (19mm) diameter ceramic support material (CSM) is loaded to a level
height above the outlet support grids.
b. A level layer of 1/4" (6mm) CSM is placed on top of the 3/4" (19mm) CSM.
c. A level layer of 1/8" (3mm) CSM is placed on top of the 1/4" (6mm) CSM.
d. When loading each layer of the catalyst support material, care must be taken so that the
previous layer of balls is not disturbed. Cratering of any layer may cause migration of the
balls, resulting in the migration of the catalyst bed.
e. The catalyst should be dense loaded by using UOP's dense loading equipment. Dense loading
has the primary advantage of allowing more catalyst to be loaded into the same reactor
volume. In general, there are only a few differences in the typical sock loading and dense
loading procedures. In dense loading, the loading machine is anchored either on the vapor-
liquid distribution tray manway or inside the reactor. A loading sock attached to the loading
hopper feeds the loading machine with catalyst. The operator of the machine regulates it so
that the catalyst is loaded uniformly and so that the level rises flatly. Even when dense
loading, it will probably be necessary to level the bed after reaching the desired catalyst
height. Afterwards, an outage measurement should be taken and recorded.
f. If the sock loading method is used, the sock should extend to the bottom of the reactor when
connected to the hopper in the reactor inlet manway. The catalyst must be loaded slowly at
first to prevent cratering of the support material. The sock should be kept moving in a figure-
eight pattern to prevent the catalyst from forming hills. It is important to keep the catalyst
bed as level as possible during loading so the loaded catalyst density is uniform throughout
the bed. The sock should be cut off as the catalyst level rises.
g. During the loading of the catalyst, an accurate count of the drums loaded and the drum lot
numbers must be recorded. It is advisable to retain a composite catalyst sample for future
reference composed of about 5cc from each drum loaded.
h. The reactor will be topped off by placing a layer of 1/4" (6mm) ceramic balls and a layer of
3/4" (19mm) ceramic balls on top of the catalyst bed. A catalyst loading diagram depicting
the actual loading should be drawn and retained for future reference (See FigureXIII-2).
Figure XIII-2
Loading Diagram
uo p DENSE LOADING
Customer Page No.
Subject Date
Project
By
UOP 3055-34
II.
supporting if the catalyst below were removed, then break up this crust and remove the material
before dumping the catalyst from the bottom of the reactor.
Continue to maintain a nitrogen blanket in the reactor, and unload the catalyst from the bottom.
If the catalyst is to be reused, it should first be screened to remove dust and fines that could cause
excessive pressure drop in the reactor, resulting in maldistribution. This can be conveniently
done during unloading by dumping the catalyst from the reactor directly into the screening
apparatus. Figure XIII-3 depicts a typical layout for this operation.
Figure XIII-3
UOP 2032-08
UOP-3054-26
For the upper beds in a multi-bed reactor, it will be necessary to use the side unloading nozzles
provided for each bed. If the reactor is equipped with angle unloading nozzles, the catalyst
should flow freely from the unloading nozzles. If the reactor is equipped with horizontal
unloading nozzles it may be necessary to use a catalyst auger or a vacuum system to induce flow
of the catalyst. Figure XIII-Figure 4 depicts an auger device for catalyst unloading.
Figure XIII-4
Catalyst Unloading Auger
B To Suit
3 5/16 1-1/2 6 2-0
3/16 PL
1/2PL
2 2
C 1/8
1/8
1/8
1/8
Grind Bolt Heads
C 1b
Lifting Lug
3/16 PL (TYP)
as Reqd to Insert
in Top Holes
2 9/16 Hole B Section C-C
(4) 9/16 Holes for 1/2x 1/2 Bolts
CTSK. Far Side 7/8 Dia. 4
4 3/16 PL Lifting Lug
Section B-B A
2 1
1b 6 SCH. 10 Pipe 1b Cut Corners
CL 1 Hole and Fair in
1/4 Pitch
6
A Discharge
BILL OF MATERIAL
ITEM DESCRIPTION
1 Rotary catalyst rake complete
1d and consisting of the following=
1a Air Motor Mounting PL a Air motor-Gast no. 8AM-FRV-2A
Guard Mounting Clip Reversible rotation, base mounted
b Gast muffler # AC 990 (for above)
1f
c Link-Belt type C shaft mounted
1c screw conveyor drive # 107D15
Provide 20 Ga. Steel
Belt Drive Guard for trough end mounting w/1 1/2
1e type B output shaft for 6 dia.
screw complete with motor bracket
Guard Mounting Clip for # 107D15 reducer to mount air
motor (item 1a above) adapter kit
2x2x1/4 Angle on Dump Funnel for # 107D15 reducer with felt seals
(See drawing #E-544-P--3) to suit output shaft. Shaft kit with
type B output shaft complete with
Section A-A retainer and self locking cap screws.
(For arrangement IT)
1g Screw Conveyer Flight
Conveyer Trough d V belt drive sheave 4.75 O.D. - 3/4
Air Hose bore . Standard keyway, single groove
1a Air Motor Worthington #3V-4.75
1d Pulley (4.75 O.D.)
e V belt drive sheave 6.50 O.D. - 3/4
1f V-Belt bore . Standard keyway, single groove
1a Pulley (6.50 O.D.) Worthington #3V-6.50
Hopper
Belt Drive Guard Platform f V belt - 3/8 x 45 Goodyear HY-T
1c Conveyor Drive Reactor C
L wedge belt #3V-450
Adjustable Legs
g Screw conveyer flight, 6 dia. right
To Standpipe hand with nominal 2 pipe shaft.
