Professional Documents
Culture Documents
Telkomsel Standard Installation IRO
Telkomsel Standard Installation IRO
www.huawei.com
Cable duct
When power cable, grounding cable and transmission cable laying on the Wall, the cable must put
on the cable duct. Power cable and LAN cable must use different cable duct
DCDU
SLPU
EMUA
BBU
CPRI and RRU power cable spare put in base frame cabinet
DCDU, SLPU, BBU must EMUA must grounding Inside cabinet grounding
grounding
All Grounding cabinet install to grounding bar with firmly and correctly,
and for outdoor installation when grounding cable came out from BTS
cabinet must use conduit protection
Rectifier BTS
Grounding
Cable
Star Net:
In this typical
configuration, the
antenna system
consists of the RET
antenna, SBT, RCU,
Star Net
and feeders. The AISG
port on the SBT is
connected to the RCU
through an AISG
control cable. the
AISG signal for each
RCU come from
different RRU. The
Net is simple and easy
to control.
too many SBT are
used.
Chain Net:
Chain Net can be used
when the antennas for
three sectors are
installed on the same
Chain Net
pole or tower and
within a short distance
of each other. The AISG
signal for 3 RCU come
from the same port.
SBT can be saved in
Chain Net system.
When install CPRI cable and RRU power cable must put inside anaconda conduit from below of
cabinet until 1 m to vertical tray.
CPRI cable and RRU power cable must use different anaconda conduit
1M
Conduit Protection install for CPRI and RRU power cable from tray horizontal until 1m to tray vertical,
make hole below conduit for water treatment.
Use separate conduit protection for CPRI and RRU power cable
All cable came out from BTS must use conduit protection
When at site only install 3G Stand alone so team must install ENVA alarm cable
from rectifier
Note :
W : White
R : Red
Y : Yellow
B : Blue