Link-belt helicoid type,
NOTE: Cat. # 6H-312-E
This drawing is presented for concept purposes only. h 6 SCH.10 (0.134 Wall) black wrought
Specific dimensions and equipment are for a device steel pipe.
designed by Unocal 76 Oil Company at its Los
Angeles refinery. UOP 3055-35
The screening apparatus should be enclosed and maintained under a nitrogen blanket to prevent
air from entering. Use the proper size screens to separate the catalyst from the ceramic balls, and
from the dust and fines. The catalyst should be dumped directly from the screening apparatus
into nitrogen blanketed metal drums. This can be accomplished by using a copper tubing line at
the unloading site to fill each drum with nitrogen before putting in catalyst. Allow the tubing to
remain in the drum as catalyst is being dumped into it to keep a steady stream of nitrogen
flowing over the catalyst.
After each drum is filled, remove the nitrogen purge line and immediately cover and tightly seal
the drum. Have CO2-type fire extinguishers and steam hoses available to quench any burning if it
should happen to occur. The CO2 is preferable if the catalyst is to be used again because it will
not wet the catalyst, and the catalyst will not, therefore, require a subsequent drying operation.
It is expected that some of the "sparking" of the pyrites will take place in any event. Therefore,
all workmen in the area must be supplied with face and eye protection. In addition, they should
wear long sleeve shirts with the collars and cuffs tightly buttoned.
Maintain a positive flow of nitrogen out of the unloading nozzle throughout the unloading. If the
catalyst becomes bridged in the unloading nozzle or is not free flowing, break the plug with a
blast of nitrogen. Do not allow air to be drawn into the reactor.
If ignition of pyrites takes place inside a reactor, stop unloading in that reactor and increase the
nitrogen purge to maximum until burning has stopped.
Purging Nitrogen
Nitrogen used for the purging and protection of austenitic stainless steels should be dry and the
oxygen content should be limited to a maximum of 1000 mol-ppm. The oxygen content of the
nitrogen used should be specified by the supplier, since the analysis for oxygen in this low
concentration range requires elaborate analytical equipment which may not normally be
available in the refinery laboratory. If the only nitrogen available has oxygen content in excess of
1000 mol-ppm, or if the oxygen content is unknown, then as a safeguard, ammoniated nitrogen
should be used where possible. However, for this case, catalyst safety considerations might be
necessary.
Ammoniated Nitrogen
To prepare ammoniated nitrogen for use in purging or blanketing an austenitic stainless steel
system, sufficient ammonia is added to the nitrogen to provide a minimum concentration of 5000
mol-ppm of ammonia. Whenever ammonia is added to the reactor system, the ammonia content
of the recycle gas should be checked frequently. It is expected that the catalyst will absorb a
considerable amount of ammonia, and, therefore, additional ammonia makeup will be required to
maintain the 5000-ppm ammonia concentration until the system reaches equilibrium. One
convenient method of adding ammonia to the system, especially when the system is at high
pressure, is to use a high pressure "blow case." With this type of arrangement liquid ammonia is
pressured into the blow case at low pressure from the ammonia cylinder, and then the blow case
is isolated. High pressure gas from the discharge of the recycle gas compressor is then used to
pressure up the blow case and to force the ammonia into the system at a location of lower
pressure.
All personnel working in the unit should be familiar with the toxic nature of ammonia, and must
follow proper safety precautions in working with the system when it contains ammonia. For
example, workers opening flanges or manways in a system containing ammonia should be
equipped with fresh air masks or other oxygen breathing equipment.
In order to preserve the activity of the catalyst in the reactors, ammonia is not to be passed over
the catalyst when it is in its oxidized form, that is, whenever the catalyst is either fresh or freshly
regenerated.
Brass and most other copper alloys are subject to corrosion attack from ammonia. Therefore,
arrangements should be made to isolate this equipment from the system before admitting any
ammonia.
present, which is usually the case during normal processing periods. As the heater tubes cool
there will be small amounts of water condensing inside the tubes; however, this water should not
be harmful in the absence of oxygen.
If the heater must be cooled down and it is suspected that trace quantities of oxygen might be
present, then before cooling the heater the system should be depressurized completely, but do not
evacuate. Evacuation at this point is perhaps possible, but not recommended because it
introduces the possibility of allowing air to enter the system. Continue to maintain the 205 C
firebox temperatures while depressurizing and purging. After the system has been depressurized,
pressure with nitrogen to any convenient pressure level. Repeat this depressurizing/pressuring
procedure as many times as required to reduce the oxygen concentration, by dilution, to as much
below 100 mol-ppm as is possible and reasonable. Then the fires can be shut down and the heater
allowed to cool.
Neutralization
If neutralization is necessary, such as when a tube or tubes are cut out of the coil, or any time
when exposure to air at temperatures below the dew point of water cannot be avoided, the tubes
should be filled with soda ash solution and allowed to soak for a minimum of two hours. With
vertical coils, where it is not possible to completely fill the unvented upper return bends, it is
necessary instead to vigorously circulate the soda ash solution through the tubes for a minimum
of two hours to assure contact of all surfaces. After draining the soda ash solution, do not flush
with steam or water but instead allow a film of protective soda ash to remain in the tubes.
Exterior Surfaces
Whenever heater fires must be shut down and the tubes are allowed to cool, it is recommended
that the exterior tube surfaces be protected, especially in heaters where fuel oil or high sulfur
content fuel gas is employed. As a result of the sulfur in the fuel, a sulfide scale can build up on
the exterior tube surfaces as well as on the inside tube surfaces. If moisture is allowed to
condense on the tubes as the heater box is cooled, the action of oxygen and moisture on the scale
can form polythionic acids which can attack the austenitic stainless steel tube surfaces and lead
to intergranular stress corrosion cracking. There are two recommended procedures that can be
followed to prevent this from occurring: First, it is possible to prevent any moisture from
condensing on the tubes, and thus prevent the formation of polythionic acids, by purging the
firebox with copious amounts of dry air. Normal instrument air is prepared by processing
through a set of driers where the dew point is reduced to a sufficiently low level to prevent
condensation from occurring at ambient conditions. This air can be effectively used to maintain a
dry air blanket in the heater box both during cooling and throughout the entire period the fires
are out. In order to minimize the consumption of instrument air, and to prevent moist air from
entering the heater box, the stack damper, all burner air registers, and all doors and ports in the
heater box should be kept closed.
Second, an alternate method of protecting the tubes from polythionic acid attack is to cover the
exterior tube surfaces with a protective film of soda ash, which will act to neutralize any
polythionic acids as they are formed. The neutralizing soda ash should be the same dilute
solution recommended for general neutralization, and should be applied to the tube surfaces as
soon as the heater box has cooled sufficiently to prevent vaporizing the soda ash solution, and
preferably before any moisture has begun to condense out on the tube surfaces. A fairly efficient
and effective method of applying the soda ash solution is to utilize a vat or tank with a small
portable pump which can pump the solution through a hose fitted with a spray nozzle which will
produce a fairly fine mist.
NOTE: A low pressure spray is advisable as high pressure may erode the refractory.
Small diameter pipe extensions can be fitted to the hose to allow reaching up to the tube areas at
the top of the heater box. This type of spray equipment will minimize the soda ash consumption
and provide a reasonable means to reach all tube surfaces that are exposed to the heater flames.
Once the soda ash solution has been applied, it should be allowed to dry to form a protective film
on the surfaces of the tubes; do not wash off this protective film.
If the exterior tube surfaces are heavily coated with an oxide or carbonaceous material, it should
be removed by wire brushing or sandblasting. This cleaning, however, will also remove any
protective soda ash film that may have been applied. In this case, the tube surfaces should be
further protected by applying another film of soda ash without delay.
On the occasions when the heater fires are shut down, it is convenient to also schedule inspection
of the tubes. Inspection should include measuring the tube outside diameters for comparison to
the original new tube ODs, dye penetrate checking of welds and heat affected zones for cracks,
and random ultrasonic flaw detection of the heat affected zones around welds. Periodic
radiographic inspection should be conducted to check for scale or deposits inside the tubes.
When the reactor internals are to be exposed to air for a prolonged period of time, such as during
a catalyst change, the reactor walls and internals should be washed very thoroughly as soon as
possible with a high pressure hose, using copious amounts of soda ash solution. A portable pump
and a vat of soda ash solution on skids is typically used for this operation. In order to do this
washing properly, a workman equipped with a fresh air mask and following all other proper
safety precautions, might have to enter the vessel to make sure all surfaces, including the
underside of the top head, are thoroughly wetted. Be especially careful to thoroughly soak
welded areas with particular emphasis on welds normally required to support heavy loads, such
as those on support beams, grids and trays.
When the reactor contains trays, which would make wetting all surfaces with soda ash solution
difficult, a sufficient amount of soda ash solution should be sprayed around the top of the reactor,
and allowed to rain down through the reactor to wet as much of the surfaces as possible in the
areas below the top tray. Be sure to thoroughly soak and keep wetted any used catalyst remaining
in the reactor, and then air can be drawn through the reactor so that personnel can enter. During
this time, a small flow of soda ash solution to the reactor should be maintained, and as each tray
manway is removed, the vessel area beneath that tray and the underside of the tray should be
thoroughly washed with soda ash solution.
Whenever spent, unregenerated catalyst is unloaded from the reactor; some amounts of catalyst
will inadvertently remain on the trays and in the bottom of the reactor. This catalyst must be kept
wet to prevent ignition of sulfide scale when air is admitted, which is another reason for
conducting a thorough washing operation with the soda ash solution.
After washing with soda ash solution, allow the surfaces to dry with a fine deposit of soda ash.
Do not rinse this residue off with water. Later, just prior to reloading catalyst, wipe as much
excess soda ash residue from the surfaces as possible with brushes or dry cloths; do not use water
or wet cloths.
the catalyst bed to a temperature which would allow entering the reactor following a catalyst
regeneration, the oxygen must first be reduced to an acceptable level. Maintain the final reactor
temperature used in the regeneration and continue gas circulation; and depressurize to the
minimum allowable for recycle compressor operation. Then pressure with nitrogen. Conduct this
procedure at least three times, or as necessary to reduce oxygen concentration in the circulating
gas by dilution to as much below 100 mol-ppm as is possible and reasonable. Maintain reactor
temperatures and gas circulation, after shutting down and draining the caustic and water systems,
until the reactor system is dry and no more water collects in the separator.
Then the system can be cooled to about 150F (65C) at the reactor outlet. At this point shut
down the recycle gas compressor but maintain heater fires sufficient to maintain about 400F
(205C) firebox temperatures throughout the shutdown period.
SECTION-11
SAMPLING PROCEDURE AND LABORATORY ANALYSIS REQUIREMENT
11.1 GENERAL
Control tests provide the information to the operating staff for making necessary adjustments to
get the maximum output and on-spec quality products. The control tests are to be made at all
steps to monitor the intermediate and final products whether or not they are at the desired
specification. Samples are taken and analyzed at regular intervals such that the operation of the
plant are monitored and any deviation (from specification will indicate some maloperation /
malfunction of the plant which can be spotted and rectified in time without undue loss of time
and product. Sometimes, samples are taken to find out the effect of certain changes brought
about in the operating conditions. The samples are to be taken with great care so that the samples
are representative samples. The frequency of sampling, the type of analysis and points where
samples are to be taken are generally specified by t he process licensor. During guarantee tests
some additional samples can be taken at higher frequencies, which will be specified, in the
technical procedures prior to test run. The following guidelines should be followed while
collecting samples.
i) The person taking samples should wear proper or appropriate safety clothing like face
shields, aprons, rubber gloves etc. to protect face, hands and body.
ii) Whenever hot samples are taken, check cooling water flow in the sample cooler is
circulating properly.
iii) Sample points usually have two valves in series. One gate valve for isolation (tight
shutoff) and other globe valve for regulating the flow. Open gate valve first and then
slowly open the globe valve after properly placing the sample containers. After the
sampling is over, close the globe valve first and then the gate. Then again open the globe
valve and drain the hold up between the gate and globe valve in case of congealing
liquid.
iv) Sample valve should be slowly opened, first slightly to check for plugging. If the
plugging is released suddenly, the liquid will escape at a dangerously uncontrolled rate.
Never tap the line to release the plugging. Call the maintenance gang to properly unplug
the line. In case of congealing type samples, sample point should be equipped with
copper coil type steam tracer. It should be ensured that steam-tracing line is functioning
normally.
v) The operator taking the sample should be careful to stand in a position such that the
liquid does not splash on him and he has unobstructed way out from the sample point in
case of accident.
vi) While taking dangerous toxic material for sampling, it will act as an observer for safety.
Proper gas mask is to be used. It is advisable to stand opposite to wind direction in case
of volatile toxic liquid.
vii) Sample should be collected in clean, dry and stoppered bottle. In case of congealing
samples use clean dry ladle.
viii) Rinsing of the bottle should be thorough before actual collection.
ix) Before collecting, ensure that the line content has been drained and fresh sample is
coming.
x) Gradually warm up the sample bottle / metallic can by repeated rinsing before collecting
the sample.
xi) Stopper the bottle immediately after collection of sample.
xii) Attach a tag to the bottle indicating date, time, and name of the product and tests to be
carried out.
xiii) A few products suffer deterioration with time.
xiv) For example, the colour of the heavier distillates slowly deteriorates with time. So these
samples should be sent to laboratory at the earliest after collection.
The samples after collection should be kept away from any source of ignition to minimize fire
hazard.
Volatile samples (e.g. naphtha) should be collected in bottles and kept in ice particularly for
some critical test like RVP.
i) The person taking sample should use personal protection appliances like apron, gas mask
and hand gloves to protect himself.
ii) Ensure that sample bomb is empty, clean and dry.
iii) Connect the sample bomb inlet valve to the sample point with a flexible hose.
iv) Open the inlet and outlet valves of the sample bomb. Hold the sample bomb. Hold the
sample bomb outlet away from person. Keep face away from hydrocarbon vapour and
stand in such a way that prevalent wind should blow hydrocarbon vapour away. Open the
gate valve of sample point slowly till full open. Then slowly cracks open the regulating
valve. One should be careful at the time of draining, because chance of icing is there. As
a result, the formation of solid hydrates is a continuing process, which leads to the
plugging of valves.
v) When all the air in the hose and bomb are displaced as seen by the hydrocarbon vapour
rising from the outlet of sample bomb close the sample outlet valve. Allow a little
quantity of liquid to spill to make sure that the bomb is receiving liquid. Frosting will be
an indication of liquid spillage.
vi) Allow liquid hydrocarbon to fill the bomb. When the bomb is full up to the specified
level, close both the valves on sample point. Close inlet valve on the sample point.
vii) Carefully disconnect the hose from the sample bomb. To allow for some vapor space in
the bomb for thermal expansion in case of overfilling, crack open the outlet valve of
bomb and discharge a small part of the liquid. Close outlet valve.
viii) Closed sampling facilities are provided at some locations where it is not desirable to
waste the costly product or if the material is toxic. For filling the sampling bomb,
pressure drop across a control valve is usually utilized or across pump discharge &
suction. Air is expelled from the bomb after it is connected to upstream of control valve
or pump discharge side. The sample is then collected and bomb is detached after closing
valves on both sides.
ix) Send sample bomb to laboratory for analysis. Protect the bomb from heat exposure.
c) Gas Sample
For collection of gas sample, which are not under high pressure and temperature, rubber bladders
are used. For the operations under vacuum or low pressure, aspirator is used. For representative
sample, purge the bladder 3 to 4 times with the gas and then take t he final sample. Use of 3
ways valve with bladder / aspirator will facilitate purging and sampling.
Sample bombs are to be used for taking gas samples from high pressure and high temperature
source. Procedure mentioned under high-pressure liquid sampling (flashing type) is to be used.
Stripper Bottom
Make-Up Hydrogen
REGENERATION CASE
Recycle Gas
Spent Caustic
Circulation Caustic
SECTION -12
EMERGENCY PROCEDURES
12.1 GENERAL
Emergencies that occur in hydrotreating units must be recognized and acted upon immediately.
The operators and supervisory personnel should carefully study in advance, and become
thoroughly familiar with, the proper steps to be taken in such situations. Some of the emergency
conditions described here will not only result in a unit shutdown, but if the situation is not
handled properly, can lead to serious damage to the catalyst and equipment.
In general, the objective of the emergency procedures is to avoid damage to equipment and
catalyst. This is accomplished by rapid cooling of the catalyst beds below reaction temperature
and by reducing the pressure whenever there is a possibility of a temperature excursion.
In addition, specific rules cannot be made to cover all situations that might arise. Therefore, the
following procedures cover only those emergency situations that are the most common and, for
the most part, only the immediate steps to be taken are listed. It should be noted that the
procedures outlined here concentrate on the reactor section. In most cases, the corrective actions
will result in upsets in the Splitter and Stabilizer columns. It is advised that care be taken to
adjust the Stripper and Splitter columns operation whenever flows and/or severity are reduced.
It should also be noted that the protection of austenitic stainless steel equipment must always be
kept in mind. The proper precautionary measures must be taken to prevent oxygen and liquid
water from coming into contact with any austenitic material that has sulfide scale. These
measures should not conflict with the immediate steps required as a result of the emergency
condition.
Any time an emergency situation occurs, especially when a reduction in space velocity or
capability of removing the heat of reaction from the catalyst is involved, a condition exists which
could lead to the generation of localized high temperatures. Therefore, if during any type of
emergency there is a rapid temperature rise in the reactor or catalyst bed; immediate steps should
be taken to depressurize the system to suppress the reactions. The objective is to prevent a
further rise in temperature and minimize the danger of damage to the reactor and other
equipment.
If a temperature in the reactor starts to rise above normal, the following steps should be taken:
I. Reduce the inlet temperature of the bed in which the high temperature occurs. Also, reduce
inlet temperatures to the catalyst beds below.
II. If the temperatures are not controlled by the corrective action of step (1), reduce the reactor
inlet temperature by reducing firing rate of the charge heater.
III. If the temperatures continue to rise 28 C above normal, remove feed from the unit.
IV. If the catalyst bed temperatures are 28C above normal and continue to rise despite the
above corrective actions, or if the temperatures exceed the maximum allowable operating
temperature of the reactor, then depressurizing will be necessary to regain control of the
reactor. If the operator decides to manually depressurize the unit via the manual emergency
depressurizing system, the following should occur automatically:
The feed pump shuts down.
The shutoff control valves in the fuel gas and fuel oil lines to the charge heaters
close, the pilots will stay lit..
The wash water pump will shut down.
NOTE: If the manual depressurizing system is activated, the recycle gas compressor will
continue to operate.
V. Verify that the charge heater burners are out. Open the stack damper and all air registers to
the full open position to establish the maximum flow of cooling air through the box. Add
snuffing steam to the heater box to aid in cooling. Be sure the steam is dry before admitting
it to the heater box.
VI. Put the product condenser fans on maximum cooling. Be careful not to exceed the reactor
product condenser maximum design temperature.
VII. The depressurizing valve may be closed when all reactor temperatures are at least 28C
below normal operating temperatures. If temperatures remain high after the unit has been
depressurized, then begin purging the reactor with nitrogen at the maximum rate possible.
VIII. If recycle compressor operation can be maintained, continue maximum gas circulation and
cool all catalyst temperature points and hydrotreating reactor outlet temperature to 205C.
IX. Hold until ready for startup.
NOTE: In the event of a serious temperature excursion, the hydrotreating unit should be
completely shut down and the affected catalyst removed, screened and reloaded. In addition, the
reactor and other affected equipment should be carefully inspected for damage.
SECTION -13
SAFETY PROCEDURE
13.1 INTRODUCTION
Safety of personnel and equipment is very important. Ignorance of the details of the unit or the
techniques of safe and efficient operation reduces the margin of safety of personnel and subjects the
equipment to more hazardous conditions. All the operating and maintenance crew therefore must
be fully familiar with the equipment and materials being handled in the unit, and recognize the
hazards involved in handling them and the measures taken to ensure safe operations.
Since the unit handles with one of the most potential source of fire and explosion, H2, Naphtha and
chemical like caustic, therefore adherence of safety rules should be given uphill importance.
c) Entry permits
Entry permits are required for entering enclosed spaces such as vessels, sewer, pits, trenches, etc.
The use of any tool or machinery, which could provide a source of ignition, is forbidden. Also,
prior to entry it should be ensured that area is well ventilated and the oxygen content in air is
about 20.9% by volume. Fresh air flow is to be ensured in the enclosed space through out the
duration of work. A gas test for H2S and flammable gases should also be performed before entry.
A person should also be on alert outside the enclosed space for rescue in case of emergency.
Procedure for carrying out work and rescue plan shall be formulated before commencement of
work.
means of proper isolation, proper ventilation and suitable check of the atmosphere inside and
availability of rescue person outside the enclosed equipment.
Note: Open a vent on the upper part of the vessel to allow gases to escape during filling and to
allow air inside the vessel during draining. Ensure proper ventilation inside the vessel by
opening all manholes. For hydrocarbon or other gases, pressurize the vessel with N2 or gas
and fill in the liquid and drain under pressure. This is to avoid hydrocarbon going to
atmosphere.
After the above operations have been made, a safety permit should be issued for carrying out the
work. A responsible operating supervisor should be personally present at the place of hot work till
the first torch is lighted. Hot work should be immediately suspended if instructed by the supervisor
or on detecting any unsafe condition. When people have to enter a vessel for inspection or other
work, one person should stand outside near the manhole of the vessel for any help needed by the
persons working inside. The person entering the vessel should have tied on his waist a rope to
enable pulling him out in case of urgency. Detail procedure for preparation for vessel entry is given
in next sub-section.
Vessel Access
Safe access must be provided both to the exterior and interior of the vessel to be entered. The
exterior access should be a solid, permanent ladder and platform or scaffolding strong enough to
support the people and equipment who will be involved in the work to be performed.
Access to the interior should also the strong and solid. Scaffolding is preferred when the vessel
is large enough. The scaffolding base should rest firmly on the bottom of the vessel and be
solidly anchored.
If the scaffolding is tall, the scaffolding should be supported in several places to prevent sway.
The platform boards should be sturdy and capable of supporting several people and equipment at
the same time and also be firmly fastened down. Rungs should be provided on the scaffolding
spaced at a comfortable distance for climbing on the structure.
If scaffolding will not fit in the vessel a ladder can be used. A rigid ladder is always preferred
over a rope ladder and is essential to avoid fatigue during lengthy periods of work inside a
vessel. The bottom and top of the ladder should be solidly anchored. If additional support is
available, then the ladder should also be anchored at intermediate locations. When possible, a
solid support should pass through the ladder under a rung, thereby providing support for the
entire weight should the bottom support fail. Only one person at a time should be allowed on the
ladder.
When a rope ladder is used, the ropes should be thoroughly inspected prior to each new job. All
rungs should be tested for strength, whether they be made of metal or wood. Each rope must be
individually secured to an immovable support. If possible, a solid support should pass through
the ladder so that a rung can help support the weight and the bottom of the ladder should be
fastened to a support to prevent the ladder from swinging. As with the rigid ladder, only one
person should climb the ladder at a time.
harness for each person entering the vessel and at least one spare harness for the people watching
the manway should be provided at the vessel entry.
some refiners). The fresh air purge should be continued throughout the time that people are
inside of the vessel. The responsible control room should be informed that instrument air is
being used for breathing so that if a change to nitrogen is required the people are removed from
the affected vessel.
A minimum of one fresh air mask for each person entering the vessel and at least one spare mask
for the hole watcher should be provided at the vessel entry. These masks should completely
cover the face, including the eyes, and have a second seal around the mouth and nose. When use
of the mask is required, it must first be donned outside of the vessel where it is easy to render
assistance in order to confirm that the air supply is safe. Each mask must have a backup air
supply that is completely independent of the main supply. It must also be independent of
electrical power. This supply is typically a small, certified cylinder fastened to the safety harness
and connected to the main supply line via a special regulator that activates when the air pressure
to the mask drops below normal. The auxiliary supply should have an alarm which alerts the
user that he is on backup supply and it should be sufficiently large to give the user 5 minutes to
escape from danger.
Additional requirements or procedures may be imposed by the refiner, but the foregoing is
considered the minimum acceptable for good safety practice.
fluoride which may be released when the scale is disturbed. If this sort of danger is present,
fresh air masks and protective clothing may be required to be worn while working inside of the
equipment.
In a turnaround inspection, every vessel nozzle must be blinded at the vessel with absolutely no
exceptions. There will always be process material at the low and high points in the lines
connecting to the vessel because it is not possible to purge them completely clean. The blinds
must all be in place before the vessel is purge.
Another factor to be cautious of, especially if entering a vessel immediately after the unit has
been shut down, is heat stress. The internals of the vessels can still be very hot from the steam-
out procedure or from operations prior to the shutdown. If that is the case, the period of time
spent working inside of the vessel should be limited and frequent breaks should be taken outside
of the vessel.
Characteristics of H2S
Hydrogen sulphide has the following characteristics:
Deadly-extremely toxic gas.
Colourless.
Heavier than air tends to settle in low lying areas.
Readily dispersed by wind movement of air currents.
Burns with a blue flame, producing Sulphur Di-oxide (SO2), which is also a toxic gas.
Odour of rotten eggs. Only in low concentrations rapidly deadens the sense of smell. Do
not depend on the sense of smell to detect H2S
Highly corrosive to certain metals.
More deadly than Carbon Monoxide (CO), and almost as toxic as Hydrogen Cyanide
(HCN) gas.
100 ppm Coughing, eye irritation, loss of sense of smell after 2-15
minutes.
200-300 ppm Marked conjunctivitis (eye inflammation) and
respiratory tact irritation after one hour of exposure.
500-700 ppm Loss of consciousness, possible death in 30 minutes to 1
hour.
700-1000 ppm Rapid unconsciousness, cessation (stopping or
pausing) of respiration and death.
1000-2000 ppm Unconsciousness at once, with early cessation of respiration
and death in few minutes. Death may occur even if individual
is removed to fresh air at once.
ppm parts of gas per million part of air by volume.
Maintenance Procedure:
There are two basic areas of maintenance operations which are inherently dangerous from
the standpoint of H2S exposure. These are venting / draining of piping and confined space
entry.
Depressurization of piping, valves, fittings, strainers, etc. in H2S service represents a safety
hazard in the unit, since the vent and drain valves are not hard-piped to a closed vent or
drain header.
Without exception, breathing air respirators are to be worn when opening piping, removing
valves or performing any operation which might permit vapours to enter the immediate area.
When valves are removed, install blind flanges.
Confined space entry is entrance into areas such as tanks, vessels, etc. This is one of the
most dangerous activities of the unit and should be avoided whenever possible.
When it is absolutely necessary that a confined entry be made, entry should be made only after the
following safety conditions have been met.
Entry permit form has been filled out and signed.
E) Emergency Procedures
If all the above procedures have been adhered to strictly, a catastrophic release of H2S should never
occur. In the unlikely event such a release does occur, the emergency procedures detailed in this
section should be followed.
a) Egress
H2S is a dangerous, deadly gas; however serious injury or death can be avoided by simply
evacuating the contaminated area and moving to a safe area upwind. Therefore, the most important
things to remember are to Stay Claim and Get Away.
Precise emergency escape procedures will be defined by the operations management of the
complex; however the following general procedures should be followed:
Remain Calm-Do Not Panic
Hold your breath
Extinguish all fires
Alert the rest of the crew
Make a quick, cursory check of the area to see if the source of the gas is obvious.
Do not spend time looking for a leak
Observe windsock to determine wind direction. Move upwind or crosswind, not downwind,
until the safe breathing area is reached.
Active alarms if not already done.
Once assembled at the safe briefing area, the foreman will make a head count to determine if
all personnel have evacuated safely.
Seek assistance at the first opportunity and make arrangements for transportation to
a medical facility to seek medical attention by a physician.
c) Abatement Procedure
Once the safety of all personnel has been determined, the next order or business is to determine the
source of H2S and stop it, if possible.
Field Personnel
Use breathing apparatus (Respirator).
Establish communication with Control Room.
Communicate with first personnel to sound alarm/notice of the H2S.
To determine the general area of the source, slowly begin searching the source from the
upwind side.
13.6.2. HYDROGEN
Hydrogen is a colourless, tasteless, odourless and highly flammable gas and is the lightest
element. Since hydrogen is lighter than air, less danger exists of it collecting in pockets in low
areas. However, the potential danger from fire or explosion is high. Gaseous fuels such as
hydrogen can mix with air or oxygen in all proportions. However, the proportions must be within
certain limits before those mixtures will burn. The limiting proportions are referred to as
flammable limits or explosive limits and are expressed as the percentage by volume of the
fuel in the air-fuel mixture. Fuel-air mixtures outside of the flammable range will not explode.
Hydrogen has a very wide range (4-75%) of flammability or explosive limits in air at
atmospheric pressure. In addition to, the flammability range becomes wider at higher pressure or
if oxygen is substituted for air. Thus, explosions can occur over a very wide range of hydrogen
concentrations in air. The safest approach to safeguard against possible fires or explosions is to
make sure that hydrogen leaks do not develop.
The auto ignition temperature of a substance is the lowest temperature required to initiate or
cause self-sustained combustion in the absence of a spark or flame. The auto ignition
temperature of hydrogen in air is 580C at atmospheric conditions. However, other factors such
as the nature, size, and shape of the igniting surface can affect this temperature.
Unlike most gases, which cool when expanded or bled off, hydrogen heats up when expanded
and great care must be exercised when bleeding down lines or compressors to the atmosphere. In
its pure state, hydrogen burns with a bluish white flame (almost invisible) that is extremely hot.
Such a hot flame can weaken any support beams or lines on which it may impinge. Any leaks
should be put under a steam blanket immediately to prevent the possibility of a fire. Be aware,
however, that many leaks can auto ignite and will be difficult to see. Replacing the source of the
hydrogen with a nitrogen or steam purge is the most effective way of combating a hydrogen fire.
Hydrogen, although a not a poisonous gas itself, is an asphyxiant (i.e. cuts off oxygen supply to
the body by displacing air in the lungs) and can cause unconsciousness and even death if the
victim falls and remains in a high hydrogen atmosphere.
Because of the small size of hydrogen molecules, a pressure check with air or nitrogen or a
hydrostatic test will not always show all leaks that will occur with hydrogen.
Major Fire fighting facilities provided in the unit comprise the following:
hydrocarbon & spread of fire. Similarly use of fire water on hot oil surfaces may cause sputtering &
spread of fire.
Head protection:- Safety helmets shall be worn by all personnel at all times in the plant for protection
of the head. They may be removed when inside rooms or buildings which do not have overhead or
other hazards.
Eye and face protection:- Safety glasses, goggles or face shields shall be worn while performing
work, which could result in eye or face injury.
Hand Protection: - Proper hand protective gloves should be worn.
Foot protection: - Safety shoes are to be worn for foot protection.
Ear protection: - Whenever personnel are required to be work in noisy areas proper ear protection
device such as ear plug etc, is to be used.
Breathing apparatus: - Whenever persons are required to work or enter an area of high
toxic/aromatic/hydrocarbon vapor concentration, wear appropriate respiratory protection, such as
self-contained breathing apparatus or an air mask with an external air supply.
SECTION -14
GENERAL OPERATING INSTRUCTIONS FOR EQUIPMENT
14.1 GENERAL
This section covers the general procedure for operation and trouble shooting of commonly used
equipment like pumps, heat exchangers and furnace etc. For specific information and more detail
refer to vendor's manuals.
In some pumps a by-pass has been provided across the check valve and discharge valve to keep the
idle pump hot. In such pumps, the by-pass valve should be closed before starting the pump. It
should be ensured that casing of these pumps are heated up sufficiently prior to starting of the pump
to guard against damage of the equipment and associated piping due to thermal shock.
14.2.2. Shutdown
Close discharge valve fully.
Stop the pump
a) If pump is going to remain as standby and has provision for keeping the pump hot, proceed
as follows:
Open the valve in the by-pass line across the discharge valve and check valve.
The circulation rate should not be so high to cause reverse rotation of idle pump and also
overloading of the running pump.
v. Unusual Vibration
Check the foundation bolts.
Check the fan cover for looseness.
Stop the pump and hand over to maintenance.
14.3.2. Shutdown
Stop the pump.
Close the suction and discharge valves.
Drain the liquid if maintenance jobs are to be carried out on the pump.
Verify that the lubrication, seal gas, and coolant systems are clean and free of contamination and
that all control systems function properly. The pre-commissioning of these package units should
follow the manufacturers recommended procedures.
Verify that the shutdown system on the compressor function according to design. The temporary
strainers on the suction should be removed prior to full-time operation.
Verify that the compressor rotate freely.
14.4.1. Start-up
i. Ensure all mechanical jobs have been completed on the compressor that is to be started
including suction line passivation.
ii. No load run of the motor to be completed before the compressor is coupled. After no load
run, de-energize the electrical supply. Couple the motor and compressor. Check the
rotating element of the compressor for free rotation turning slowly by hand. If the rotor
rubs, rotation should be stopped immediately and the difficulty located and repaired.
iii. Check oil level in lube oil tank and refill as required bringing the oil level to the high
mark on the sight glass. Do not overfill.
iv. Line-up and start seal and lube oil circulation to make certain that bearings of the
compressor and driver are well lubricated.
v. Establish the pressure of lubricating oil in bearings and seal oil to seal.
Note: Seal system is to be in operation whenever any pressure is in the compressor, even
though the machine is idle.
vi. Bar the unit over once to be sure all moving parts are clear.
vii. Make sure that water cooler and air coolers coming in compressor circuit are in
operation.
viii. Ensure that compressor casing has also been purged with inert gas. Pressurise the
compressor with nitrogen and leak test.
ix. Open suction valve/discharge valve and line up to the system. Remove any accumulated
liquid from the casing by opening casing drain.
x. Start the drive as per the vendors recommendations and run the compressor.
xi. Allow the oil to warm up to 40o C. Watch compressor motor amperage. Listen for
unusual noise or vibration during the warm up period.
xii. Auxiliary motor driven lube oil pump will be stopped when shaft-driven pump develops
normal oil pressure and kept ready for auto start.
xiii. When the unit is warmed up and determined to be operating satisfactorily, gradually start
throttling the valve beyond surge requirements of the compressor.
xiv. Load the compressor to the required capacity in the above mentioned manner.
Note: The compressor before trial run on the actual medium may be tried on air with suction and
discharge open to atmosphere. While attempting to run the Compressor on air, Vendor's
instructions and recommendations are to be followed. It is to be noted that scaling
arrangement may be required to be changed to suit the machine running on air.
14.4.2. Shutdown
i. Stop the drive.
ii. Start the oil pump to lubricate the bearing till required.
iii. Close the discharge valve.
iv. Close the suction valve.
v. Turn off cooling water to oil cooler as applicable.
vi. If the compressor is to be given for maintenance, isolate, depressurise and purge with
inert gas to make the compressor free of hydrocarbons.
iv. Listen for any unusual noise while the machine is operating. These should be
investigated immediately.
v. Periodically drain from suction pot etc.
vi. Watch differential pressure across oil filter to check cleanliness; change over filter, if
necessary and arrange cleaning of choked filter.
vii. Keep the exterior of the compressor and the compressor room floor clean.
The exchangers have been provided with draining and flushing connections. The coolers and
condensers have been provided with TSV's on the cooling water side to guard against possible rise
of pressure due to faulty operations with the safety release to atmosphere. Temperature gauges or
thermo wells have been provided at the inlet and outlet of exchangers. Where water is the cooling
medium, no temperature measurement is provided for water inlet temperature which is the same as
cooling water supply header temperature.
AIR COOLERS
The air coolers/condensers comprise of a fin tube assembly running parallel between the inlet
and outlet headers. These are of the forced draft type. The forced draft fans provided have auto
variable speed rotors in which the fan speeds are adjusted during rotation. This allows variation
in air flow as per the cooling requirements. A high vibration switch is provided with alarm to
indicate any mechanical damage.
EXCHANGERS
Shell and Tube type heat exchangers can be broadly classified into following types: -
Water Coolers/condensers
Steam heaters (reboiler)
Exchangers
Start-up /shut down procedures for each unit shall vary slightly from case to case. However,
general start-up /shut-down procedures are discussed in the following paragraphs.
14.5.1. Start-Up
After the heat exchanger has been pressure tested and all blinds removed, proceed as follows:
i. Open cooling medium vent valve to displace non-condensable (air, fuel gas, inert gas
etc.) from the system. Ensure the drain valves are capped. For high pressure system,
drain valves should be flanged. This activity is not required if gas is the medium.
ii. Open cooling medium inlet valve. Close vent valve when liquid starts coming out
through it, then open cold medium outlet valve and fully open the inlet valve also. Where
cold medium is also hot, warming up of cold medium side gradually is also essential.
iii. Open hot medium side vent valve to displace non condensable (air, fuel inert gas etc.).
Check that the drain is closed and capped. This activity is not required if gas is the
medium.
iv. Crack open hot medium inlet valve. When liquid starts coming out from the vent valve,
close it. Open hot medium inlet valve and then open the outlet valve fully. In case of
steam heaters, initially the condensate shall be drained to sewer till pressure in the
system builds up to a level where it can be lined up to the return condensate header.
v. In case by passes are provided across shells and tube side, gradually close the bypass on
the cold medium side and then the bypass across the hot medium side.
vi. Check for normal inlet and outlet temperatures. Check that TSVs are not popping.
vii. The operation of inlet and outlet valves should be done carefully ensuring that the
exchangers are not subjected to thermal shock.
viii. In case of coolers/condensers, adjust the water flow to maintain the required temperatures
at the outlet.
ix. For avoiding fouling, velocity of water should be at least 1 m/sec in a cooler/condenser.
14.5.2. Shutdown
Shut down of an exchanger, coolers, condenser is considered when the equipment is to be isolated
for handling over to maintenance while the main plant is in operation. The following is the
suggested procedure for isolation of the piece of equipment
i. Isolate the hot medium first. In case both hot and cold medium are from process streams,
exchanger shall remain in service till the hot stream has cooled down enough.
ii. In case of a cooler, adjust cooling water flow to the cooler which is in line so that product
temperature is within allowable unit.
iii. Isolate the cold medium next.
iv. Drain out the shell and tube sides to OWS/Sewer/Closed blow down system as
applicable. In case flushing oil connection is given flush the exchanger to CBD. Ensure that
the CBD drum has sufficient level to receive the flushing of the exchanger
v. Depressurize the system to atmosphere/flare/blow down system as applicable.
vi. Purge/flush if required. This is particularly important in congealing services.
vii. Blind inlet and outlet lines before handing over the equipment for maintenance.